CN103490514A - Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method - Google Patents

Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method Download PDF

Info

Publication number
CN103490514A
CN103490514A CN201310426261.5A CN201310426261A CN103490514A CN 103490514 A CN103490514 A CN 103490514A CN 201310426261 A CN201310426261 A CN 201310426261A CN 103490514 A CN103490514 A CN 103490514A
Authority
CN
China
Prior art keywords
earth leakage
protective device
leakage protective
controlling center
power distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310426261.5A
Other languages
Chinese (zh)
Other versions
CN103490514B (en
Inventor
邓国平
贺伟明
贺铁光
张志辉
陈剑刚
张敏
朱佐平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Xiangtan Power Supply Co of State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Xiangtan Power Supply Co of State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Xiangtan Power Supply Co of State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310426261.5A priority Critical patent/CN103490514B/en
Publication of CN103490514A publication Critical patent/CN103490514A/en
Application granted granted Critical
Publication of CN103490514B publication Critical patent/CN103490514B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method. According to the method, phase currents of secondary sides of transformers in power distribution rooms can be automatically collected through an intelligent terminal, then a tripping type can be judged according to the situations that whether tripping operation records exist and whether tripping is finished in a defined time period, and according to the magnitude of the phase currents in tripping, a tripping instruction is sent to electricity leakage protection devices through a control main station to detect whether the electricity leakage protection devices can work normally, and the control main station analyzes the operation situations of the current electricity leakage protection device according to protection starting records and protection motion results. According to the method, the electric leakage protection devices of the power distribution rooms can be monitored remotely and can be remotely controlled to operate, operation reasons of the electric leakage protection devices can be distinguished, and fault detection can be carried out on the electricity leakage protection devices.

Description

The method that the monitoring of Rural Power Distribution Network earth leakage protective device and control and fault are patrolled and examined
Technical field
The present invention relates to the method that the monitoring of a kind of Rural Power Distribution Network earth leakage protective device and control and fault are patrolled and examined.
Background technology
China's rural power grids are by transformation and construction for many years, earth leakage protective device (generally by earth leakage protective device, adding that A.C. contactor forms) is extensively universal, become the important defence line that ensures rural area client's Electrical Safety, but in actual motion management to the earth leakage protective device backward state in manual maintenance also, can't understand in time the running status of earth leakage protective device, can not find in time and process after the earth leakage protective device tripping operation, and Xu Tai district person is to on-the-spot Power resumption, can't the effective guarantee power supply reliability, and whether the labor management pattern can't accurately be grasped earth leakage protective device intact, whether work.
Summary of the invention
Technical problem to be solved by this invention is, the method that provides the monitoring of a kind of Rural Power Distribution Network earth leakage protective device and control and fault to patrol and examine, adopt the method to carry out remote monitoring to the earth leakage protective device of each power distribution station, to understand in time the running status of earth leakage protective device; Earth leakage protective device action that can each power distribution station of Long-distance Control, to restore electricity in time; Can distinguish the action reason of earth leakage protective device, with handled easily, personnel process accordingly; Can carry out fault to earth leakage protective device and patrol and examine, to find in time the fault of earth leakage protective device.
For solving the problems of the technologies described above, the method that Rural Power Distribution Network earth leakage protective device provided by the invention monitoring and control and fault are patrolled and examined, it comprises the following steps:
(1), by an intelligent terminal control loop, the power line of the earth leakage protective device on each transmission line circuit of power distribution station is connected, the position signalling contact of the earth leakage protective device on each transmission line circuit of power distribution station is accessed to the signal circuit of corresponding intelligent terminal, each intelligent terminal and a controlling center are passed through to the GPRS/CDMA wireless connections, by the earth leakage protective device on each transmission line circuit of each power distribution station of controlling center Long-distance Control, tripped, close a floodgate, the release closing operation, state by the earth leakage protective device on each transmission line circuit of each power distribution station of controlling center Real-Time Monitoring,
(2), by intelligent terminal, automatically gather the phase current I of each power distribution station Circuit Fault on Secondary Transformer a, I b, I cand report to controlling center;
(3), when controlling center has monitored earth leakage protective device when tripping operation, the controlling center inquiry has or not corresponding trip operation record, if having, is judged to be the remote operation tripping operation, if do not have, is judged to be on-the-spot tripping operation;
(4), by controlling center, set earth leakage protective device state-detection duration t and be issued to each intelligent terminal, during on-the-spot tripping operation, whether intelligent terminal detects corresponding earth leakage protective device and trips in time t-close a floodgate-tripping operation, if, judge that earth leakage protective device is as normal tripping operation, if not, judge that earth leakage protective device is as abnormal tripping operation;
(5) set the overload electric current I by controlling center, during on-the-spot tripping operation, if corresponding intelligent terminal detects any phase current of corresponding power distribution station Circuit Fault on Secondary Transformer, surpass I, be judged to be the overload tripping operation;
(6), by controlling center, select the earth leakage protective device on the transformer transmission line circuit of power distribution station to carry out artificial long-range test tripping operation, after controlling center issues the trial jump instruction, whether the earth leakage protective device that intelligent terminal detects on corresponding transmission line circuit trips, if, intelligent terminal sends the information of safing and arrives controlling center, if not, the intelligent terminal controlling center that sends a warning message;
(7), by controlling center, the trial jump task is set; specify trial jump time and trial jump loop; automatically at the appointed time the earth leakage protective device on each transmission line circuit of the power distribution station transformer of appointment is sent to trip command successively; then detect corresponding earth leakage protective device by intelligent terminal and whether complete trip operation; if; intelligent terminal sends the normal information of earth leakage protective device to controlling center; and control earth leakage protective device and close a floodgate; if not, intelligent terminal sends the information of earth leakage protective device fault to controlling center.
(8), by controlling center, carry out earth leakage protective device running status intelligent decision; controlling center starts record and protection the result of the action according to protection; analyze current earth leakage protective apparatus ruuning situation; after protection starts; if earth leakage protective device tripping operation displacement is correct, show that earth leakage protective device is normal, after protection starts; if earth leakage protective device trips unsuccessfully, show that earth leakage protective device is abnormal.
As improvement, when controlling center receives the information of earth leakage protective device fault, controlling center, by the short message content of customization, sends note and informs administrative staff.
After adopting above method, the present invention compared with prior art, has advantages of following:
Wiring of the present invention is simple, applied widely, and the running status of earth leakage protective device that can each power distribution station of Real-Time Monitoring by controlling center, once find that there is the earth leakage protective device tripping operation, can find in time and process; By controlling center, can send instructions down to corresponding intelligent terminal, control corresponding earth leakage protective device action by intelligent terminal again, make controlling center to carry out the actions such as tripping operation, combined floodgate, release combined floodgate by the Long-distance Control earth leakage protective device, when finding that there is the earth leakage protective device tripping operation, can close a floodgate by the Long-distance Control earth leakage protective device, to restore electricity in time; Can distinguish the remote operation tripping operation of earth leakage protective device, on-the-spot tripping operation, normal tripping operation, abnormal tripping operation, overload tripping operation, make operating personnel to process accordingly according to different action reasons; By controlling center, can be patrolled and examined the earth leakage protective device of each power distribution station; that is to say the earth leakage protective device on each transmission line circuit in each power distribution station is sent to trip command successively; then detect corresponding earth leakage protective device by intelligent terminal and whether complete trip operation; to find in time the fault of earth leakage protective device, can fix a breakdown in time.
In addition; when controlling center receives the information of earth leakage protective device fault; controlling center can send the customization note and inform administrative staff, so that administrative staff can learn the fault message of earth leakage protective device in time, reaches the spot in time earth leakage protective device is carried out to the fault eliminating.
Embodiment
Below in conjunction with embodiment, the present invention is described in more detail.
The invention provides the method that the monitoring of a kind of Rural Power Distribution Network earth leakage protective device and control and fault are patrolled and examined, it comprises the following steps:
(1), the power line of the earth leakage protective device on each transmission line circuit of the control loop of one intelligent terminal and power distribution station is connected, the position signalling contact of the earth leakage protective device on each transmission line circuit of power distribution station is accessed to the signal circuit of corresponding intelligent terminal, the position signalling contact is the auxiliary contact for output signal on earth leakage protective device namely, the information that whether earth leakage protective device can be completed to the tripping operation action by the position signalling contact feeds back to corresponding intelligent terminal, by each intelligent terminal and controlling center GPRS/CDMA wireless connections, by the earth leakage protective device on each transmission line circuit of each power distribution station of controlling center Long-distance Control, tripped, close a floodgate, the release closing operation, state by the earth leakage protective device on each transmission line circuit of each power distribution station of controlling center Real-Time Monitoring,
(2), by intelligent terminal, automatically gather the phase current I of each power distribution station Circuit Fault on Secondary Transformer a, I b, I cand report to controlling center;
(3), monitored earth leakage protective device when tripping operation when controlling center, the controlling center inquiry has on controlling center without corresponding trip operation record, if having, is judged to be the remote operation tripping operation, if do not have, is judged to be on-the-spot tripping operation;
(4), by controlling center, set earth leakage protective device state-detection duration t and be issued to each intelligent terminal; during on-the-spot tripping operation; whether intelligent terminal detects corresponding earth leakage protective device and trips in time t-close a floodgate-tripping operation; if; judge that earth leakage protective device is as normal tripping operation; if not, judge that earth leakage protective device is as abnormal tripping operation
(5) set the overload electric current I by controlling center, during on-the-spot tripping operation, if corresponding intelligent terminal detects any phase current of corresponding power distribution station Circuit Fault on Secondary Transformer, surpass I, be judged to be the overload tripping operation;
(6), by controlling center, select the earth leakage protective device on the transformer transmission line circuit of power distribution station to carry out artificial long-range test tripping operation, after controlling center issues the trial jump instruction, whether the earth leakage protective device that intelligent terminal detects on corresponding transmission line circuit trips, that is to say whether the position signalling contact that intelligent terminal detects the earth leakage protective device on corresponding transmission line circuit has had the information of combined floodgate to feed back to intelligent terminal, if, intelligent terminal sends the information of safing and arrives controlling center, if not, the intelligent terminal controlling center that sends a warning message;
(7), by controlling center, the trial jump task is set, specify trial jump time and trial jump loop, automatically at the appointed time (about zero point, user's idle) earth leakage protective device on each transmission line circuit of the power distribution station transformer of appointment is sent to trip command successively, then detect corresponding earth leakage protective device by intelligent terminal and whether complete trip operation, if, intelligent terminal sends the normal information of earth leakage protective device to controlling center, and control earth leakage protective device and close a floodgate, if be not, intelligent terminal sends the information of earth leakage protective device fault to controlling center.Whether the wiring that judges on-the-spot earth leakage protective device with this is normal, undesiredly gathers to administrative staff.
(8), by controlling center, carry out earth leakage protective device running status intelligent decision, take main station system according to start two kinds of data of record and protection the result of the action (being the earth leakage protective device displacement) because of protection, analyze current earth leakage protective apparatus ruuning situation.After protection starts, if earth leakage protective device tripping operation displacement is correct, show that earth leakage protective device is normal; After protection starts, if earth leakage protective device trips unsuccessfully, show that earth leakage protective device is abnormal.
When controlling center receives the information of earth leakage protective device fault, controlling center sends the customizable content note and informs administrative staff.
Below only with regard to the present invention, apply preferably example and made explanation, but can not be interpreted as it is limitations on claims, structure of the present invention can have other variations, is not limited to said structure.In a word, all various variations of doing in the protection range of independent claims of the present invention are all in protection scope of the present invention.

Claims (2)

1. the method that Rural Power Distribution Network earth leakage protective device monitoring and control and fault are patrolled and examined, is characterized in that, it comprises the following steps:
(1), by an intelligent terminal control loop, the power line of the earth leakage protective device on each transmission line circuit of power distribution station is connected, the position signalling contact of the earth leakage protective device on each transmission line circuit of power distribution station is accessed to the signal circuit of corresponding intelligent terminal, each intelligent terminal and a controlling center are passed through to the GPRS/CDMA wireless connections, by the earth leakage protective device on each transmission line circuit of each power distribution station of controlling center Long-distance Control, tripped, close a floodgate, the release closing operation, state by the earth leakage protective device on each transmission line circuit of each power distribution station of controlling center Real-Time Monitoring,
(2), by intelligent terminal, automatically gather the phase current I of each power distribution station Circuit Fault on Secondary Transformer a, I b, I cand report to controlling center;
(3), when controlling center has monitored earth leakage protective device when tripping operation, the controlling center inquiry has or not corresponding trip operation record, if having, is judged to be the remote operation tripping operation, if do not have, is judged to be on-the-spot tripping operation;
(4), by controlling center, set earth leakage protective device state-detection duration t and be issued to each intelligent terminal, during on-the-spot tripping operation, whether intelligent terminal detects corresponding earth leakage protective device and trips in time t-close a floodgate-tripping operation, if, judge that earth leakage protective device is as normal tripping operation, if not, judge that earth leakage protective device is as abnormal tripping operation;
(5) set the overload electric current I by controlling center, during on-the-spot tripping operation, if corresponding intelligent terminal detects any phase current of corresponding power distribution station Circuit Fault on Secondary Transformer, surpass I, be judged to be the overload tripping operation;
(6), by controlling center, select the earth leakage protective device on the transformer transmission line circuit of power distribution station to carry out artificial long-range test tripping operation, after controlling center issues the trial jump instruction, whether the earth leakage protective device that intelligent terminal detects on corresponding transmission line circuit trips, if, intelligent terminal sends the information of safing and arrives controlling center, if not, the intelligent terminal controlling center that sends a warning message;
(7), by controlling center, the trial jump task is set; specify trial jump time and trial jump loop; automatically at the appointed time the earth leakage protective device on each transmission line circuit of the power distribution station transformer of appointment is sent to trip command successively; then detect corresponding earth leakage protective device by intelligent terminal and whether complete trip operation; if; intelligent terminal sends the normal information of earth leakage protective device to controlling center; and control earth leakage protective device and close a floodgate; if not, intelligent terminal sends the information of earth leakage protective device fault to controlling center.
(8), by controlling center, carry out earth leakage protective device running status intelligent decision; controlling center starts record and protection the result of the action according to protection; analyze current earth leakage protective apparatus ruuning situation; after protection starts; if earth leakage protective device tripping operation displacement is correct, show that earth leakage protective device is normal, after protection starts; if earth leakage protective device trips unsuccessfully, show that earth leakage protective device is abnormal.
2. the method that Rural Power Distribution Network earth leakage protective device according to claim 1 monitoring and control and fault are patrolled and examined; it is characterized in that: when controlling center receives the information of earth leakage protective device fault; controlling center, by the short message content of customization, sends note and informs administrative staff.
CN201310426261.5A 2013-09-18 2013-09-18 Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method Active CN103490514B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310426261.5A CN103490514B (en) 2013-09-18 2013-09-18 Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310426261.5A CN103490514B (en) 2013-09-18 2013-09-18 Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method

Publications (2)

Publication Number Publication Date
CN103490514A true CN103490514A (en) 2014-01-01
CN103490514B CN103490514B (en) 2015-02-04

Family

ID=49830539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310426261.5A Active CN103490514B (en) 2013-09-18 2013-09-18 Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method

Country Status (1)

Country Link
CN (1) CN103490514B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105226618A (en) * 2015-09-23 2016-01-06 国网山东桓台县供电公司 Earth leakage protective device and leakage switch centralized control method
CN105990820A (en) * 2015-03-18 2016-10-05 南华大学 Short-circuit fault tripping method for improving power supply reliability of rural power grid
CN107976603A (en) * 2017-11-21 2018-05-01 国网山东省电力公司淄博供电公司 Portable concentrated gas meter box earth detector
CN109031023A (en) * 2018-08-16 2018-12-18 杭州华春科技有限公司 A kind of current leakage detection system with tripping catch function
CN112421782A (en) * 2020-11-20 2021-02-26 云南电网有限责任公司临沧供电局 Leakage protection switch on-line monitoring device
CN113030715A (en) * 2021-03-02 2021-06-25 国网浙江省电力有限公司湖州供电公司 Residual current operated circuit breaker performance detection device and fault judgment method
CN114389369A (en) * 2022-03-23 2022-04-22 广东承能电力安装有限公司 Intelligent monitoring system and method for electric room load
CN116760191A (en) * 2023-08-15 2023-09-15 国网山西省电力公司晋中供电公司 Power load debugging method and device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011037288A1 (en) * 2009-09-28 2011-03-31 한국전력공사 Electric distribution protection cooperative system and an operating method thereof
CN102510128A (en) * 2011-10-27 2012-06-20 王成楷 Intelligent electric leakage remote monitoring protector of low-voltage power grid
CN203086238U (en) * 2012-11-23 2013-07-24 中国西电电气股份有限公司 Intelligent high-voltage switch control signal conversion equipment
CN203086241U (en) * 2012-12-09 2013-07-24 国家电网公司 Electric leakage protection test monitoring system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011037288A1 (en) * 2009-09-28 2011-03-31 한국전력공사 Electric distribution protection cooperative system and an operating method thereof
CN102510128A (en) * 2011-10-27 2012-06-20 王成楷 Intelligent electric leakage remote monitoring protector of low-voltage power grid
CN203086238U (en) * 2012-11-23 2013-07-24 中国西电电气股份有限公司 Intelligent high-voltage switch control signal conversion equipment
CN203086241U (en) * 2012-12-09 2013-07-24 国家电网公司 Electric leakage protection test monitoring system

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105990820A (en) * 2015-03-18 2016-10-05 南华大学 Short-circuit fault tripping method for improving power supply reliability of rural power grid
CN105226618A (en) * 2015-09-23 2016-01-06 国网山东桓台县供电公司 Earth leakage protective device and leakage switch centralized control method
CN107976603A (en) * 2017-11-21 2018-05-01 国网山东省电力公司淄博供电公司 Portable concentrated gas meter box earth detector
CN109031023A (en) * 2018-08-16 2018-12-18 杭州华春科技有限公司 A kind of current leakage detection system with tripping catch function
CN112421782A (en) * 2020-11-20 2021-02-26 云南电网有限责任公司临沧供电局 Leakage protection switch on-line monitoring device
CN113030715A (en) * 2021-03-02 2021-06-25 国网浙江省电力有限公司湖州供电公司 Residual current operated circuit breaker performance detection device and fault judgment method
CN113030715B (en) * 2021-03-02 2024-03-26 国网浙江省电力有限公司湖州供电公司 Residual current operated circuit breaker performance detection device and fault judgment method
CN114389369A (en) * 2022-03-23 2022-04-22 广东承能电力安装有限公司 Intelligent monitoring system and method for electric room load
CN114389369B (en) * 2022-03-23 2022-07-05 广东承能电力安装有限公司 Intelligent monitoring system and method for electric room load
CN116760191A (en) * 2023-08-15 2023-09-15 国网山西省电力公司晋中供电公司 Power load debugging method and device

Also Published As

Publication number Publication date
CN103490514B (en) 2015-02-04

Similar Documents

Publication Publication Date Title
CN103490514B (en) Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method
CN102611086B (en) Centralized protection system and method for region distribution network
CN103606910B (en) The fault self-recovery method in a kind of outlet of the distribution feeder based on Wide-area Measurement Information dead band
CN109459664A (en) A kind of detection of distribution network failure and positioning analysis system
CN102299563B (en) Digital-analog (DA) protection method for intelligent distribution network
CN106556766A (en) A kind of distribution network failure monitoring system based on distribution line multidate information
CN107238774B (en) State monitoring system for drop-out fuse
CN102075005B (en) Processing method for 110KV zone automatic standby power switching action on basis of EMS (Engine Management System) system
CN103490392A (en) Fault handling method of power distribution network comprising distributed power supplies and microgrids
CN103606909A (en) Protecting system and method for power distribution network circuit
CN103138390A (en) Power distribution network fault handling method based on self-recovering control
CN203691057U (en) Arc online monitoring and protecting system
CN101752909B (en) Remote checking method of operation circuit
CN106501657A (en) A kind of monitoring system of electric distribution network overhead wire failure
CN102116823A (en) System for automatically judging and positioning faults of automatic blocking and continuous railway power lines in railway distribution network
CN112421615A (en) Power distribution station self-healing control method and system based on intelligent breaker action
CN112421614A (en) Power distribution station self-healing control system and method based on local communication and topology identification
CN103915900B (en) A kind of track traffic electric power monitors DC load monitoring method
CN102624090B (en) Based on the intelligent high-pressure panel switches of electronic mutual inductor
CN104332999A (en) Automatic main grid power supply transferring strategy generation method for regional power grid
CN105514989A (en) Urban power network power supply recovery method based on backup automatic switching of 10kV special feed line
CN107741548A (en) A kind of controller switching equipment monitoring method
CN103762557A (en) Device and method for open-circuit-resistant protection of current transformer
CN104020393B (en) A kind of with electrical network one-phase short-circuit current Fault Locating Method
CN212031582U (en) Intelligent box-type substation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant