CN103628502A - Method for using plastic drainage plates as hollow floor of underground engineering base plates - Google Patents
Method for using plastic drainage plates as hollow floor of underground engineering base plates Download PDFInfo
- Publication number
- CN103628502A CN103628502A CN201210298732.4A CN201210298732A CN103628502A CN 103628502 A CN103628502 A CN 103628502A CN 201210298732 A CN201210298732 A CN 201210298732A CN 103628502 A CN103628502 A CN 103628502A
- Authority
- CN
- China
- Prior art keywords
- base plate
- fulcrum
- make
- plastic
- plastic draining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000004033 plastic Substances 0.000 title claims abstract description 31
- 229920003023 plastic Polymers 0.000 title claims abstract description 31
- 238000000034 method Methods 0.000 title claims abstract description 19
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 32
- 238000010276 construction Methods 0.000 claims abstract description 28
- 239000002390 adhesive tape Substances 0.000 claims abstract description 9
- 238000004140 cleaning Methods 0.000 claims abstract description 7
- 239000002344 surface layer Substances 0.000 claims description 9
- 239000010410 layer Substances 0.000 claims description 8
- 239000011800 void material Substances 0.000 claims description 7
- 238000005192 partition Methods 0.000 claims description 4
- 239000006260 foam Substances 0.000 claims description 3
- 239000003292 glue Substances 0.000 claims description 3
- 238000012423 maintenance Methods 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 239000003351 stiffener Substances 0.000 claims description 3
- 229920000297 Rayon Polymers 0.000 claims description 2
- 238000005516 engineering process Methods 0.000 abstract description 4
- 238000009413 insulation Methods 0.000 abstract description 4
- 230000003014 reinforcing effect Effects 0.000 abstract 1
- 238000004078 waterproofing Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 2
- 241001270131 Agaricus moelleri Species 0.000 description 1
- 239000004698 Polyethylene Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- -1 polyethylene Polymers 0.000 description 1
- 229920000573 polyethylene Polymers 0.000 description 1
Images
Abstract
The invention relates to a method for using plastic drainage plates as a hollow floor of underground engineering base plates. According to the method, the plastic drainage plates are used as the hollow concrete floor of the indoor underground engineering base plates and used for drainage and moisture insulation, and thus the purpose of engineering water resistance can be achieved. The method relates to multiple items of content such as structural plane slope finding, drainage ditch and drainage plate product connection modes and construction technologies. First, a slope is found on the surface of the structural bottom plates, when the structure surface is an integral plane, leaking water enters a water collection well, and cleaning water firstly enters a drainage ditch and then enters the water collection well. The self-sticking plastic drainage plates have rolled hollow fulcrums and bonded through adhesive tape or connected in an overlapped mode, joint strips are arranged between the drainage plates and the wall, and concrete can be poured and pounded at two times or at one time in the final construction. The fulcrums of the drainage plates are made to be square, polygonal or prismatic, concave and convex reinforcing ribs are arranged on the side faces of the fulcrums, and the fulcrums can be arranged in an orthogonal row and column or crossed row and column mode.
Description
Technical field
The invention belongs to buildings waterproof scope, particularly the indoor position of underground construction base plate is done hollow concrete terrace with plastic draining board and is reached engineering waterproofing object for draining, damp proof insulation, comprises structural plane and look for slope, gutter, band drain product, connecting mode and the multinomial independent claims of construction technology in this total invention of underground construction base plate draining damp proof insulation.
Background technology
< < water-proof technology of underground projects rules > > GB50108-2008, waterproof guard be " 1, cut and cover method underground construction one-level, should select waterproof concrete and waterproofing materials together with other; 2, hidden construction process underground construction one-level, should select liner structure and a kind of waterproofing materials ".The present invention be directed to cut and cover method underground construction, this project all wants to do in addition at the chamber internal surface of structure base slab the concrete terrace that one deck 50~300mm is thick again, the present invention makes void layer exactly between deck and surface layer, can get rid of percolating water, reaches construction work permanent waterproof damp proof insulation object.
Summary of the invention
First analyze source and the drainage direction of percolating water, the percolating water of structure base slab is to flow to collecting well in the surface void layer of deck, take collecting well edge as ± 0.00 measurement total face, on structure base slab surface, to have 30~200mm high look for slope, make underground leakage water naturally flow into collecting well.
Water pipe all will be let slip in every partition wall, threshold and gutter of drainage line of stopping up, and makes current unimpeded.Also will solve the relation in ground cleaning water and gutter: when body structure surface is integral planar, the percolating water of base plate enters collecting well from void layer, ground cleaning water enters gutter and flows into collecting well; When body structure surface has recessed gutter, base plate leakage water enters gutter and collecting well from void layer, and ground cleaning water enters gutter, then enters collecting well.
The plastic draining board of the hollow fulcrum of web-like is that drum-type is produced continuously, squeezes into one~tetra-butyl adhesive tape during production, self-adhesion at normal temperatures, and the release paper slip of adhesive tape upper cover, is self-adhesion plastic draining board.Can hasp about during construction one row's fulcrum bonding or dull and stereotyped superimposed bonding; Front and back hasp one row's fulcrum of band drain, a sticky adhesive tape in the plane between fulcrum.In order to make plastics fulcrum have enough compressive strength to bear working load, fulcrum is done to squarely, polygon, prismatic, there is concavo-convex ribbed stiffener fulcrum side, and it can be quadrature housing in row that fulcrum is arranged, and can be also intersection housing in row.The connection of above plastic draining board can, without viscose glue, be also only all around hasp one row's fulcrum.
At the band drain unifying and wall joints position, in order to prevent concrete spillage, then paste plastic board or a foam lath that 30~100mm is wide, fill and lead up gap.Then be to wire-tie to water concrete surface layer, on the band drain unifying, first hollow fulcrum leveled up with concrete, after maintenance, wire-tie again, after watering whole concrete or directly wire-tiing on plastic plate, property is watered concrete surface layer again.
Accompanying drawing explanation
Fig. 1 is underground construction base arrangement sectional view.
Fig. 2 a, Fig. 2 b are underground construction base arrangement, surface layer gutter sectional view.
Fig. 3 a, Fig. 3 b, Fig. 3 c, Fig. 3 d are the bonding sectional views of self-adhesion plastic draining board left and right adhesive tape.
Fig. 4 a, 4b are front and rear fulcrum overlap joint sectional views.
Fig. 5 a, Fig. 5 b, Fig. 5 c draining board wall edge joint stitch and water concrete process sectional view
Fig. 6 is the water pipe sectional view excessively of partition wall, threshold.
Fig. 7 a, Fig. 7 b, Fig. 7 c, Fig. 7 d be plastics fulcrum, overlook, face, quadrature ranks, the ranks figure that intersects.
The specific embodiment
Fig. 1 underground construction base arrangement is analysed and observe and is seen, take the edge (4) of collecting well (2) is ± 0.00, on structure base slab surface (1), to have 30~200mm high look for slope (3), make underground leakage water naturally flow into collecting well.
Fig. 2 a body structure surface (1) is integral planar, the percolating water of base plate enters collecting well (2) from void layer (5), from gutter, (6) flow into collecting well (2) to ground cleaning water, should bury water pipe (7) in the sloping layer in gutter.Fig. 2 b works as body structure surface (1) recessed gutter (8), and base plate leakage water enters gutter (8) and collecting well (2) from void layer (5), and ground cleaning water enters gutter (8) and enters collecting well (2) again.
Fig. 3 a, Fig. 3 b, Fig. 3 c adopt polyethylene drainage plate (9), squeeze into one~tetra-adhesive tape (10) about during production to cover release liners, tear release liners left and right can hasp one row's fulcrum bonding during construction.Fig. 3 d is that left and right is dull and stereotyped superimposed bonding.
Fig. 4 a, Fig. 4 b are overlap joint one row's fulcrums before and after band drain (9), glue by hand an adhesive tape (10) when Fig. 4 a wherein constructs again.
Fig. 5 a is the band drain (9) that unifies and the position of wall joints, pastes wide plastic board or a foam lath (11) of 30~100mm and fills and leads up gap, deck surface (1), local finding slope (3).Fig. 5 b is upper at the band drain unifying (9), first by hollow for fulcrum concrete (12) level up, after maintenance, wire-tie again and water whole concrete (13).Fig. 5 c directly wire-ties (14) on plastic plate (9), and property is watered concrete surface layer (13) again.
Fig. 6 is that partition wall, threshold etc. are arranged at top, structural plan (1), let slip water pipe (7), makes current unimpeded.
Fig. 7 a, Fig. 7 b are band drain fulcrum profiles, fulcrum flat-top (15), and fulcrum side is concavo-convex ribbed stiffener.
Fig. 7 c is fulcrum quadrature ranks layout, and Fig. 7 d is fulcrum intersection column-row arrangement.
Claims (10)
1. of plastic draining board, make the method for underground construction base plate hollow terrace, to make draining space between the structural plane of base plate and concrete surface layer, it is characterized in that: take collecting well edge as ± 0.00, on structure base slab surface, to have 30~200mm high look for slope, make underground leakage water naturally flow into collecting well.
2. of plastic draining board, making the method for underground construction base plate hollow terrace, is to make draining space between the structural plane of base plate and concrete surface layer, it is characterized in that: water pipe all will be let slip in every partition wall, threshold and gutter of drainage line of stopping up, and makes current unimpeded.
3. of plastic draining board, make the method for underground construction base plate hollow terrace, to make draining space between the structural plane of base plate and concrete surface layer, it is characterized in that: when body structure surface is integral planar, the percolating water of base plate enters collecting well from void layer, ground cleaning water enters gutter and flows into collecting well.
4. of plastic draining board, making the method for underground construction base plate hollow terrace, is with web-like, to have the plastic draining board of hollow fulcrum, it is characterized in that: during production, in left and right, squeezing into one~tetra-adhesive tape, cover release liners, is self-adhesion plastic draining board.
5. according to claim 4, of plastic draining board, make the method for underground construction base plate hollow terrace, it is characterized in that: can hasp about during construction one row's fulcrum bonding or dull and stereotyped superimposed bonding; Hasp one row's fulcrum before and after band drain, a sticky adhesive tape in the plane between fulcrum.
6. of plastic draining board, making the method for underground construction base plate hollow terrace, is with web-like, to have the plastic draining board of hollow fulcrum, it is characterized in that: during construction, without viscose glue, be only all around hasp one row's fulcrum.
7. according to claim 4,5,6 of plastic draining boards, make the method for underground construction base plate hollow terrace, it is characterized in that: at the position of the band drain unifying and wall joints, paste plastic board or a foam lath that 30~100mm is wide, fill and lead up gap.
8. according to claim 4,5,6,7 of plastic draining boards, make the method for underground construction base plate hollow terrace, it is characterized in that: on the band drain unifying, first hollow fulcrum is leveled up with concrete, after maintenance, wire-tie again, water whole concrete, or after directly wire-tiing on plastic plate again property water concrete surface layer.
9. of plastic draining board, make the method for underground construction base plate hollow terrace, relate to raising band drain and prop up compressive strength for point contact, it is characterized in that: fulcrum is done to squarely, polygon, prismatic, and there is concavo-convex ribbed stiffener side.
10. according to claim 9, of plastic draining board, make the method for underground construction base plate hollow terrace, it is characterized in that: it can be quadrature housing in row or the housing in row that intersects that fulcrum is arranged.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210298732.4A CN103628502B (en) | 2012-08-21 | 2012-08-21 | The method for doing underground engineering bottom plate hollow floor with plastic draining board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210298732.4A CN103628502B (en) | 2012-08-21 | 2012-08-21 | The method for doing underground engineering bottom plate hollow floor with plastic draining board |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103628502A true CN103628502A (en) | 2014-03-12 |
CN103628502B CN103628502B (en) | 2018-07-27 |
Family
ID=50209929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210298732.4A Active CN103628502B (en) | 2012-08-21 | 2012-08-21 | The method for doing underground engineering bottom plate hollow floor with plastic draining board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103628502B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059946A (en) * | 2017-06-20 | 2017-08-18 | 中国华西企业有限公司 | A kind of basement drain plate and its construction |
CN107700554A (en) * | 2017-09-29 | 2018-02-16 | 上海三彩科技发展有限公司 | Underground engineering hollow floor and wall, the damp proof insulation way of post |
CN108589794A (en) * | 2018-04-04 | 2018-09-28 | 上海三彩塑料排水板工程有限公司 | Leakage of underground engineering, moist repairerment method |
CN108868185A (en) * | 2018-06-30 | 2018-11-23 | 厦门防水博士建筑工程有限公司 | A kind of flooring channeling water leakage repairerment system |
CN111779039A (en) * | 2019-04-04 | 2020-10-16 | 上海三彩科技发展有限公司 | Method for pre-burying cleaning water and structure seepage water collecting observation box on basement bottom plate |
CN111851288A (en) * | 2019-04-28 | 2020-10-30 | 上海三彩科技发展有限公司 | Method for arranging seepage water collecting pit in basement bottom plate |
WO2021184399A1 (en) * | 2019-09-16 | 2021-09-23 | 邹新建 | Method for installing glass observation sheet on hollow floor in underground engineering room |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108612267B (en) * | 2018-04-04 | 2022-02-11 | 上海三彩塑料排水板工程有限公司 | Method for eliminating water pressure by using cut-off leakage water communicating pipe in roof |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0321726A (en) * | 1989-06-16 | 1991-01-30 | Toho:Kk | Spring water treating structure using block |
CN101307647A (en) * | 2008-06-06 | 2008-11-19 | 邹新建 | Injection moulding cup-shaped concrete mould and methods for using them |
CN201593203U (en) * | 2010-01-25 | 2010-09-29 | 江苏双楼建设集团有限公司 | Hiddenly-distributed seepage-proof water guiding system of baseboard of basement |
-
2012
- 2012-08-21 CN CN201210298732.4A patent/CN103628502B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0321726A (en) * | 1989-06-16 | 1991-01-30 | Toho:Kk | Spring water treating structure using block |
CN101307647A (en) * | 2008-06-06 | 2008-11-19 | 邹新建 | Injection moulding cup-shaped concrete mould and methods for using them |
CN201593203U (en) * | 2010-01-25 | 2010-09-29 | 江苏双楼建设集团有限公司 | Hiddenly-distributed seepage-proof water guiding system of baseboard of basement |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059946A (en) * | 2017-06-20 | 2017-08-18 | 中国华西企业有限公司 | A kind of basement drain plate and its construction |
CN107700554A (en) * | 2017-09-29 | 2018-02-16 | 上海三彩科技发展有限公司 | Underground engineering hollow floor and wall, the damp proof insulation way of post |
CN108589794A (en) * | 2018-04-04 | 2018-09-28 | 上海三彩塑料排水板工程有限公司 | Leakage of underground engineering, moist repairerment method |
CN108868185A (en) * | 2018-06-30 | 2018-11-23 | 厦门防水博士建筑工程有限公司 | A kind of flooring channeling water leakage repairerment system |
CN111779039A (en) * | 2019-04-04 | 2020-10-16 | 上海三彩科技发展有限公司 | Method for pre-burying cleaning water and structure seepage water collecting observation box on basement bottom plate |
CN111851288A (en) * | 2019-04-28 | 2020-10-30 | 上海三彩科技发展有限公司 | Method for arranging seepage water collecting pit in basement bottom plate |
WO2021184399A1 (en) * | 2019-09-16 | 2021-09-23 | 邹新建 | Method for installing glass observation sheet on hollow floor in underground engineering room |
Also Published As
Publication number | Publication date |
---|---|
CN103628502B (en) | 2018-07-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103628502A (en) | Method for using plastic drainage plates as hollow floor of underground engineering base plates | |
CN207775945U (en) | A kind of bridging arrangement of Novel underground room bottom plate and side wall difference waterproof material | |
CN101096850B (en) | Plastics water discharge plate application method for underground engineering wall surface | |
CN105220713B (en) | The waterproof construction of outer wall of basement subsiding crack | |
CN208792809U (en) | Basement side wall leakage repairs structure | |
CN105780940B (en) | building expansion joint anti-leakage structure | |
CN205688670U (en) | A kind of roofworks system structure | |
CN108104164A (en) | A kind of underground pipe gallery waterproof construction | |
CN112962876A (en) | Self-adhesion canned type drainage system | |
CN209066505U (en) | A kind of diaphragm wall circular construction joint waterproof construction | |
CN206448296U (en) | Protective barrier for rigid concrete structure | |
CN206085865U (en) | Waterproof roll | |
CN203247778U (en) | Novel high roof seam water resisting structure | |
CN207959270U (en) | A kind of underground pipe gallery waterproof construction | |
KR101171037B1 (en) | Method for compartmentalized tunnel waterproofing | |
CN205062857U (en) | Side wall water proof structure | |
CN207959269U (en) | A kind of waterproof slab node for underground pipe gallery | |
CN205000360U (en) | Basement structure with waterproof structure | |
CN206706843U (en) | A kind of basement induction crack structure with gutter | |
CN204356808U (en) | Basement waterproofing deformation joint | |
CN103031887B (en) | Construction method and water guide system of house bathroom water guide system | |
CN106700962A (en) | Novel waterproof coiled material | |
CN207919918U (en) | Water-proof drainage integrated board | |
CN207512792U (en) | A kind of subsiding crack water distributor of basement bottom board | |
CN103628630A (en) | Comprehensive technology and construction method of planted roof engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20191231 Address after: 201824 room 404, No. 10, Lane 1930, Cao'an Road, Jiading District, Shanghai Patentee after: SHANGHAI SANCAI TECHNOLOGY DEVELOPMENT Co.,Ltd. Address before: 200444 Shanghai city Baoshan District Fengxiang Road 128 Lane 101 Patentee before: Zou Xinjian |
|
TR01 | Transfer of patent right | ||
OL01 | Statement of open license |