CN103437285B - 满堂支架现浇箱梁施工工艺 - Google Patents

满堂支架现浇箱梁施工工艺 Download PDF

Info

Publication number
CN103437285B
CN103437285B CN201310280033.1A CN201310280033A CN103437285B CN 103437285 B CN103437285 B CN 103437285B CN 201310280033 A CN201310280033 A CN 201310280033A CN 103437285 B CN103437285 B CN 103437285B
Authority
CN
China
Prior art keywords
concrete
web
girder
building
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310280033.1A
Other languages
English (en)
Other versions
CN103437285A (zh
Inventor
朱晓明
刘华
田新平
徐习宝
赵军科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHB First Engineering Co Ltd
Original Assignee
CCCC SHB First Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHB First Engineering Co Ltd filed Critical CCCC SHB First Engineering Co Ltd
Priority to CN201310280033.1A priority Critical patent/CN103437285B/zh
Publication of CN103437285A publication Critical patent/CN103437285A/zh
Application granted granted Critical
Publication of CN103437285B publication Critical patent/CN103437285B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种满堂支架现浇箱梁施工艺,它根据柔性支架的特点,采用从预留空间处开始往两墩顶方向浇筑砼,然后再来施工中间预留的底、腹板及顶板的箱梁砼,它包括如下步骤:(1)第一次砼浇筑,先进行箱梁底腹板区域砼浇筑,在主梁跨中中间预留空间距离长为H的底腹板不浇筑;(2)第二次砼浇筑,进行顶板和箱梁剩余的底腹板区域砼浇筑,再来进行浇筑两侧的顶板及步骤(1)中中间预留距离长为H的底腹板箱梁砼。本发明的工艺适用于超宽或受施工条件限制的现浇箱梁桥梁工程,该工艺可以最大限度减小支架沉降变形对主梁的影响,从根本上消除支架变形过大给现浇箱梁带来的危害,同时可节约支架材料的投入,并能确保施工安全。<!--1-->

Description

满堂支架现浇箱梁施工工艺
技术领域
本发明涉及桥梁现浇施工领域,具体的是指一种满堂支架现浇箱梁施工工艺。
背景技术
满堂支架法是种按一定间距,密布搭设,起支撑作用的脚手架的施工方法。目前常见于现浇桥梁施工。满堂支架法施工是一种长期被采用的方法,施工时需要大量的模板支架。支架法施工是在桥位处搭设支架,在支架上浇筑桥梁体砼,待砼达到强度后拆除模板及支架。支架法施工最大的优点是不需要大型吊装设备,其缺点是施工用的支架模板消耗量大、工期长,对山区桥梁及高墩有很大的局限性。
满堂支架法现浇预应力砼连续箱梁在桥梁工程中是一种较为常见的施工方法,最近几年,随着国内铁路、公路交通基础设施建设的高速发展,按照满堂支架施工设计的桥梁也越来越多,满堂支架的施工技术得到了大大的推广应用,满堂支架施工工艺也不断进行改进。
现代满堂支架施工技术亦朝着大吨位、大跨径方向发展,常规满堂支架钢管杆件本身承载能力有限,所以探讨如何实现在特殊大吨位箱梁、高墩、大断面现浇箱梁等工况条件下的现浇箱梁施工是桥梁建设者经常考虑的问题之一。
在目前的桥梁现浇主梁砼施工中,现浇箱梁砼施工常规施工方法一般分一次、二次或多次浇筑,支架因砼浇注加载,会对主梁线性和结构产生影响,过大的沉降变形会对主梁结构产生危害。在保证现浇箱梁成品质量和安全的前提下,投入临时支撑的数量成为焦点,也直接影响工程措施费的投入。
如何在临时支持数量不改变或减少的基础上,通过改进浇箱梁砼施工工艺来降低主梁过大的沉降变形,是目前需要研究解决的重要课题。
发明内容
针对现有技术的不足,本发明的目的是提供一种满堂支架现浇箱梁施工工艺,它是适合超宽或受施工条件限制的现浇箱梁的支架的新型施工技术,能有效地减少支架沉降变形对主梁浇筑质量的影响。
为实现上述目的,本发明的提供的满堂支架现浇箱梁施工艺,它根据柔性支架的特点,采用从预留空间处开始往两墩顶方向浇筑砼,然后再来施工中间预留的底、腹板及顶板的箱梁砼,它包括如下步骤:
(1)第一次砼浇筑,先进行箱梁底腹板区域砼浇筑,在浇筑箱梁底腹板时,在主梁跨中中间预留空间距离长为H的底腹板不浇筑,浇筑底腹板的顺序为从跨中间开始往两边墩位方向浇筑,保证墩顶不出现结构裂缝;
(2)第二次砼浇筑,进行顶板和箱梁剩余的底腹板区域砼浇筑,待步骤(1)中浇筑后的底腹板砼强度达到拆模强度后拆除底腹板的模板,再来进行从主梁跨中向墩位方向浇筑两侧的顶板及步骤(1)中中间预留距离长为H的底腹板箱梁砼先后一次浇筑。
作为优选方案,所述步骤(1)中将主梁跨中预留空间距离长H为1.2m。
进一步地,现浇箱梁的浇筑顺序:首先浇筑底腹板砼,主梁跨中间预留1.2m长底腹板暂不浇筑;其次从主梁跨中向墩位方向浇筑两侧的顶板砼;然后再浇筑主梁跨中的1.2m底腹板及顶板砼。
本发明的优点在于:本发明的工艺适用于超宽或受施工条件限制的现浇箱梁桥梁工程,该工艺的浇筑砼的方式,可以最大限度减小支架沉降变形对主梁的影响,从根本上消除支架变形过大给现浇箱梁带来的危害,同时可节约支架材料的投入,以较少的材料投入,合理的施工结构和工法,确保施工安全。
附图说明:
图1是本发明的主梁第一次浇筑纵断面示意图。
图2是本发明的主梁第二次浇筑纵断面示意图。
图3是本发明的主梁浇筑横断面示意图。
图中:1、顶板,2、腹板,3、底板,4、箱梁中心线,A阴影部分为主梁第二次浇筑的底腹板及顶板,B阴影部分为主梁第一次浇筑的底腹板,C为第二次浇筑区域,D为第一次浇筑区域。
具体实施方式
以下结合附图和实施例对本发明作进一步地详细描述。
如图1所示的桥梁为预应力砼连续梁桥,主线桥采用等截面大悬臂单箱多室斜腹板箱梁,标准顶板宽度25.5m,标准底板宽度16.3m;翼缘板悬臂4m,外挑翼缘厚度22。各联均采用砼连续箱梁,箱梁顶板厚度26cm,底板厚度24~50cm,腹板厚度45~80cm,梁高为1.7m。箱梁支点设横梁,端横梁宽度1.65m,中横梁宽度2.6m。主梁中间受力越大,越容易沉降变形。
砼浇筑采用输送泵车。如图2所示第一次砼浇筑,先进行箱梁底腹板区域砼浇筑,在浇筑箱梁底腹板时,中间预留1.2m的底腹板不浇筑(预留长度主要考虑箱梁的外观,1.2m是一块竹胶板的宽度),从跨中开始往两侧墩位方向浇筑,保证墩顶不出现结构裂缝;按每孔横隔划分成多段进行,最先段底板砼浇筑后要求先进行第二段底板砼浇筑,到第三段底板为止,再回到第一段进行腹板砼浇筑,使得底板砼有一定的凝结力,这主要是针对商品砼流动性能大这一特性。砼浇筑时注意砼下料冲击力,下料时避免冲击钢筋和预应力波纹管。
如图3所示第二次进行箱梁剩余的底腹板和顶板砼的浇筑。顶板底模的安装需在底板砼凝固以后再施工,并在第一次砼浇筑完成后及时将腹板砼顶面凿毛处理。
箱梁砼浇筑由于采用集中拌和砼进行浇筑,砼初凝时间较短,反映出温度升高快,容易产生收缩裂缝,又由于箱梁节段长、方量大,浇筑时间也较长,先浇段砼的养护应及时进行洒水湿润,初凝后立即用土工布覆盖并洒水养护。砼的洒水养护时间一般为7天,每天洒水的次数以能保持砼表面经常处于湿润状态为度。
在该桥梁中现浇箱梁浇筑底腹板的顺序为:从跨中开始往两侧墩位方向浇筑,保证墩顶不出现结构裂缝;待底腹板砼强度达到拆模强度后拆除底腹板的模板,开始施工顶板的钢筋和砼施工的准备工作,顶板及剩余腹板的砼浇筑顺序尤为重要。
一座高架桥梁宽度25.5m,主梁跨径39.0m,上跨一座跨径为25.0m的空心板梁桥,且净空较小,由于空心板梁桥的承载力和桥下净空的限制,给高架现浇梁桥的施工临时支撑带来极大的困难。通过使用本发明的施工工艺,第一次浇筑时,消除了支架的非弹性变形和80%的弹性变形,且对箱梁无影响;第二次浇筑时,支架只发生20%的弹性变形,只有第二次的支架变形对主梁结构产生影响,且影响很小。科学合理的施工结构和工法,不仅确保了施工质量和安全,而且还减少了材料的投入,直接带了良好的经济效益上百万元。
其它未详细说明的部分均为现有技术。

Claims (3)

1.一种满堂支架现浇箱梁施工工艺,它根据柔性支架的特点,采用从预留空间处开始往两墩顶方向浇筑砼,然后再来施工中间预留的底、腹板及顶板的箱梁砼,它包括如下步骤:
(1)第一次砼浇筑,先进行箱梁底腹板区域砼浇筑,在浇筑箱梁底腹板时,在主梁跨中中间预留空间距离长为H的底腹板不浇筑,浇筑底腹板的顺序为从跨中间开始往两边墩位方向浇筑,保证墩顶不出现结构裂缝;
(2))第二次砼浇筑,进行顶板和箱梁剩余的底腹板区域砼浇筑,待步骤(1)中浇筑后的底腹板砼强度达到拆模强度后拆除底腹板的模板,再来进行从主梁跨中向墩位方向浇筑两侧的顶板及步骤(1)中中间预留距离长为H的底腹板箱梁砼先后一次浇筑。
2.根据权利1所述的满堂支架现浇箱梁施工工艺,其特征在于:所述步骤(1)中将主梁跨中预留空间距离长H为1.2m。
3.根据权利2所述的满堂支架现浇箱梁施工工艺,其特征在于:现浇箱梁的浇筑顺序:首先浇筑底腹板砼,主梁跨中间预留1.2m长底腹板暂不浇筑;其次从主梁跨中向墩位方向浇筑两侧的顶板砼;然后再浇筑主梁跨中的1.2m底腹板及顶板砼。
CN201310280033.1A 2013-07-05 2013-07-05 满堂支架现浇箱梁施工工艺 Active CN103437285B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310280033.1A CN103437285B (zh) 2013-07-05 2013-07-05 满堂支架现浇箱梁施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310280033.1A CN103437285B (zh) 2013-07-05 2013-07-05 满堂支架现浇箱梁施工工艺

Publications (2)

Publication Number Publication Date
CN103437285A CN103437285A (zh) 2013-12-11
CN103437285B true CN103437285B (zh) 2016-04-13

Family

ID=49690994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310280033.1A Active CN103437285B (zh) 2013-07-05 2013-07-05 满堂支架现浇箱梁施工工艺

Country Status (1)

Country Link
CN (1) CN103437285B (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106758824B (zh) * 2016-11-21 2018-08-07 武汉理工大学 大跨径曲线梁桥预应力筋张拉方法
CN110258340A (zh) * 2019-06-11 2019-09-20 中铁一局集团有限公司 一种槽型连续梁的分段式高效施工方法
CN113202010A (zh) * 2021-05-07 2021-08-03 中交一公局集团有限公司 一种预应力混凝土现浇箱梁结构及其施工方法
CN113529576B (zh) * 2021-06-11 2023-04-14 珠海十字门中央商务区建设控股有限公司 预应力钢筋混凝土连续箱梁二次浇筑顶板混凝土裂缝预防方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101130942A (zh) * 2007-09-06 2008-02-27 长业建设集团有限公司 软土地基多孔双悬臂拱形桥结构及其施工方法
CN101824800A (zh) * 2010-04-28 2010-09-08 中铁三局集团有限公司 一种桥位现浇预应力混凝土连续梁的施工方法
CN102116052A (zh) * 2009-12-30 2011-07-06 贵阳铝镁设计研究院 一种钢筋混凝土操作平台梁的浇筑方法
CN102168407A (zh) * 2011-03-23 2011-08-31 中交三航局第三工程有限公司 长大节段支架悬浇箱梁结构裂缝的预防和控制方法
CN102206934A (zh) * 2010-08-30 2011-10-05 江西省交通设计院 一种采用军用桁架移模分块浇筑砼连续梁桥的方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101130942A (zh) * 2007-09-06 2008-02-27 长业建设集团有限公司 软土地基多孔双悬臂拱形桥结构及其施工方法
CN102116052A (zh) * 2009-12-30 2011-07-06 贵阳铝镁设计研究院 一种钢筋混凝土操作平台梁的浇筑方法
CN101824800A (zh) * 2010-04-28 2010-09-08 中铁三局集团有限公司 一种桥位现浇预应力混凝土连续梁的施工方法
CN102206934A (zh) * 2010-08-30 2011-10-05 江西省交通设计院 一种采用军用桁架移模分块浇筑砼连续梁桥的方法
CN102168407A (zh) * 2011-03-23 2011-08-31 中交三航局第三工程有限公司 长大节段支架悬浇箱梁结构裂缝的预防和控制方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"低净空下斜交上跨桥现浇箱梁支架施工技术";张琨然;《城市建设理论研究(电子版)》;20120630(第6期);第1-8页 *

Also Published As

Publication number Publication date
CN103437285A (zh) 2013-12-11

Similar Documents

Publication Publication Date Title
CN104963290A (zh) 平纵曲线组合段变截面现浇箱梁支模结构及施工方法
CN103437285B (zh) 满堂支架现浇箱梁施工工艺
CN108004927B (zh) 双肢三角挂篮及大跨度连续刚构桥悬臂梁段施工方法
CN103981803B (zh) 预制拼装组合型门型墩及其施工方法
CN105538484B (zh) 一种用于防止放张拉应力破坏的u型梁模具及u型梁制备方法
CN102900230B (zh) 一种可升降钢筋混凝土后浇带施工方法
CN107905111B (zh) 一种刚构连续梁边跨施工工艺
CN107905124B (zh) 一种对称式刚构连续梁施工工艺
CN110700105B (zh) 高墩墩柱与系梁同步施工方法及所用模板
CN201738463U (zh) 主体结构与填充墙体之间的竖向连接结构
CN103147385B (zh) 双拼式矮塔斜拉桥
CN203559354U (zh) 一种应用于预应力混凝土部分斜拉桥的斜拉索锚固结构
CN204875533U (zh) 平纵曲线组合段变截面现浇箱梁支模结构
CN113846746A (zh) 一种利于高效施工的地下室结构及施工方法
CN211729676U (zh) 用于镂空桥梁面板的组合式模板
CN102303351B (zh) 一种一次性浇注成型的t型梁制梁方法
CN104746434B (zh) 一种不拆除外模的合龙段模板系统
CN208280023U (zh) 后张法预应力梁体梁端封锚定型模板
CN217326423U (zh) 一种现浇混凝土墙体免拆模支护一体构造
CN208088108U (zh) 一种简支变连续桥梁结构构造
CN215882010U (zh) 一种可调节的混凝土箱梁内模装置
CN202117319U (zh) 端头模板
CN203065975U (zh) 箱梁0号块浇筑支撑系统
CN207452730U (zh) 一种异形箱梁支架体系
CN206034272U (zh) 一种体外预应力钢锚固装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant