CN103670413A - Method for slowing longwall mining pressure appearance of shallow coal seam below gully - Google Patents

Method for slowing longwall mining pressure appearance of shallow coal seam below gully Download PDF

Info

Publication number
CN103670413A
CN103670413A CN201210378536.8A CN201210378536A CN103670413A CN 103670413 A CN103670413 A CN 103670413A CN 201210378536 A CN201210378536 A CN 201210378536A CN 103670413 A CN103670413 A CN 103670413A
Authority
CN
China
Prior art keywords
gully
mining
coombe
coal seam
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210378536.8A
Other languages
Chinese (zh)
Other versions
CN103670413B (en
Inventor
王旭锋
张东升
张杨
范钢伟
张呈国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201210378536.8A priority Critical patent/CN103670413B/en
Publication of CN103670413A publication Critical patent/CN103670413A/en
Application granted granted Critical
Publication of CN103670413B publication Critical patent/CN103670413B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention belongs to the field of mineral engineering, and in particular relates to a method for slowing the longwall mining pressure appearance of a shallow coal seam below a gully. In order to solve the problem of longwall mining pressure appearance abnormality of the shallow coal seam below the gully, the invention proposes that the development situation of a ground surface gully needs to be taken into consideration as an important influence factor when shallow coal seam longwall mining is performed in a gully development area. According to a propagation angle and an overburden rock breaking angle, the mining influence area of the gully is divided into an influence-free area, an influence area and a strong influence area; the determination of the position of a stop line of gully-avoiding mining and the arrangement of a working surface of gully-along mining are based on the following principles: during the gully-avoiding mining, the position of the stop line is positioned out of the strong influence area; during the gully-along mining, the boundary position, close to one side of the gully, of the working surface is in the area where the overburden rock height is more than the fissure area height. The method involves few calculation parameters, facilitates field implementation, has high safety, and can be widely applied to large-scale safe mining of the shallow coal seam below the gully.

