CN103448883A - Installation guiding and temporary fixing device of groined beam of sliding channel - Google Patents

Installation guiding and temporary fixing device of groined beam of sliding channel Download PDF

Info

Publication number
CN103448883A
CN103448883A CN2013103754665A CN201310375466A CN103448883A CN 103448883 A CN103448883 A CN 103448883A CN 2013103754665 A CN2013103754665 A CN 2013103754665A CN 201310375466 A CN201310375466 A CN 201310375466A CN 103448883 A CN103448883 A CN 103448883A
Authority
CN
China
Prior art keywords
cross beam
slideway cross
temporary
supporting bracket
fastening device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013103754665A
Other languages
Chinese (zh)
Other versions
CN103448883B (en
Inventor
张鸿
罗自立
李宗哲
郭劲
程茂林
李海方
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201310375466.5A priority Critical patent/CN103448883B/en
Publication of CN103448883A publication Critical patent/CN103448883A/en
Application granted granted Critical
Publication of CN103448883B publication Critical patent/CN103448883B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The invention discloses an installation guiding and temporary fixing device of a groined beam of a sliding channel. The installation guiding and temporary fixing device comprises a temporary supporting corbel which is fixedly connected with the groined beam of the sliding channel, and is also connected with a base of a length-adjustable supporting device by bolts. The installation guiding and temporary fixing device disclosed by the invention solves the technical difficulty that after the accurate positioning construction of the groined beam of the sliding channel is finished, the accurate fixation of in-position elevation of the groined beam of the sliding channel is poor and that an unsmooth placing plane of pile tops causes difficult selection of temporary supporting cushion blocks. The installation guiding and temporary fixing device has the characteristics of compact structure and convenience in installation and disassembly.

Description

A kind of slideway cross beam is installed guiding and temporary fastening device
Technical field
The present invention relates to the arine railway technical field of construction, refer to particularly a kind of slideway cross beam installation guiding and temporary fastening device.
Background technology
In recent years, the Port System that Chinese Water Transportation had formed already was rationally distributed, well arranged, multiple functional, have complementary advantages, national high-grade waterway net also basically forms simultaneously.Lasting vigorous along with water transport market, the increase of ship structure yardstick, the track groups number of comb type side slipway increases thereupon, and the slideway underwater penetration is also deepened thereupon, and this installation to track girder has brought larger challenge.In the prior art, the slideway cross beam is laid in the pile cover top, both sides at pile cover bilge logs cross beam are provided with the pile cover block, and the slideway cross beam is after completing accurate adjustment position construction, usually adopts pad steel-sheet method to carry out the adjustment of absolute altitude in place to the beam section and carry out temporary fixed before building of node concrete under water.But this kind of construction method can't meet the high precision installation requirement that the slideway cross beam gets on the right track (rail top of steel rail absolute altitude error<± 3mm).
Therefore, need be improved prior art.
Summary of the invention
Purpose of the present invention is exactly the deficiency that will solve the above-mentioned background technology, and a kind of compact conformation, the assembling and disassembling guiding of slideway cross beam installation easily and temporary fastening device are provided.
Technical scheme of the present invention is: a kind of slideway cross beam is installed guiding and temporary fastening device, it is characterized in that: it comprises the temporary supporting bracket be fixedly connected with the slideway cross beam, and described temporary supporting bracket is with together with the base of length-adjustable bracing or strutting arrangement is bolted.
In such scheme:
The bottom of described temporary supporting bracket is welded with the Horizontal limiting ring flat-plate, and the base of bracing or strutting arrangement is placed in the Horizontal limiting ring flat-plate.
Described bracing or strutting arrangement is supported in the top of pile cover block.
Described bracing or strutting arrangement is lifting screw, and the base of described lifting screw is with together with the temporary supporting bracket is bolted, and the piston rod of lifting screw is supported in the top of pile cover block.
Pre-buried structure weld together in described temporary supporting bracket and slideway cross beam.
Described pre-buried structure comprises the vertical anchor slab be arranged on slideway cross beam sidewall, described vertical anchor slab one side and temporary supporting bracket weld together, the opposite side of vertical anchor slab and an end weld together that is embedded in the horizontal dowel in the slideway cross beam, laterally the other end of dowel is connected with the anchor plate be embedded in the slideway cross beam.
Described temporary supporting bracket below is provided with the guiding stiffener.
The invention has the advantages that:
1), adopt the method for lifting screw to carry out " accurately fixing " to the absolute altitude in place with the slideway cross beam, avoid carrying out traditional artificial absolute altitude adjustment, can meet the high precision installation requirement that the slideway cross beam gets on the right track, overcome the difficulty that the plane injustice is selected the temporary supporting cushion block of shelving due to pile cover;
2), lifting screw and temporary supporting bracket are connected into to the slideway cross beam temporary fastening device of compact conformation, simplified slideway cross beam temporary fixed working procedure under water, improved the operating efficiency of slideway cross beam;
3), assembling and disassembling is convenient, the present invention can make lifting screw separate with the temporary supporting bracket, facilitates the turnover of lifting screw to use, and has significantly shortened the temporary fixed construction period of slideway cross beam.
The invention solves the slideway cross beam after completing the construction of accurate adjustment position, the slideway cross beam is carried out to " accurately fixing " of absolute altitude in place and injustice that plane is shelved on the stake top is difficult to the technical barrier of selection to the temporary supporting cushion block, and there is the temporary fastening device compact conformation, the characteristics of easy installation and removal.
The accompanying drawing explanation
Fig. 1 is facade structures schematic diagram of the present invention;
Fig. 2 is planar structure schematic diagram of the present invention.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in further detail.
As shown in Figure 1 and Figure 2, a kind of slideway cross beam of the present invention is installed guiding and temporary fastening device, it comprises the temporary supporting bracket 5 be fixedly connected with slideway cross beam 11, described temporary supporting bracket 5 links together by bolt 4 with the base of length-adjustable bracing or strutting arrangement 7, removing bolt 4 just can make bracing or strutting arrangement 7 separate with temporary supporting bracket 5, facilitate the turnover of bracing or strutting arrangement 7 to use, significantly shortened the temporary fixed construction period of slideway cross beam 11
The bottom of temporary supporting bracket 5 is welded with Horizontal limiting ring flat-plate 6, and the base of bracing or strutting arrangement 7 is arranged in Horizontal limiting ring flat-plate 6, and Horizontal limiting ring flat-plate 6 can carry out level to spacing to lifting screw 7.
Bracing or strutting arrangement 7 can be supported according to actual state the top of pile cover block 10.Bracing or strutting arrangement 7 is lifting screw, and the base of lifting screw and temporary supporting bracket 5 link together by bolt 4, and the piston rod of lifting screw is supported in the top of pile cover block 10.Adopt the method for lifting screw to carry out " accurately fixing " to the absolute altitude in place with slideway cross beam 11, avoid carrying out traditional artificial absolute altitude adjustment, can meet slideway cross beam 11(track) the high precision installation requirement, overcome the difficulty that the plane injustice is selected the temporary supporting cushion block of shelving due to pile cover 9;
Pre-buried structure weld together in temporary supporting bracket 5 and slideway cross beam 11, wherein pre-buried structure comprises the vertical anchor slab 3 on the sidewall that is arranged on slideway cross beam 11, described vertical anchor slab 3 one sides and temporary supporting bracket 5 weld togethers, the opposite side of vertical anchor slab 3 be embedded in slideway cross beam 11 and an end weld together of the horizontal dowel 2 of spaced set, laterally the other end of dowel 2 is connected with the anchor plate 1 be embedded in slideway cross beam 11.
Described temporary supporting bracket 5 belows are provided with guiding stiffener 8, vertical anchor slab 3, temporary supporting bracket 5 and guiding stiffener 8 form one-piece construction by the mode of welding, guiding stiffener 8 has not only been strengthened temporary supporting bracket 5 structures, and can also tentatively be located in 10 guide piecees of shelving on plane of pile cover block as slideway cross beam 11.
When practical operation, after slideway cross beam 11 completes the fine adjustment construction, by the present invention, designed slideway cross beam is installed to lead and is arranged on four toe places of slideway cross beam 11 with temporary fastening device, now operation is pushed up with the lifting screw that temporary supporting bracket 5 links together, make it stretch out piston rod and be supported in the top of pile cover block 10, guarantee that lifting screw and pile cover block 10 hold out against, guarantee that slideway cross beam 11 fine adjustment systems are after off-load, can smoothly the load of slideway cross beam 11 be transformed on lifting screw, by the operation lifting screw, after guaranteeing 11 installations of slideway cross beam, its four toe places are stressed evenly, complete " accurately fixing " of slideway cross beam 11, completing after node concrete is built of slideway cross beam under water, twist and remove bolt 4, lifting screw is removed, make lifting screw can have enough to meet the need use.
Slideway cross beam 11 in the present invention is by four-point supporting, and the height that every some needs prop up pad differs, and corresponding stake top mark height also demand differs, and, by the lifting screw in operation the present invention, can meet the high demand differed of a top mark.
The invention solves slideway cross beam 11 after completing the fine adjustment construction, slideway cross beam 11 is carried out to " accurately fixing " of absolute altitude in place and injustice that plane is shelved on the stake top is difficult to the technical barrier of selection to the temporary supporting cushion block, and there is the temporary fastening device compact conformation, the characteristics of easy installation and removal.

Claims (7)

1. a slideway cross beam is installed guiding and temporary fastening device, it is characterized in that: it comprises the temporary supporting bracket (5) be fixedly connected with slideway cross beam (11), and described temporary supporting bracket (5) links together by bolt (4) with the base of length-adjustable bracing or strutting arrangement (7).
2. slideway cross beam according to claim 1 is installed guiding and temporary fastening device, it is characterized in that: the bottom of described temporary supporting bracket (5) is welded with Horizontal limiting ring flat-plate (6), and the base of bracing or strutting arrangement (7) is arranged in Horizontal limiting ring flat-plate (6).
3. slideway cross beam according to claim 1 is installed guiding and temporary fastening device, and it is characterized in that: described bracing or strutting arrangement (7) is supported in the top of pile cover block (10).
4. slideway cross beam according to claim 3 is installed guiding and temporary fastening device, it is characterized in that: described bracing or strutting arrangement (7) is lifting screw, the base of described lifting screw and temporary supporting bracket (5) link together by bolt (4), and the piston rod of lifting screw is supported in the top of pile cover block (10).
5. slideway cross beam according to claim 1 is installed guiding and temporary fastening device, it is characterized in that: the pre-buried structure weld together in described temporary supporting bracket (5) and slideway cross beam (11).
6. slideway cross beam according to claim 5 is installed guiding and temporary fastening device, it is characterized in that: described pre-buried structure comprises the vertical anchor slab (3) on the sidewall that is arranged on slideway cross beam (11), described vertical anchor slab (3) one sides and temporary supporting bracket (5) weld together, the opposite side of vertical anchor slab (3) and an end weld together that is embedded in the horizontal dowel (2) in slideway cross beam (11), laterally the other end of dowel (2) is connected with the anchor plate (1) be embedded in slideway cross beam (11).
7. slideway cross beam according to claim 6 is installed guiding and temporary fastening device, it is characterized in that: described temporary supporting bracket (5) below is provided with guiding stiffener (8).
CN201310375466.5A 2013-08-26 2013-08-26 A kind of slideway cross beam installs guiding and temporary fastening device Active CN103448883B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310375466.5A CN103448883B (en) 2013-08-26 2013-08-26 A kind of slideway cross beam installs guiding and temporary fastening device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310375466.5A CN103448883B (en) 2013-08-26 2013-08-26 A kind of slideway cross beam installs guiding and temporary fastening device

Publications (2)

Publication Number Publication Date
CN103448883A true CN103448883A (en) 2013-12-18
CN103448883B CN103448883B (en) 2016-03-30

Family

ID=49731823

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310375466.5A Active CN103448883B (en) 2013-08-26 2013-08-26 A kind of slideway cross beam installs guiding and temporary fastening device

Country Status (1)

Country Link
CN (1) CN103448883B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103482042A (en) * 2013-09-22 2014-01-01 中交第二航务工程局有限公司 Mounting and constructing method for deepwater comb-shaped slide cross beam
CN103879527A (en) * 2014-03-19 2014-06-25 中交第二航务工程局有限公司 Linear control method for deep water high precision mounting of pectination slideway well-shaped beam
CN104260853A (en) * 2014-09-15 2015-01-07 中交第二航务工程局有限公司 Underwater three-way displacement adjusting device of slide way cross beam

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL99416C (en) *
SE514307C2 (en) * 1998-09-01 2001-02-05 Hans Ingmar Granlind Laying out slipway track for launching boat, by joining U=shaped rail beams end to end with splice sections
CN201172797Y (en) * 2008-04-03 2008-12-31 中铁十一局集团第六工程有限公司 Portable movable mould frame bridging machine
CN203497149U (en) * 2013-08-26 2014-03-26 中交第二航务工程局有限公司 Slideway cross beam mounting orientation and temporary fixation device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL99416C (en) *
SE514307C2 (en) * 1998-09-01 2001-02-05 Hans Ingmar Granlind Laying out slipway track for launching boat, by joining U=shaped rail beams end to end with splice sections
CN201172797Y (en) * 2008-04-03 2008-12-31 中铁十一局集团第六工程有限公司 Portable movable mould frame bridging machine
CN203497149U (en) * 2013-08-26 2014-03-26 中交第二航务工程局有限公司 Slideway cross beam mounting orientation and temporary fixation device

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
吴鹏程: "沪东造船厂2号船台滑道水下接长工程施工工艺", 《水运工程》, no. 09, 25 September 2002 (2002-09-25) *
李亮等: "滑道梁多样化施工方案综述", 《现代商贸工业》, no. 23, 31 December 2012 (2012-12-31) *
郭成喜: "沉箱预制场水下滑道工艺设计与施工", 《山西建筑》, vol. 32, no. 22, 30 November 2006 (2006-11-30) *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103482042A (en) * 2013-09-22 2014-01-01 中交第二航务工程局有限公司 Mounting and constructing method for deepwater comb-shaped slide cross beam
CN103482042B (en) * 2013-09-22 2015-09-02 中交第二航务工程局有限公司 A kind of deep water comb shape slideway cross beam construction method of installation
CN103879527A (en) * 2014-03-19 2014-06-25 中交第二航务工程局有限公司 Linear control method for deep water high precision mounting of pectination slideway well-shaped beam
CN104260853A (en) * 2014-09-15 2015-01-07 中交第二航务工程局有限公司 Underwater three-way displacement adjusting device of slide way cross beam

Also Published As

Publication number Publication date
CN103448883B (en) 2016-03-30

Similar Documents

Publication Publication Date Title
CN105220769A (en) Large area bolt-ball net frame integral top lifting construction method
CN102587281A (en) Walking type multi-point jacking-pushing construction method
CN103448883A (en) Installation guiding and temporary fixing device of groined beam of sliding channel
CN104831632A (en) Upper transverse beam and lower transverse beam construction method for bridge cable bent tower
CN201560397U (en) Whole support for steel box girder precise location installation
CN203497149U (en) Slideway cross beam mounting orientation and temporary fixation device
CN202000265U (en) Concrete construction formwork for high pier of bridge
EP1835076A1 (en) Method and arrangement for moving a bridge
CN203321529U (en) Train type rapid lifting and folding work platform for tunnel engineering
CN202745364U (en) Template support structure
CN202380732U (en) Self-load bearing template support device utilizing steel reinforced concrete beam
CN103967332A (en) Construction method of building site barrier
CN109629350B (en) Prestressed seamless connection concrete track beam for empty iron and construction method thereof
CN203821878U (en) Integral horizontal moving device for building with foundation
CN203795435U (en) Diagonal bracing reinforcing structure
CN203034605U (en) Jacking support frame for latticed shell structure
CN202705907U (en) Post-tensioning method pre-stressed girder horizontal girder moving system
CN202689585U (en) Ground fitting up assembly mould of large steel truss
MX2021007820A (en) Floating platform for high-power wind turbines.
CN202139543U (en) Bracket structure used for construction of continuous box girders
CN201843352U (en) Sliding framework platform for large-column gird large-area net frame structure
CN205276166U (en) Guardrail stand positioner
CN211364328U (en) A adjustment type base for installation of contact net channel in tunnel
CN201208688Y (en) Fixture for welding large-sized H section steel structural part
CN211713712U (en) Incremental launching sliding rail device with limiting function for bridge construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant