CN103487040A - 一种钢柱安装的测量方法 - Google Patents

一种钢柱安装的测量方法 Download PDF

Info

Publication number
CN103487040A
CN103487040A CN201310391140.1A CN201310391140A CN103487040A CN 103487040 A CN103487040 A CN 103487040A CN 201310391140 A CN201310391140 A CN 201310391140A CN 103487040 A CN103487040 A CN 103487040A
Authority
CN
China
Prior art keywords
steel column
mounting
measuring method
column
transit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310391140.1A
Other languages
English (en)
Other versions
CN103487040B (zh
Inventor
董超
刘明路
王馥琴
贾文彬
韩向科
徐宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CMTCC Shanghai Shisanye Construction Co Ltd filed Critical CMTCC Shanghai Shisanye Construction Co Ltd
Priority to CN201310391140.1A priority Critical patent/CN103487040B/zh
Publication of CN103487040A publication Critical patent/CN103487040A/zh
Application granted granted Critical
Publication of CN103487040B publication Critical patent/CN103487040B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C1/00Measuring angles
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • G01C15/02Means for marking measuring points
    • G01C15/06Surveyors' staffs; Movable markers
    • G01C15/08Plumbing or registering staffs or markers over ground marks

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种钢柱安装的测量方法,具体包括三个步骤:1)柱顶测量标记布设;2)引测控制轴线的偏移线;3)安装测量。首先利用建筑的控制轴线,向一侧引测平行的轴线偏移线;将钢柱柱顶轴线和几何归方线用墨线弹出;最后在钢柱安装时,将仪器架设在轴线偏移线上,观测柱顶的标尺。本发明能够直接控制钢柱安装的轴线,观测精度高;并且其架设在钢柱的轴线偏移线上,只需进行柱顶的观测,不需要对整个钢柱从下往上观测,能够有效的避开复杂条件的障碍物,特别适用于障碍物干扰多的复杂条件下的安装测量工作。

Description

一种钢柱安装的测量方法
技术领域
本发明属工程测量技术领域,特别是涉及一种钢柱安装的测量方法。
背景技术
随着钢结构建筑的发展,在钢柱施工时,现场会有很多脚手架、平台、支撑等,或者是与其他的专业交叉施工,这些都会极大的阻碍测量视线。故而需要一种方法,能够在复杂条件下高效的完成钢柱的安装测量工作。
某海外综合楼工程,工程总量9200吨;其中规格为□1000*60的箱形柱60根,重量约700吨;规格为φ1200*30的钢柱138根,重量约1396吨;钢柱重量合计2096吨。本工程施工现场,土建与钢结构交叉施工,各种脚手架、施工平台等形成了十分复杂的测量环境,测量障碍物多,测量难度大。此测量方法避开障碍物顺利施测,加快了施工测量速度,提高了钢柱的安装速度。
目前,控制钢柱安装竖向精度的方法主要是将经纬仪架设在轴线上,观测钢柱的中心线标记。观测钢柱的中心线标记,需要沿着钢柱竖向观测,观测视线被阻挡的几率很大,这就需要不断的调整仪器的架设位置来避开障碍物(有时障碍过多过密,无法避开),大大的影响现场施测速度。
相比起来,本专利在测量时将仪器架设在轴线偏移线上观测柱顶的标尺,轴线偏移线的偏移距离能够根据现场实际情况取值,能够有效的避开障碍物;并且安装钢柱时柱顶会高出场内的障碍物,故而标尺位置比较空旷,能够有效的观测。
发明内容
本发明所要解决的技术问题是提供一种钢柱安装的测量方法,以解决原有测量方法过于繁琐且效率不高的问题。
本发明解决其技术问题所采用的技术方案是:提供一种钢柱安装的测量方法,包括:
1)首先根据控制点,测量放置安装钢柱用的控制轴线,控制轴线为通过混凝土浇注孔中心的两根相互垂直的直线,检查施工现场的测量条件、障碍物的情况,根据实际情况确定轴线偏移线相对于控制轴线的方向和距离,根据轴线偏移线的位置和距离,测量放置轴线偏移线,并用墨线弹出;
2)根据将要安装钢柱的长度和位置,在轴线偏移线上选一架设点作为经纬仪的架设位置,并架设经纬仪;
3)以架设点轴线偏移线的远端为后视点,调整经纬仪;
4)钢柱顶端水平放置两根彼此相互垂直塔尺,安装钢柱使得两塔尺与钢柱底部相应的控制轴线平行,调整经纬仪,对准钢柱柱顶的塔尺进行读数;
5)经纬仪的读数如果不符合理论计算的结果,继续调整钢柱位置,直到两个测量方向经纬仪的读数均与理论结果相符为止。
有益效果
本发明避开了测量视线的障碍物,节约了反复架设仪器的时间,加快了钢柱安装测量速度。
附图说明
图1为本发明钢柱安装示意图。
图2为本发明示意图。
具体实施方式
下面结合具体实施例,进一步阐述本发明。应理解,这些实施例仅用于说明本发明而不用于限制本发明的范围。此外应理解,在阅读了本发明讲授的内容之后,本领域技术人员可以对本发明作各种改动或修改,这些等价形式同样落于本申请所附权利要求书所限定的范围。
实施例1
如图1~图2所示,一种钢柱安装的测量方法,归方线a,轴线b,混凝土浇注孔c,轴线偏移线d,塔尺e,经纬仪f,钢柱g,经纬仪f的轴线偏移量均为1800mm,将塔尺±0标记放置在柱中心,第一个经纬仪f读数为1790mm,第二个经纬仪f读数为1811mm。这时就应当调整钢柱g,使其柱顶位置往第二个经纬仪f方向移动10mm,并沿第一个经纬仪的反方向移动11mm。这样两个经纬仪f均调整到读数为1800mm,满足要求,同时注意如果在柱顶中心线上放置塔尺e,读数视线受到阻碍的时候,可以将塔尺e放在归方线a上进行观察,避开障碍物,归方线a为钢柱g顶部与轴线b平行的一组直线。

Claims (1)

1.一种钢柱安装的测量方法,包括:
1)首先根据控制点,测量放置安装钢柱(g)用的控制轴线(b),控制轴线(b)为通过混凝土浇注孔(c)中心的两根相互垂直的直线,检查施工现场的测量条件、障碍物的情况,根据实际情况确定轴线偏移线(d)相对于控制轴线(b)的方向和距离,根据轴线偏移线(d)的位置和距离,测量放置轴线偏移线(d),并用墨线弹出;
2)根据将要安装钢柱(g)的长度和位置,在轴线偏移线(d)上选一架设点作为经纬仪(f)的架设位置,并架设经纬仪(f);
3)以架设点轴线偏移线的远端为后视点,调整经纬仪(f);
4)钢柱(g)顶端水平放置两根彼此相互垂直塔尺(e),安装钢柱(g)使得两塔尺(e)与钢柱(g)底部相应的控制轴线(b)平行,调整经纬仪(f),对准钢柱(g)柱顶的塔尺(e)进行读数;
5)经纬仪(f)的读数如果不符合理论计算的结果,继续调整钢柱(g)位置,直到两个测量方向经纬仪(f)的读数均与理论结果相符为止。
CN201310391140.1A 2013-08-30 2013-08-30 一种钢柱安装的测量方法 Active CN103487040B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310391140.1A CN103487040B (zh) 2013-08-30 2013-08-30 一种钢柱安装的测量方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310391140.1A CN103487040B (zh) 2013-08-30 2013-08-30 一种钢柱安装的测量方法

Publications (2)

Publication Number Publication Date
CN103487040A true CN103487040A (zh) 2014-01-01
CN103487040B CN103487040B (zh) 2015-10-28

Family

ID=49827454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310391140.1A Active CN103487040B (zh) 2013-08-30 2013-08-30 一种钢柱安装的测量方法

Country Status (1)

Country Link
CN (1) CN103487040B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109018194A (zh) * 2017-06-12 2018-12-18 上海船厂船舶有限公司 集装箱箱脚立柱安装方法
CN110629780A (zh) * 2019-08-23 2019-12-31 安徽世慧科技有限公司 一种组合拼接式上下层承台的设计、制作和安装方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01267409A (ja) * 1988-04-19 1989-10-25 Sokkisha Co Ltd 高塔の鉛直度の測定法
TW201005154A (en) * 2008-07-21 2010-02-01 jun-wen Wang Measuring and positioning method of top-down construction steel column and structure thereof
CN101691815A (zh) * 2009-09-03 2010-04-07 中国建筑第四工程局有限公司 一种大型钢架快速吊装对正方法及钢架底座结构
CN102331225A (zh) * 2011-06-08 2012-01-25 西安建筑科技大学 一种高支模体系立杆垂直度的测量方法
CN102400559A (zh) * 2010-09-13 2012-04-04 五冶集团上海有限公司 苯加氢工程主体框架钢结构安装中钢柱校正方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01267409A (ja) * 1988-04-19 1989-10-25 Sokkisha Co Ltd 高塔の鉛直度の測定法
TW201005154A (en) * 2008-07-21 2010-02-01 jun-wen Wang Measuring and positioning method of top-down construction steel column and structure thereof
CN101691815A (zh) * 2009-09-03 2010-04-07 中国建筑第四工程局有限公司 一种大型钢架快速吊装对正方法及钢架底座结构
CN102400559A (zh) * 2010-09-13 2012-04-04 五冶集团上海有限公司 苯加氢工程主体框架钢结构安装中钢柱校正方法
CN102331225A (zh) * 2011-06-08 2012-01-25 西安建筑科技大学 一种高支模体系立杆垂直度的测量方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109018194A (zh) * 2017-06-12 2018-12-18 上海船厂船舶有限公司 集装箱箱脚立柱安装方法
CN110629780A (zh) * 2019-08-23 2019-12-31 安徽世慧科技有限公司 一种组合拼接式上下层承台的设计、制作和安装方法

Also Published As

Publication number Publication date
CN103487040B (zh) 2015-10-28

Similar Documents

Publication Publication Date Title
CN102080960B (zh) 基于gps的超高层建筑物垂直度测控方法
CN111174771A (zh) 一种立柱垂直度测量方法
CN103499340B (zh) 一种实现大高差高程竖直传递的测量装置及测量方法
CN106840129B (zh) 一种快速测量地铁管片中心三维坐标的方法
CN102607516B (zh) 测量核电工程中的基准的高程的方法
CN102155230B (zh) 基于圆坐标的隧道曲线段放样方法
CN205300569U (zh) 隧道变形监测设备和系统
CN203824548U (zh) 一种桥梁结构砼表面观测区面积测定仪
CN104034319A (zh) 一种高层建筑测量控制点投射定位辅助装置及其使用方法
CN105798067A (zh) 轧机底座安装精确测量方法
CN102680942A (zh) 一种基于全站仪的高炉框架测量定位方法
CN203857958U (zh) 一种巷道全断面变形监测装置
CN103453886A (zh) 一种测量既有建筑物不可触及测点垂直度的方法
CN104457788A (zh) 一种大尺寸移动式基线桩及标定方法
CN103487040A (zh) 一种钢柱安装的测量方法
CN101464146A (zh) 将地面水准点高程精确传递到高架桥上的测量方法及其装置
CN104634315A (zh) 多层楼板分层水平位移监测系统
CN204040007U (zh) 基线法测量基坑坡顶水平变形的辅助工具
JP2019052864A (ja) 芯座標計測装置及び芯座標計測方法
CN104006798B (zh) 墩柱垂直度测量仪
CN104121897B (zh) 卫星定位测量杆
CN204128555U (zh) 一种组合式工程测量仪器
CN207335711U (zh) 一种全站仪坐标放样测量的棱镜装置
CN203148425U (zh) 一种用于验收轨道的水准测量装置
JP7487863B2 (ja) 測量システム、丁張設置支援方法、丁張設置支援プログラム

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Patentee after: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address before: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Patentee before: CMTCC Shanghai 13th Construction Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190705

Address after: Room A, Room 403, 1325 Mudanjiang Road, Baoshan District, Shanghai, 20199

Co-patentee after: CHINA MCC20 GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: Room A, Room 403, 1325 Mudanjiang Road, Baoshan District, Shanghai, 20199

Patentee before: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.