CN103590446B CN201310563866.9A CN201310563866A CN103590446B CN 103590446 B CN103590446 B CN 103590446B CN 201310563866 A CN201310563866 A CN 201310563866A CN 103590446 B CN103590446 B CN 103590446B
Authority
CN
China
Prior art keywords
soft board
attic tank
tank
board band
hot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310563866.9A
Other languages
Chinese (zh)
Other versions
CN103590446A (en
Inventor
高天放
黄信安
陈笃行
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI OYAS NANO TECHNOLOGY Co Ltd
Original Assignee
SHANGHAI OYAS NANO TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI OYAS NANO TECHNOLOGY Co Ltd filed Critical SHANGHAI OYAS NANO TECHNOLOGY Co Ltd
Priority to CN201310563866.9A priority Critical patent/CN103590446B/en
Publication of CN103590446A publication Critical patent/CN103590446A/en
Application granted granted Critical
Publication of CN103590446B publication Critical patent/CN103590446B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a method for improving a roof tank. The method for improving the roof tank comprises the following steps that (1) a plurality of expansion bolts are installed in the tops of the inner faces of the periphery of the roof tank at intervals in a driven mode; (2) a plurality of hot melting connecting fixing blocks are installed on the inner faces of the periphery of the roof tank through the expansion bolts; (3) soft PE plate strips are cut off according to the size of the roof tank; (4) a plurality of through holes which correspond to the expansion bolts arranged on the tops of the inner faces of the periphery of the roof tank in position are formed in one end of each cut soft PE plate strip; (5) the soft PE plate strips are installed; (6) every two adjacent soft PE plate strips which are in lap joint with each other are combined together in a hot melting mode through a hot melting gun; (7) a water inlet pipe and a water outlet pipe are installed; (8) the hot-melt soft PE plate strips are connected in a lap joint mode; (9) the soft PE plate strips are fixedly connected with the hot melting connecting fixing blocks. The hygienic roof tank obtained through the method for improving the roof tank has the advantages of being short in construction period, low in cost and the like, secondary pollution cannot be caused to water in the improved roof tank, and the requirement for environmental protection is met.

Description

A kind of method that attic tank is transformed and the roof sanitary water fitting obtained thereof
Technical field
The concrete tank that the present invention relates to old-fashioned house high level carries out renovation technique field, particularly a kind of method transformed attic tank and the roof sanitary water fitting obtained thereof.
Background technology
Present attic tank, as widely used way of supplying water, has the function of " water supply ", " peak regulation " and " preemergency ".Wherein the attic tank majority in multilayer room and old-fashioned old public housing is that the brick of " black large benzene is thick " is mixed, steel and concrete structure.
At present, these bricks mix, the inner face of the attic tank of steel and concrete structure cement wall surface substantially, and easy breed bacteria, causes water pollution once again, needs periodic cleaning, otherwise water quality is difficult to reach standard.And it is comparatively large to clean hourly water consumption, the time is long, makes troubles to people's life.
In order to ensure water hygiene and the safety of resident, some city starts to transform the attic tank in multilayer room and old-fashioned old public housing at present.
At present mainly contain following several to the method for the attic tank transformation in multilayer room and old-fashioned old public housing:
1, adopt and in the inner wall surface of attic tank, paste ceramic tile method transform, this method cycle is long, brings constant to the life of people.
2, adopt install stainless steel inner container additional in attic tank, but such improvement expenses is expensive, to financial build-up of pressure.
3, adopt attic tank inner wall surface paste PVC board attic tank is transformed, its construction period is also long.
Summary of the invention
One of technical problem to be solved by this invention is a kind of method transformed concrete tank providing easy construction, cost low for the deficiency existing for above-mentioned prior art.
Two of technical problem to be solved by this invention is to provide the roof sanitary water fitting obtained after said method transformation.
Technical problem solved by the invention can realize by the following technical solutions:
To the method that attic tank is transformed, be specifically made up of following steps:
1) squeeze into some expansion bolts at the head clearance of the surrounding inner face of attic tank, the some expansion bolts squeezing into the surrounding inner face top of attic tank are positioned on same level line;
2) on the surrounding inner face of attic tank, adopt expansion bolt that some hot-melt adhesive paste fixed blocks are installed;
3) according to the size cut PE soft board band of attic tank; The length that PE soft board band intercepts can be carried out overlap joint hot melt in the bottom surface of attic tank with the PE soft board band on the opposed inner faces of attic tank and is advisable;
4) some through holes corresponding with some expansion bolt positions at the surrounding inner face top of attic tank are offered in the one end of the PE soft board band intercepted;
5) offer with PE soft board band the upper end that one end of some described through holes is PE soft board band, and make the expansion bolt at the surrounding inner face top of attic tank through after the through hole of corresponding PE soft board band one end, be pressed on the upper end of PE soft board band with the stainless steel platen offering some through holes, make the expansion bolt at the surrounding inner face top of attic tank also through the through hole on stainless steel platen simultaneously, then nut to be screwed on expansion bolt and to tighten, stainless steel platen is made tightly to be pressed in the upper end of PE soft board band on the top metope of the surrounding inner face of attic tank, the upper end of PE soft board band is made to hang on the surrounding inner face top of attic tank, finally naturally put down PE soft board band, adjacent two pieces of PE soft board bands overlap mutually,
6) use hot melt gun by adjacent two pieces of PE soft board band hot melts mutually overlapped together;
7) entering of attic tank is being corresponded to, the PE soft ribbons plate of outlet pipe position is offered into, outlet pipe is through hole, wherein enter, outlet pipe through the internal diameter in hole be less than respectively into, the external diameter of outlet pipe, to have into, outlet pipe suitably heats through the PE soft ribbons plate of hole site, limit heating edge will be entered, outlet pipe pass into, outlet pipe is through hole, owing to entering, outlet pipe through the internal diameter in hole be less than respectively into, the external diameter of outlet pipe, enter, outlet pipe pass into, outlet pipe is through in the process of hole, enter, outlet pipe forms an annular covering portion extended in attic tank through the peripheral unnecessary PE in hole, cooling after annular covering portion be tightly coated on into, on the outer wall of outlet pipe, then anchor ear is adopted this annular covering portion to be held tightly, on the outer wall of outlet pipe,
8) hot melt gun is used first by an opposing lap joint ends PE soft board band hot melt on the bottom surface of attic tank together, then by the PE soft board band hot melt of another opposing lap joint ends together; On the bottom surface of attic tank, be superimposed after the PE soft board band overlap joint hot melt that the PE soft board band extended and another opposed inner faces by attic tank extend by an opposed inner faces of attic tank;
9) use hot melt gun on described hot-melt adhesive paste fixed block, also to make PE soft board band be fastenedly connected on hot-melt adhesive paste fixed block after the cooling period the PE soft board band hot melt corresponding to this position in the position of each hot-melt adhesive paste fixed block, finally formed with PE inner water tank.
In a preferred embodiment of the invention, described hot-melt adhesive paste fixed block offers the counterbore passed for expansion bolt and the some glue holes being opened in described counterbore surrounding, and to contact with the metope of attic tank in one side at described hot-melt adhesive paste fixed block and be provided with flange, this flange makes hot-melt adhesive paste fixed block contact with the metope of attic tank and simultaneously and between the metope of attic tank forms a glue storage cavity; When after PE soft board band hot melt, the sizing material of flowing penetrates in glue storage cavity by the glue hole on hot-melt adhesive paste fixed block, makes PE soft board band be connected more firm with hot-melt adhesive paste fixed block.
In a preferred embodiment of the invention, between described PE soft board band and the metope of attic tank, arrange a drinking-water pipe, this drinking-water pipe connects a water pumper, to extract out because of the water penetrated into after the breakage of PE inner water tank in attic tank.
In a preferred embodiment of the invention, the content gauge that one extends to the bottom surface of attic tank is provided with between described PE soft board band and the metope of attic tank, this content gauge connects described water pumper by a control device, when reaching certain liquid level because of the water penetrated in attic tank after the breakage of PE inner water tank, the liquid level signal input control device that content gauge will detect, control device starts water pumper and draws water.
In a preferred embodiment of the invention, described control device can detect the time of pumping of water pumper and initiation culture, if time of pumping is long or the number of starts frequent, then PE inner water tank badly broken is described, maintenance personal keeps in repair simultaneously.
In a preferred embodiment of the invention, described control device connects host computer by wired or wireless mode.
Roof of the present invention sanitary water fitting is by the obtained roof sanitary water fitting of said method.
Owing to have employed technical scheme as above, the present invention adopts PE soft board band to transform existing attic tank, and the duration is short, and cost is low, and the water quality of improved attic tank can not form secondary pollution, meets the requirement of environmental protection.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the present invention when installing expansion bolt and hot-melt adhesive paste fixed block.
Structural representation when Fig. 2 is installation PE soft board band of the present invention.
Fig. 3 be attic tank of the present invention bottom surface on PE soft board band overlap joint structural representation.
Fig. 4 is the structural representation of the upper end of PE soft board band of the present invention when fixing.
Fig. 5 be hot-melt adhesive paste fixed block of the present invention and PE soft board band hot-melt adhesive paste time structural representation.
Fig. 6 is the structural representation after the present invention has installed inlet tube and outlet tube.
Fig. 7 is that the present invention carries out fitting structural representation when heated to the PE soft ribbons plate of inlet tube and outlet tube through hole site.
Fig. 8 is the structural representation after inlet tube and outlet tube of the present invention and PE soft ribbons plate are installed.
Fig. 9 is the structural representation after the inlet tube and outlet tube of the another kind of embodiment of the present invention and PE soft ribbons plate are installed.
Figure 10 is the structural representation after installation of the present invention.
Detailed description of the invention
The technological means realized to make the present invention, creation characteristic, reaching object and effect is easy to understand, below in conjunction with concrete diagram, setting forth the present invention further.
See a kind of roof sanitary water fitting 1000 shown in Fig. 1 to Figure 10, this roof sanitary water fitting 1000 has PE inner water tank, and it obtains on the basis of transforming attic tank 100, and concrete remodeling method is as follows:
Shown in composition graphs 1, squeeze into some expansion bolts 200 at the head clearance of the surrounding inner face of attic tank 100, the some expansion bolts 200 squeezing into the surrounding inner face top of attic tank 100 are positioned on same level line; The surrounding inner face of attic tank 100 adopt expansion bolt 220 some hot-melt adhesive paste fixed blocks 300 are installed.
Shown in composition graphs 2 to Fig. 5, the length that size cut PE soft board band 400, the PE soft board band 400 according to attic tank 100 intercepts can be carried out overlap joint hot melt in the bottom surface of attic tank 100 with the PE soft board band 400 on the opposed inner faces of attic tank 100 and is advisable.
The upper end of PE soft board band 400 offers some through hole 400as corresponding with expansion bolt 210 position.During installation, shown in Fig. 2 and Fig. 5, make the expansion bolt 200 at the surrounding inner face top of attic tank 100 through after the through hole 400a of corresponding PE soft board band 400 upper end, be pressed on the upper end of PE soft board band 400 with stainless steel platen 410, stainless steel platen 410 offers some through holes 411 passed for expansion bolt 200, make the expansion bolt 200 at the surrounding inner face top of attic tank 100 also through the through hole 411 on stainless steel platen 410, then nut 210 to be screwed on expansion bolt 200 and to tighten, stainless steel platen 410 is made tightly to be pressed in the upper end of PE soft board band 400 on the top metope of the surrounding inner face of attic tank 100, the upper end of PE soft board band 400 is hung on the surrounding inner face top of attic tank 100.
Then naturally put down PE soft board band 400, use hot melt gun by adjacent two pieces of PE soft board band 400 hot melts mutually overlapped together.Shown in Figure 3, use hot melt gun first by opposing lap joint ends PE soft board band 400 hot melt on the bottom surface of attic tank 100 together, then by PE soft board band 400 hot melt of another opposing lap joint ends together; On the bottom surface of attic tank 100, be superimposed after the PE soft board band 400 extended and the PE soft board band 400 extended by another opposed inner faces of attic tank 100 overlap hot melt by an opposed inner faces of attic tank 100.
Shown in Figure 5, hot-melt adhesive paste fixed block 300 offers the counterbore 303 passed for expansion bolt 220 and the some glue holes 301 being opened in counterbore 303 surrounding, to contact with the metope of attic tank 100 in one side at hot-melt adhesive paste fixed block 300 and be provided with flange 304, this flange 304 makes hot-melt adhesive paste fixed block 300 contact with the metope of attic tank 100 and simultaneously and between the metope of attic tank 100 forms a glue storage cavity 302.Use hot melt gun will to correspond to PE soft board band 400 hot melt of this position on hot-melt adhesive paste fixed block 300 in the position of each hot-melt adhesive paste fixed block 300, when after PE soft board band 400 hot melt, the sizing material 400b of flowing is penetrated in glue storage cavity 302 by the glue hole 301 on hot-melt adhesive paste fixed block 300, makes PE soft board band 400 be connected more firm with hot-melt adhesive paste fixed block 300.
See shown in Fig. 6 to Fig. 8, be provided with in the bottom of PE soft ribbons plate into, outlet pipe, through hole 401, enters, outlet pipe corresponds to entering bottom attic tank 100 through the position in hole 401, outlet pipe position, and enter, outlet pipe through the internal diameter in hole 401 be less than respectively into, outlet pipe 510, the external diameter of 520, utilize heater 600 to have into, outlet pipe suitably heats through the PE soft ribbons plate 400 of position, hole 401, and limit heating edge will be entered, outlet pipe 510, 520 pass into, outlet pipe passes hole 401, owing to entering, outlet pipe through the internal diameter in hole 401 be less than respectively into, outlet pipe 510, the external diameter of 520, enters, outlet pipe 510, 520 pass into, outlet pipe, through in the process of hole 401, enters, outlet pipe forms an annular covering portion 410 extended in attic tank 100 through the peripheral unnecessary PE in hole 401, after cooling annular covering portion 410 be tightly coated on into, outlet pipe 510, on the outer wall of 520, anchor ear 530 is then adopted this annular covering portion 410 to be held tightly, outlet pipe 510, on the outer wall of 520.And inlet tube and outlet tube 510,520 is metal inlet tube and outlet tube or PE inlet tube and outlet tube, as schemed can also to be trapped among hot melt one deck PE layer 540 at the outer of anchor ear 530, increase the sealing of inlet tube and outlet tube 510,520, prevent anchor ear 530 long period of soaking breed bacteria in water.
PE inner water tank has been made through above-mentioned steps.
Shown in Figure 10, one drinking-water pipe 710 is set between PE soft board band 400 and the metope of attic tank 100, the top of this drinking-water pipe 710 connects water pumper 730, bottom extends position between PE soft board band 400 and the bottom surface of attic tank 100, and between PE soft board band 400 and the metope of attic tank 100, be also provided with the content gauge 720 that extends to the bottom surface of attic tank 100, this content gauge 720 connects water pumper 730 by a control device 750, when reaching certain liquid level because of the water penetrated in attic tank 100 after the breakage of PE inner water tank, the liquid level signal input control device 750 that content gauge 730 will detect, control device 750 starts water pumper 730 and draws water.
Control device 730 connects host computer 740 by wired or wireless mode, control device 730 can detect the time of pumping of water pumper 730 and initiation culture, if time of pumping is long or the number of starts is frequent, PE inner water tank badly broken is then described, maintenance personal keeps in repair simultaneously.
By above-mentioned remodeling method, existing attic tank 100 can be transformed into the roof sanitary water fitting 1000 containing PE inner water tank, it is short that this roof sanitary water fitting 1000 transforms the duration, cost is low, the water quality of improved roof sanitary water fitting 1000 can not form secondary pollution, meets the requirement of environmental protection.
More than show and describe general principle of the present invention and principal character and advantage of the present invention.The technician of the industry should understand; the present invention is not restricted to the described embodiments; what describe in above-described embodiment and manual just illustrates principle of the present invention; without departing from the spirit and scope of the present invention; the present invention also has various changes and modifications, and these changes and improvements all fall in the claimed scope of the invention.Application claims protection domain is defined by appending claims and equivalent thereof.

Claims (6)

1. to the method that attic tank is transformed, it is characterized in that, be made up of following steps:
1) squeeze into some expansion bolts at the head clearance of the surrounding inner face of attic tank, the some expansion bolts squeezing into the surrounding inner face top of attic tank are positioned on same level line;
2) on the surrounding inner face of attic tank, adopt expansion bolt that some hot-melt adhesive paste fixed blocks are installed, described hot-melt adhesive paste fixed block offers the counterbore passed for expansion bolt and the some glue holes being opened in described counterbore surrounding, and to contact with the metope of attic tank in one side at described hot-melt adhesive paste fixed block and be provided with flange, this flange makes hot-melt adhesive paste fixed block contact with the metope of attic tank and simultaneously and between the metope of attic tank forms a glue storage cavity;
3) according to the size cut PE soft board band of attic tank; The length that PE soft board band intercepts can be carried out overlap joint hot melt in the bottom surface of attic tank with the PE soft board band on the opposed inner faces of attic tank and is advisable;
4) some through holes corresponding with some expansion bolt positions at the surrounding inner face top of attic tank are offered in the one end of the PE soft board band intercepted;
5) offer with PE soft board band the upper end that one end of some described through holes is PE soft board band, and make the expansion bolt at the surrounding inner face top of attic tank through after the through hole of corresponding PE soft board band one end, be pressed on the upper end of PE soft board band with the stainless steel platen offering some through holes, make the expansion bolt at the surrounding inner face top of attic tank also through the through hole on stainless steel platen simultaneously, then nut to be screwed on expansion bolt and to tighten, stainless steel platen is made tightly to be pressed in the upper end of PE soft board band on the top metope of the surrounding inner face of attic tank, the upper end of PE soft board band is made to hang on the surrounding inner face top of attic tank, finally naturally put down PE soft board band, adjacent two pieces of PE soft board bands overlap mutually,
6) use hot melt gun by adjacent two pieces of PE soft board band hot melts mutually overlapped together;
7) entering of attic tank is being corresponded to, the PE soft ribbons plate of outlet pipe position is offered into, outlet pipe is through hole, wherein enter, outlet pipe through the internal diameter in hole be less than respectively into, the external diameter of outlet pipe, to have into, outlet pipe suitably heats through the PE soft ribbons plate of hole site, limit heating edge will be entered, outlet pipe pass into, outlet pipe is through hole, owing to entering, outlet pipe through the internal diameter in hole be less than respectively into, the external diameter of outlet pipe, enter, outlet pipe pass into, outlet pipe is through in the process of hole, enter, outlet pipe forms an annular covering portion extended in attic tank through the peripheral unnecessary PE in hole, cooling after annular covering portion be tightly coated on into, on the outer wall of outlet pipe, then anchor ear is adopted this annular covering portion to be held tightly, on the outer wall of outlet pipe,
8) hot melt gun is used first by an opposing lap joint ends PE soft board band hot melt on the bottom surface of attic tank together, then by the PE soft board band hot melt of another opposing lap joint ends together; On the bottom surface of attic tank, be superimposed after the PE soft board band overlap joint hot melt that the PE soft board band extended and another opposed inner faces by attic tank extend by an opposed inner faces of attic tank;
9) hot melt gun is used on described hot-melt adhesive paste fixed block, also to make PE soft board band be fastenedly connected on hot-melt adhesive paste fixed block after the cooling period the PE soft board band hot melt corresponding to this position in the position of each hot-melt adhesive paste fixed block, when after PE soft board band hot melt, the sizing material of flowing penetrates in glue storage cavity by the glue hole on hot-melt adhesive paste fixed block, PE soft board band is connected with hot-melt adhesive paste fixed block more firm, is finally formed with PE inner water tank.
2. a kind of method that attic tank is transformed as claimed in claim 1, it is characterized in that, between described PE soft board band and the metope of attic tank, arrange a drinking-water pipe, this drinking-water pipe connects a water pumper, to extract out because of the water penetrated into after the breakage of PE inner water tank in attic tank.
3. a kind of method that attic tank is transformed as claimed in claim 2, it is characterized in that, the content gauge that one extends to the bottom surface of attic tank is provided with between described PE soft board band and the metope of attic tank, this content gauge connects described water pumper by a control device, when reaching certain liquid level because of the water penetrated in attic tank after the breakage of PE inner water tank, the liquid level signal input control device that content gauge will detect, control device starts water pumper and draws water.
4. a kind of method that attic tank is transformed as claimed in claim 3, it is characterized in that, described control device can detect the time of pumping of water pumper and initiation culture, if time of pumping is long or the number of starts is frequent, PE inner water tank badly broken is then described, maintenance personal keeps in repair simultaneously.
5. a kind of method transformed attic tank as claimed in claim 4, it is characterized in that, described control device connects host computer by wired or wireless mode.
6. a roof sanitary water fitting, is characterized in that by the obtained roof sanitary water fitting of claim 1 to 5 either method.
CN201310563866.9A 2013-11-14 2013-11-14 Method for improving roof tank and hygienic roof tank obtained through method Active CN103590446B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310563866.9A CN103590446B (en) 2013-11-14 2013-11-14 Method for improving roof tank and hygienic roof tank obtained through method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310563866.9A CN103590446B (en) 2013-11-14 2013-11-14 Method for improving roof tank and hygienic roof tank obtained through method

Publications (2)

Publication Number Publication Date
CN103590446A CN103590446A (en) 2014-02-19
CN103590446B true CN103590446B (en) 2015-05-13

Family

ID=50080748

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310563866.9A Active CN103590446B (en) 2013-11-14 2013-11-14 Method for improving roof tank and hygienic roof tank obtained through method

Country Status (1)

Country Link
CN (1) CN103590446B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111335408A (en) * 2020-03-13 2020-06-26 福建利河伯科技有限公司 Assembled water tank

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4595435A (en) * 1981-03-10 1986-06-17 Steuler-Industriewerke Gmbh Method for producing lining panels which are cast into concrete as an integral lining
KR20010065052A (en) * 1999-12-21 2001-07-11 고윤철 Water prevention method of a drainpipe penetration part of a water tank
CN2571687Y (en) * 2002-08-05 2003-09-10 黄平华 Concret pool, double plastics and glue corrosion-resistant liner in trough
CN101247996A (en) * 2005-04-07 2008-08-20 Sika技术股份公司 Method for lining a container and lining of a container
KR101301033B1 (en) * 2011-12-14 2013-09-12 (주) 창우텍 Elastic cover for lining of concret water tank

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090012515A (en) * 2007-07-30 2009-02-04 이남서 The waterproof structure of water tank use polyethylene sheet

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4595435A (en) * 1981-03-10 1986-06-17 Steuler-Industriewerke Gmbh Method for producing lining panels which are cast into concrete as an integral lining
KR20010065052A (en) * 1999-12-21 2001-07-11 고윤철 Water prevention method of a drainpipe penetration part of a water tank
CN2571687Y (en) * 2002-08-05 2003-09-10 黄平华 Concret pool, double plastics and glue corrosion-resistant liner in trough
CN101247996A (en) * 2005-04-07 2008-08-20 Sika技术股份公司 Method for lining a container and lining of a container
KR101301033B1 (en) * 2011-12-14 2013-09-12 (주) 창우텍 Elastic cover for lining of concret water tank

Also Published As

Publication number Publication date
CN103590446A (en) 2014-02-19

Similar Documents

Publication Publication Date Title
CN101579888B (en) Electrothermal heating maintenance device inside concrete
CN210117865U (en) Waterproof structure of electric lighting and smoke discharging skylight of colored profiled steel sheet
CN205530780U (en) Wall body door and window mouth structure
CN103696580A (en) Vertical thin-walled mass concrete spray maintenance device and method thereof
CN103437556A (en) Waterproof and heat-preservation construction method for building water supply and drainage and heating engineering
CN103590446B (en) Method for improving roof tank and hygienic roof tank obtained through method
CN209942071U (en) Flashing joint structure for steel skeleton light plate roof and parapet wall
CN109404608A (en) Water supply thin-walled stainless steel tube cartridge connection construction
CN206512866U (en) Concealed installation Fire Hose backing apparatus
CN211774666U (en) Concrete wall body induced joint construction structures
CN104328898A (en) Rendering maintenance device for building external wall
CN210032569U (en) Hanging die structure for assembled laminated slab
CN204212380U (en) A kind of external wall whitewashes curing means
CN203957093U (en) A kind of concrete cooling device
CN203213319U (en) Water stopping steel plate fixing device in building construction
CN203569633U (en) Hot melting connecting fixing blocks applied to roof hygienic water tank
CN208533383U (en) A kind of bridge water guider of restricting water supply
CN208763317U (en) Fillet Plastering trowel
CN208817577U (en) A kind of wall body structure of solar heating
CN208535348U (en) A kind of new indoor hot water pipe and its mounting structure
CN106351411B (en) The construction method and mortar of the mortar protection structure of steel plate shear force wall protect structure
CN206368459U (en) Steel building Side fascia crack stopper
CN203784476U (en) Metal tube sealing connecting structure of sanitary roof water tank
CN203569632U (en) Water tank inner container fixing structure applied to roof hygienic water tank
CN203571319U (en) Tight connection structure for PE pipes of roof sanitation water tank

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant