CN103498566A - Constructing method for steel structure workshop and concrete or brick wall workshop - Google Patents
Constructing method for steel structure workshop and concrete or brick wall workshop Download PDFInfo
- Publication number
- CN103498566A CN103498566A CN201310460495.1A CN201310460495A CN103498566A CN 103498566 A CN103498566 A CN 103498566A CN 201310460495 A CN201310460495 A CN 201310460495A CN 103498566 A CN103498566 A CN 103498566A
- Authority
- CN
- China
- Prior art keywords
- steel
- factory building
- concrete
- brick wall
- supporting part
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Load-Bearing And Curtain Walls (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a constructing method for a steel structure workshop and a concrete or brick wall workshop. The constructing method is used for constructing a new workshop between the steel structure workshop and the concrete or brick wall workshop. According to the constructing method, a first steel bearing part is welded on a steel column, facing the concrete or brick wall workshop, of the steel structure workshop, a steel plate is installed on the surface, facing the steel structure workshop, of the concrete or brick wall workshop, a second steel bearing part is welded on the steel plate, and a workshop framework is built on the first steel bearing part and the second bearing part. According to the construction method, the construction method saves labor and materials to a large extend and greatly shortens construction period.
Description
Technical field
The present invention relates to a kind of job practices of between steel-structure factory building and concrete (or brick wall) factory building, building new factory building.
Background technology
In the newly-built of factory building and reconstruction, have the situation of rebuilding new factory building between steel-structure factory building and concrete (or brick wall) factory building.General job practices is to utilize original vacant lot, dig basis, concreting, build factory building, cost larger, consuming time than long, the region limitation is large.
Summary of the invention
While in order to solve, between steel-structure factory building and concrete (or brick wall) factory building, building new factory building, larger, the consuming time length of cost, the construction problem that the region limitation is large, the invention provides the job practices that a kind of steel-structure factory building and concrete (or brick wall) factory building is built, for above-mentioned situation, constructed specially, the method low cost, reliable in quality, easy for installation and quick, the region limitation is little, to steel-structure factory building and mixing of concrete (or brick wall) factory building building particularly important.
For addressing the above problem, the invention provides the job practices that a kind of steel-structure factory building and concrete factory building are built, for between steel-structure factory building and concrete factory building, building new factory building, weld respectively the first steel supporting part at steel-structure factory building on the steel post of concrete factory building, on the surface of steel-structure factory building, steel plate is installed at concrete factory building concrete wall, on steel plate, welding the second steel supporting part is built mill building frame on the first steel supporting part and the second steel supporting part.
Alternatively, the first steel supporting part and the second steel supporting part adopt i iron.
Alternatively, on the both sides of concrete wall, steel plate all is installed, the steel plate on both sides is bolted, these bolt-through concrete wall.
Alternatively, the first steel supporting part and the second steel supporting part are in equal height.
For addressing the above problem, the invention provides the job practices that a kind of steel-structure factory building and brick wall factory building are built, for between steel-structure factory building and brick wall factory building, building new factory building, weld respectively the first steel supporting part at steel-structure factory building on the steel post of brick wall factory building, on the surface of steel-structure factory building, steel plate is installed at brick wall factory building brick wall, on steel plate, welding the second steel supporting part is built mill building frame on the first steel supporting part and the second steel supporting part.
Alternatively, the first steel supporting part and the second steel supporting part adopt i iron.
Alternatively, on the both sides of brick wall, steel plate all is installed, the steel plate on both sides is bolted, this bolt-through brick wall.
Alternatively, the first steel supporting part and the second steel supporting part are in equal height.
According to the present invention, can be reduced in the cost of building new factory building between steel-structure factory building and concrete (or brick wall) factory building, reliable in quality, easy for installation and quick, shorten its engineering time, the region limitation is little.
The accompanying drawing explanation
Fig. 1 is situation sketch to be constructed the factory buildings;
Fig. 2 for arranging the schematic top plan view of braced structures according to the embodiment of the present invention on concrete (or brick wall);
Fig. 3 is for to build schematic diagram according to the mill building frame of the embodiment of the present invention.
The specific embodiment
Below, describe embodiments of the invention in detail with reference to accompanying drawing.
In Fig. 1, factory building 1 and factory building 2 are steel-structure factory building, utilize steel post 10 to support roof, and factory building 3 is the brick wall factory building, possesses the brick wall 20 for supporting roof.Wherein, steel post 10 preferably adopts i iron.As shown in Figure 1, in the newly-built of factory building and reconstruction, have the situation of rebuilding new factory building between steel-structure factory building and brick wall (or concrete) factory building, as between factory building 1 and factory building 3, built new factory building, treating in Fig. 1 constructs the factory buildings.
Referring to figs. 1 through Fig. 3, as follows according to the concrete construction method of the embodiment of the present invention:
On the left side to be constructed the factory buildings, save steel post 10 and basis, directly utilize the original steel post 10 of left side factory building (that is, the factory building 1 in Fig. 1), on steel post 10, welding the first steel supporting part 12 is as factory building support member (referring to Fig. 3).This first steel supporting part 12 preferably adopts i iron.
Waiting the right that constructs the factory buildings, on the brick wall 20 of factory building (that is, the factory building 3 in Fig. 1), braced structures is set on the right, to carry out load-bearing.Particularly, utilize puncher, positional punch as required on the brick wall 20 of original factory building, at steel plate 22 reinforcings for brick wall 20 both sides that have openning hole, the stressed (punch position of steel plate 22 on brick wall, offer isometrical bolt hole), with after bolt 21 connections fixation steel plate 22, welding the second steel supporting part 14(is referring to Fig. 2 and Fig. 3).The second steel supporting part 14 preferably adopts i iron.Symbol 23 in Fig. 2 means weld seam.
After completing above operation, on the first steel supporting part 12 and the second steel supporting part 14, build mill building frame 30(referring to Fig. 3).On the mill building frame 30 of putting up, color steel watt is installed and is got final product.
Utilize above-mentioned job practices, can use manpower and material resources sparingly to a great extent, and greatly shorten construction period.
Above, the brick wall factory building of take is described as example, but above-mentioned job practices obviously also goes for the situation of between steel-structure factory building and concrete factory building, building new factory building.Now, above-mentioned braced structures being set on the concrete wall of concrete factory building gets final product.
And, punch position, quantity and aperture on concrete wall (or brick wall), the thickness of steel plate and length and width size, the concrete welding position of the first steel supporting part and the second steel supporting part, quantity etc. can suitably be chosen as required.And steel plate can be set to the whole length across concrete wall (or brick wall), a plurality of steel plates that also can be set to be separated from each other.
And the alleged steel-structure factory building of the present invention is not limited to only utilize steel post to support the factory building on roof, as long as supported with steel post towards a side to be constructed the factory buildings, belongs to the alleged steel-structure factory building of the present invention.Similarly, brick wall (or concrete) factory building also is not limited to only utilize brick wall (or concrete) to support the factory building on roof, as long as supported towards a brick wall for side (or concrete) to be constructed the factory buildings, belong to the alleged brick wall of the present invention (or concrete) factory building.
The above; be only the preferred embodiment of the present invention, but protection scope of the present invention is not limited to this, anyly is familiar with those skilled in the art in the technical scope that the present invention discloses; the variation that can expect easily or replacement, within all should being encompassed in protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with the protection domain of described claim.
Claims (8)
1. the job practices that a steel-structure factory building and concrete factory building are built, for between steel-structure factory building and concrete factory building, building new factory building, it is characterized in that, steel-structure factory building towards welding the first steel supporting part on the steel post of concrete factory building, on the surface of steel-structure factory building, steel plate is installed at concrete factory building concrete wall, on steel plate, welding the second steel supporting part is built mill building frame on the first steel supporting part and the second steel supporting part.
2. the job practices that steel-structure factory building as claimed in claim 1 and concrete factory building are built, is characterized in that, the first steel supporting part and the second steel supporting part adopt i iron.
3. the job practices that steel-structure factory building as claimed in claim 1 or 2 and concrete factory building are built, is characterized in that, on the both sides of concrete wall, steel plate all is installed, and the steel plate on both sides is bolted, these bolt-through concrete wall.
4. the job practices that steel-structure factory building as claimed in claim 1 or 2 and concrete factory building are built, is characterized in that, the first steel supporting part and the second steel supporting part are in equal height.
5. the job practices that a steel-structure factory building and brick wall factory building are built, for between steel-structure factory building and brick wall factory building, building new factory building, it is characterized in that, steel-structure factory building towards welding the first steel supporting part on the steel post of brick wall factory building, on the surface of steel-structure factory building, steel plate is installed at brick wall factory building brick wall, on steel plate, welding the second steel supporting part is built mill building frame on the first steel supporting part and the second steel supporting part.
6. the job practices that steel-structure factory building as claimed in claim 5 and brick wall factory building are built, is characterized in that, the first steel supporting part and the second steel supporting part adopt i iron.
7. the job practices that steel-structure factory building as described as claim 5 or 6 and brick wall factory building are built, is characterized in that, on the both sides of brick wall, steel plate all is installed, and the steel plate on both sides is bolted, this bolt-through brick wall.
8. the job practices that steel-structure factory building as described as claim 5 or 6 and brick wall factory building are built, is characterized in that, the first steel supporting part and the second steel supporting part are in equal height.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310460495.1A CN103498566B (en) | 2013-09-30 | 2013-09-30 | The construction method that steel-structure factory building and concrete or brick wall factory building are built |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310460495.1A CN103498566B (en) | 2013-09-30 | 2013-09-30 | The construction method that steel-structure factory building and concrete or brick wall factory building are built |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103498566A true CN103498566A (en) | 2014-01-08 |
CN103498566B CN103498566B (en) | 2015-09-30 |
Family
ID=49863816
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310460495.1A Active CN103498566B (en) | 2013-09-30 | 2013-09-30 | The construction method that steel-structure factory building and concrete or brick wall factory building are built |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103498566B (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1730849A (en) * | 2005-09-07 | 2006-02-08 | 贵阳铝镁设计研究院 | Existing one-storied factory continuation end foundation construction method |
JP2007126910A (en) * | 2005-11-04 | 2007-05-24 | Miracle Three Corporation | Extension building |
JP2009235882A (en) * | 2008-03-28 | 2009-10-15 | Yashima Kogyo Kk | Scaffolding structure and removal method of coating using the same |
CN201588413U (en) * | 2009-12-28 | 2010-09-22 | 贵阳铝镁设计研究院 | Reinforcing structure for concrete bracket in original workshop |
-
2013
- 2013-09-30 CN CN201310460495.1A patent/CN103498566B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1730849A (en) * | 2005-09-07 | 2006-02-08 | 贵阳铝镁设计研究院 | Existing one-storied factory continuation end foundation construction method |
JP2007126910A (en) * | 2005-11-04 | 2007-05-24 | Miracle Three Corporation | Extension building |
JP2009235882A (en) * | 2008-03-28 | 2009-10-15 | Yashima Kogyo Kk | Scaffolding structure and removal method of coating using the same |
CN201588413U (en) * | 2009-12-28 | 2010-09-22 | 贵阳铝镁设计研究院 | Reinforcing structure for concrete bracket in original workshop |
Also Published As
Publication number | Publication date |
---|---|
CN103498566B (en) | 2015-09-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103243817A (en) | Fabricated beam-column connecting device | |
CN203834682U (en) | Exposed type column base with shear key | |
CN110145033B (en) | Assembled combined house structure | |
CN105780989B (en) | A kind of twin beams building cover structure | |
CN210177806U (en) | Detachable prefabricated steel-concrete combined beam | |
CN111218983A (en) | Lattice formula structure concrete frame house | |
CN104895221A (en) | Assembled profile steel confined concrete shear wall structure | |
CN106703073B (en) | Super High building hoist exempts from return back to top steel beam foundation and its construction method | |
CN204825945U (en) | A fixture for fixing buried bolt in advance | |
CN110952457A (en) | Steel plate combined beam bridge support-free cast-in-place concrete device and construction method | |
CN103498566A (en) | Constructing method for steel structure workshop and concrete or brick wall workshop | |
CN102155095A (en) | Arrangement method of steel rib concrete steel bars of large metallurgical industry factory building | |
CN105926820B (en) | Construction method for precast beam steel support plate resistance mesh combined floor | |
CN212388558U (en) | Car ramp area steel construction trades props device | |
CN211498477U (en) | Steel plate combined beam bridge structure with dismantling-free template | |
CN204225503U (en) | Large span steel truss high altitude bulk conversion beam moulding bed | |
CN204098224U (en) | Detachable concrete prefabricated wall plate structure house | |
CN102587649A (en) | Template profiled bar supporting system of high and large cantilever structure | |
CN102747737A (en) | Soil discharge platform of foundation pit structure and construction method thereof | |
CN208039004U (en) | Suitable for the UHPC prefabricated panel trestles under strong corrosive environment | |
JP6816941B2 (en) | Foundation structure of seismic isolated building | |
CN110284716A (en) | The construction method of the lifter plate node structure of steel bar truss floor support plate | |
CN204531350U (en) | A kind of operating platform | |
CN219524560U (en) | Building construction site separates storehouse with shaped steel combination formula reinforcing bar convenient to turnover | |
CN103866853B (en) | The many high-rise assembling type steel structure frame systems of a kind of industrialized modular |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |