CN103672921A - Method for mounting industrial incineration disposal equipment - Google Patents
Method for mounting industrial incineration disposal equipment Download PDFInfo
- Publication number
- CN103672921A CN103672921A CN201310681542.5A CN201310681542A CN103672921A CN 103672921 A CN103672921 A CN 103672921A CN 201310681542 A CN201310681542 A CN 201310681542A CN 103672921 A CN103672921 A CN 103672921A
- Authority
- CN
- China
- Prior art keywords
- disposal equipment
- burning disposal
- industrial burning
- industrial
- top cover
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The invention discloses a method for mounting industrial incineration disposal equipment. The method for mounting the industrial incineration disposal equipment comprises the steps that (1) two lifting devices are assembled and are distributed and arranged in a bilateral symmetrical mode; (2) the bottom, a barrel body and a top cover of the industrial incineration disposal equipment are assembled in sequence; (3) joint pieces are added on the two sides of the bottom, and the bottom is lifted and arranged at a bottom mounting position by the lifting devices; (4) lifting pieces are added on the two sides of the barrel body, the barrel body is lifted and arranged on the bottom by the lifting devices, and then the barrel body and the bottom are welded and fixed into a whole; (5) lifting pieces are added on the two sides of the top cover, the top cover is lifted and arranged on the barrel body by the lifting devices, and then the top cover and the barrel body are welded and fixed into a whole. The method for mounting the industrial incineration disposal equipment effectively solves the problems that the industrial incineration disposal equipment is low in mounting efficiency and poor in quality, mounting is simple, convenient to carry out, safe and reliable, and the safety and quality of engineering construction are ensured. Meanwhile, the method for mounting the industrial incineration disposal equipment is capable of saving a large amount of cost, economical and reasonable and is advanced in technology.
Description
Technical field
The present invention relates to industrial equipment mounting technique field, be specifically related to a kind of industrial burning disposal equipment installation method.
Background technology
National to environmental improvement and the increasing of protection input, newly-built civilian more with industrial solid refuse treatment engineering in recent years, for the waste gas producing in burning process, waste residue standard-required, also day by day improve.It is the main processing workshop of destructor plant that workshop is burned in industry, and its production Technology and equipment operation performance will be the key point that build in workshop.It is high that the requirement of workshop appliance installation accuracy is burned in industry, complex process, and installation difficulty is large.
Along with developing rapidly of modern science and technology, increasing industrial refuse and incineration workshop adopts automation integrated production line technology, to give full play to the advantage of modern science and technology, due to the restriction at the existing construction technology of production equipment installation process and device, cause industry burning Workshop Production equipment installation effectiveness and quality low, do not reach design and production requirement.
Summary of the invention
Object of the present invention, provides a kind of industrial burning disposal equipment installation method exactly in order to address the above problem, it is succinctly convenient, safe and reliable to install, and has guaranteed engineering construction safety and quality.
The object of the present invention is achieved like this:
A kind of industrial burning disposal equipment installation method of the present invention, comprises the following steps:
Step 1: assemble two lifting devices, and be symmetrical shape and distribute and install fixing;
Step 2: the bottom of industrial burning disposal equipment, cylindrical shell and top cover have been assembled successively;
Step 3: add bottom joint hinge in the both sides of the bottom of industrial burning disposal equipment, described lifting device promotes and be positioned over installation site, bottom by bottom joint hinge by the bottom of described industrial burning disposal equipment, is then installed and fixes;
Step 4: the both sides at the cylindrical shell of industrial burning disposal equipment add cylindrical shell joint hinge, described lifting device promotes the cylindrical shell of described industrial burning disposal equipment be positioned on the bottom of described industrial burning disposal equipment by cylindrical shell joint hinge, then the cylindrical shell of described industrial burning disposal equipment and bottom welding is fixed into one;
Step 5: the both sides at the top cover of industrial burning disposal equipment add top cover joint hinge, described lifting device promotes the top cover of described industrial burning disposal equipment be positioned on the cylindrical shell of described industrial burning disposal equipment by top cover joint hinge, then the top cover of described industrial burning disposal equipment and barrel soldering is fixed into one.
Above-mentioned a kind of industrial burning disposal equipment installation method, wherein, in described step 1, described lifting device comprises support bar, is located at the fixed pulley of this supporting bar top and is arranged in the lifting rope on described fixed pulley.
Above-mentioned a kind of industrial burning disposal equipment installation method, wherein, after described step 5, comprises industrial burning disposal equipment appurtenance installation steps, comprises the following steps:
After industrial burning disposal equipment appurtenance assembling, be installed on the annex installation site of industrial burning disposal equipment.
The present invention's industry burning disposal equipment installation method, has solved industrial burning disposal equipment installation effectiveness and the low problem of quality effectively, and it is succinctly convenient, safe and reliable to install, and has guaranteed engineering construction safety and quality.Saved great amount of cost, economical rationality, advanced technology simultaneously.Compare conventional mounting process, more safe and convenient, economical and efficient.
Accompanying drawing explanation
Structural representation when Fig. 1 is the bottom of establishing industrial burning disposal equipment according to hanging of exemplary embodiment of the present invention;
Fig. 2 is that Fig. 1 is the structural representation while establishing the cylindrical shell of industrial burning disposal equipment according to hanging of exemplary embodiment of the present invention;
Fig. 3 is the structural representation while establishing the top cover of industrial burning disposal equipment according to hanging of exemplary embodiment of the present invention.
The specific embodiment
Below in conjunction with embodiment, the invention will be further described.
To describe in detail according to the industrial burning disposal equipment installation method of exemplary embodiment of the present invention now, mainly comprise the following steps:
Step 1: assemble two lifting devices 1, and be symmetrical shape and distribute and install fixing; Wherein, lifting device 1 comprises support bar 11, is located at the fixed pulley 12 on these support bar 11 tops and is arranged in the lifting rope 13 on fixed pulley 12;
Step 2: the bottom of industrial burning disposal equipment 21, cylindrical shell 22 and top cover 23 have been assembled successively;
Step 3: as shown in Figure 1, in the both sides of the bottom 21 of industrial burning disposal equipment, add bottom joint hinge 31, one end of lifting device 1 lifting rope 13 is fixed on the joint hinge 31 of bottom, thus, lifting device 1 promotes and is positioned over installation site, bottom by the bottom of industrial burning disposal equipment 21, is then installed fixing;
Step 4: as shown in Figure 2, both sides at the cylindrical shell 22 of industrial burning disposal equipment add cylindrical shell joint hinge 32, one end of lifting device 1 lifting rope 13 is fixed on cylindrical shell joint hinge 32, thus, lifting device 1 promotes the cylindrical shell of industrial burning disposal equipment 22 be positioned on the bottom 21 of industrial burning disposal equipment, then the cylindrical shell of industrial burning disposal equipment 22 and bottom 21 is welded and fixed and is integral;
Step 5: as shown in Figure 3, both sides at the top cover 23 of industrial burning disposal equipment add top cover joint hinge 33, one end of lifting device 1 lifting rope 13 is fixed on top cover joint hinge 33, thus, lifting device 1 promotes the top cover of industrial burning disposal equipment 23 be positioned on the cylindrical shell 22 of industrial burning disposal equipment, then the top cover of industrial burning disposal equipment 33 and cylindrical shell 23 is welded and fixed and is integral;
Step 6: after industrial burning disposal equipment appurtenance assembling, be installed on the annex installation site of industrial burning disposal equipment.
The present invention's industry burning disposal equipment installation method, has solved industrial burning disposal equipment installation effectiveness and the low problem of quality effectively, and it is succinctly convenient, safe and reliable to install, and has guaranteed engineering construction safety and quality.Saved great amount of cost, economical rationality, advanced technology simultaneously.
Above embodiment is used for illustrative purposes only, but not limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, can also make various conversion or modification, therefore all technical schemes that are equal to also should belong to category of the present invention, should be limited by each claim.
Claims (3)
1. an industrial burning disposal equipment installation method, is characterized in that, comprises the following steps:
Step 1: assemble two lifting devices, and be symmetrical shape and distribute and install fixing;
Step 2: the bottom of industrial burning disposal equipment, cylindrical shell and top cover have been assembled successively;
Step 3: add bottom joint hinge in the both sides of the bottom of industrial burning disposal equipment, described lifting device promotes and be positioned over installation site, bottom by bottom joint hinge by the bottom of described industrial burning disposal equipment, is then installed and fixes;
Step 4: the both sides at the cylindrical shell of industrial burning disposal equipment add cylindrical shell joint hinge, described lifting device promotes the cylindrical shell of described industrial burning disposal equipment be positioned on the bottom of described industrial burning disposal equipment by cylindrical shell joint hinge, then the cylindrical shell of described industrial burning disposal equipment and bottom welding is fixed into one;
Step 5: the both sides at the top cover of industrial burning disposal equipment add top cover joint hinge, described lifting device promotes the top cover of described industrial burning disposal equipment be positioned on the cylindrical shell of described industrial burning disposal equipment by top cover joint hinge, then the top cover of described industrial burning disposal equipment and barrel soldering is fixed into one.
2. a kind of industrial burning disposal equipment installation method as claimed in claim 1, is characterized in that, in described step 1, described lifting device comprises support bar, is located at the fixed pulley of this supporting bar top and is arranged in the lifting rope on described fixed pulley.
3. a kind of industrial burning disposal equipment installation method as claimed in claim 1, is characterized in that, after described step 5, comprises industrial burning disposal equipment appurtenance installation steps, comprises the following steps:
After industrial burning disposal equipment appurtenance assembling, be installed on the annex installation site of industrial burning disposal equipment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310681542.5A CN103672921B (en) | 2013-12-12 | 2013-12-12 | Industry burning disposal equipment installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310681542.5A CN103672921B (en) | 2013-12-12 | 2013-12-12 | Industry burning disposal equipment installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103672921A true CN103672921A (en) | 2014-03-26 |
CN103672921B CN103672921B (en) | 2016-05-04 |
Family
ID=50311255
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310681542.5A Active CN103672921B (en) | 2013-12-12 | 2013-12-12 | Industry burning disposal equipment installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103672921B (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004212021A (en) * | 2003-01-09 | 2004-07-29 | Kazuhiro Takao | Incinerator, and its malfunction preventing device |
CN102051995A (en) * | 2010-12-24 | 2011-05-11 | 二十三冶建设集团有限公司 | Hoisting method of hyperbolic water-tower water tank and hoisting device |
CN102530782A (en) * | 2012-02-22 | 2012-07-04 | 象王重工股份有限公司 | Hydraulic synchronous lifting hoisting technology and equipment for ultra-large members |
CN202415096U (en) * | 2011-10-14 | 2012-09-05 | 上汽通用五菱汽车股份有限公司 | Material rack lifting mechanism |
-
2013
- 2013-12-12 CN CN201310681542.5A patent/CN103672921B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004212021A (en) * | 2003-01-09 | 2004-07-29 | Kazuhiro Takao | Incinerator, and its malfunction preventing device |
CN102051995A (en) * | 2010-12-24 | 2011-05-11 | 二十三冶建设集团有限公司 | Hoisting method of hyperbolic water-tower water tank and hoisting device |
CN202415096U (en) * | 2011-10-14 | 2012-09-05 | 上汽通用五菱汽车股份有限公司 | Material rack lifting mechanism |
CN102530782A (en) * | 2012-02-22 | 2012-07-04 | 象王重工股份有限公司 | Hydraulic synchronous lifting hoisting technology and equipment for ultra-large members |
Non-Patent Citations (1)
Title |
---|
奥云军: "垃圾焚烧炉施工技术", 《结构与设备安装》 * |
Also Published As
Publication number | Publication date |
---|---|
CN103672921B (en) | 2016-05-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203237913U (en) | Lifting appliance for L-shaped flange tower barrel | |
CN203645310U (en) | Clockwise/counterclockwise rotation control circuit of motor used for conveying steel pipes | |
CN204535392U (en) | A kind of atmosphere tube type stove | |
CN103672921A (en) | Method for mounting industrial incineration disposal equipment | |
CN203571610U (en) | Multifunctional vertical rod for construction | |
CN204570785U (en) | Excavator fluid pressure line mounting structure | |
CN207468036U (en) | A kind of movable type gantry rack device | |
CN204320278U (en) | A kind of refuse process plasma reaction furnace apparatus | |
CN203924659U (en) | Hanging frame type construction platform device | |
CN208269136U (en) | A kind of waste incineration pyrolysis oven with dedusting function | |
CN204320279U (en) | A kind of refuse process plasma reaction furnace apparatus | |
CN104437301B (en) | A kind of refuse process plasma reaction furnace apparatus | |
CN205619226U (en) | Anti -explosion lamp | |
CN205208520U (en) | Novel two dry coke quenching exhaust -heat boiler that press of self deoxidization | |
CN210206206U (en) | Environment-friendly waste gas treatment tower | |
CN203401482U (en) | Two-section petroleum pipeline mark belt | |
CN204649088U (en) | A kind of explosive cartridge easy to use | |
CN202900985U (en) | Detachable spool | |
CN203899450U (en) | Tank of photocatalysis organic waste gas purifier | |
CN103590612B (en) | Convenient purline correction device | |
CN203599062U (en) | Sieve plate used for desulphurization | |
CN109869471A (en) | A kind of speed reducer base | |
CN202729550U (en) | Flue gas denitrification catalyst module hoisting device in thermal power plant | |
CN203053249U (en) | Boiler utilizing exhaust gas waste heat of annealing furnace | |
CN204953650U (en) | System head machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 200949 No. 8415 Hu Tai Road, Shanghai, Baoshan District Patentee after: Shanghai General Construction Engineering Co., Ltd. Address before: 200949 No. 8415 Hu Tai Road, Shanghai, Baoshan District Patentee before: Shanghai General Metal Structure Engineering Co.,Ltd. |
|
CP01 | Change in the name or title of a patent holder |