Description

Slow down shallow buried coal seam broadwall ore deposit under coombe and press the method manifesting
Technical field
The invention belongs to Mineral Engineering field, be specifically related to slow down shallow buried coal seam broadwall ore deposit under coombe and press the method manifesting.
Background technology
Along with the continuous enforcement of China's development of the West Regions state basic policy, the developing focus of coal resources in China has started to shift to western part.Compare with southwestern coalfield, coalfield, northwest surface vegetation is sparse, water and soil conservation ability is weak, earth's surface water erosion serious, coombe in length and breadth, slope body occurrence changes greatly, landform is incoherent, relative relief has more than 100 meters, mostly is coombe development area.The adverse effect that surface relief produces seam mining is confirmed by increasing theoretical research and engineering practice.For example, in old mine coal column removal process, repeatedly there is the unexpected unstable phenomenon of irregular coal column in the safe group of Inner Mongol gouy, causes large area roof fall; In the progradation of new mine coal wall, stope can be pressed suddenly, and intensity surpasses old top first weighting, then advances after certain distance, returns to normal again, and theoretical unaccountable phenomenon is pressed in these conventional ore deposits, all relevant with Coal Face Passing Through earth's surface coombe.Under coombe during shallow buried coal seam broadwall, for a series of ore deposits such as hydraulic support pushed down, coal wall caving are serious, press and manifest abnormal phenomenon, there is the problem of poor stability, high cost in existing technical measures, has a strong impact on the safety in production of mine.
Summary of the invention
In order to solve shallow buried coal seam broadwall ore deposit pressure under coombe, manifest abnormal problem, the present invention proposes and slow down the method that under coombe, shallow buried coal seam broadwall ore deposit pressure manifests, the method is convenient to practical operation, can be widely used in the extensive safe working of coal resources under coombe.
For achieving the above object, the present invention adopts following technical scheme: while carrying out shallow buried coal seam broadwall in coombe development area, earth's surface coombe developmental state is considered as an important factor in order.According to mining effect angle and the disrumpent feelings angle of overlying strata, coombe is divided into without influence area, influence area and strong effect district the influence area of exploitation.When exploiting deployment, for reducing or avoiding the body activity of coombe slope on the impact of exploiting, by changing work plane the position of terminal mining line and adjusting advance of the face direction, avoid coombe exploitation (keeping away ditch exploitation) or move towards exploitation (along ditch exploitation) along coombe.Keep away the determining with arrange along ditch exploitation work plane should be according to following principle of ditch exploitation the position of terminal mining line: while keeping away ditch exploitation, work plane the position of terminal mining line should be positioned at outside coombe strong effect district; While exploiting along ditch, the boundary position of nearly ditch one side of work plane should be within overlying strata height be greater than the region of fissure zone height.
The present invention slows down the beneficial effect of pressure process for show in shallow buried coal seam broadwall ore deposit under coombe:
(1) can effectively slow down under coombe shallow buried coal seam broadwall ore deposit and press and manifest the impacts such as the hydraulic support pushed down, the coal wall caving that extremely cause be serious, ensure the safe working of mine;
(2) make up the deficiency of shallow buried coal seam broadwall method under current coombe;
(3) the method applicability is strong, easy to implement, can improve to greatest extent the rate of recovery of coal resources.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, embodiments of the present invention are further described:
Accompanying drawing is the schematic diagram that the present invention slows down pressure process for show in shallow buried coal seam broadwall ore deposit under coombe.
In figure: 1-keeps away ditch exploitation work plane and stops adopting position, and 2-exploits nearly ditch side work plane boundary position along ditch, top, 3-coombe slope, the line of demarcation in 4-influence area and strong effect district, I-is without influence area, II-influence area, III-strong effect district, δ-mining effect angle,
Figure BSA00000786303200021
-overlying strata are disrumpent feelings angle, the fissure zone height of h-position 2 correspondences, the overlying strata height of H-position 2 correspondences.
The specific embodiment
When exploiting deployment, for reducing or avoiding the impact of coombe slope body activity on exploitation, by changing work plane the position of terminal mining line and adjusting advance of the face direction, realization keeps away ditch and exploits or exploit along ditch.
With reference to accompanying drawing, keep away ditch when exploitation, according to mining effect angle (δ), overlying strata are disrumpent feelings angle
Figure BSA00000786303200022
coombe is divided into without influence area (I), influence area (II) and strong effect district (III) the influence area of exploitation.Mining effect angle (δ) and the disrumpent feelings angle of overlying strata
Figure BSA00000786303200023
can consult and obtain by the field data in each mining area.When top, coombe slope (3) is subject to mining influence, the line of demarcation of work plane Ji Wu influence area, residing position (I) and influence area (II); By top, coombe slope (3), do the disrumpent feelings angle of overlying strata
Figure BSA00000786303200024
, corresponding position (4) is the line of demarcation of influence area (II) and strong effect district (III).Work plane the position of terminal mining line (1) should be positioned at outside coombe strong effect district (III).While exploiting along ditch, the boundary position (2) of nearly ditch one side of work plane should be within overlying strata height (H) be greater than the region of fissure zone height (h).Overlying strata height (H) can obtain by consulting the borehole data in mining area.The feature that while considering shallow buried coal seam broadwall under the body of coombe slope, fissure zone is grown, in conjunction with UDEC numerical result, laboratory results of Physical and coombe, grow the field measurement data (10~14 times that fissure zone height is mining height) of mining area shallow buried coal seam broadwall, the design formulas of fissure zone height (h): h=10.9M+10.62 while obtaining shallow buried coal seam broadwall under the body of coombe slope.
In formula: h-fissure zone height, m.
M-mining height, m.

Claims (3)

1. the present invention slows down the method that under coombe, shallow buried coal seam broadwall ore deposit pressure manifests, it is characterized in that: when exploiting deployment, for reducing or avoiding the impact of coombe on exploitation, by changing work plane the position of terminal mining line and adjusting advance of the face direction, realize and keep away ditch exploitation or exploit along ditch.
2. according to claim 1ly slow down shallow buried coal seam broadwall ore deposit under coombe and press the method manifesting, it is characterized in that: while keeping away ditch exploitation, according to mining effect angle (δ), overlying strata are disrumpent feelings angle
Figure FSA00000786303100011
coombe is divided into without influence area (I), influence area (II) and strong effect district (III) the influence area of exploitation.Work plane the position of terminal mining line (1) should be positioned at outside coombe strong effect district (III).
3. according to claim 1ly slow down shallow buried coal seam broadwall ore deposit under coombe and press the method manifesting, it is characterized in that: while exploiting along ditch, the boundary position (2) of nearly ditch one side of work plane should be within overlying strata height (H) be greater than the region of fissure zone height (h).
CN201210378536.8A 2012-09-21 2012-09-21 Under slowing down coombe, the method manifested is pressed in shallow buried coal seam broadwall ore deposit Active CN103670413B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210378536.8A CN103670413B (en) 2012-09-21 2012-09-21 Under slowing down coombe, the method manifested is pressed in shallow buried coal seam broadwall ore deposit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210378536.8A CN103670413B (en) 2012-09-21 2012-09-21 Under slowing down coombe, the method manifested is pressed in shallow buried coal seam broadwall ore deposit

Publications (2)

Publication Number Publication Date
CN103670413A true CN103670413A (en) 2014-03-26
CN103670413B CN103670413B (en) 2016-03-02

Family

ID=50309102

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210378536.8A Active CN103670413B (en) 2012-09-21 2012-09-21 Under slowing down coombe, the method manifested is pressed in shallow buried coal seam broadwall ore deposit

Country Status (1)

Country Link
CN (1) CN103670413B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115860314A (en) * 2023-02-14 2023-03-28 北京科技大学 Method and system for preventing and treating coal seam working surface impact danger based on surface gully

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4887935A (en) * 1987-12-23 1989-12-19 Bochumer Eisenhutte Heintzmann Gmbh & Co. Kg Method of controlling the movement of a longwall excavation front, especially the face or breast of a coal seam
CN101109283A (en) * 2007-08-20 2008-01-23 太原理工大学 quantitative decision method for feasibility of mining above hollow
RU2341657C1 (en) * 2007-06-15 2008-12-20 Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт имени Г.В. Плеханова (технический университет)" Method of prevention of development entries in coal bed areas
CN101509378A (en) * 2008-02-17 2009-08-19 刘玉德 Shallow buried thin bedrock coal bed short wall continuous mining technology suitable condition classification method
CN102536238A (en) * 2012-01-09 2012-07-04 中国矿业大学 Mining method for large-inclined angle laminar non-coal solid mineral deposit

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4887935A (en) * 1987-12-23 1989-12-19 Bochumer Eisenhutte Heintzmann Gmbh & Co. Kg Method of controlling the movement of a longwall excavation front, especially the face or breast of a coal seam
RU2341657C1 (en) * 2007-06-15 2008-12-20 Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт имени Г.В. Плеханова (технический университет)" Method of prevention of development entries in coal bed areas
CN101109283A (en) * 2007-08-20 2008-01-23 太原理工大学 quantitative decision method for feasibility of mining above hollow
CN101509378A (en) * 2008-02-17 2009-08-19 刘玉德 Shallow buried thin bedrock coal bed short wall continuous mining technology suitable condition classification method
CN102536238A (en) * 2012-01-09 2012-07-04 中国矿业大学 Mining method for large-inclined angle laminar non-coal solid mineral deposit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王旭锋: "冲沟发育矿区浅埋煤层采动坡体活动机理及其控制研究", 《中国博士学位论文全文数据库工程科技Ⅰ辑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115860314A (en) * 2023-02-14 2023-03-28 北京科技大学 Method and system for preventing and treating coal seam working surface impact danger based on surface gully

Also Published As

Publication number Publication date
CN103670413B (en) 2016-03-02

Similar Documents

Publication Publication Date Title
AU2019376347B2 (en) A method for coal mining based on frozen aquifer for underground longwall face under water-conservation condition
CN104389606B (en) A kind of mine reduction-type based on environmental protection many well connection mining method
CN103498696B (en) A kind of method from roadway in the roof grouting filling compacting goaf filling body
CN100560944C (en) Aquifer preventing and controlling method for coal face roof plate separation layer
CN104314570B (en) Long thick ore body Wall ore reclaims and the transitional exploitation method of open air trestle
CN103790586B (en) Long-wall overlying strata settlement coordination water-preserving coal mining method
Guo et al. Subsidence control and farmland conservation by solid backfilling mining technology
CN100560937C (en) A kind of thin basic rock shallow buried coal seam longwall face water retaining exploitation method
CN104775816B (en) Isolated grouting-filling mining method for overburden rock without village migration under cut-side local pressed-coal conditions
CN104074541A (en) Solid filling mining design method under water body
CN102913280B (en) Method for draining roof water in flood mine
CN104314610A (en) Coal road stripe region burst-preventing method
CN103422469A (en) Artificial retaining dam for coal mine underground reservoir and connecting method of artificial retaining dam and coal pillar dam bodies as well as surrounding rocks
AU2016370451A1 (en) Method for determining length of filling section of fully mechanized coal mining-filling mixed mining working face
CN103758560A (en) Method for gas treatment in multiple progressive protection seam grouping regions
Wang et al. Mechanism of mining-induced slope movement for gullies overlaying shallow coal seams
CN104504180A (en) Method for classifying damages by water during loess gully runoff mining
CN103557001B (en) A kind of low section high oper cylinler shrink afterwards filling mining method
CN104141506A (en) Mine pressure control method of intense mine pressure appearance fully mechanized top coal caving face
CN115749776A (en) Coal pillar recovery method based on fault grouting transformation
CN103670413B (en) Under slowing down coombe, the method manifested is pressed in shallow buried coal seam broadwall ore deposit
CN103557029A (en) Method for transition from non-pillar sublevel caving method to upward horizontal cut-and-fill method
CN107780937A (en) Based on the filling mining method in exploitation of mineral resources
CN103147758A (en) Coal mining rate control method matching with isolated grouting filling of mining overburden zone
CN204163730U (en) Slurry shield Slurry treatment system mud pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant