CN103590302B - Prefabricated Cushion-layer-free permeable ecological grassing terrace and its mould and construction method - Google Patents
Prefabricated Cushion-layer-free permeable ecological grassing terrace and its mould and construction method Download PDFInfo
- Publication number
- CN103590302B CN103590302B CN201210291764.1A CN201210291764A CN103590302B CN 103590302 B CN103590302 B CN 103590302B CN 201210291764 A CN201210291764 A CN 201210291764A CN 103590302 B CN103590302 B CN 103590302B
- Authority
- CN
- China
- Prior art keywords
- reinforcing bar
- terrace
- ecological
- arc
- coupling beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
The present invention discloses a kind of prefabricated Cushion-layer-free permeable ecological grassing terrace, mould and construction method, and this terrace is included by reinforcing bar(3)And concrete(4)The body pouring(121), body includes bar shaped and tramples body(51), coupling beam(61)And plantation hole(71);Body is linked by multiple body unit, and each body unit is trampled halfbody by four being connected by coupling beam and formed, and tramples halfbody including two major axis and two short axles trample halfbody, and two of opposite side to trample half shape identical;Plantation hole is four and tramples halfbody and coupling beam encloses the space setting;Two adjacent bar shapeds are trampled in the middle part of body all with semicircle vertical connecting hole(521), the shape identical of two adjacent body unit tramples halfbody relatively, and is connected to form body by the reinforcing bar exposing in described connecting hole.Present configuration is simple, easy to assembly, according to design size construction, makes parking lot, garden road, footpath, Entertainment Plaza etc. need the paving of hardening to reach the effect of greening.
Description
Technical field
The present invention relates to a kind of prefabricated Cushion-layer-free permeable ecological grassing terrace and its mould and construction method, more particularly, to one
Plant prefabricated ecology terrace parking lot, garden road, footpath, Entertainment Plaza etc. being needed hardening paving can afforest.
Background technology
With the fast development of China's economy, urbanization process dramatically speeds up, the expansion of city size, and urban population is swift and violent
Increase, vehicle increases rapidly, bring environmental pollution seriously, environmental quality declines, the problems such as aggravating, then expand greening
Area becomes protecting box and improves one of major measure of urban environment.
At present urban road, place paving field carry out garden road, parking lot etc. laying method varied, using relatively
Many is using brick, concrete material laying hardening, although these method hardening effects are pretty good, cannot afforest, bring on the contrary
Environmental disruption.In order to increase green coverage, people adopt grass-planting brick, Lawn planted etc., such as novel grass-planting brick(The patent No.:
03219904x), grass-planting brick(The patent No.:01204009.6), height hold cultivation grass planting land(The patent No.:200720149042.7)Deng.
Grass-planting brick be in the middle of the brick or the cavity of surrounding setting at planting plants, its low cost but cavity is little leads to vegetation to be capped rate
Low, it is hardly formed entirety between brick and brick simultaneously, be easily destroyed;Although it is high, at ground that height holds cultivation grass planting land bearing capacity
Reason sandstone used, concrete cushion make root system of plant prick deep soil under being difficult to, and the water below bed course is difficult to lead to simultaneously
Cross root system of plant and absorb formation Natural Circulation, and need substantial amounts of artificial water seasoning, while waste water resource, increase the later stage
Maintenance cost.Long-term effects are not good enough.
Content of the invention
The invention aims to overcoming the shortcomings of that above-mentioned prior art exists, provide a kind of prefabricated no bed course permeable life
State grass planting land and its mould and construction method.The present invention prefabricated ecology terrace can be connected to each other and form entirety, overcome grass planting
The deficiency of brick prose style free from parallelism structure;The present invention prefabricated ecology terrace, without sandstone, concrete cushion, overcomes high-mechanic grass planting land and plants
The deficiency of deep soil is pricked under thing root system hardly possible.The present invention prefabricated ecology floor structure is simple, and Assembling is easy to operate, permissible
According to the ecological terrace of design size construction, parking lot, garden road etc. is made to need the paving of hardening to reach the effect of greening.
For realizing the above-mentioned purpose of the present invention, provide technical scheme below.
A kind of prefabricated Cushion-layer-free permeable ecological grassing terrace, including the body by reinforcing bar and concreting, body
On include bar shaped and trample body, coupling beam and plantation hole;Described body is linked by multiple body unit, each body unit by
Four being connected by coupling beam trample halfbody composition, trample halfbody including two major axis and two short axles trample halfbody, phase
Two shapes trampling halfbody of offside are identical;Described plantation hole is four and tramples halfbody and coupling beam encloses the space setting;Phase
Two adjacent bar shapeds are trampled all with semicircle vertical connecting hole in the middle part of body, and the shape identical of two adjacent body unit is stepped on
Step on halfbody relatively, and body is connected to form by the reinforcing bar exposing in described connecting hole.
Particularly, the formation that can interlink between body is overall.The ecological terrace that multiple body one phases are formed mainly is used
The pavings such as Yu Yuanlu, parking lot.
Wherein body two ends are trampled in bar shaped is circular arc.
Particularly, body is trampled in bar shaped is in amplify foot type from top to bottom.Two adjacent described bar shapeds are trampled and are carried in the middle part of body
Semicircle vertical connecting hole.
Particularly bar shaped is trampled and is connected with coupling beam between body, and even depth of beam tramples, less than described bar shaped, the height carrying, and is
The growth of plant with avoid trampling, roll and leave space.
Wherein coupling beam width is gradually increased from top to bottom, in amplification foot type;Coupling beam is distributed in bar shaped and tramples body both sides, in eight
Font is tiltedly as arrangement.
Particularly, it is furnished with reinforcing bar in ecological terrace, reinforcing bar passes through coupling beam and bar shaped to trample in the middle part of body, reinforcing bar connects vertical
In the hole forms reinforcing bar arc ring, forms downward reinforcing bar crotch in the opposite side of vertical connecting hole.
Particularly, ecological terrace has plantation hole, and plantation hole is trampled body by bar shaped and enclosed with coupling beam and forms, horizontal cross-section by
Top to bottm it is gradually reduced.
Vegetation wherein can be planted in plantation hole, form green ecological terrace.
Particularly, after ecological terrace is built by laying bricks or stones, need connecting in the hole joints cement slurry, to protect reinforcing bar to exempt from the same of corrosion
When make that ecological terrace connects more firm.
The upper state floor structure of the present invention is to be formed by special ecological terrace mould is prefabricated, and prefabricated ecology terrace becomes
Pattern has, and including square body and two accessories, square body pours chamber, coupling beam groove, plantation foot, baffle plate, handle, steel by bar shaped
Muscle straight trough, reinforcing bar arc groove composition, two accessories are straight bolt or arc bolt.
Particularly the terrace mould bar shaped of prefabricated ecology pours chamber two ends is garden arc, is in amplify foot type from down to up;
The polygon that the bottom of described coupling beam groove encloses.This polygonal area is gradually reduced from the bottom to top, forms prism-frustum-shaped kind
Plant foot.
Wherein prefabricated ecology terrace mould plantation foot plate surface is part arc-shaped side and the side being poured bottom of chamber face by bar shaped
Side, the polygon that even base of groove encloses.This polygonal area is gradually reduced from the bottom to top, forms prism-frustum-shaped plantation
Foot.
Particularly prefabricated ecology terrace mould baffle plate five face is surrounded, a face opening, and shape such as drawer, with handle, steel
Muscle straight trough, semicolumn and reinforcing bar arc groove.
Wherein reinforcing bar arc groove is located on semicolumn, and the depth of reinforcing bar arc groove is less than the depth of reinforcing bar straight trough.
The straight bolt of particularly prefabricated ecology terrace mould is matching used component, hollow, bottom with reinforcing bar straight trough
With circular arc cutaway, top is connected and carries handle, the closure as reinforcing bar straight trough;Arc bolt is to support the use with reinforcing bar arc groove
Component, be made up of solid material, top carry handle, the closure as reinforcing bar arc groove.
The present invention prefabricated ecology method for constructing terrace, comprises the steps:
1) screwing steel bars;2)Reinforcing bar and accessory are installed;3)Casting concrete;4)Molding ecology terrace 5)Ground grading
Make side bar;7)Assembling ecology terrace 8)Backfill planting soil;9)Plantation vegetation.
The effect of wherein screwing steel bars is to make reinforcing bar cyclization, and carries two reinforcing bar crotches and two reinforcing bar arc rings.
Particularly reinforcing bar and accessory are installed, its method is that the reinforcing bar processing is put into the reinforcing bar of ecological terrace mould
In straight trough and reinforcing bar arc groove, reinforcing bar crotch correspondence is made to be placed on reinforcing bar straight trough side, reinforcing bar arc ring correspondence is placed on reinforcing bar arc groove one
Side.Then block up reinforcing bar straight trough with straight bolt seal, make ecological terrace mould not spillage;Block up reinforcing bar arc groove with arc bolt seal, make reinforcing bar
Arc groove is not blocked by concrete, in order to open mould.
Wherein pouring concrete when need vibration compacting.
Particularly, molding ecology terrace, its method is the concrete curing initial set treated in prefabricated ecology terrace mould
Afterwards, straight for accessory bolt and arc bolt are pulled up, then prefabricated ecology terrace mould is overturn 1800And slowly pull up described mould,
Make ecological terrace in described mould outer water seasoning consolidation.
Wherein ground grading is tamped, then according to setting with only need to simply flatten place to be onstructed when making side bar
Meter size makes armored concrete side bar in place surrounding.
Particularly Assembling ecology terrace, its method is by the reinforcing bar crotch of prefabricated ecology terrace and another ecological ground
The reinforcing bar arc ring on level ground links together, and connects in the hole joints cement slurry semicircle, so that prefabricated ecology terrace is connected to one another at
Formed overall together.
Wherein backfill planting soil, its method is by plantation earthen backfill in plantation hole, and backfill height is flushed with coupling beam, makes kind
Plant soil to link into an integrated entity with natural ground, in planting soil can planting plants, include tall filling grass class.
Beneficial effects of the present invention embody in the following areas:
1)The plantation hole of the present invention can plant vegetation, carries out the greening in place and road surface, has ecological afforestation benefit.
2)The bar shaped of present invention ecology terrace is trampled body top surface length and width and is designed according to the length and width meansigma methodss of people's foot, and pedestrian is not
Easily river bend foot, woman's high-heel shoes are also easy to walk, i.e. ecological Eloor Design hommization, this is compared with other grass planting lands at present
Have significantly creative.
3)The planting soil top surface of the present invention is flushed with even top surface, and top surface is trampled in coupling beam top surface and bar shaped a certain distance,
Avoid plant to be rolled trampling, leave growing space for it, ensured plant normal growth.
4)The bar shaped of present invention ecology terrace trample pass through between body coupling beam be interconnected to form overall so that ecology terrace
There is globality.Meanwhile, body is trampled in bar shaped is in amplify foot type, and includes reinforcement constitution so that ecological terrace has high-mechanic
Power and reliability that is stable, durable, being suitable for, can meet pedestrian, parking, the requirement of driving.
5)The ground of present invention ecology terrace tamped without sandstone, concreting hard bed course but using only making leveling
The natural soils processing, it is directly connected with the planting soil in ecological terrace, and vegetation root system can descend to prick wherein, and ground vapour is identical, has
Beneficial to plant long term growth, improve its vitality, reach the effect of long-term greening.This and other grass planting land sand gravels current
Or root system of plant can not prick down nature ground and compares after concrete Ground Treatment, technology has and significantly breaks through, more Ecological Effect
Benefit.
6)Present configuration design is simple, and Prefabrication state terrace can carry out factory's mass production, on-site construction operations
Simply, thus greatly improving efficiency of construction.
7)The ecological terrace plantation hole of the present invention can retain accumulation rainwater and have water penetration, and rainwater etc. can be straight from plantation hole
Connect down and ooze, it reduce the effluent pressure that rainwater is drained by drainage system by traditional hardening paving enough, the rain simultaneously retaining
Water can be contained by soil, Root Absorption, inverted evaporation, for plant provide moisture while adjusting air humidity, reduce support
Shield irrigation times, reduces cost, there is the benefit of accumulation and effectively utilizes water resource.This with use sandstone or mixed a few days ago
The grass planting land that solidifying soil processed ground can only seep water it is impossible to absorb subsoil water to have compared significantly creativeness.
Brief description
Fig. 1 a is the three-dimensional effect diagram of the present invention prefabricated ecology terrace body.
Fig. 1 b is the three-dimensional effect diagram of the present invention prefabricated ecology terrace body assembly.
Fig. 2 is the three-view diagram of the present invention prefabricated ecology terrace.
Fig. 3 is the present invention prefabricated ecology terrace coupling beam cross-sectional view.
Fig. 4 is that the present invention prefabricated ecology terrace tramples body drawing in side sectional elevation.
Fig. 5 is the vertical view audio-visual picture of invention prefabricated ecology terrace mould.
Fig. 6 be the present invention prefabricated ecology terrace mould look up audio-visual picture.
Fig. 7 is the attached view of the present invention prefabricated ecology terrace mould.
Fig. 8 is the upward view of the present invention prefabricated ecology terrace mould.
Fig. 9 is the front view of the present invention prefabricated ecology terrace mould.
Figure 10 is the side view of the present invention prefabricated ecology terrace mould.
Figure 11 is four views of the present invention prefabricated ecology straight bolt of terrace mould.
Figure 12 is four views of the present invention prefabricated ecology terrace mould arc bolt.
Figure 13 is that the present invention prefabricated ecology terrace mould is embodied as dimensional drawing.
Figure 14 is the dimensional drawing of the present invention prefabricated ecology straight bolt of terrace mould.
Figure 15 is the dimensional drawing of the present invention prefabricated ecology terrace mould arc bolt.
Figure 16 is the present invention prefabricated ecology terrace combination construction design sketch.
Figure 17 is the application effect figure of the present invention prefabricated ecology terrace.
Description of reference numerals:12- square body, 121- body;3- reinforcing bar;34- reinforcing bar straight trough;35- reinforcing bar arc groove;341-
Straight bolt;351- arc bolt;342- reinforcing bar crotch;352- reinforcing bar arc ring;36- reinforced hole;4- concrete;5- bar shaped pours chamber;51- bar
Shape tramples body;52- semicolumn;521- connecting hole;6- coupling beam groove;61- coupling beam;7- kind plants foot;71- plantation hole;9- side bar;92-
Baffle plate;93rd, 94,95- handle.
Specific embodiment
Shown in ecology terrace combination construction design sketch as prefabricated in Figure 16 present invention, the ecological terrace of the present invention includes bar shaped and steps on
Step on body 51, coupling beam 61, plantation hole 71, side bar 9.
It is in from top to bottom amplification foot type that body 51 is trampled in bar shaped, as shown in figure 4, it is circular arc that body 51 two ends are trampled in bar shaped.Even
Beam 61 is in from top to bottom amplification foot type, as shown in figure 3, coupling beam 61 height tramples the height of body 51 less than bar shaped.Coupling beam 61 and bar
Shape is trampled body 51 and is surrounded plantation hole 71.The horizontal cross-section of plantation hole 71 is from top to bottom gradually reduced.
The surrounding of the ecological terrace ragged edge of the present invention has side bar 9.The height phase of body 51 is trampled in the height of side bar 9 and bar shaped
With side bar 9 is arranged according to on-site actual situations.
Body 121 of the present invention may be combined use, and the paving such as can be used for stopping is built by laying bricks or stones, as shown in Figure 1 b.For little
The paving that area's parking is had concurrently with garden road also can use.
The top surface length and width size design that body 51 is trampled in the bar shaped of the present invention is the meansigma methodss of length and wide putting down according to people's foot
Average design, walk thereon pleasant.
In the plantation hole 71 of the present invention can planting plants, include tall filling grass class.So, the paving that can make needs hardening reaches
Afforestation Landscape effect, expands the green coverage in city.
There is inside the present invention bar construction, reinforcing bar is oblique to be staggered to form bar-mat reinforcement, body 51 is trampled by coupling beam 61, bar shaped
Center.
The concrete making of mould of the present invention can be processed for raw material by resin mould or rubber, plastics etc..
Prefabricated ecology terrace mould as Figure 13 present invention is embodied as shown in dimensional drawing, and the bar shaped of the present invention pours
The top surface length and width in chamber 5 design according to the length and width meansigma methodss of people's foot.Concrete size is as follows:
The long 33.1cm of mould of the present invention.Wide 30.1cm, high 10.8cm, Weir Plate Thickness 0.8cm.Wherein bar shaped pours chamber
Long 25.5cm, middle width 9cm, the longitudinally radius 4.5cm at two garden arc ends in 5 tops.Wherein coupling beam groove 6 thickness is 4cm, bottom width
For 6cm, top width 8cm, the wherein angle of cut in bar shaped founder chamber 5 are 420.Wherein plantation foot 7 bottom surface is eight deformation, long in top surface
17.5cm, middle width 6cm, the wide 0.24cm in end, close to zero, the widest 10.1cm, two, middle part side be radius be 5.5cm, arc length be
The indent garden segmental arc of 9.83cm, plantation foot 7 height is 10cm, and cross section is gradually reduced to top surface by bottom surface, and inclination angle is 840.Become
The plantation foot that pattern has four angles is a quarter of above-mentioned octagon terrace with edge.
Dimensional drawing and the prefabricated ecology of Figure 15 present invention as the prefabricated ecology terrace mould accessory 341 of Figure 14 present invention
Shown in the dimensional drawing of terrace mould accessory 351, the straight bolt 341 of two accessories of the present invention and arc bolt 351 are mainly distinguished
Closure as reinforcing bar straight trough 34 and reinforcing bar arc groove 35.Concrete size is as follows:The straight long 3cm of bolt 341, wide 1cm, high 3.8cm;Shape is such as
U-shaped card slot, the high 1cm of bottom notch, wide 1cm.Top carries handle, and handle is made by common cord, handle at least 1cm length.
Arc bolt 351 is made up of arc solid material, width 1cm, high 3.6cm, and section is arc, and radian is 84 ° ~ 96 °
Arc bolt is used for arc groove and blocks, arc length 3.35cm ~ 5.35cm, and top carries handle, and handle is made by common cord, facilitates peace to tear open,
Handle length at least 1cm.
The present invention prefabricated ecology terrace implementation steps are as follows:
1)Screwing steel bars 3:Make reinforcing bar cyclization, and carry two reinforcing bar crotches 341 and two reinforcing bar arc rings 351.
2)Reinforcing bar 3 and reinforcing bar crotch 342 and reinforcing bar arc ring 352 are installed:The reinforcing bar processing 3 is put into ecological terrace molding
In the reinforcing bar straight trough 34 of mould and reinforcing bar arc groove 35, reinforcing bar crotch 341 correspondence is made to be placed on reinforcing bar straight trough 34 side, reinforcing bar
Arc ring 351 correspondence is placed on reinforcing bar arc groove 35 side.Then block reinforcing bar straight trough 34 with straight bolt 341, make ecological terrace
Mould not spillage;Block reinforcing bar arc groove 35 with arc bolt 351, so that reinforcing bar arc groove is not blocked by concrete, in order to open mould.
3)Casting concrete 4:Need to be vibrated during casting concrete 4 secret room.
4)Molding ecology terrace:After the concrete 4 maintenance initial set in prefabricated ecology terrace mould, by straight bolt 341
Pull up with arc bolt 351, then prefabricated ecology terrace mould is overturn 180 ° and slowly pulls up described mould, make ecological terrace
Separate rear water seasoning consolidation with described mould.
5)Ground grading 72:Only place 72 to be onstructed simply need to be flattened and tamp.This step can be with above-mentioned steps
1)~4)Parallel carry out.
6)Make side bar(9);Make armored concrete side bar 9 according to design size in place surrounding, can basis during making
Concrete condition first makes both sides, seals up other both sides or treat that prefabricated ecology terrace all installs after installing prefabricated ecology terrace
Carry out edge sealing afterwards again.
7)Assembling ecology terrace:Reinforcing bar by the reinforcing bar crotch 342 of prefabricated ecology terrace and another ecological terrace
Arc ring 352 links together, and joints cement slurry in semicircle connecting hole 521, makes prefabricated ecology terrace be connected to one another at one
Rise and form entirety.
8)Backfill planting soil 73:Earthen backfill will be planted in plantation hole 71, backfill height is flushed with coupling beam 61, makes planting soil
73 are linked into an integrated entity with natural ground 72.
9)Plantation vegetation 74:Planting plants 74 in planting soil, it may include tall filling grass class.
Although the present invention has been described above with particularity, but the invention is not restricted to this, those skilled in the art can
Modified with the principle according to the present invention, therefore, the various modifications that all principles according to the present invention are carried out all should be understood to
Fall into protection scope of the present invention.
Claims (16)
1. a kind of prefabricated Cushion-layer-free permeable ecological grassing terrace is it is characterised in that include by reinforcing bar(3)And concrete(4)Pour
Body(121), body(121)On include bar shaped and trample body(51), coupling beam(61)And plantation hole(71);Described body
Linked by multiple body unit, each body unit is trampled halfbody by four being connected by coupling beam and formed, including
Two major axis trample halfbody and two short axles trample halfbody, and two shapes trampling halfbody of opposite side are identical;Described plantation hole
Trample halfbody for four and coupling beam encloses the space setting;Two adjacent bar shapeds are trampled and are all vertically connected with semicircle in the middle part of body
Knot hole(521), the shape identical of two adjacent body unit tramples halfbody relatively, and by exposing in described connecting hole
Reinforcing bar is connected to form body.
2. grass-planting ecological terrace as claimed in claim 1 is it is characterised in that body is trampled in described bar shaped(51)Two ends are circular arc
Shape, body is trampled in described bar shaped(51)It is in amplify foot type from top to bottom.
3. grass-planting ecological terrace as claimed in claim 1 is it is characterised in that described coupling beam(61)Height be less than described bar shaped
Trample body(51)Height;Described coupling beam(61)Width is gradually increased from top to bottom, in amplification foot type;Described coupling beam(61)Distribution
Trample body in bar shaped(51)Both sides, diagonally disposed in splayed.
4. grass-planting ecological terrace as claimed in claim 1 is it is characterised in that described reinforcing bar(3)Through described coupling beam(61)'s
Middle part;Described reinforcing bar(3)In vertical connecting hole(521)Interior formation reinforcing bar arc ring(352);Described reinforcing bar(3)In vertical connecting hole
Opposite side form downward reinforcing bar crotch(342).
5. grass-planting ecological terrace as claimed in claim 1 is it is characterised in that described plantation hole(71)Body is trampled by bar shaped(51)
With coupling beam(61)Enclose and form, horizontal cross-section is gradually reduced from top to bottom.
6. grass-planting ecological terrace as claimed in claim 4 is it is characterised in that described body unit is curved by reinforcing bar each other
Hook(342)With reinforcing bar arc ring(352)Connect and form entirety.
7. a kind of prefabricated Cushion-layer-free permeable ecological grassing terrace forming die is it is characterised in that include square body(12)With two
Individual accessory, square body(12)Chamber is poured by bar shaped(5), coupling beam groove(6), plantation foot(7), baffle plate(92), handle(93), reinforcing bar
Straight trough(34), reinforcing bar arc groove(35)Composition, two accessories are straight bolt(341)With arc bolt(351).
8. as claimed in claim 7 prefabricated Cushion-layer-free permeable ecological grassing terrace forming die it is characterised in that described bar shaped
Pour chamber(5)Two ends are circular arc, are in amplify foot type from down to up.
9. as claimed in claim 7 prefabricated Cushion-layer-free permeable ecological grassing terrace forming die it is characterised in that described coupling beam
Groove(6)Width is gradually increased from down to up, in amplification foot type;Described coupling beam groove(6)It is distributed in bar shaped and pour chamber(5)Both sides, be in
Splayed is diagonally disposed, and bar is poured chamber(5)Communicate with each other.
10. as claimed in claim 7 prefabricated Cushion-layer-free permeable ecological grassing terrace forming die it is characterised in that described kind
Plant foot(7)Bottom surface is to pour chamber by bar shaped(5)The part arc-shaped side of bottom surface and side, coupling beam groove(6)Base enclose
Polygon;This polygonal area is gradually reduced from the bottom to top, forms prism-frustum-shaped plantation foot(7).
11. as claimed in claim 7 prefabricated Cushion-layer-free permeable ecological grassing terrace forming die it is characterised in that described gear
Plate(92)Five faces enclose, a face opening, and shape such as drawer, with handle(93), reinforcing bar straight trough(34), semicolumn(52)With reinforcing bar arc
Groove(35), wherein reinforcing bar arc groove(35)Positioned at semicolumn(52)On.
12. as claimed in claim 11 prefabricated Cushion-layer-free permeable ecological grassing terrace forming die it is characterised in that described steel
Muscle arc groove(35)Depth be less than reinforcing bar straight trough(34)Depth.
13. as claimed in claim 7 prefabricated Cushion-layer-free permeable ecological grassing terrace forming die it is characterised in that described straight
Bolt(341)It is and reinforcing bar straight trough(34)Matching used component, hollow, bottom carries circular arc cutaway, and top is connected and carries
Handle(94), as reinforcing bar straight trough(34)Closure;Described arc bolt(351)It is and reinforcing bar arc groove(35)Matching used component,
It is made up of solid material, top carries handle(95), as reinforcing bar arc groove(35)Matching used component, by solid material group
Become, top carries handle(95), as reinforcing bar arc groove(35)Closure.
A kind of 14. prefabricated Cushion-layer-free permeable ecological grassing terrace construction methods are it is characterised in that comprise the steps:
Screwing steel bars(3);2)Reinforcing bar is installed(3)And straight bolt(341), arc bolt(351);3)Casting concrete(4);4)Molding is ecological
Terrace;5)Smooth floor(72);6)Make side bar(9);7)Assembling ecology terrace;8)Backfill planting soil(73);9)Plantation
Vegetation(74);
Described installation reinforcing bar(3)And straight bolt(341), arc bolt(351), its method is by the reinforcing bar processing(3)Put into ecological ground
The reinforcing bar straight trough of level ground mould(34)And reinforcing bar arc groove(35)In, then use straight bolt(341)Closure reinforcing bar straight trough(34)Use arc
Bolt(351)Closure reinforcing bar arc groove(35).
15. as claimed in claim 14 prefabricated Cushion-layer-free permeable ecological grassing terrace construction method it is characterised in that described existing
The ecological terrace of field assembling, its method is by the reinforcing bar crotch of prefabricated ecology terrace(342)Reinforcing bar arc with another ecological terrace
Ring(352)It is connected so as to be formed overall.
16. as claimed in claim 14 prefabricated Cushion-layer-free permeable ecological grassing terrace construction method it is characterised in that described time
Fill out planting soil(73), its method is by planting soil(73)Backfill is in plantation hole(71)Interior, backfill height and coupling beam(61)Flush.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210291764.1A CN103590302B (en) | 2012-08-16 | 2012-08-16 | Prefabricated Cushion-layer-free permeable ecological grassing terrace and its mould and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210291764.1A CN103590302B (en) | 2012-08-16 | 2012-08-16 | Prefabricated Cushion-layer-free permeable ecological grassing terrace and its mould and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103590302A CN103590302A (en) | 2014-02-19 |
CN103590302B true CN103590302B (en) | 2017-03-01 |
Family
ID=50080605
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210291764.1A Active CN103590302B (en) | 2012-08-16 | 2012-08-16 | Prefabricated Cushion-layer-free permeable ecological grassing terrace and its mould and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103590302B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107366208A (en) * | 2016-11-14 | 2017-11-21 | 苏州他石复合建材有限公司 | A kind of cast-in-place concrete grid mould |
CN108103889A (en) * | 2017-12-30 | 2018-06-01 | 贵州交勘生态园林有限责任公司 | A kind of greening pavement for landscape garden |
CN109940741B (en) * | 2019-04-16 | 2021-03-16 | 浙江中浩项目管理有限公司 | Construction method and construction mold for concrete grass planting parking space |
CN118238262A (en) * | 2024-05-07 | 2024-06-25 | 江苏瑞皇新型建材有限公司 | Efficient ecological grass planting terrace construction device |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2210150A (en) * | 1938-08-06 | 1940-08-06 | Notari Gennaro | Concrete block for paths, roads, and the like |
BE763880A (en) * | 1971-02-15 | 1971-08-02 | E A H Naue K G | STRINGING FOR DYKS, DAMS AND OTHER HYDRAULIC CONSTRUCTIONS |
CN2714607Y (en) * | 2004-04-02 | 2005-08-03 | 陈瑞文 | Water penetrable grass planting brick structure |
CN2808991Y (en) * | 2005-06-23 | 2006-08-23 | 武卫平 | Composite lawn brick |
CN2856122Y (en) * | 2005-11-30 | 2007-01-10 | 深圳市建筑科学研究院 | Grass planting bricks able to bury reinforced bar |
CN201036278Y (en) * | 2007-04-30 | 2008-03-19 | 北京中技引玉园林景观工程科技发展有限公司 | Grass planting terrace mould |
-
2012
- 2012-08-16 CN CN201210291764.1A patent/CN103590302B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2210150A (en) * | 1938-08-06 | 1940-08-06 | Notari Gennaro | Concrete block for paths, roads, and the like |
BE763880A (en) * | 1971-02-15 | 1971-08-02 | E A H Naue K G | STRINGING FOR DYKS, DAMS AND OTHER HYDRAULIC CONSTRUCTIONS |
CN2714607Y (en) * | 2004-04-02 | 2005-08-03 | 陈瑞文 | Water penetrable grass planting brick structure |
CN2808991Y (en) * | 2005-06-23 | 2006-08-23 | 武卫平 | Composite lawn brick |
CN2856122Y (en) * | 2005-11-30 | 2007-01-10 | 深圳市建筑科学研究院 | Grass planting bricks able to bury reinforced bar |
CN201036278Y (en) * | 2007-04-30 | 2008-03-19 | 北京中技引玉园林景观工程科技发展有限公司 | Grass planting terrace mould |
Also Published As
Publication number | Publication date |
---|---|
CN103590302A (en) | 2014-02-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106149625B (en) | A kind of ecological self-purification type landscape revetment reconstruction structure and its construction method | |
CN103590302B (en) | Prefabricated Cushion-layer-free permeable ecological grassing terrace and its mould and construction method | |
CN108589654A (en) | A kind of ecological brick and its ecological revetment system | |
CN113585296B (en) | Artificial slope assembly type flexible support ecological comprehensive treatment structure and construction method thereof | |
CN112144552A (en) | Damaged mountain ecological vegetation restoration structure, implementation method and application thereof | |
CN108755593A (en) | A kind of concrete for plant growth prefabricated components and construction method for side slope protection | |
CN105052487B (en) | The structures and methods of sports turf are built using building waste | |
CN206800113U (en) | A kind of permeable road of ecology garden landscape | |
CN212405094U (en) | High water content clay fill foundation drainage system | |
CN103590301B (en) | The construction method of Cushion-layer-free permeable ecological grassing terrace | |
CN206438465U (en) | A kind of ecological self-purification type landscape revetment reconstruction structure | |
CN108301281B (en) | Prefabricated vegetation permeable concrete pavement brick and manufacturing method thereof | |
CN207878440U (en) | A kind of reinforcement composite foundation structure suitable for soft soil foundation | |
CN109487901A (en) | A kind of the Demonstration for Ecological Sanitation trench system and construction method in sponge city | |
RU2425474C1 (en) | Method to reinforce slopes of waterlogged lands | |
CN114000510A (en) | Construction method of greening concrete on wet soil soft slope | |
CN110714479B (en) | Water-permeable gravity retaining wall structure with embedded gravel column and construction method thereof | |
JP5270748B2 (en) | Planting base structure | |
CN203188079U (en) | Water-permeable ecological grassed terrace without cushion course | |
CN208038957U (en) | A kind of tree well protective device for taking into account security protection and rainwater-collecting | |
CN105672366A (en) | Vegetation type water dispersing structure and construction method thereof | |
CN205804371U (en) | A kind of structure protecting swell-shrink characteristic ground cut slope | |
CN218405533U (en) | Water-saving greening structure for retaining wall | |
CN219305500U (en) | Light and thin tree pool capable of inhibiting roadbed damage and retaining water and soil | |
CN218779424U (en) | Ecological concrete bank protection |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |