CN203086241U - Electric leakage protection test monitoring system - Google Patents

Electric leakage protection test monitoring system Download PDF

Info

Publication number
CN203086241U
CN203086241U CN2012206712468U CN201220671246U CN203086241U CN 203086241 U CN203086241 U CN 203086241U CN 2012206712468 U CN2012206712468 U CN 2012206712468U CN 201220671246 U CN201220671246 U CN 201220671246U CN 203086241 U CN203086241 U CN 203086241U
Authority
CN
China
Prior art keywords
remote monitoring
test
electric leakage
earth leakage
leakage protective
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012206712468U
Other languages
Chinese (zh)
Inventor
宋晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEIXIANG COUNTY ELECTRIC POWER BUREAU
State Grid Corp of China SGCC
Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
NEIXIANG COUNTY ELECTRIC POWER BUREAU
State Grid Corp of China SGCC
Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NEIXIANG COUNTY ELECTRIC POWER BUREAU, State Grid Corp of China SGCC, Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical NEIXIANG COUNTY ELECTRIC POWER BUREAU
Priority to CN2012206712468U priority Critical patent/CN203086241U/en
Application granted granted Critical
Publication of CN203086241U publication Critical patent/CN203086241U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/126Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wireless data transmission

Abstract

The utility model discloses an electric leakage protection test monitoring system comprising an electric leakage protector, a test recorder and a remote monitoring terminal, which are disposed in a housing of the electric leakage protector. The test recorder is provided with a wireless transmission device, which is in a data connection with the remote monitoring terminal by a wireless network. The remote monitoring terminal is connected with a cell phone terminal of a management staff by a 3G network. The utility model is characterized in that the test recorder can be effectively protected, the reliability of the data can be improved, the test recorder and the remote monitoring terminal are in a data connection by the wireless network, therefore the remote data receiving and the test data recording can be realized, and the object of regular test of the remote monitoring electric leakage protector can be achieved; the remote monitoring terminal is connected with the cell phone terminal of the management staff by the 3G network, therefore the management staff can be prompted by short messages or voice prompting, when faults or problems occur. The utility model is advantageous in that the traditional routine inspection way can be changed, the working pressure of inspectors can be relieved by the remote monitoring, a lot of manpower and material resources can be saved, and the electric leakage protection test monitoring system is worthy of wide application and popularization.

Description

A kind of earth leakage protective test monitoring system
Technical field
The utility model belongs to operation of power networks inspection management technical field, particularly a kind of earth leakage protective test monitoring system.
Background technology
At present; in the operation of power networks management; the earth leakage protective routine test in platform district is a daily necessary job that ensures electric equipment and power network safety operation; normally used is register; by the data form is filled in record; the earth leakage protective index in district is put into effect in reaction; but for the people of some careless general ideas or busy especially peak time; the workmen loses register extremely easily; for not on the pan and punishment; some irresponsible personnel will forge test record; these phenomenons all can not be accomplished real routine test, in case earth leakage protective device damages or performance reduces, all might cause the damage of equipment and the large tracts of land paralysis of electrical network; will cause the great normal electricity consumption of resident that influenced, also cause the tremendous economic loss.So being necessary to propose a kind of new means goes to ensure the true and reliable property of the earth leakage protective routine test in platform district.CN 102468648 A disclose a kind of grid system integrated protector tester, it comprises power circuit, voltage analog circuit and current analog circuit, and simulation produces operating voltage and the operating current of high-voltage fence under overload, short circuit, overvoltage, under voltage; Simulation produces residual voltage and zero-sequence current carries out the leak current fault simulation of GZBD; Chronograph is used to write down the fault actions time of comprehensive protection device; Be used for the test function selector switch selected in various fault test functions; GZBD, DZBD test selector switch; Output relay produces leakage ground impedance leakage earth potential device W4 to be used for simulation.Described grid system integrated protector tester can carry out the test and the verification of all parameters and performance by Offhost, can be used for failure diagnosis, but and be not suitable for regular visit record usefulness, some wastes resource.
The utility model content
The utility model purpose is to address the above problem, and a kind of simple and practical, safe and reliable earth leakage protective test monitoring system is provided.
To achieve these goals; the technical solution adopted in the utility model is: a kind of earth leakage protective test monitoring system; comprise earth leakage protective device, testing recorder and remote monitoring end; described testing recorder is arranged in the protector housing of described earth leakage protective device; described testing recorder is connected with described earth leakage protective device lead; described testing recorder is provided with wireless launcher, and described wireless launcher is connected with described remote monitoring end data by wireless network.
Described remote monitoring end comprises radio receiver and computer, and described radio receiver is connected by data wire with described computer.
Described remote monitoring end is by 3G network connection management personnel mobile phone terminal.
The utility model is provided with testing recorder in the protector housing of described earth leakage protective device, effectively avoid described testing recorder to be damaged by extraneous layabout or irresponsible personnel, the assurance data can not changed, improve the true and reliable property of data, described testing recorder is provided with wireless launcher, described wireless launcher is connected with described remote monitoring end data by wireless network, described remote monitoring end comprises radio receiver and computer, described radio receiver is connected by data wire with described computer, long-range reception and record test record data have been realized, reached the purpose of remote monitoring earth leakage protective device routine test, the performance that ensures earth leakage protective device is in state preferably at any time, for electric power netting safe running is got rid of potential safety hazard; Described remote monitoring end can in time be notified administrative staff with note or voice reminder by 3G network connection management personnel mobile phone terminal when fault and problem are arranged, greatly improve troubleshooting efficient; The utility model has changed traditional routine inspection mode, and remote monitoring has alleviated patrols and examines personnel's operating pressure, has saved a large amount of manpower and materials, meets the electric power requirement of present efficient quick.The utility model is simple and practical, cost is low, and benefit is good, and use should be widely promoted.
Description of drawings
The utility model is further described below in conjunction with accompanying drawing:
Fig. 1 is a structural representation of the present utility model.
Embodiment
As described in Figure 1; a kind of earth leakage protective test monitoring system; comprise earth leakage protective device 1, testing recorder 2 and remote monitoring end; described testing recorder 2 is arranged in the protector housing of described earth leakage protective device 1; described testing recorder 2 is connected with described earth leakage protective device 1 lead; described testing recorder 2 is provided with wireless launcher 3, and described wireless transmission is adorned 3 and put by wireless network and be connected with described remote monitoring end data.
Described remote monitoring end comprises radio receiver 4 and computer 5, and described radio receiver 4 and described computer 5 are connected by data wire.
Described remote monitoring end is by 3G network connection management personnel mobile phone terminal 6.
The utility model is provided with testing recorder 2 in protector 1 housing of described earth leakage protective device, effectively avoid described testing recorder to be damaged by extraneous layabout or irresponsible personnel, the assurance data can not changed, improve the true and reliable property of data, described testing recorder 2 is provided with wireless launcher 3, described wireless launcher 3 is connected with described remote monitoring end data by wireless network, described remote monitoring end comprises radio receiver 4 and computer 5, described radio receiver 4 and described computer 5 are connected by data wire, long-range reception and record test record data have been realized, reached the purpose of remote monitoring earth leakage protective device 1 routine test, the performance that ensures earth leakage protective device 1 is in state preferably at any time, for electric power netting safe running is got rid of potential safety hazard; Described remote monitoring end can in time be notified administrative staff with note or voice reminder by 3G network connection management personnel mobile phone terminal 6 when fault and problem are arranged, greatly improve troubleshooting efficient; The utility model has changed traditional routine inspection mode, and remote monitoring has alleviated patrols and examines personnel's operating pressure, has saved a large amount of manpower and materials, meets the electric power requirement of present efficient quick.The utility model is simple and practical, cost is low, and benefit is good, and use should be widely promoted.

Claims (3)

1. an earth leakage protective is tested monitoring system; it is characterized in that: comprise earth leakage protective device, testing recorder and remote monitoring end; described testing recorder is arranged in the protector housing of described earth leakage protective device; described testing recorder is connected with described earth leakage protective device lead; described testing recorder is provided with wireless launcher, and described wireless launcher is connected with described remote monitoring end data by wireless network.
2. earth leakage protective is tested monitoring system according to claim 1, and it is characterized in that: described remote monitoring end comprises radio receiver and computer, and described radio receiver is connected by data wire with described computer.
3. earth leakage protective is tested monitoring system as claimed in claim 1 or 2, it is characterized in that: described remote monitoring end is by 3G network connection management personnel mobile phone terminal.
CN2012206712468U 2012-12-09 2012-12-09 Electric leakage protection test monitoring system Expired - Fee Related CN203086241U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012206712468U CN203086241U (en) 2012-12-09 2012-12-09 Electric leakage protection test monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012206712468U CN203086241U (en) 2012-12-09 2012-12-09 Electric leakage protection test monitoring system

Publications (1)

Publication Number Publication Date
CN203086241U true CN203086241U (en) 2013-07-24

Family

ID=48832046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012206712468U Expired - Fee Related CN203086241U (en) 2012-12-09 2012-12-09 Electric leakage protection test monitoring system

Country Status (1)

Country Link
CN (1) CN203086241U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103490514A (en) * 2013-09-18 2014-01-01 国家电网公司 Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method
CN107976603A (en) * 2017-11-21 2018-05-01 国网山东省电力公司淄博供电公司 Portable concentrated gas meter box earth detector

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103490514A (en) * 2013-09-18 2014-01-01 国家电网公司 Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method
CN107976603A (en) * 2017-11-21 2018-05-01 国网山东省电力公司淄博供电公司 Portable concentrated gas meter box earth detector

Similar Documents

Publication Publication Date Title
CN103760454B (en) MOV lightning arrester leakance detection device, long distance control system and method
CN201946099U (en) Comprehensively monitored data acquiring device for solar zigbee wireless power transmission line
CN202230150U (en) On-line monitoring intelligent terminal for electric power lightning arrester with fiber for power supply
CN110780227A (en) Online monitoring device and method for leakage current of lightning arrester of power transmission line
CN202758035U (en) Cable fault tester
CN201247302Y (en) Apparatus for measuring polar of isonym end of current mutual inductor or transformer
CN103344885A (en) High-voltage single-core cable protective covering grounding online monitoring device and control method
CN202275131U (en) Temperature and outlet cable fault monitoring device for switch cabinet
CN202631641U (en) On-line monitoring system for high-voltage condenser
CN210626591U (en) Intelligent alarm device for monitoring state of low-voltage distribution substation area
CN203086241U (en) Electric leakage protection test monitoring system
CN204925314U (en) Distribution network checkout system that fault locating used
CN204789793U (en) Earth -leakage protector's state verification ware under explosion -proof environment
CN202676855U (en) Long-distance positioning device for lightning stroke fault point of power transmission line
CN214310746U (en) Distribution network leakage monitoring and warning system
CN105337805B (en) Portable intelligent substation remote signaling and remote measuring calibration device and system
CN105652107A (en) Reliability detection method of direct-current transmission converter valve trigger monitoring unit
CN204575773U (en) The impedance of grounding net of transformer substation frequency sweep and the automatic test diagnosis equipment of amplitude-frequency response
CN203396822U (en) On-line monitoring device for grounding currents flowing through sheaths of high-voltage single-core cables
CN202676799U (en) On-line monitoring device for lightning arrester
CN102073277A (en) Computer control system for power frequency insulating test
CN104076259A (en) Device for detecting pollution flashover of insulator on transmission line in real time
CN203759108U (en) Low-voltage power grid leakage current record analyzer
CN201663479U (en) Intelligent remote information system device for packaged high/low voltage power distribution cabinet
CN203164357U (en) Automatic power line fault detecting device for power data acquisition system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130724

Termination date: 20131209