CN103590595A - Detachable welding operation platform - Google Patents

Detachable welding operation platform Download PDF

Info

Publication number
CN103590595A
CN103590595A CN201310625212.4A CN201310625212A CN103590595A CN 103590595 A CN103590595 A CN 103590595A CN 201310625212 A CN201310625212 A CN 201310625212A CN 103590595 A CN103590595 A CN 103590595A
Authority
CN
China
Prior art keywords
angle steel
corner bracket
welding operation
operation platform
otic placode
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310625212.4A
Other languages
Chinese (zh)
Other versions
CN103590595B (en
Inventor
葛杰
王桂玲
陈新喜
戴耀军
沈健
苗冬梅
马荣全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201310625212.4A priority Critical patent/CN103590595B/en
Publication of CN103590595A publication Critical patent/CN103590595A/en
Application granted granted Critical
Publication of CN103590595B publication Critical patent/CN103590595B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a detachable welding operation platform. The detachable welding operation platform comprises a first supporting body, a second supporting body and a platform board, wherein the first supporting body and the second supporting body are both connected with a beam body in need of butt joint and are placed vertically, and the platform board is arranged between the first supporting body and the second supporting body in a stretching-over mode. The first supporting body and the second supporting body are formed by a first angle frame and a second angle frame in a butt-joint mode, wherein the first angle frame and the second angle frame are the same in structure. The first angle frame is in butt joint with the second angle frame, so that a supporting point is formed, and the beam body is connected with the supporting point. The detachable welding operation platform is fast and flexible to assemble, and meanwhile provides a stable hoisting butt-joint operation environment for workers. The detachable welding operation platform has the advantages of being simple in structure, safe and reliable.

Description

Detachable welding operation platform
Technical field
The present invention relates to a kind of jig system, relate in particular to a kind of detachable welding operation platform for long-span steel pipe docking.
Background technology
Current large-span steel pipe truss wants segmental hoisting, overhead connection to connect conventionally, after aerial docking, needs the end of two sections of truss to weld, and now, for ease of workman's operation, just overhead welding temporary operating platform need to be set.
The common way of overhead welding operating platform has two kinds:
Be to adopt the rod members such as reinforcing bar to weld formed reinforcing cage as an operating desk, single reinforcing cage is wherein suspended on steel pipe truss or two reinforcing cages connect the both sides that ride over steel pipe truss by rod member, and this just makes operating desk stability be difficult to guarantee;
Another kind of way is that the operating desk that reinforcing cage is formed is welded on steel pipe truss again.Although this kind of way guaranteed the stability of operating desk to a certain extent, because a large amount of welding processes can make steel pipe truss mother metal, be easy to sustain damage, and in fact, this type of operating desk is dismounting dumb also uneconomical in fact.
Lack at present and a kind ofly can guarantee the stability of operating platform own, can reduce the high-altitude operation platform that agent structure mother metal is caused to welding damage again.
Summary of the invention
For overcoming the existing defect of prior art, now provide a kind of detachable welding operation platform, in quick flexible assembling, for staff provides a stable lifting docking operation environment.Platform comprises: be connected with the two ends of the beam body of required docking respectively and the first supporter and second supporter of vertical placement; And across the landing slab being arranged between the first supporter and the second supporter.
Beneficial effect of the present invention is:
1) draw materials at any time and utilize angle steel very general in construction as support, and form the structure of similar truss;
2) can between tripod, lay fast flat board, to form platform;
3) by quick bolt, connect each assembly, avoid welding damage.
The further improvement of the detachable welding operation platform of the present invention is,
The first supporter is all mutually docked and is formed by the first identical corner bracket of structure and the second corner bracket with the second supporter;
Thereby the first corner bracket and the docking of the second corner bracket form the strong point, and the two ends of beam body are connected with the strong point.
The further improvement of the detachable welding operation platform of the present invention is,
The first corner bracket and the second corner bracket comprise respectively the first angle steel, the second angle steel and diagonal member, and are connected to form a triangle body;
The first angle steel horizontal positioned also has the first link and the second link;
The second angle steel is vertically placed and is had upper link and lower link, and the first link of lower link and the first angle steel is affixed;
The two ends of diagonal member are connected with upper link with the second link respectively.
The further improvement of the detachable welding operation platform of the present invention is,
Landing slab passes triangle body, and is placed on the first angle steel;
The two ends of the second angle steel are provided with angle steel connecting hole, and the first corner bracket is connected by angle steel connecting hole bolt with the second corner bracket.
The further improvement of the detachable welding operation platform of the present invention is,
Between the first corner bracket and the second corner bracket, by the first connection otic placode and the second engaging lug crab bolt, dock;
First connects otic placode is connected with the angle steel connecting hole of the second angle steel upper end, to form the described strong point;
Second connects otic placode is connected with the angle steel connecting hole of the second angle steel lower end;
Beam body is connected otic placode and connects with first.
The further improvement of the detachable welding operation platform of the present invention is,
The first connection otic placode is connected otic placode and is provided with the otic placode connecting hole consistent with angle steel connecting hole hole count with second.
Advantage of the present invention: simple in structure, safety and stability.
Accompanying drawing explanation
Fig. 1 is the overall structure schematic diagram of the detachable welding operation platform of the present invention;
Fig. 2 is the STRUCTURE DECOMPOSITION schematic diagram of the detachable welding operation platform of the present invention;
Fig. 3 is the supporting frame schematic diagram of the detachable welding operation platform of the present invention.
The specific embodiment
For the benefit of the understanding to structure of the present invention, describes below in conjunction with drawings and Examples.
Shown in Fig. 1, the invention provides a kind of detachable welding operation platform, in quick flexible assembling, for staff provides a stable lifting docking operation environment.Platform comprises: be vertically positioned over bottom surface supporting component 2, for supporting whole platform; And by the bottom deck assembly 3 of supporting component 2 tiling settings, on supporting component 2, fix and support the beam body 1 of required docking.
Below the comparatively preferred structure setting of the present invention:
In conjunction with shown in Fig. 1 to Fig. 3, supporting component 2 consists of two supporters 20 that are connected in beam body 1 two ends, is respectively the first supporter and the second supporter, between the first supporter and the second supporter, bottom deck assembly 30 is set, and is specially two landing slabs.
The structure of two supporters 20 is identical, is formed respectively by two corner bracket docking.Wherein, corner bracket specifically comprise horizontal positioned the first angle steel 201,, the second angle steel 202 of vertically placing and the diagonal member 203 being connected with the second angle steel with the first angle steel 201 respectively.The first angle steel 201 has the first link and the second link, and the second angle steel 202 has upper link and lower link, and lower link and the first link are affixed.Can to be that one bending is affixed form for two angle steel affixed, can be to be also previously welded.
The two ends of diagonal member 203 are connected with the upper link of the second angle steel 202 and the second link of the first angle steel 201 respectively, with this, form a triangle body.Bottom deck assembly 30, namely two landing slabs, through triangle body, and are all placed on the first angle steel.
Vertically the lower end of angle steel is provided with row's angle steel connecting hole 204, and vertically the upper end of angle steel is provided with row's angle steel connecting hole 205 equally.Between the tripod of docking, can connect by the second connection otic placode 206 bolts, also can directly carry out bolt docking.On the second connection otic placode 206, offer the otic placode connecting hole 207 consistent with angle steel connecting hole 204 hole counts.
And the beam body 1 of required lifting docking connects otic placode 10 by first in Fig. 2 and is fixedly connected on the rear formed strong point of bipod support body docking.First connects the lower end that otic placode 10 is arranged at beam body 1.
Below specific embodiment of the invention process:
With affixed two angle steel of mode of welding or bending and molding, two angle steel are mutually vertical, form the first angle steel 201 and the second angle steel 202 of Fig. 3, and weld a diagonal member 203.At the upper and lower side of the second angle steel 202, offer respectively row's angle steel connecting hole, be angle steel connecting hole 204 and angle steel connecting hole 205 in Fig. 3.Thus, form the corner bracket of two triangle body shapes.
Afterwards, first in angle steel connecting hole 204 positions of triangle support body lower end, arrange one second and connect otic placode 206, and by this second connection otic placode 206, bolt docks two corner brackets, like this, has just formed an independently supporter 20.Two parallel arranging of identical supporter 20, just form the first supporter and the second supporter in Fig. 2 again.Finally, on the supporter 20 arranging, lay landing slab 30, landing slab 30, through the triangle body in corner bracket, is stood while operating for staff.
After supporting component 2 has arranged, first affixed one first of both sides, the lower end difference at required lifting docking beam body 1 connects otic placode 10.Then, staff, on landing slab 30, connects otic placode 10 first of both sides respectively and is bolted angle steel connecting hole 205 positions in corner bracket upper end, with this, completes whole implementation process.
Below embodiment has been described in detail the present invention by reference to the accompanying drawings, and those skilled in the art can make many variations example to the present invention according to the above description.Thereby some details in embodiment should not form limitation of the invention, the present invention will be usingd scope that appended claims defines as protection domain.

Claims (6)

1. a detachable welding operation platform, is characterized in that, comprising:
The first supporter and the second supporter that are connected respectively also vertical placement with the beam body of required docking; And across the landing slab being arranged between described the first supporter and the second supporter.
2. detachable welding operation platform according to claim 1, is characterized in that:
Described the first supporter is all mutually docked and is formed by the first identical corner bracket of structure and the second corner bracket with the second supporter;
Thereby described the first corner bracket and the docking of the second corner bracket form the strong point, and described beam body is connected with the described strong point.
3. detachable welding operation platform according to claim 2, is characterized in that,
Described the first corner bracket and the second corner bracket comprise respectively the first angle steel, the second angle steel and diagonal member, and are connected to form a triangle body;
Described the first angle steel horizontal positioned also has the first link and the second link;
Described the second angle steel is vertically placed and is had upper link and lower link, and the first link of described lower link and described the first angle steel is affixed;
The two ends of described diagonal member are connected with described upper link with described the second link respectively.
4. detachable welding operation platform according to claim 3, is characterized in that:
Described landing slab passes described triangle body, and is placed on described the first angle steel;
The two ends of described the second angle steel are provided with angle steel connecting hole, and described the first corner bracket is connected by described angle steel connecting hole bolt with the second corner bracket.
5. detachable welding operation platform according to claim 4, is characterized in that:
Between described the first corner bracket and the second corner bracket, by the first connection otic placode and the second engaging lug crab bolt, dock;
Described first connects otic placode is connected with the angle steel connecting hole of the second angle steel upper end, to form the described strong point;
Described second connects otic placode is connected with the angle steel connecting hole of described the second angle steel lower end;
Described beam body is connected otic placode and connects with described first.
6. detachable welding operation platform according to claim 5, is characterized in that:
Described the first connection otic placode is connected otic placode and is all provided with the otic placode connecting hole consistent with described angle steel connecting hole hole count with second.
CN201310625212.4A 2013-11-28 2013-11-28 Detachable welding operation platform Active CN103590595B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310625212.4A CN103590595B (en) 2013-11-28 2013-11-28 Detachable welding operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310625212.4A CN103590595B (en) 2013-11-28 2013-11-28 Detachable welding operation platform

Publications (2)

Publication Number Publication Date
CN103590595A true CN103590595A (en) 2014-02-19
CN103590595B CN103590595B (en) 2015-11-18

Family

ID=50080895

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310625212.4A Active CN103590595B (en) 2013-11-28 2013-11-28 Detachable welding operation platform

Country Status (1)

Country Link
CN (1) CN103590595B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006070485A (en) * 2004-08-31 2006-03-16 Kunimoto Co Ltd Bracket for bearing scaffolding board
CN102489904A (en) * 2011-11-14 2012-06-13 铜陵市弘润机电有限责任公司 Welding support
CN102817468A (en) * 2012-08-15 2012-12-12 中建钢构有限公司 Portable detachable structural steel operating platform
CN202745352U (en) * 2012-05-24 2013-02-20 浙江精工钢结构有限公司 Combined-type high-altitude operation platform easy for assembly and disassembly
CN202954551U (en) * 2012-12-05 2013-05-29 中建六局建设发展有限公司 Simple steel reinforcement cage for high-altitude welding
CN203223003U (en) * 2013-05-08 2013-10-02 北京城建精工钢结构工程有限公司 Detachable triangular jig frame for steel truss assembling

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006070485A (en) * 2004-08-31 2006-03-16 Kunimoto Co Ltd Bracket for bearing scaffolding board
CN102489904A (en) * 2011-11-14 2012-06-13 铜陵市弘润机电有限责任公司 Welding support
CN202745352U (en) * 2012-05-24 2013-02-20 浙江精工钢结构有限公司 Combined-type high-altitude operation platform easy for assembly and disassembly
CN102817468A (en) * 2012-08-15 2012-12-12 中建钢构有限公司 Portable detachable structural steel operating platform
CN202954551U (en) * 2012-12-05 2013-05-29 中建六局建设发展有限公司 Simple steel reinforcement cage for high-altitude welding
CN203223003U (en) * 2013-05-08 2013-10-02 北京城建精工钢结构工程有限公司 Detachable triangular jig frame for steel truss assembling

Also Published As

Publication number Publication date
CN103590595B (en) 2015-11-18

Similar Documents

Publication Publication Date Title
CN103031978B (en) The auxiliary mounting system vertical for iron tower of power transmission line group and method for assembling thereof
CN203188589U (en) Rigid-frame continuous beam zero block construction bracket supporting system
CN103821376A (en) Single-layer reticulated shell structure high-altitude inclined rail accumulated slide moving construction method
CN204815441U (en) High altitude construction safety belt hangs lifeline system
CN101503908A (en) Construction method for spacing suspension cable structural template support platform
CN210289067U (en) Robot lifting operation platform
CN204023429U (en) The support system of helistop
JP6101556B2 (en) Material transfer device
CN103590595B (en) Detachable welding operation platform
CN204024084U (en) Easy unloading type triangular pipe truss just spells moulding bed
KR20140000687U (en) Stiffener jig of a ship's block or a pffshore structure's block
CN103174300B (en) Viscous damper installation construction method
CN206987351U (en) A kind of special workbench of I-beam
CN103628692B (en) A kind of floor beam mounting bracket and use it to install the method for floor beam
CN103498559A (en) Splicing movable bridge frame of steel structure industrial factory building and construction method for applying splicing movable bridge frame to roof construction
CN204002841U (en) A kind of outrigger formula mobile formwork for support of tunnel wall pouring construction
CN210266380U (en) A gallows structure based on BIM
CN206998116U (en) A kind of ship stern post welding equipment device
CN112609953A (en) A operation platform for managing truss
CN204212069U (en) A kind of building operations Hanging Basket
CN216427966U (en) Assembled steel construction landing stage
CN205350732U (en) Equipment support structure with displacement compensation function
CN205153507U (en) Silo lateral wall high altitude vestibule erection device
CN204299011U (en) The supporting construction of high-low bay floor support plate
CN204609297U (en) Large-scale high-altitude load-bearing Cantilever Beams device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant