CN103669424A CN201310708034.1A CN201310708034A CN103669424A CN 103669424 A CN103669424 A CN 103669424A CN 201310708034 A CN201310708034 A CN 201310708034A CN 103669424 A CN103669424 A CN 103669424A
Authority
CN
China
Prior art keywords
basement
building
waterproof
groove
building basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310708034.1A
Other languages
Chinese (zh)
Other versions
CN103669424B (en
Inventor
王立群
王烨
李建伟
管盈铭
李正君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huajian Construction Co Ltd
Original Assignee
Jiangsu Huajian Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huajian Construction Co Ltd filed Critical Jiangsu Huajian Construction Co Ltd
Priority to CN201310708034.1A priority Critical patent/CN103669424B/en
Publication of CN103669424A publication Critical patent/CN103669424A/en
Application granted granted Critical
Publication of CN103669424B publication Critical patent/CN103669424B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to a building basement waterproof method and a building basement waterproof structure which has the underground waterproof function and is suitable for a closed underground structure formed through a basement floor and a reinforced concrete wall on the lower portion of the basement floor, and belongs to the field of waterproof technology of building underground engineering. To guarantee that the building underground engineering meets the waterproof performance, the construction technology of storing part of air under the basement floor through the structure sealing performance is utilized, the basement floor is effectively isolated from underground water based on the air pressure balancing principle through the technology, and therefore the waterproof effect is achieved. The building basement waterproof method and the building basement waterproof system can meet the functional requirements for the underground engineering waterproofing, seepage resisting and corrosion preventing and the like, and have the advantages that the structure is simple, construction is convenient and engineering cost is saved. Meanwhile, cost is greatly saved, and economic benefits are obvious.

Description

Building basement waterproof method and structure thereof
Technical field
The present invention relates to a kind of building basement waterproof method and structure thereof, have underground waterproof function, the reinforced concrete wall that is applicable to basement bottom board and its underpart forms the subsurface structure of enclosed construction, belongs to the waterproof technique field of building underground construction.
Background technology
In some building underground engineering construction, the restriction that basement bottom board waterproof is subject to the reasons such as geological conditions, Structural Tectonics, execution conditions and economy is not easy to carry out outer subsides coiled material construction,
For guaranteeing that building underground construction meets water resistance, invented a kind of constructing technology that utilizes structure airtight performance storage part air under basement bottom board, this technology utilizes atmospheric pressure equilibrium principle that basement floor and underground water are effectively isolated, thereby reaches waterproof effect.This invention not only meets underground project waterproof, the functional requirement such as impervious, anticorrosion, and has advantages of simple structure, easy construction, saving engineering cost.
Summary of the invention
The object of this invention is to provide a kind of building basement waterproof method and structure thereof, for not doing the situation of waterproof coiled material on basement bed course because of odjective cause, propose the constructure scheme of a kind of rational in infrastructure, easy construction, economy.
The object of the invention is to be achieved through the following technical solutions, a kind of building basement waterproof method, it is characterized in that, described method is under the base plate of basement, to construct the confined space of storing air, utilize the air balance groundwater pressure in confined space, stop underground water upwards to enter basement bottom board.
Realize the structure of building basement waterproof method, comprise body of wall and the base plate of basement, the foundation ditch under base plate, it is characterized in that, near constructing some grooves of vertical and horizontal in the plain earth foundation plane in the foundation ditch of base plate, the notch capping of groove, is concrete cushion between each groove and base plate.
The degree of depth of described groove and width are 28-32cm, and the spacing of each groove is 1.9-2.1m.
Described flute surfaces is amassed and accounted for the foundation ditch gross area is 19-21%.
Described groove notch adopts template capping, and template both sides width exceeds groove 15cm suitable for reading, and the split joint of capping is tight.
The thickness of described concrete cushion is not less than 100mm.
The present invention meets water resistance for guaranteeing building underground construction, utilizes the constructing technology of structure airtight performance storage part air under basement bottom board, and this technology utilizes atmospheric pressure equilibrium principle that basement floor and underground water are effectively isolated, thereby reaches waterproof effect.The present invention not only meets underground project waterproof, the functional requirement such as impervious, anticorrosion, and has advantages of simple structure, easy construction, saving engineering cost.Greatly save cost, economic benefit is obvious simultaneously.
Accompanying drawing explanation
Fig. 1 is the structural representation of one embodiment of the invention;
Fig. 2 is the local structure for amplifying schematic diagram in Fig. 1;
In figure, 1 basement, 2 base plates, 3 bed courses, 4 grooves, 5 foundation ditches, 6 element soil, 7 templates.
The specific embodiment
Further illustrate in conjunction with the accompanying drawings and embodiments the present invention.The method of the invention is to construct at the base plate of basement 1 confined space of storing air for 2 times, utilizes the air balance groundwater pressure in confined space, stops underground water upwards to enter basement 1 base plate 2.
Realize the present embodiment storage air method structure as shown in Figure 1 and Figure 2, direction in length and breadth along basic plane, when foundation ditch 5 element soil 6 rammers are filled out, base plate 2 across in≤1m is with external position, in native 6 planes of element, excavate groined type groove 4, the degree of depth and the width of groove 4 are 30cm, along foundation ditch 5 planes, arrange together the every 2m of direction left and right in length and breadth.Whole foundation ditch 5 planes form a groined type plane that groove is crisscross, and as shown in Figure 1, then in groined type groove 4 covering template 7 suitable for reading, template 7 both sides width exceed groove 15cm suitable for reading, and capping template 7 split joints are tight, prevent that concrete from pouring into.After whole foundation ditch 5 cappings complete into rammer, foundation ditch 5 as shown in Figure 2, is finally built bed course 3 concrete.The degree of depth of groove and width are 28-32cm, and the spacing of each groove is 1.9-2.1m, and flute surfaces is amassed and accounted for the foundation ditch gross area is 19-21%, and the thickness of concrete cushion is not less than 100mm.
It is simple, easy to operate that foundation ditch after the technical finesse of the present embodiment utilization storage air method underground waterproof has technique, waterproof, impervious successful, and cost is lower, and techno-economic effect is obvious.

Claims (6)

1. a building basement waterproof method, is characterized in that, described method is under the base plate of basement, to construct the confined space of storing air, utilizes the air balance groundwater pressure in confined space, stops underground water upwards to enter basement bottom board.
2. realize the structure of building basement waterproof method described in claim 1, the body of wall and the base plate that comprise basement, foundation ditch under base plate, it is characterized in that, near constructing some grooves of vertical and horizontal in the plain earth foundation plane in the foundation ditch of base plate, the notch capping of groove is concrete cushion between each groove and base plate.
3. the structure of building basement waterproof method according to claim 2, is characterized in that, the degree of depth of described groove and width are 28-32cm, and the spacing of each groove is 1.9-2.1m.
4. according to the structure of building basement waterproof method described in claim 2 or 3, it is characterized in that the long-pending 19-21% that accounts for the foundation ditch gross area of described flute surfaces.
5. according to the structure of building basement waterproof method described in claim 2 or 3, it is characterized in that, described groove notch adopts template capping, and template both sides width exceeds groove 15cm suitable for reading, and the split joint of capping is tight.
6. the structure of building basement waterproof method according to claim 2, is characterized in that, the thickness of described concrete cushion is not less than 100mm.
CN201310708034.1A 2013-12-20 2013-12-20 Building basement waterproof construction Active CN103669424B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310708034.1A CN103669424B (en) 2013-12-20 2013-12-20 Building basement waterproof construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310708034.1A CN103669424B (en) 2013-12-20 2013-12-20 Building basement waterproof construction

Publications (2)

Publication Number Publication Date
CN103669424A true CN103669424A (en) 2014-03-26
CN103669424B CN103669424B (en) 2015-12-09

Family

ID=50308138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310708034.1A Active CN103669424B (en) 2013-12-20 2013-12-20 Building basement waterproof construction

Country Status (1)

Country Link
CN (1) CN103669424B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0539620A (en) * 1991-08-07 1993-02-19 Takenaka Komuten Co Ltd Cut-off method and structure using pneumatics for underground construction
CN101705691A (en) * 2009-10-30 2010-05-12 南通建工集团股份有限公司 Construction method of dewatering well under foundation slab in foundation pit
CN201593203U (en) * 2010-01-25 2010-09-29 江苏双楼建设集团有限公司 Hiddenly-distributed seepage-proof water guiding system of baseboard of basement
CN103410175A (en) * 2013-08-05 2013-11-27 中铁十二局集团有限公司 Water seepage control construction method for karst water-rich geological underground structure waterproof construction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0539620A (en) * 1991-08-07 1993-02-19 Takenaka Komuten Co Ltd Cut-off method and structure using pneumatics for underground construction
CN101705691A (en) * 2009-10-30 2010-05-12 南通建工集团股份有限公司 Construction method of dewatering well under foundation slab in foundation pit
CN201593203U (en) * 2010-01-25 2010-09-29 江苏双楼建设集团有限公司 Hiddenly-distributed seepage-proof water guiding system of baseboard of basement
CN103410175A (en) * 2013-08-05 2013-11-27 中铁十二局集团有限公司 Water seepage control construction method for karst water-rich geological underground structure waterproof construction

Also Published As

Publication number Publication date
CN103669424B (en) 2015-12-09

Similar Documents

Publication Publication Date Title
CN104099943B (en) Diaphram wall and discarded underground civil defense engineering intersection processing method
CN204023501U (en) A remove dangerous and consolidate prevention of seepage processing structure for earth and rockfill dam
CN103669375A (en) Double-layer steel sheet pile soil core composite cofferdam structure without inner support and application thereof
CN203755341U (en) Geogrid retaining wall
CN203161244U (en) Existing subway underground excavation running tunnel protection structure
CN202851027U (en) Support system treating soft rock roadway floor heaves
CN203729306U (en) Anti-slide pile and soil retaining plate supporting structure
CN206157670U (en) Asphalt concrete seepage prevention structure
CN1804239A (en) Construction method for deformation resistant building foundation in subsidence area
CN102797265A (en) Protective structure for bedding slope bridge piers and abutments
CN202100263U (en) High-backfill open cut tunnel lining structure of high-intensity swelled ground region
CN203654330U (en) Building basement waterproof structure
CN105256811A (en) Sheet pile supporting structure with water stopping function and construction method
CN202830994U (en) Protective structure for bedding slope bridge abutments
CN203808101U (en) Reinforced earth retaining wall with concrete panel
CN201372439Y (en) Single-wall and double-wall combined steel cofferdam
CN103669424B (en) Building basement waterproof construction
CN102839689A (en) Large-deformation-adaptable water stop for use between sluice bottom and deep overburden layer foundation cutoff wall top, and construction method
CN205000296U (en) Use concrete panel structure of high toe wall
CN205012351U (en) Arcading formula sheet pile supporting construction
CN202557760U (en) Double-wall cast-in-situ bored pile high pile cap dock wall structure
CN202598918U (en) Buried heat storage container
CN205314057U (en) Concrete seepage -proofing panel reconsitution dam heel apron stagnant water structure
CN206035047U (en) Prefabricated assembled underground granary of plastic cover
CN207131405U (en) Deep cheuch cut-and-cover tunnel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model