CN103473414A - Engineering construction simulation method - Google Patents
Engineering construction simulation method Download PDFInfo
- Publication number
- CN103473414A CN103473414A CN2013104125872A CN201310412587A CN103473414A CN 103473414 A CN103473414 A CN 103473414A CN 2013104125872 A CN2013104125872 A CN 2013104125872A CN 201310412587 A CN201310412587 A CN 201310412587A CN 103473414 A CN103473414 A CN 103473414A
- Authority
- CN
- China
- Prior art keywords
- construction
- engineering construction
- lifting
- emulation mode
- simulated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 67
- 238000000034 method Methods 0.000 title claims abstract description 11
- 238000004088 simulation Methods 0.000 title claims abstract description 11
- 238000005259 measurement Methods 0.000 claims description 4
- 238000005516 engineering process Methods 0.000 abstract description 8
- 238000004364 calculation method Methods 0.000 abstract 1
- 230000007812 deficiency Effects 0.000 description 2
- 208000019901 Anxiety disease Diseases 0.000 description 1
- 230000036506 anxiety Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005094 computer simulation Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention relates to a simulation construction technology, discloses an engineering construction simulation method, and solves the problems of low precision, insufficient capability of forecasting on-site complex environment and low construction efficiency caused by only relying on theoretical calculation in the traditional technology. The method comprises the following steps: a. formulating a preliminary construction scheme according to the condition of the engineering construction site; b. performing working condition modeling on a computer by adopting three-dimensional software; c. setting various animation paths on the basis of the established working condition model to carry out simulated hoisting construction; d. recording data of simulated hoisting construction; e. and carrying out actual construction according to the data of the simulated hoisting construction. The scheme of the invention is not only suitable for municipal engineering construction, but also suitable for other types of engineering construction.
Description
Technical field
The present invention relates to the construction simulation technology, specifically, relate to the engineering construction emulation mode.
Background technology
Municipal works have construction environment complexity, duration anxiety, safe mass requirement high outward, the hoisting engineering of especially large-scale structure, calculate and can't meet construction requirement by traditional theory: traditional theoretical computational accuracy is not high, anticipation ability deficiency to on-the-spot complex environment, thereby need to carry out a large amount of examinations hang work before formal construction, operating efficiency is low.
Summary of the invention
Technical matters to be solved by this invention is: a kind of engineering construction emulation mode is proposed, solve in conventional art only rely on theoretical calculate the precision of bringing not high, to on-the-spot complex environment anticipation ability deficiency, the problem that operating efficiency is low.
The present invention solves the problems of the technologies described above adopted technical scheme:
The engineering construction emulation mode comprises the following steps:
A. formulate preliminary arrangement and method for construction according to the engineering construction field condition;
B. adopt on computers three-dimensional software to carry out state modeling;
C. on the basis of the condition model of setting up, various animation paths are set and are simulated lifting construction;
D. the data of lifting construction simulated in record;
E. carry out practice of construction according to the data of simulation lifting construction.
Concrete, in step a, describedly according to the engineering construction field condition, formulate selection and the primary election of loop wheel machine model that preliminary arrangement and method for construction comprises the lifting form.
Concrete, in step b, described three-dimensional software is can Accurate Model and the three-dimensional software of measurement, as: SKETUP or Tekla etc.
Concrete, in step b, the described state modeling that carries out refers to according to the ratio of 1: 1 and carries out state modeling.
Concrete, in step c, the ultimate limit state when being simulated lifting construction will meet the lifting performance table of loop wheel machine, if ultimate limit state should be selected other model loop wheel machines else not within the lifting performance table scope of loop wheel machine.
Concrete, in steps d, the data of described record simulation lifting construction comprise: loop wheel machine erect-position, track route and arm elevation data.
The invention has the beneficial effects as follows: by utilize three-dimensional software to carry out state modeling at computing machine after, simulated lifting construction on the basis of modeling, and record simulated data, finally according to simulated data, carry out practice of construction, making construction in complex engineering reach can be simulated, realize the effect of What You See Is What You Get, thereby formulate proactive arrangement and method for construction, accuracy is high; And can omit examination suspension ring joint, improve operating efficiency, to meet construction period.
The accompanying drawing explanation
Engineering construction emulation mode process flow diagram in Fig. 1 embodiment of the present invention.
Embodiment
Emulation technology is a kind of computer modeling technique of rising in recent years, it utilizes computing machine to carry out modeling, carry out the virtual field operation on the basis of modeling, purpose of the present invention utilizes emulation technology to create facility for engineering construction exactly, only depended on theoretical calculating to solve in conventional art before engineering construction, cause precision not high, to on-the-spot complex environment anticipation ability is not enough, operating efficiency is low problem.
Below in conjunction with drawings and Examples, the solution of the present invention is further described:
Referring to Fig. 1, take Municipal Engineering Construction as example, the engineering construction method in this example adopts following steps to realize:
Step 101, according to the Municipal Engineering Construction field condition, formulate preliminary arrangement and method for construction; In this step, can grasp detailed field working conditions data information by checking design drawing and the in-site measurement of the on-the-spot existing structure of municipal works, according to actual conditions, select lifting form and the primary election of loop wheel machine model;
Step 102, adopt three-dimensional software to carry out state modeling on computers; In this step, can utilize SKETUP or Tekla etc. can Accurate Model and the three-dimensional software of measurement carry out state modeling according to the ratio of 1: 1;
Step 103, on the basis of the condition model of setting up, various animation paths are set and are simulated lifting construction; In this step, the ultimate limit state when being simulated lifting construction will meet the lifting performance table of loop wheel machine, if ultimate limit state should be selected other model loop wheel machines else not within the lifting performance table scope of loop wheel machine.
The data of step 104, record simulation lifting construction; In this step, in the three-dimensional visual simulation work progress, to make a record simulated data, particularly the data such as loop wheel machine erect-position, track route and the arm elevation angle;
Step 105, according to the simulation lifting construction data carry out practice of construction; In this step, during practice of construction, to be constructed in strict accordance with the simulated data of record, be forbidden arbitrarily changing construction parameter.
It should be noted that; scheme in the present invention is not only applicable to Municipal Engineering Construction; be equally applicable to other type engineering construction; be that the scope of protection of present invention comprises but is not limited only to above-described embodiment; those skilled in the art are described in the equivalent modifications of in the situation that does not break away from Spirit Essence of the present invention, technology contents of the present invention being made/replacement according to above, all within protection scope of the present invention.
Claims (6)
1. engineering construction emulation mode, is characterized in that, comprises the following steps:
A. formulate preliminary arrangement and method for construction according to the engineering construction field condition;
B. adopt on computers three-dimensional software to carry out state modeling;
C. on the basis of the condition model of setting up, various animation paths are set and are simulated lifting construction;
D. the data of lifting construction simulated in record;
E. carry out practice of construction according to the data of simulation lifting construction.
2. engineering construction emulation mode as claimed in claim 1, is characterized in that, in step a, describedly according to the engineering construction field condition, formulates selection and the primary election of loop wheel machine model that preliminary arrangement and method for construction comprises the lifting form.
3. engineering construction emulation mode as claimed in claim 1 or 2, is characterized in that, in step b, described three-dimensional software is can Accurate Model and the three-dimensional software of measurement.
4. engineering construction emulation mode as claimed in claim 1 or 2, is characterized in that, in step b, the described state modeling that carries out refers to according to the ratio of 1: 1 and carries out state modeling.
5. engineering construction emulation mode as claimed in claim 1 or 2, it is characterized in that, in step c, the ultimate limit state when being simulated lifting construction will meet the lifting performance table of loop wheel machine, if ultimate limit state, within the lifting performance table scope of loop wheel machine, should not selected other model loop wheel machines else.
6. engineering construction emulation mode as claimed in claim 1 or 2, is characterized in that, in steps d, the data of described record simulation lifting construction comprise: loop wheel machine erect-position, track route and arm elevation data.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013104125872A CN103473414A (en) | 2013-09-11 | 2013-09-11 | Engineering construction simulation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013104125872A CN103473414A (en) | 2013-09-11 | 2013-09-11 | Engineering construction simulation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103473414A true CN103473414A (en) | 2013-12-25 |
Family
ID=49798262
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013104125872A Pending CN103473414A (en) | 2013-09-11 | 2013-09-11 | Engineering construction simulation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103473414A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104951581A (en) * | 2014-03-31 | 2015-09-30 | 中国石油天然气股份有限公司 | Equipment installation construction scheme simulation verification method and device based on CAM platform |
CN105550422A (en) * | 2015-12-08 | 2016-05-04 | 中国一冶集团有限公司 | Method for simulating hoisting process based on BIM technology |
CN107010542A (en) * | 2017-04-17 | 2017-08-04 | 山东建筑大学 | A kind of intelligent Lift-on/Lift-off System of assembled architecture and method |
CN108269069A (en) * | 2018-02-14 | 2018-07-10 | 安徽工大信息技术有限公司 | A kind of analog platform and analogy method of the construction site based on dehumidifying antiseepage equipment |
CN110135757A (en) * | 2019-05-23 | 2019-08-16 | 中铁二局集团有限公司 | A kind of method of weight in determining limited space, big lifting component scheme |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060155402A1 (en) * | 2001-11-21 | 2006-07-13 | Dale Read | 3d virtual manufacturing process |
CN102184285A (en) * | 2011-05-03 | 2011-09-14 | 三一集团有限公司 | Digital prototyping design integrated development method and system |
CN102663196A (en) * | 2012-04-17 | 2012-09-12 | 中南大学 | Automobile crane hoisting simulation method on basis of virtual reality |
CN102968518A (en) * | 2012-10-08 | 2013-03-13 | 蔡坤 | Topology optimization design method for novel down-the-hole arc-shaped hydraulic steel gate |
-
2013
- 2013-09-11 CN CN2013104125872A patent/CN103473414A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060155402A1 (en) * | 2001-11-21 | 2006-07-13 | Dale Read | 3d virtual manufacturing process |
CN102184285A (en) * | 2011-05-03 | 2011-09-14 | 三一集团有限公司 | Digital prototyping design integrated development method and system |
CN102663196A (en) * | 2012-04-17 | 2012-09-12 | 中南大学 | Automobile crane hoisting simulation method on basis of virtual reality |
CN102968518A (en) * | 2012-10-08 | 2013-03-13 | 蔡坤 | Topology optimization design method for novel down-the-hole arc-shaped hydraulic steel gate |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104951581A (en) * | 2014-03-31 | 2015-09-30 | 中国石油天然气股份有限公司 | Equipment installation construction scheme simulation verification method and device based on CAM platform |
CN104951581B (en) * | 2014-03-31 | 2018-07-10 | 中国石油天然气股份有限公司 | Equipment installation construction scheme simulation verification method and device based on CAM platform |
CN105550422A (en) * | 2015-12-08 | 2016-05-04 | 中国一冶集团有限公司 | Method for simulating hoisting process based on BIM technology |
CN107010542A (en) * | 2017-04-17 | 2017-08-04 | 山东建筑大学 | A kind of intelligent Lift-on/Lift-off System of assembled architecture and method |
CN107010542B (en) * | 2017-04-17 | 2018-08-03 | 山东建筑大学 | A kind of assembled architecture intelligence hanging method |
CN108269069A (en) * | 2018-02-14 | 2018-07-10 | 安徽工大信息技术有限公司 | A kind of analog platform and analogy method of the construction site based on dehumidifying antiseepage equipment |
CN108269069B (en) * | 2018-02-14 | 2021-03-02 | 安徽工大信息技术有限公司 | Construction site simulation platform and simulation method based on dehumidification and seepage-proofing equipment |
CN110135757A (en) * | 2019-05-23 | 2019-08-16 | 中铁二局集团有限公司 | A kind of method of weight in determining limited space, big lifting component scheme |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110580376B (en) | Revit and Dynamo-based pile foundation model creation method | |
CN103473414A (en) | Engineering construction simulation method | |
CN104965947B (en) | A kind of bridge three-dimensional design method based on BIM technology | |
Liu et al. | Investigation of the effects of platform motion on the aerodynamics of a floating offshore wind turbine | |
CN102750420B (en) | Method for establishing virtual prototype of hydraulic excavator | |
CN103336854B (en) | A kind of modeling method of high slope three-dimensional finite element model | |
CN105586995A (en) | BIM-based deformation monitoring method for deep foundation pit | |
CN105912780B (en) | The method of underground hole group three dimensional design and construction speed simulation interactive | |
CN103149600B (en) | Automatic wiring method for determining hydrogeological parameters based on optimization control point | |
CN108090313A (en) | A kind of Complex Rock model of fissuration models recognition methods | |
CN111241660A (en) | Civil engineering experiment detection system and method based on cloud computing technology | |
CN104318030A (en) | Deformation-equivalence based automatic comprehensive deformation modulus calculating method for arch-dam foundations | |
CN104504210B (en) | A kind of complex electromechanical systems Reliability Modeling based on Petri network | |
Mallardo et al. | An improved isogeometric boundary element method approach in two dimensional elastostatics | |
CN105302979A (en) | Modeling method and system of valve groups in two-phase fluid network model | |
CN106066829A (en) | A kind of missile-borne time-consuming real-time computing technique of embedded Control software cycle | |
CN203164728U (en) | Cable tunnel remote automation monitoring system | |
CN104461852A (en) | Fan power consumption calculation method | |
CN104808647B (en) | The fault detection method of rod-pumped well under wireless network environment | |
CN104451012B (en) | The expansion drum liquid level fault detect flexible measurement method of blast furnace soft water closed circulation system | |
RU2013132608A (en) | METHOD FOR SCENARIOUS DYNAMIC MODELING OF TECHNICAL AND ECONOMIC INDICATORS OF A LIFE CYCLE OF A POWER OBJECT AND A SOFTWARE AND HARDWARE COMPLEX FOR ITS IMPLEMENTATION | |
CN107368651A (en) | Hydropower Station Underground formula factory building kinematic analysis numerical model design method | |
Yuan et al. | Design and Simulation Analysis of Compound Bucket Hydraulic System of Excavator | |
Zhang et al. | Pumping unit optimization design based on virtual prototype technology | |
Zhong et al. | Mechanical-hydraulic coupling simulation for hydraulic excavator working mechanism |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20131225 |