Prior art keywords
water stop
preformed hole
junction
pile cap
pile foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210324616.5A
Other languages
Chinese (zh)
Inventor
颜可仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201210324616.5A priority Critical patent/CN103669415A/en
Publication of CN103669415A publication Critical patent/CN103669415A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

At present, construction of cross-sea bridges is in the industrialized production stage, however, due to the fact that water stop at the junction between a preformed hole of a prefabricated pile cap and a pile foundation is not achieved effectively, the industrialized progress of the bridges is hindered. The invention provides a method for water stop construction at the junction between the preformed hole of the prefabricated pile cap and the pile foundation. The method for the water stop construction at the junction between the preformed hole of the prefabricated pile cap and the pile foundation aims to achieve the water stop at the junction between the preformed hole of the prefabricated pile cap and the pile foundation. According to the method for the water stop construction at the junction between the preformed hole of the prefabricated pile cap and the pile foundation, an upper movable flange ring and a lower movable flange ring are arranged in the preformed hole of the prefabricated pile cap, the distance between the upper movable flange ring and the lower movable flange ring is about 40cm, the upper movable flange ring and the lower movable flange ring are respectively provided with a water stop rubber belt, a grouting pipe and a grout outlet pipe are pre-buried in the middle, high-pressure water is pressed into the grouting pipe continuously before the pile cap enters sludge so that the sludge can be prevented from entering an grouting area, and the grouting pipe is filled with water stop materials immediately after the pile cap is in place.

Description

Prefabricated cushion cap preformed hole and pile foundation junction water stop construction method
Technical field
The present invention relates to a kind of bridge prefabrication cushion cap preformed hole and pile foundation junction water stop construction method.
Technical background
The construction of bridge spanning the sea has at present entered the batch production production phase, and the sealing problem of prefabricated cushion cap preformed hole and pile foundation joining place not yet effectively solves, and has hindered the process of bridge girder plant.
Summary of the invention
The sealing problem being connected with pile foundation for solving prefabricated cushion cap preformed hole, the invention provides a kind of bridge prefabrication cushion cap preformed hole and pile foundation junction water stop construction method.
The technical solution adopted for the present invention to solve the technical problems is, in prefabricated cushion cap preformed hole, establish upper and lower two interval, road 40cm left and right with the loose flange circle of watertight rubber band, middle built-in slip casting pipe and outlet pipe, before cushion cap enters mud, in Grouting Pipe, do not stop to be pressed into water under high pressure, to prevent that mud from entering slip casting district, after cushion cap is in place, in Grouting Pipe, inject immediately sealing material (band fibrous cement paste).
The invention has the beneficial effects as follows, reliable construction quality, stagnant water effect is good.
Accompanying drawing explanation
Fig. 1 is prefabricated cushion cap preformed hole and pile foundation junction water stop construction method plan view
Fig. 2 is prefabricated cushion cap preformed hole and pile foundation junction water stop construction method sectional drawing
In figure: 1. prefabricated reinforced concrete cushion cap; 2. two after date pouring concretes; 3. pile foundation; 4. descend antipriming; 5. go up antipriming; 6. Grouting Pipe; 7. outlet pipe; 8. slip casting district.
Specific implementation method
In Fig. 2, lower antipriming (4), upper antipriming (5) are fixed on cage of reinforcement when prefabricated reinforced concrete cushion cap (1) is prefabricated, Grouting Pipe (6) outlet pipe (7) is installed simultaneously, build prefabricated reinforced concrete cushion cap (1), prefabricated reinforced concrete cushion cap (1) is arranged in pile foundation (3), then in Grouting Pipe (6), waterproofing materials (band fibrous cement paste) is injected to slip casting district (8) till outlet pipe (7) pulp.

Claims (1)

1. prefabricated cushion cap preformed hole and a pile foundation junction water stop construction method, is characterized in that: in prefabricated cushion cap preformed hole, establish upper and lower two road antiprimings, establish Grouting Pipe and inject sealing material between Er road antipriming.
CN201210324616.5A 2012-08-29 2012-08-29 Method for water stop construction at junction between preformed hole of prefabricated pile cap and pile foundation Pending CN103669415A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210324616.5A CN103669415A (en) 2012-08-29 2012-08-29 Method for water stop construction at junction between preformed hole of prefabricated pile cap and pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210324616.5A CN103669415A (en) 2012-08-29 2012-08-29 Method for water stop construction at junction between preformed hole of prefabricated pile cap and pile foundation

Publications (1)

Publication Number Publication Date
CN103669415A true CN103669415A (en) 2014-03-26

Family

ID=50308129

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210324616.5A Pending CN103669415A (en) 2012-08-29 2012-08-29 Method for water stop construction at junction between preformed hole of prefabricated pile cap and pile foundation

Country Status (1)

Country Link
CN (1) CN103669415A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101158161A (en) * 2007-10-19 2008-04-09 山东高速集团青岛高速公路有限公司 Underwater no-bottom closing concrete boxed cofferdam and method of use thereof
CN101260674A (en) * 2008-04-15 2008-09-10 钟爱民 Hermetic seal process for box body and pile body
CN201137151Y (en) * 2007-10-19 2008-10-22 山东高速集团青岛高速公路有限公司 Underwater bottom cover-free concrete case box
CN201512800U (en) * 2009-06-17 2010-06-23 钟爱民 Guide bell
CN102605795A (en) * 2012-04-06 2012-07-25 山东高速青岛公路有限公司 Waterproof sleeve for repairing concrete surface of water table fluctuation region and application method of waterproof sleeve

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101158161A (en) * 2007-10-19 2008-04-09 山东高速集团青岛高速公路有限公司 Underwater no-bottom closing concrete boxed cofferdam and method of use thereof
CN201137151Y (en) * 2007-10-19 2008-10-22 山东高速集团青岛高速公路有限公司 Underwater bottom cover-free concrete case box
CN101260674A (en) * 2008-04-15 2008-09-10 钟爱民 Hermetic seal process for box body and pile body
CN201512800U (en) * 2009-06-17 2010-06-23 钟爱民 Guide bell
CN102605795A (en) * 2012-04-06 2012-07-25 山东高速青岛公路有限公司 Waterproof sleeve for repairing concrete surface of water table fluctuation region and application method of waterproof sleeve

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
姜言泉等: "特大跨海桥梁水下无封底混凝土套箱关键技术", 《公路》 *

Similar Documents

Publication Publication Date Title
CN205276316U (en) Modular prefabricated piping lane
CN101831875A (en) Precast assembly process of prestressed concrete cylindrical hollow pier
CN208981531U (en) A kind of prefabricated assembled parapet connection structure
CN109083131A (en) Prefabricated draining bamboo joint pile and preparation method thereof
CN105804410A (en) Sub-cabin pressure grouting method for vertical connection of prefabricated concrete structure
CN201554493U (en) Quick water-retaining wall in mine
CN102041810B (en) Construction method for pouring dam foundation concrete in zone with centralized water gushing
CN109024870A (en) The connection structure and its construction method of assembled underground structure vertical member
CN105113660B (en) A kind of construction method for the constructional column constructed simultaneously with frame structure filling wall
CN104652417A (en) High-performance concrete corrugated sheet pile, forming die and production method for high-performance concrete corrugated sheet pile
CN203668963U (en) Double-way water blocking device at combining portion of prefabricated bearing platform reserved hole and pile foundation
CN105756100B (en) Basement post-pouring zone system and preparation method thereof
CN104032713B (en) A kind of pressure diversion tunnel composite lining concrete anti-seepage structure and construction technology thereof
CN106149877A (en) Docking structure at concrete frame structure prefabricated post and beam slab node and method
CN209040133U (en) Well-covering device for dewatering well suitable for rich groundwater region
CN104594389A (en) Post-cast strip external wall plugging structure with elastic water stoppers
CN103924676A (en) Prestressed connecting joint for concrete beam and circular steel pipe concrete column
CN203855937U (en) Composite lining concrete impervious structure of pressure water diversion tunnel
CN203514332U (en) Casing for blocking dewatering tube well of post-cast strip
CN104452746A (en) Construction method for bored pile
CN103669415A (en) Method for water stop construction at junction between preformed hole of prefabricated pile cap and pile foundation
CN102518129A (en) Post pressure-grouting pre-stressed hollow square pile and manufacturing method thereof
CN202247914U (en) Fitting-slope foundation structure for rocky slope
CN205475215U (en) Concrete pipe pile
CN205224781U (en) Cooling tower pond structure of in cold areas prestressing without bondn structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140326