CN103498479A - 阶梯形独立基础模板支设方法 - Google Patents

阶梯形独立基础模板支设方法 Download PDF

Info

Publication number
CN103498479A
CN103498479A CN201310486938.4A CN201310486938A CN103498479A CN 103498479 A CN103498479 A CN 103498479A CN 201310486938 A CN201310486938 A CN 201310486938A CN 103498479 A CN103498479 A CN 103498479A
Authority
CN
China
Prior art keywords
fastener
ladder
flitch
stepped
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310486938.4A
Other languages
English (en)
Other versions
CN103498479B (zh
Inventor
杨正华
杨正丽
严新华
黄勇
刘来勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG HUAXIN CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
NANTONG HUAXIN CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG HUAXIN CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical NANTONG HUAXIN CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201310486938.4A priority Critical patent/CN103498479B/zh
Publication of CN103498479A publication Critical patent/CN103498479A/zh
Application granted granted Critical
Publication of CN103498479B publication Critical patent/CN103498479B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

本发明涉及一种阶梯形独立基础模板支设方法,包括以下步骤:1)根据图纸尺寸制作每一个阶梯模板;2)在地表设置混凝土垫层,完成后在其上绘制阶梯的投影视图线条;3)搭建底层阶梯模板;4)上层逐层搭建;5)保证阶梯模板组合后支撑牢固,向阶梯模板内注入混凝土;6)待混凝土达到强度要求后对阶梯模板进行拆除,并进行养护。该方法不仅操作简便,减少施工工序,加快施工进度,降低施工成本,同时施工质量可靠。

Description

阶梯形独立基础模板支设方法
技术领域
本发明涉及一种阶梯形独立基础模板支设方法,属于一种建筑施工方法。
背景技术
当今世界,随着改革开放的进一步深入,经济建设呈加速度发展,建设一流的工业化厂房,改善投资环境已成为地区发展不可缺少的资源,随着工业化厂房的建设,钢结构在工业厂房上的应用也得到了长足的发展。施工单位如何确保钢结构工程预埋螺栓的施工质量、确保安全生产、文明施工是每个施工企业在钢结构工程施工中需要解决的最关键问题。
在以往生产的阶梯形独立基础手工层层搭建,不仅生产效果差,而且浪费了大量的人力物力,增加生产成本。
发明内容
本发明要解决的技术问题是提供一种阶梯形独立基础模板支设方法,该方法不仅操作简便,减少施工工序,加快施工进度,降低施工成本,同时施工质量可靠。
为解决以上问题,本发明的具体技术方案如下:一种阶梯形独立基础模板支设方法,包括以下步骤:
1)根据图纸尺寸制作每一个阶梯模板:阶梯模板为长方形,在阶梯模板的外表面上下分别设有一对平行设置的木方,每对木方的间隙等于支撑钢管的直径;
2)在地表设置混凝土垫层,完成后在其上绘制阶梯的投影视图线条;
3)搭建底层阶梯模板:将四个阶梯模板沿投影视图线条拼成矩形,在每对木方中插入支撑钢管主龙骨并相互间通过扣件固定;在木方的外侧面两端分别设置竖向支撑架,在竖向支撑架的上方通过扣件连接四根形成矩形的水平支撑架,其高度与基础的总高度一致;在混凝土垫层的外沿等距处设有均匀分布的预埋钢筋,斜向支撑架的一端通过扣件与预埋钢筋连接,另一端通过扣件与水平支撑架连接;
4)上层逐层搭建:每层的阶梯模板分别组成矩形,在每对木方中插入支撑钢管主龙骨并相互间通过扣件固定;在木方的外侧面两端分别设置竖向支撑架,竖向支撑架的底部通过扣件连接水平龙骨,水平龙骨的另一端通过扣件与斜向支撑架连接;竖向支撑架的顶部与上层的水平龙骨通过扣件连接;
5)保证阶梯模板组合后支撑牢固,向阶梯模板内注入混凝土;
6)待混凝土达到强度要求后对阶梯模板进行拆除,并进行养护。
该阶梯形独立基础模板支设方法采用上述步骤,可以快速的加工出阶梯形独立基础,不仅结构牢固,而且外形尺寸准确,复合图纸的要求。
附图说明
图1为阶梯模板的主视图。
图2为阶梯模板的侧视图。
图3为阶梯形独立基础的整体支设结构示意图。
具体实施方式
一种阶梯形独立基础模板支设方法,包括以下步骤:
1)根据图纸尺寸制作每一个阶梯模板:如图1和图2所示,阶梯模板2为长方形,在阶梯模板2的外表面上下分别设有一对平行设置的木方3,每对木方3的间隙等于支撑钢管的直径;
2)在地表设置混凝土垫层1,完成后在其上绘制阶梯的投影视图线条;
3)如图3所示,搭建底层阶梯模板:将四个阶梯模板沿投影视图线条拼成矩形,在每对木方3中插入支撑钢管主龙骨4并相互间通过扣件固定;在木方3的外侧面两端分别设置竖向支撑架5,在竖向支撑架5的上方通过扣件连接四根形成矩形的水平支撑架6,其高度与基础的总高度一致;在混凝土垫层1的外沿等距处设有均匀分布的预埋钢筋7,斜向支撑架8的一端通过扣件与预埋钢筋7连接,另一端通过扣件与水平支撑架6连接;
4)上层逐层搭建:每层的阶梯模板2分别组成矩形,在每对木方3中插入支撑钢管主龙骨4并相互间通过扣件固定;在木方3的外侧面两端分别设置竖向支撑架5,竖向支撑架5的底部通过扣件连接水平龙骨9,水平龙骨9的另一端通过扣件与斜向支撑架8连接;竖向支撑架5的顶部与上层的水平龙骨9通过扣件连接;
5)保证阶梯模板组合后支撑牢固,向阶梯模板内注入混凝土;
6)待混凝土达到强度要求后对阶梯模板2进行拆除,并进行养护。

Claims (1)

1.一种阶梯形独立基础模板支设方法,其特征在于包括以下步骤:
1)根据图纸尺寸制作每一个阶梯模板:阶梯模板(2)为长方形,在阶梯模板(2)的外表面上下分别设有一对平行设置的木方(3),每对木方(3)的间隙等于支撑钢管的直径;
2)在地表设置混凝土垫层(1),完成后在其上绘制阶梯的投影视图线条;
3)搭建底层阶梯模板:将四个阶梯模板沿投影视图线条拼成矩形,在每对木方(3)中插入支撑钢管主龙骨(4)并相互间通过扣件固定;在木方(3)的外侧面两端分别设置竖向支撑架(5),在竖向支撑架(5)的上方通过扣件连接四根形成矩形的水平支撑架(6),其高度与基础的总高度一致;在混凝土垫层(1)的外沿等距处设有均匀分布的预埋钢筋(7),斜向支撑架(8)的一端通过扣件与预埋钢筋(7)连接,另一端通过扣件与水平支撑架(6)连接;
4)上层逐层搭建:每层的阶梯模板(2)分别组成矩形,在每对木方(3)中插入支撑钢管主龙骨(4)并相互间通过扣件固定;在木方(3)的外侧面两端分别设置竖向支撑架(5),竖向支撑架(5)的底部通过扣件连接水平龙骨(9),水平龙骨(9)的另一端通过扣件与斜向支撑架(8)连接;竖向支撑架(5)的顶部与上层的水平龙骨(9)通过扣件连接;
5)保证阶梯模板组合后支撑牢固,向阶梯模板内注入混凝土;
6)待混凝土达到强度要求后对阶梯模板(2)进行拆除,并进行养护。
CN201310486938.4A 2013-10-17 2013-10-17 阶梯形独立基础模板支设方法 Active CN103498479B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310486938.4A CN103498479B (zh) 2013-10-17 2013-10-17 阶梯形独立基础模板支设方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310486938.4A CN103498479B (zh) 2013-10-17 2013-10-17 阶梯形独立基础模板支设方法

Publications (2)

Publication Number Publication Date
CN103498479A true CN103498479A (zh) 2014-01-08
CN103498479B CN103498479B (zh) 2016-01-20

Family

ID=49863729

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310486938.4A Active CN103498479B (zh) 2013-10-17 2013-10-17 阶梯形独立基础模板支设方法

Country Status (1)

Country Link
CN (1) CN103498479B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104988941A (zh) * 2015-05-21 2015-10-21 中国化学工程第三建设有限公司 一种大型承台类基础吊支模及施工方法
CN106284402A (zh) * 2016-08-11 2017-01-04 中国十九冶集团有限公司 地脚套筒螺栓安装工具及地脚套筒螺栓的预埋施工方法
CN108301415A (zh) * 2018-04-10 2018-07-20 山西省工业设备安装集团有限公司 台阶式独立基础浇筑用模板的整体加固结构
CN111877384A (zh) * 2020-08-06 2020-11-03 广州协安建设工程有限公司 阶梯型独立扩展基础一次成型施工方法
CN112031002A (zh) * 2020-09-08 2020-12-04 浙江世润建创科技发展有限公司 桩承式生态护坡及施工方法
CN113482029A (zh) * 2021-06-30 2021-10-08 中国一冶集团有限公司 一种工业厂房台阶式独立基础模板加固方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1425294A1 (ru) * 1987-03-25 1988-09-23 Кузбасский Политехнический Институт Блочна опалубка дл бетонировани фундаментов
CN101285343A (zh) * 2008-06-06 2008-10-15 南通华汇建筑工程有限公司 钢管脚手架支撑系统单面支模的方法
CN202055521U (zh) * 2011-05-12 2011-11-30 中建七局第二建筑有限公司 一种大型钢筋混凝土独立基础侧模板固定结构
CN202731290U (zh) * 2012-08-09 2013-02-13 中国二十二冶集团有限公司 钢木组合龙骨模板支撑装置

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1425294A1 (ru) * 1987-03-25 1988-09-23 Кузбасский Политехнический Институт Блочна опалубка дл бетонировани фундаментов
CN101285343A (zh) * 2008-06-06 2008-10-15 南通华汇建筑工程有限公司 钢管脚手架支撑系统单面支模的方法
CN202055521U (zh) * 2011-05-12 2011-11-30 中建七局第二建筑有限公司 一种大型钢筋混凝土独立基础侧模板固定结构
CN202731290U (zh) * 2012-08-09 2013-02-13 中国二十二冶集团有限公司 钢木组合龙骨模板支撑装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周华中: "台阶式柱基支模方法的改进", 《建筑工人》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104988941A (zh) * 2015-05-21 2015-10-21 中国化学工程第三建设有限公司 一种大型承台类基础吊支模及施工方法
CN104988941B (zh) * 2015-05-21 2017-02-22 中国化学工程第三建设有限公司 一种大型承台类基础吊支模及施工方法
CN106284402A (zh) * 2016-08-11 2017-01-04 中国十九冶集团有限公司 地脚套筒螺栓安装工具及地脚套筒螺栓的预埋施工方法
CN108301415A (zh) * 2018-04-10 2018-07-20 山西省工业设备安装集团有限公司 台阶式独立基础浇筑用模板的整体加固结构
CN111877384A (zh) * 2020-08-06 2020-11-03 广州协安建设工程有限公司 阶梯型独立扩展基础一次成型施工方法
CN112031002A (zh) * 2020-09-08 2020-12-04 浙江世润建创科技发展有限公司 桩承式生态护坡及施工方法
CN113482029A (zh) * 2021-06-30 2021-10-08 中国一冶集团有限公司 一种工业厂房台阶式独立基础模板加固方法
CN113482029B (zh) * 2021-06-30 2022-12-16 中国一冶集团有限公司 一种工业厂房台阶式独立基础模板加固方法

Also Published As

Publication number Publication date
CN103498479B (zh) 2016-01-20

Similar Documents

Publication Publication Date Title
CN103498479B (zh) 阶梯形独立基础模板支设方法
CN104631706B (zh) 一种免拆模混凝土柱及其施工方法
CN204609154U (zh) 一种预制装配式钢筋混凝土空心楼梯体系
CN203429641U (zh) 建筑施工用单侧支模加固结构体系
CN203487779U (zh) 工具式砌体构造柱混凝土浇注定型模具
CN205382488U (zh) 一种水工混凝土坝体专用模板
CN103233479B (zh) 一种浇注混凝土杯型基础的方法
CN102409848A (zh) 一种轻质密肋楼板和轻质密肋楼盖的施工成型方法
CN203066099U (zh) 杯口基础施工用的组合钢模板
CN104295093B (zh) 框架结构双柱间变形缝浇筑支模系统的施工方法
CN204983661U (zh) 轻钢大模框、保温防护装饰一体免拆模板支护系统
CN203755173U (zh) 用于桥梁高墩液压爬升的模板装置
CN204080844U (zh) 用于房屋建筑工程基础承台的装配式钢模
CN102777026A (zh) 一种贝雷架构建超长后浇板支撑体系的方法
CN203361642U (zh) 装配式结构现浇楼梯钢模板
CN102661037A (zh) 一种快捷式建筑用平面模板及支撑体系
CN204510688U (zh) 一种预制外墙板的临时固定结构
CN210263116U (zh) 一种柱下独立基础混凝土反填充快速安拆定型模板
CN207363112U (zh) 一种独立格构柱
CN209163831U (zh) 一种公路隧道排水沟内衬工具式模板
CN205206314U (zh) 楼梯定型钢木组合模板
CN202787956U (zh) 多功能外墙大模板
CN207392583U (zh) 一种具有横跨结构的3d打印墙体
CN203684655U (zh) 伸缩缝处剪力墙定型模板
CN205088678U (zh) 一种用于桩顶混凝土二次浇筑的模具

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant