CN103485358B - The construction method of underground structure precipitation open caisson - Google Patents

The construction method of underground structure precipitation open caisson Download PDF

Info

Publication number
CN103485358B
CN103485358B CN201310380958.3A CN201310380958A CN103485358B CN 103485358 B CN103485358 B CN 103485358B CN 201310380958 A CN201310380958 A CN 201310380958A CN 103485358 B CN103485358 B CN 103485358B
Authority
CN
China
Prior art keywords
precipitation
steel pipe
open caisson
well
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310380958.3A
Other languages
Chinese (zh)
Other versions
CN103485358A (en
Inventor
游兴荣
徐书龙
游靓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN201310380958.3A priority Critical patent/CN103485358B/en
Publication of CN103485358A publication Critical patent/CN103485358A/en
Application granted granted Critical
Publication of CN103485358B publication Critical patent/CN103485358B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses the construction method of underground structure precipitation open caisson, comprise the following steps: make open caisson well dish and precipitation steel pipe, the uniform infiltration through hole in precipitation steel pipe lower end is outside filter screen wrapped multiple also; Lay wooden well dish and build open caisson by laying bricks or stones at Jing Panshang; Well sinking is to desired depth; Put into precipitation steel pipe and fill up with rubble; Draw water from precipitation steel pipe until complete base arrangement; Well casing shutoff.Structure of the present invention is simple, constructs easily, quick construction, with low cost, respond well.

Description

The construction method of underground structure precipitation open caisson
Technical field
The present invention relates to a kind of construction method of underground structure precipitation open caisson.
Background technology
The design of highrise building underground structure often has elevator pit or collecting well, its degree of depth all can exceed nearly 2 meters of absolute altitude at the bottom of normal configuration, and Underground Construction usually needs to reduce underground water, in construction, owner is in order to reduce precipitation cost, when quantity and the depth design of dewatering well usually according to normal configuration bed course at the bottom of absolute altitude (structure centre position) 0.5 meter-1 meter downwards, whole precipitation event is that foundation ditch surrounding reduces the highest ramp shaped that presents in the minimum centre of water level, because elevator shaft and collecting well are often many in the middle part of underground structure, therefore need to take auxiliary precipitation just to seem economical lower than the elevator pit of this part or collecting well.And this part due to precipitation not in place and after earth excavation water can form spring or there is spring at this position itself in this segment set, the auxiliary improper meeting of precipitation method causes this position dewatering effect difference and occurs that the earthwork is caved in, and then affect this position normal construction, affect duration, quality and safety, and construction cost is very high.
Normal practice:
1, heavy caliber dewatering well is increased at this position: equipment difficulty is in place, long in time limit, and cost is high;
2, adopt Application of light well point precipitation: cost is high, long in time limit, hinder structure construction;
3, cement mixing pile is adopted to block water: construction equipment is difficult to enter, and cost is high, long in time limit.
Simple and easy way: we invent a kind of simple and easy open caisson construction method, namely artificial simple and easy open caisson is done at elevator pit or sump bed course (comprising structure to need to make slope) outer correct position, special steel pipe is put in well, submersible pump precipitation in steel pipe meets construction requirement: well depth as required precipitation depth and transmission coefficient and precipitation range computation is determined, a general open caisson just can meet, and special circumstances are accelerated.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of construction method of underground structure precipitation open caisson.
In order to solve the problems of the technologies described above, the technical solution used in the present invention is: the construction method of underground structure precipitation open caisson, comprises the following steps:
(1) precipitation steel pipe is made, the length of precipitation steel pipe is by the dewatering well degree of depth and structure base slab thickness and stretch out base arrangement face 100mm and calculate, the uniform water seepage hole in precipitation steel pipe lower end, outside screen pack wrapped multiple, is welded with two road seal rings on the top of precipitation steel pipe;
(2) annular wells dish is made with plank;
(3) annular wells dish is laid to the center pre-determining dewatering well;
(4) the annularly well dish J-shaped wall of standard common brick laid dry thickness 240mm, adds iron wire at vertical direction stretcher wall several piece plank when often building 1 meter high by laying bricks or stones and reinforces tighten along outer ring;
(5) manually to dredge a well clearly open caisson one piece of integral sinking that interior sand or soil allows annular wells dish and brick wall form, reduce shoveling difficulty with giant punching soil if desired, or suitably add load and accelerate;
(6) sink while upwards add block header wall, until open caisson reaches desired depth, whole in frustum of a cone after open caisson completes;
(7) put 200mm thick 1-3 level stone in shaft bottom, put into the precipitation steel pipe made above, outside steel pipe, surrounding throws in elevation location at the bottom of 1-3 level stone to bed course;
(8) muddy water in precipitation steel pipe is taken out with foul water pump until be all clear water and not containing silt stone, change submersible pump and carry out continuous pumpage dewatering;
(9) precipitation should carry out continuously, determines whether continue precipitation after base arrangement concrete completes as required, causing ground influenced, being also used as maintenance water and retaining a period of time if do not taken silt out of;
(10) after Underground Construction completes, well casing shutoff is carried out after reaching design strength; Well casing shutoff comprises the following steps:
(11) along precipitation steel pipe base arrangement concrete pavement dug out circular groove in advance and clean up;
(12) accelerate to draw water reduction underground water;
(13) fast hardening concrete quick closure is used lower than blinding concrete absolute altitude 200mm with lower part steel pipe;
(14) immediately by the 200mm height steel duct below the downward jam-pack blinding concrete of cork made in advance, with 50mm position below the precipitation steel pipe on the fast hardening concrete quick closure blinding concrete of band microdilatancy to base arrangement surface layer, top is closed by the steel plate rapid welding that thickness 16mm, diameter equal pipe diameter immediately, then slices off the steel pipe of the bottom 130mm exceeding artificial raggle on base plate; Slice off steel pipe for convenience, the depth of groove that artificial raggle bottom steel pipe is formed is 30mm, groove diameter is that outer diameter of steel pipes adds the distance 100mm being convenient to cut off construction, after slicing off steel pipe, finally build groove and base arrangement face put down with carrying higher leveled microdilatancy pea gravel concreten than base arrangement concrete strength again.
As preferably, the thickness making annular wells dish plank in step (2) is not less than 35mm.
As preferably, in step (6), the back cut diameter of open caisson is not less than 600mm, and lower port diameter is 900mm.
As preferably, the wide 50mm of circular groove, dark 30mm in step (11).
As preferably, in step (14), cork thickness is 200mm.
The invention has the beneficial effects as follows:
Structure is simple, constructs easily, quick construction, with low cost, respond well.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the present invention is further detailed explanation.
Fig. 1 is the structural representation of the construction method embodiment of underground structure precipitation open caisson of the present invention.
In figure, 1-well dish, 2-brick wall, 3-screen pack, 4-water seepage hole, 5-stone, 6-precipitation steel pipe, 7-cork, 8-blinding concrete, 9-underplate concrete, 10-seal ring, 11-closes steel plate, 12-confining bed.
Detailed description of the invention
Fig. 1 is a kind of underground structure precipitation open caisson, and its construction method comprises the following steps:
(1) precipitation steel pipe 6 is made, the length of precipitation steel pipe is by the dewatering well degree of depth and structure base slab thickness and stretch out base arrangement face 100mm and calculate, the uniform water seepage hole 4 in precipitation steel pipe lower end, outside screen pack 3 wraps up plural layer, is welded with two road seal rings 10 on the top of precipitation steel pipe;
(2) the plank making annular wells dish 1 of 35mm is not less than with thickness;
(3) annular wells dish is laid to the center pre-determining dewatering well;
(4) the T-shaped brick wall 2 of annularly well dish standard common brick laid dry thickness 240mm, adds iron wire at vertical direction stretcher wall several piece plank when often building 1 meter high by laying bricks or stones and reinforces tighten along outer ring;
(5) manually to dredge a well clearly open caisson one piece of integral sinking that interior sand or soil allows annular wells dish and brick wall form, reduce shoveling difficulty with giant punching soil if desired, also suitably can add load and accelerate;
(6) sink while upwards add block J-shaped wall, until open caisson reaches desired depth, whole in frustum of a cone after open caisson completes, back cut diameter is not less than 600mm, and lower port diameter is 900mm;
(7) put 200mm thick 1-3 level stone in shaft bottom, put into the precipitation steel pipe 6 made above, outside steel pipe, surrounding throws in elevation location at the bottom of 1 ~ 3 grade of stone 5 to bed course;
(8) muddy water in precipitation steel pipe is taken out with foul water pump until be all clear water and not containing silt stone, change submersible pump and carry out continuous pumpage dewatering;
(9) precipitation should carry out continuously, determines whether continue precipitation after underplate concrete 9 completes as required, causing ground influenced, can also be used as maintenance water and retaining a period of time if do not taken silt out of;
(10) can carry out well casing shutoff after Underground Construction completes and after reaching design strength, well casing shutoff comprises the following steps:
(11) along precipitation steel pipe, the circular groove of the wide 50mm of base arrangement concrete pavement artificial chisel, dark 30mm is cleaned up in advance;
(12) accelerate to draw water reduction underground water;
(13) fast hardening concrete quick closure is used lower than blinding concrete absolute altitude 200mm with lower part steel pipe;
(14) immediately by the 200mm height steel duct below the downward jam-pack of cork (thickness 200) blinding concrete made in advance, with 50mm position below the precipitation steel pipe on the fast hardening concrete quick closure blinding concrete of band microdilatancy to base arrangement surface layer, top is closed by the steel plate rapid welding that thickness 16mm, diameter equal pipe diameter immediately, then slices off the steel pipe exceeding base plate (bottom of artificial raggle) 130mm; Slice off steel pipe for convenience, the depth of groove that artificial raggle bottom steel pipe is formed is 30mm, groove diameter is that outer diameter of steel pipes adds the distance 100mm being convenient to cut off construction, after slicing off steel pipe, finally build groove and base arrangement face put down with carrying higher leveled microdilatancy pea gravel concreten than base arrangement concrete strength again.
Above-described embodiment of the present invention, does not form limiting the scope of the present invention.Any amendment done within the spirit and principles in the present invention, equivalent replacement and improvement etc., all should be included within claims of the present invention.

Claims (5)

1. the construction method of underground structure precipitation open caisson, is characterized in that comprising the following steps:
(1) precipitation steel pipe is made, the length of precipitation steel pipe is by the dewatering well degree of depth and structure base slab thickness and stretch out base arrangement face 100mm and calculate, the uniform water seepage hole in precipitation steel pipe lower end, outside screen pack wrapped multiple, is welded with two road seal rings on the top of precipitation steel pipe;
(2) annular wells dish is made with plank;
(3) annular wells dish is laid to the center pre-determining dewatering well;
(4) the annularly well dish J-shaped wall of standard common brick laid dry thickness 240mm, adds iron wire at vertical direction stretcher wall several piece plank when often building 1 meter high by laying bricks or stones and reinforces tighten along outer ring;
(5) manually to dredge a well clearly open caisson one piece of integral sinking that interior sand or soil allows annular wells dish and brick wall form, reduce shoveling difficulty with giant punching soil if desired, or suitably add load and accelerate;
(6) sink while upwards add block J-shaped wall, until open caisson reaches desired depth, whole in frustum of a cone after open caisson completes;
(7) put 200mm thick 1-3 level stone in shaft bottom, put into the precipitation steel pipe made above, outside steel pipe, surrounding throws in elevation location at the bottom of 1-3 level stone to bed course;
(8) muddy water in precipitation steel pipe is taken out with foul water pump until be all clear water and not containing silt stone, change submersible pump and carry out continuous pumpage dewatering;
(9) precipitation should carry out continuously, determines whether continue precipitation after base arrangement concrete completes as required, causing ground influenced, being also used as maintenance water and retaining a period of time if do not taken silt out of;
(10) after Underground Construction completes, well casing shutoff is carried out after reaching design strength; Described well casing shutoff comprises the following steps:
(11) along precipitation steel pipe base arrangement concrete pavement dug out circular groove in advance and clean up;
(12) accelerate to draw water reduction underground water;
(13) fast hardening concrete quick closure is used lower than blinding concrete absolute altitude 200mm with lower part steel pipe;
(14) immediately by the 200mm height steel duct below the downward jam-pack blinding concrete of cork made in advance, with 50mm position below the precipitation steel pipe on the fast hardening concrete quick closure blinding concrete of band microdilatancy to base arrangement surface layer, top is closed by the steel plate rapid welding that thickness 16mm, diameter equal pipe diameter immediately, then slices off the steel pipe of the bottom 130mm exceeding artificial raggle on base plate; Slice off steel pipe for convenience, the depth of groove that artificial raggle bottom steel pipe is formed is 30mm, groove diameter is that outer diameter of steel pipes adds the distance 100mm being convenient to cut off construction, after slicing off steel pipe, finally build groove and base arrangement face put down with carrying higher leveled microdilatancy pea gravel concreten than base arrangement concrete strength again.
2. the construction method of underground structure precipitation open caisson according to claim 1, is characterized in that: the thickness making annular wells dish plank in step (2) is not less than 35mm.
3. the construction method of underground structure precipitation open caisson according to claim 1, is characterized in that: in step (6), the back cut diameter of open caisson is not less than 600mm, and lower port diameter is 900mm.
4. the construction method of underground structure precipitation open caisson according to claim 1, is characterized in that: the wide 50mm of circular groove, dark 30mm in step (11).
5. the construction method of underground structure precipitation open caisson according to claim 1, is characterized in that: in step (14), cork thickness is 200mm.
CN201310380958.3A 2013-08-28 2013-08-28 The construction method of underground structure precipitation open caisson Expired - Fee Related CN103485358B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310380958.3A CN103485358B (en) 2013-08-28 2013-08-28 The construction method of underground structure precipitation open caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310380958.3A CN103485358B (en) 2013-08-28 2013-08-28 The construction method of underground structure precipitation open caisson

Publications (2)

Publication Number Publication Date
CN103485358A CN103485358A (en) 2014-01-01
CN103485358B true CN103485358B (en) 2016-02-24

Family

ID=49825913

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310380958.3A Expired - Fee Related CN103485358B (en) 2013-08-28 2013-08-28 The construction method of underground structure precipitation open caisson

Country Status (1)

Country Link
CN (1) CN103485358B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105133628B (en) * 2015-09-14 2017-05-24 中国建筑第二工程局有限公司 Under-pressure leaking stoppage structure and method for underground garage sump
CN105350553A (en) * 2015-09-25 2016-02-24 中国二十冶集团有限公司 Dewatering tube well for foundation pit construction with cover-excavation method and foundation pit construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000087679A (en) * 1998-09-10 2000-03-28 Kato Kensetsu:Kk Underground structure, and its constructing method
CN2644525Y (en) * 2003-09-19 2004-09-29 盛爱华 Seepage control sunk well
JP4232263B2 (en) * 1999-03-19 2009-03-04 株式会社大林組 Construction method for underwater foundation
CN101787703A (en) * 2010-03-17 2010-07-28 中国二十二冶集团有限公司 Sinking construction method of sinking well with geology of gravel and pebble beds under saturated water condition
CN102454167A (en) * 2010-10-21 2012-05-16 五冶集团上海有限公司 Construction method for large ultra-deep well

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000087679A (en) * 1998-09-10 2000-03-28 Kato Kensetsu:Kk Underground structure, and its constructing method
JP4232263B2 (en) * 1999-03-19 2009-03-04 株式会社大林組 Construction method for underwater foundation
CN2644525Y (en) * 2003-09-19 2004-09-29 盛爱华 Seepage control sunk well
CN101787703A (en) * 2010-03-17 2010-07-28 中国二十二冶集团有限公司 Sinking construction method of sinking well with geology of gravel and pebble beds under saturated water condition
CN102454167A (en) * 2010-10-21 2012-05-16 五冶集团上海有限公司 Construction method for large ultra-deep well

Also Published As

Publication number Publication date
CN103485358A (en) 2014-01-01

Similar Documents

Publication Publication Date Title
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN102454167A (en) Construction method for large ultra-deep well
CN108560542B (en) Waste tire coated building slag bidirectional reinforcement and construction method thereof
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN104110038A (en) Construction method for large-area pit support structure in deep-sludge type soft soil area
CN102383412A (en) Construction method by adopting dewatering and water recharging to control sedimentation surrounding deep foundation pit
CN206706792U (en) Deep foundation pit precipitation well construction
CN107217683B (en) Drainage pipeline foundation filling seepage-proofing collapse-proofing structure and construction method thereof
CN104153371A (en) Grouting-to-stop-water construction method of underwater rubble bed
CN112160324A (en) Construction method for deep foundation pit support
CN104499560B (en) Combined rainwater seepage well and construction method
CN101936032A (en) Method for mounting and constructing polyethylene double-wall corrugated water discharge pipe
CN103806470A (en) Production and installation method for reinforced concrete inspection well
CN104179189A (en) Dewatering and drainage structure of foundation pit deep drop area and construction method thereof
CN204174631U (en) A kind of foundation ditch falls the water drainage structure in dark region
CN103290911B (en) Steel concrete eco-drainage ditch and construction method thereof
CN107059904B (en) A kind of underground pipe gallery ponding well excavation method
CN102330436A (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN103485358B (en) The construction method of underground structure precipitation open caisson
CN106320368A (en) Construction method suitable for open cut pipeline of composite stratum
CN117738192A (en) Construction method combining deep well shallow excavation and open caisson method
CN203559426U (en) Dewatering open caisson of underground structure
CN217053672U (en) Large-diameter inspection well pile drilling method construction system
CN102587391A (en) Construction process for large-aperture brick and concrete reverse hanging well
CN205062744U (en) Half gravity type two -stage view anti -flood wall on half cantilever

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160224