CN103362312B - 支住混凝土构件提升环的方法和用于该提升环的支撑件 - Google Patents
支住混凝土构件提升环的方法和用于该提升环的支撑件 Download PDFInfo
- Publication number
- CN103362312B CN103362312B CN201310130149.7A CN201310130149A CN103362312B CN 103362312 B CN103362312 B CN 103362312B CN 201310130149 A CN201310130149 A CN 201310130149A CN 103362312 B CN103362312 B CN 103362312B
- Authority
- CN
- China
- Prior art keywords
- enhancing ring
- concrete component
- support member
- depression
- component
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/142—Means in or on the elements for connecting same to handling apparatus
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Load-Engaging Elements For Cranes (AREA)
- Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明涉及支住混凝土构件提升环的方法和用于该提升环的支撑件。混凝土构件的提升操作通过使用提升环实现,在至少在混凝土构件的提升操作过程中支住滑模浇注的混凝土构件的提升环(3,13)的方法中,该提升环至少部分地位于在混凝土构件的表面上预留的凹陷内,在该方法中,至少相对于待提升的混凝土构件是纵向的且施加到提升环的力借助于支撑件(1,11)传递到待提升的混凝土构件,该支撑件(1,11)至少部分地被设置在与该提升环相关地预留的所述混凝土构件的凹陷内。本发明还涉及这样一种提升环支撑件。
Description
技术领域
本发明涉及当混凝土构件正被提升时对混凝土构件的提升环,例如滑模空心板或大体积板的支住。更特别的是,本发明涉及至少在混凝土构件提升操作过程中支住提升环的方法,以及至少在提升操作过程中与混凝土构件提升环相关联地使用的支撑件。
背景技术
在混凝土构件的制造过程中,其通常补充有各种提升环,所述提升环具有固定其内的起重机提升钩以提升混凝土构件。这些提升环能以更快捷、更方便、更安全的方式进行起重机的提升和安置沉重的混凝土构件。
用于滑模板的提升环,特别是空心板情况下的提升环通常在滑模之后、混凝土混合料固化之前被附接到所述板上。
在空心板中,通常通过破坏新浇筑空心板的顶表面,与空腔或空腔间的颈部一致,并通过在由此得到的凹陷内放置提升环成型零件来安装所述提升环。为了确保提升环的附接,该提升环成型零件可被设置为抵靠空心板的预应力钢绞线支承,例如通过在空心板的预应力钢绞线下方放置该提升环成型零件的端部。
一般由金属棒弯曲成适当形式而形成该提升环成型零件,其形成包括设置于混凝土板内部的提升环成型零件或端部,也可位于滑模浇筑混凝土板的预应力钢绞线的下方。
该提升环一般也可以这样的方式设置在滑模板中,即提升环的最高点变为基本上与具有凹陷的该板顶表面齐平,该凹陷围绕提升环布置以使提升钩与提升环连接。当提升环位于这样的凹陷中时,在提升和放置所述板之后不需从所述板单独去除提升环,因为通过例如用砂浆或其他合适的找平混合物填充该提升环凹陷很容易建造完整和光滑的板顶表面。
在空心板的情况下,在安装提升环的过程中,在空心板的顶表面上围绕提升环打开的开口中插入通常为塑料的杯型组件以在空心板已经安装在位之后,在完成顶表面光滑度的过程中防止水准混合物扩散到空心板的空腔内。
该提升环通常设置在滑模板的顶表面上,使得该板的各端部区域固定两个并排的提升环。在这种情况下,借助于起重臂执行所述板的提升,该起重臂能消除提升环上过度的斜负载。过度的斜负载可导致改变提升环成型零件在待提升的板中的位置,并因此导致他们的连接力下降,最糟糕的情况是在提升操作过程中引起提升环从所述板脱离,而且因此造成待提升的板破碎以及可能造成工地上的人员受伤。
发明内容
根据本发明的解决方案,向滑模浇筑的混凝土构件中、在提升环附近为提升环准备的凹陷内插入支撑件,该支撑件用于在混凝土构件中,至少在混凝土构件的纵向支住所述提升环。因此,至少那些混凝土构件的纵向力以及在混凝土构件的提升操作中施加到提升环的那些力可顺利地从提升环传递到待提升的混凝土构件。在这种情况下,不用起重臂就可完成混凝土构件的提升,因此促进和推动了提升混凝土构件的处理和布置,特别是在工地上。
在本发明中,由金属棒,通过将金属棒弯曲成适当形状而形成提升环或形成提升环的零件。例如,这些类型的提升环成型零件在文献EP1878854和WO2008/025894中是已知的。
在本发明的解决方案中,用于提升环的该支撑件优选地被构造成使得偏离混凝土构件的纵向并在混凝土构件的提升操作中施加到提升环的一些力同样由此被传递到混凝土构件。
在本发明的解决方案中,用于提升环的该支撑件优选地被构造成使得一旦提升钩插入到提升环的内部,支撑件就地夹紧。因此,在提升操作过程中,该提升钩保持提升环支撑件稳定,同时施加到支撑件的力达到其最大值。因此,由于施加到支撑件的力,可在提升操作中防止支撑件移动。
在本发明的解决方案中,用于提升环的该支撑件优选的是单独构件,该支撑件被设置在混凝土构件的提升环凹陷内以在混凝土构件提升操作之前支住所述提升环,而且该支撑件在提升操作之后从混凝土构件去除。因此,该支撑件可优选地被整合为用于混凝土构件提升的提升设备的零件,特别是通过与用于提升操作的提升钩相关地布置支撑件。
用于本发明解决方案的该支撑件对于提升大体积板或空心板的处理是特别有用的。
根据本发明用于混凝土构件提升环的该支撑件包括抵靠围绕该混凝土构件提升环预留的凹陷的侧壁设置的部分以及将抵靠凹陷侧壁设置的所述部分和该提升环的外表面连接的部分,用于将至少混凝土构件的纵向力而且在提升操作中施加到提升环的力从提升环传递到混凝土构件。
本发明的支撑件包括,优选的在该支撑件在抵靠凹陷的侧壁设置的部分的上边缘处包括抵靠混凝土产品的外表面设置的部分,即抵靠围绕用于混凝土产品提升环的凹陷的表面设置的部分。抵靠混凝土产品的外表面设置的该部分改善了支撑件的支住作用以及支撑件的固定性。
本发明的支撑件优选地被构造成使得将抵靠混凝土构件的凹陷的侧壁设置的部分和该提升环的外表面连接的所述部分具有大体与混凝土构件的凹陷直径相匹配的横截面长度,该连接部分具有开口,该开口的宽度大体与提升环的宽度相匹配。另外,所讨论的开口具有优选地可与待布置在该开口内的提升环的各个尺寸相匹配的长度。
更具体地,本发明提供了一种至少在混凝土构件的提升操作过程中支住滑模浇注的混凝土构件的提升环的方法,该混凝土构件的提升操作通过使用提升环实现,其中所述提升环由金属棒弯曲成如下形式而形成,所述形式包括提升环成型部分和被设置在所述混凝土构件内的端部,且所述提升环至少部分地位于在所述混凝土构件的表面上预留的凹陷内,其中,至少相对于待提升的混凝土构件是纵向的且施加到所述提升环的力借助于支撑件传递到所述待提升的混凝土构件,所述支撑件至少部分地设置在与所述提升环相关地形成的所述混凝土构件的凹陷中。
优选地,从所述混凝土构件的纵向方向偏离并施加到所述提升环的力同样经由所述支撑件传递到所述待提升的混凝土构件。
优选地,所述支撑件是单独的构件,所述支撑件在混凝土构件提升操作之前与所述混凝土构件的所述凹陷以及位于所述凹陷中的所述提升环相关地布置,并且所述支撑件在所述提升操作后从所述混凝土构件移除。
优选地,所述支撑件与待固定在所述提升环中的提升钩相关地装配。
优选地,通过将所述提升钩布置在由所述支撑件支住的所述提升环中,所述支撑件夹紧在适当位置。
优选地,所述滑模浇注的混凝土构件是大体积板或空心板。
本发明还提供了一种用于提升环的支撑件,所述提升环由金属棒弯曲成适当形式而形成并位于滑模浇注的混凝土构件中,所述形式包括提升环成型部分和被设置在所述混凝土构件内的端部,所述支撑件包括设置成抵靠与混凝土构件的提升环相关地预留的凹陷的壁的第一部分,以及将设置成抵靠所述凹陷的壁的所述第一部分和所述提升环的外表面连接以用于将至少在混凝土构件提升操作中施加到所述提升环而且相对于所述混凝土构件为纵向的力从所述提升环传递到所述混凝土构件的第二部分。
优选地,所述支撑件在设置成抵靠所述凹陷的壁的所述第一部分的上边缘处包括设置成抵靠所述混凝土构件的顶表面的第三部分。
优选地,与用于所述混凝土构件的提升操作中的提升钩相关地装配所述支撑件。
优选地,将设置成抵靠所述混凝土构件的凹陷的壁的所述第一部分和所述提升环的外表面连接的所述第二部分具有与所述混凝土构件的凹陷的直径相匹配的横截面长度,所述第二部分具有开口,所述开口的宽度与所述提升环的宽度相匹配。
附图说明
将通过举例的方式并参照附图进行更确切的描述本发明,其中
图1A和1B示意性地示出了与混凝土构件提升环相关地设置的本发明的一个解决方案,以及
图2A和2B示意性地示出了与混凝土构件提升环相关地设置的本发明的另一个可选择的解决方案。
具体实施方式
图1A和1B示意性地示出了本发明的一个支撑件1,该支撑件与用于混凝土构件的提升环3相关地设置,在这种情况下,该混凝土构件是空心板2。图1A示出了支撑件1的横截面,图1B是支撑件的俯视图。
该支撑件1由抵靠在空心板2中预留的开口或凹陷的侧壁设置的第一部分4、与抵靠该凹陷的侧壁设置的第一部分4和提升环3的外表面连接的第二部分5,以及抵靠空心板2的顶表面设置的第三部分6构成。
在图1A和1B所示的实施例中,该支撑件1具有基本为圆柱形的第一部分4,第一部分4被底部固定的第二部分5覆盖,所述第二部分5形成有切口或开口,如图所示,提升环3至少在空心板的纵向与其大致紧密的设置在切口或开口中。在这种情况下,第三部分6环绕第一部分4并沿第一部分4的上边缘作法兰式的延伸,第三部分6与支撑件1的第一部分4的上边缘连接。
当通过提升环3提升空心板2时,所述提升环受到图1A中箭头指示方向的斜应力。在这种情况下,该提升环3抵靠支撑件1的第二部分5支承,所述第二部分5经由第一部分4将应力传递到空心板2的凹陷的壁。因此,通过提升空心板2在提升环3上造成的该斜应力不允许弯曲整个提升环成型部分,因为保留在支撑件外部的提升环部分基本上仅承载提升应力的垂直分量。因此,装配有本发明提升环的空心板不用单独的起重臂就可被提升。
该支撑件1优选地由金属制成,例如钢板,优选地支撑件构成能够与提升环3连接的提升设备的零件。在这种情况下,该支撑件1优选地不是提升环组件的固定到空心板2的部分。
对于图1A和1B所示的实施例,应该注意的是抵靠空心板的凹陷的侧表面设置的第一部分4不一定需要一直延伸到成形的凹陷底部,连接提升环3和第一部分4的第二部分5不一定需要位于在凹陷的底部。在本发明的解决方案中,仅是需要第二部分5距离提升环3的上表面一定的距离,从而使得待布置在提升环内的提升钩可装配在提升环3中的适当位置。由此,该提升钩在适当位置夹紧支撑件1并防止其从空心板的凹陷中脱离,这响应于在提升操作过程中施加在支撑件上的力。
图2A和2B示意性地示出了本发明的可选择的另一支撑件11,该支撑件与用于混凝土构件的提升环13相关地设置,在这种情况下该混凝土构件是空心板12。图2A示出了支撑件11的横截面,图2B示出了支撑件的俯视图。
在该实施例中,该支撑件11由抵靠在空心板12中预留的开口或凹陷的侧壁设置的第一部分14、与第一部分14和提升环13的外表面连接的第二部分15、以及抵靠空心板12的顶表面设置并位于第一部分14范围之上的第三部分16构成。
由此构建的该支撑件11在空心板12的提升操作中支撑提升环13,优选地,例如仅在空心板的纵向上,第一部分14和第三部分16朝空心板的纵向中心区域设置。通过空心板12的提升操作而在支撑件11上造成的其它方向的分力基本上由支撑件11的结构承担。
相比于图1A和1B的实施例,图2A和2B的实施例能为支撑件提供更精简的构造,其减少了制造和材料成本,还足以在最基本的弯曲应力方向支撑提升环。
在上面的示例中,明显的是这些在本发明范围内接受的众多修改和变型对本领域技术人员来说是显而易见的。因此,本发明的上述实施例对于本发明绝不是限制性的。
Claims (10)
1.一种至少在混凝土构件的提升操作过程中支住滑模浇注的混凝土构件的提升环(3,13)的方法,该混凝土构件的提升操作通过使用提升环实现,其中所述提升环由金属棒弯曲成如下形式而形成,所述形式包括提升环成型部分和被设置在所述混凝土构件内的端部,且所述提升环至少部分地位于在所述混凝土构件的表面上预留的凹陷内,其中,至少相对于待提升的混凝土构件是纵向的且施加到所述提升环的力借助于支撑件(1,11)传递到所述待提升的混凝土构件,所述支撑件(1,11)至少部分地设置在与所述提升环相关地形成的所述混凝土构件的凹陷中。
2.根据权利要求1所述的方法,其中,从所述混凝土构件的纵向方向偏离并施加到所述提升环(3)的力同样经由所述支撑件(1)传递到所述待提升的混凝土构件。
3.根据权利要求1或2所述的方法,其中,所述支撑件(1,11)是单独的构件,所述支撑件在混凝土构件提升操作之前与所述混凝土构件的所述凹陷以及位于所述凹陷中的所述提升环(3,13)相关地布置,并且所述支撑件在所述提升操作后从所述混凝土构件移除。
4.根据权利要求1或2所述的方法,其中,所述支撑件(1,11)与待固定在所述提升环(3,13)中的提升钩相关地装配。
5.根据权利要求4所述的方法,其中,通过将所述提升钩布置在由所述支撑件支住的所述提升环(3,13)中,所述支撑件(1,11)夹紧在适当位置。
6.根据权利要求1或2所述的方法,其中,所述滑模浇注的混凝土构件是大体积板或空心板。
7.一种用于提升环(3,13)的支撑件(1,11),所述提升环由金属棒弯曲成适当形式而形成并位于滑模浇注的混凝土构件中,所述形式包括提升环成型部分和被设置在所述混凝土构件内的端部,所述支撑件包括设置成抵靠与混凝土构件的提升环相关地预留的凹陷的壁的第一部分(4,14),以及将设置成抵靠所述凹陷的壁的所述第一部分和所述提升环的外表面连接以用于将至少在混凝土构件提升操作中施加到所述提升环而且相对于所述混凝土构件为纵向的力从所述提升环传递到所述混凝土构件的第二部分(5,15)。
8.根据权利要求7所述的支撑件(1,11),其中,所述支撑件在设置成抵靠所述凹陷的壁的所述第一部分(14)的上边缘处包括设置成抵靠所述混凝土构件的顶表面的第三部分(6,16)。
9.根据权利要求7或8所述的支撑件(1,11),其中,与用于所述混凝土构件的提升操作中的提升钩相关地装配所述支撑件。
10.根据权利要求7或8所述的支撑件(1,11),其中,将设置成抵靠所述混凝土构件的凹陷的壁的所述第一部分(4,14)和所述提升环(3,13)的外表面连接的所述第二部分(5,15)具有与所述混凝土构件的凹陷的直径相匹配的横截面长度,所述第二部分(5,15)具有开口,所述开口的宽度与所述提升环的宽度相匹配。
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
FI20125342 | 2012-03-27 | ||
FI20125342 | 2012-03-27 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103362312A CN103362312A (zh) | 2013-10-23 |
CN103362312B true CN103362312B (zh) | 2016-09-14 |
Family
ID=47845802
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310130149.7A Expired - Fee Related CN103362312B (zh) | 2012-03-27 | 2013-03-27 | 支住混凝土构件提升环的方法和用于该提升环的支撑件 |
Country Status (4)
Country | Link |
---|---|
US (1) | US20130257073A1 (zh) |
EP (1) | EP2644803A3 (zh) |
CN (1) | CN103362312B (zh) |
RU (1) | RU2541000C2 (zh) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FI126297B (en) * | 2013-11-22 | 2016-09-30 | Elematic Oyj | Plug for a lift hole |
FI20165851L (fi) * | 2016-11-14 | 2018-05-15 | Elematic Oyj | Menetelmä ja laitteisto esivalmistettujen betonituotteiden valamiseksi |
FI128825B (en) * | 2018-11-26 | 2020-12-31 | Elematic Oyj | Edge unit and system for casting precast concrete products |
EE01588U1 (et) * | 2022-03-31 | 2022-11-15 | Lifting Loops OÜ | Betoneeritav karbiku ja tõsterihma koost |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3124385A (en) * | 1964-03-10 | Cable lift pick-up unit | ||
DE2617866A1 (de) * | 1976-04-23 | 1977-10-27 | Walter Otto Kitter | Vorrichtung zum anschlagen von betonfertigteilen |
US6092849A (en) * | 1996-09-30 | 2000-07-25 | Zambelli; Sergio | Device for lifting prefabricated components, particularly made of concrete, or the like |
CN1793591A (zh) * | 2006-01-05 | 2006-06-28 | 北京市机械施工有限公司 | 进行构件吊装的支撑移位方法和支撑系统 |
CN101835948A (zh) * | 2007-06-21 | 2010-09-15 | 伍德斯托克泊卡逊有限公司 | 可拆卸的提升链接装置 |
Family Cites Families (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1684247A1 (de) * | 1966-09-27 | 1971-03-04 | Franz Gaertner | Einlageelement und Herstellungsverfahren zur Bildung einer Zugriffsausnehmung |
US4018470A (en) * | 1975-06-09 | 1977-04-19 | Superior Concrete Accessories, Inc. | Anchor insert for embedment in a concrete slab |
US4017115A (en) * | 1975-12-17 | 1977-04-12 | The Burke Company | Lift system for concrete slabs |
USRE31131E (en) * | 1976-07-12 | 1983-01-25 | The Burke Company | Concrete slab hoisting apparatus |
US4087947A (en) * | 1976-09-15 | 1978-05-09 | Superior Concrete Accessories, Inc. | Edge-lifting system for a concrete slab |
SU783218A1 (ru) * | 1979-02-28 | 1980-11-30 | Конструкторско-технологическое бюро "Мосоргстройматериалы" | Инвентарна монтажна петл |
SU1155458A1 (ru) * | 1983-02-11 | 1985-05-15 | Yalov Grigorij N | Устройство дл образовани лунок в издели х из бетонных смесей под утопленные монтажные петли |
US4784398A (en) * | 1987-05-18 | 1988-11-15 | Lund Arnold M | Core lifting chuck |
US5226265A (en) * | 1989-03-22 | 1993-07-13 | The Burke Company | Apparatus and method for lifting tilt-up wall constructions |
RU15741U1 (ru) * | 2000-06-30 | 2000-11-10 | Государственное унитарное предприятие "Научно-исследовательский, проектно-конструкторский и технологический институт бетона и железобетона" | Монтажная петля |
US20070126249A1 (en) * | 2005-12-07 | 2007-06-07 | Leach Terry A | Concrete lifting eye-flexi lift |
FI121809B (fi) | 2006-07-12 | 2011-04-29 | Elematic Oy Ab | Menetelmä ja laitteisto nostolenkkien asettamiseksi betonista valettuun ontelolaattaan |
FR2905397B1 (fr) | 2006-08-30 | 2015-01-16 | Kp1 | Dalle alveolee pourvue d'au moins un anneau de levage. |
AU2009230822B2 (en) * | 2008-12-02 | 2016-05-12 | Illinois Tool Works Inc. | An anchor for lifting a concrete component |
-
2013
- 2013-03-11 EP EP13158500.2A patent/EP2644803A3/en not_active Withdrawn
- 2013-03-21 RU RU2013112550/03A patent/RU2541000C2/ru not_active IP Right Cessation
- 2013-03-27 CN CN201310130149.7A patent/CN103362312B/zh not_active Expired - Fee Related
- 2013-03-27 US US13/851,272 patent/US20130257073A1/en not_active Abandoned
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3124385A (en) * | 1964-03-10 | Cable lift pick-up unit | ||
DE2617866A1 (de) * | 1976-04-23 | 1977-10-27 | Walter Otto Kitter | Vorrichtung zum anschlagen von betonfertigteilen |
US6092849A (en) * | 1996-09-30 | 2000-07-25 | Zambelli; Sergio | Device for lifting prefabricated components, particularly made of concrete, or the like |
CN1793591A (zh) * | 2006-01-05 | 2006-06-28 | 北京市机械施工有限公司 | 进行构件吊装的支撑移位方法和支撑系统 |
CN101835948A (zh) * | 2007-06-21 | 2010-09-15 | 伍德斯托克泊卡逊有限公司 | 可拆卸的提升链接装置 |
Also Published As
Publication number | Publication date |
---|---|
RU2541000C2 (ru) | 2015-02-10 |
CN103362312A (zh) | 2013-10-23 |
US20130257073A1 (en) | 2013-10-03 |
EP2644803A3 (en) | 2014-10-29 |
RU2013112550A (ru) | 2014-09-27 |
EP2644803A2 (en) | 2013-10-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106013530B (zh) | 基于3d打印的混凝土剪力墙的配筋结构 | |
CN104847014B (zh) | 装配式混凝土剪力墙竖向连接构造及施工方法 | |
CN103362312B (zh) | 支住混凝土构件提升环的方法和用于该提升环的支撑件 | |
CN106988436B (zh) | 一种预留孔洞封堵的方法 | |
CN106245931A (zh) | 砖混结构中承重墙的托换装置及施工方法 | |
ES2533339T3 (es) | Módulos de encofrar, ensamblables y desechables, para construir encofrados modulares para hacer cimientos de hormigón | |
CN109057171A (zh) | 装配式剪力墙竖向灌浆套筒连接结构及其施工方法 | |
CN106368365A (zh) | 通筋式混凝土叠合楼板结构及其制作和装配方法 | |
CN103628575B (zh) | 大高差变截面混凝土结构施工缝及其施工方法 | |
CN110952659B (zh) | 预制柱节点连接结构及施工方法 | |
KR100996728B1 (ko) | 결합이 용이한 현장타설 팽이파일 | |
CN106639305A (zh) | 可滑移提升式构造柱钢模板及其施工方法 | |
CN108265888A (zh) | 一种装配式混凝土竖向构件连接结构及施工方法 | |
CN205063056U (zh) | 装配式建筑外墙干挂节点的防腐结构 | |
CN106884664B (zh) | 隧道仰拱模板及隧道仰拱填充快速施工方法 | |
CN204475714U (zh) | 一种快装式预制楼梯 | |
CN106382002B (zh) | 一种大型砼制元件模具及其使用方法 | |
CN108130917A (zh) | 桩基挡土墙施工方法 | |
CN207794436U (zh) | 用于钢筋混凝土柱的铰接柱脚 | |
CN210679123U (zh) | 浇注成型水泥杆的外模 | |
CN209350486U (zh) | 一种构造柱穿墙加固预制块及模具 | |
CN208105677U (zh) | 一种装配式混凝土竖向构件连接结构 | |
CN207436515U (zh) | 高效预制楼板施工的吊装梁 | |
CN106677527B (zh) | 电梯井内隔梁一次浇筑成型施工方法 | |
CN110409820A (zh) | 悬挑结构施工用的支模装置及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: Finland toijala Applicant after: Ai Lemai Tie Ke group Address before: Finland toijala Applicant before: Elematic Oy Ab |
|
COR | Change of bibliographic data | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160914 Termination date: 20180327 |
|
CF01 | Termination of patent right due to non-payment of annual fee |