CN103353902B - Construction method for secondary equipment simulation model of electric power system - Google Patents

Construction method for secondary equipment simulation model of electric power system Download PDF

Info

Publication number
CN103353902B
CN103353902B CN201210563811.3A CN201210563811A CN103353902B CN 103353902 B CN103353902 B CN 103353902B CN 201210563811 A CN201210563811 A CN 201210563811A CN 103353902 B CN103353902 B CN 103353902B
Authority
CN
China
Prior art keywords
secondary device
secondary equipment
model
construction method
electric power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210563811.3A
Other languages
Chinese (zh)
Other versions
CN103353902A (en
Inventor
赵晓波
何心仲
毕会静
张红艳
白廷玉
纪璐
林昌年
徐正清
吴海宏
高峰
王国平
葛贤军
胡兴勇
黄帮局
曹柏林
张鹏程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Kedong Electric Power Control System Co Ltd
Training Center of State Grid Hebei Electric Power Co Ltd
Original Assignee
Beijing Kedong Electric Power Control System Co Ltd
Training Center of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Kedong Electric Power Control System Co Ltd, Training Center of State Grid Hebei Electric Power Co Ltd filed Critical Beijing Kedong Electric Power Control System Co Ltd
Priority to CN201210563811.3A priority Critical patent/CN103353902B/en
Publication of CN103353902A publication Critical patent/CN103353902A/en
Application granted granted Critical
Publication of CN103353902B publication Critical patent/CN103353902B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a construction method for a secondary equipment simulation model of an electric power system. The construction method comprises the following steps: (1) generating a training simulation system flexible bus; (2) drawing the appearance of the secondary equipment; (3) analyzing properties and functions of the secondary equipment; (4) analyzing input data and output data of the secondary equipment, ordering the input data of the secondary equipment from the training simulation system flexible bus, and defining the output data; (3) defining appearance logic node of the secondary equipment; (6) expanding the incidence relation between inside properties of the secondary equipment simulation model, expressing inside mechanism of model behavior, and realizing the defining of the properties and the functions; (7) storing the generated secondary equipment simulation model in a secondary equipment model base. The method can describe the physical property mechanism of the secondary equipment in detail, accurately simulate all appearance properties and action properties, and meets practical requirements of quick configuration and deployment.

Description

A kind of construction method for secondary equipment simulation model of electric power
Technical field
The present invention relates to a kind of method building secondary equipment simulation model of electric power, belong to Simulating technique in Electric Power System Field.
Background technology
Electric system simulation calculates the basic tool being Electrical Power System Dynamic analysis with security control, and power system modeling It is the basis realizing simulation calculation.Currently, with the development of power system automation technology, the model of secondary equipment in power system More and more, function becomes increasingly complex, integrated level more and more higher, brings new technological challenge to the structure of phantom.Existing In some Training Simulation System, secondary equipment in power system(Equipment, loop)Model has generally carried out considerable degree of practicality Property simplify.There is the defect of simulating realistic aspect based on the simulation calculation of above-mentioned simplified model, do not adapted to currently adjust Control integration, the demand of O&M integration Training Simulation System unified Modeling.
In existing training on electric power analogue system, conventional modeling method can be divided into:Processor-oriented modeling, towards The modeling of data, the modeling of Information, the modeling of decision making-oriented and five kinds of Object -Oriented Model.Wherein, processor-oriented Modeling method is process to be regarded as the essential part of system model, and data is as process and produces.Data-oriented modeling Method is the input and output of concern model, and function follows data.The modeling method of Information is the logical number from whole system Start according to model, by a global information demand view come master data entities all in explanation system and its mutual pass System, progressively constructs whole model on this basis, and information model record system runs required information entity.The building of decision making-oriented Mould method is that the institutional analysis result of decision-making drawing up principle by system and mechanism, system sets up model.Towards The modeling method of object is to utilize Object--oriented method, with encapsulation, inherit, the mechanism such as polymorphic to construct virtual reality system System.
Object-oriented(object-oriented)Method is generally recognised as the effective technology means solving the above problems.Due to right As system structure and the existing mutual independence of problem-solving system(Packaging effects)Connect each other again, therefore can ensure that software system constantly expands Exhibition and maintenance.Because power system is a complicated large scale system, the required data volume of modeling is very huge, and structure is very multiple Miscellaneous.Phantom must change with the change of application function.The scale of phantom, structure also will be with power system developments Often change.Drafting one needs research and discovery repeatedly with Object-oriented Technique for the model scheme instructing.Object-oriented skill Art introducing power system simulation software is significant to the exploitation of software, but still has many particular problems to need research and visit Simulation modeling of rope, such as secondary equipment in power system etc..
Content of the invention
The technical problem to be solved is to provide a kind of construction method for secondary equipment simulation model of electric power.
For realizing above-mentioned goal of the invention, the present invention adopts following technical schemes:
A kind of construction method for secondary equipment simulation model of electric power, comprises the steps:
(1)Using visual modeling tool, generate Training Simulation System flexible bus;
(2)Using visual modeling tool, draw the outward appearance of secondary device;
(3)The attribute of analysis secondary device and function;
(4)The input data of analysis secondary device and output data, and order secondary from Training Simulation System flexible bus The input data of equipment, defines output data;
(5)Using visual modeling tool, define the outward appearance logical node of secondary device;
(6)According to IEC61850 reference format, extend the incidence relation between secondary device phantom built-in attribute, table State the internal mechanism of model behavior, realize the definition of attribute and function;
(7)According to IEC61850 reference format, the secondary device phantom being generated in secondary device model library storage.
Wherein more preferably, described step(1)In, draw power system main wiring diagram and the cross, straight flow graph of plant stand further.
Wherein more preferably, described secondary device phantom is made up of logical node, and described logical node comprises to embody two Secondary device state, parameter, definite value, interface and unit connect attribute and the function of topological relation.
Wherein more preferably, described step(3)In, attribute and the function of secondary device is analyzed by described logical node.
Wherein more preferably, described visual modeling tool includes equipment modeling instrument and power network modeling instrument.
Compared with prior art, the present invention has following technical characterstic:
1. can accurately describe the physical characteristics mechanism of secondary device in detail, all appearance attributes of accurate simulation and action belong to Property;
2. adopt IEC61850 standard, disclosure satisfy that the practical requirement of rapid configuration deployment.
Brief description
Fig. 1 is the logical construction schematic diagram of secondary equipment simulation model of electric power;
Fig. 2 is in visual modeling tool, setting logical node attribute, the schematic diagram of data;
Fig. 3 is the schematic diagram of the extended model of IEC61850 standard;
Fig. 4 is the schematic diagram of primary system flexible bus;
Fig. 5 is the schematic diagram of DC power-supply system flexible bus.
Specific embodiment
Currently, the demand in order to meet power system unified Modeling and realize seamless communication, International Electrotechnical Commission 57th technical committee(IECTC57)Successively issue very important two standards for power system information integration: IEC61850 and IEC61970.Wherein, the communication protocol in all transformer stations is all using IEC61850 standard.IEC61850 standard It is the transformer substation system common communication standard based on universal network communication platform, by a series of standardization to secondary device, Form it into the output of a specification, realize the seamless connection of each secondary device in transformer substation system.
In the present invention, secondary device phantom is made up of logical node, meets the relevant rule in IEC61850 standard Fixed.As shown in figure 1, this logical node is the basic unit module according to the definition of secondary device function, logical node comprises accordingly Attribute and function, the state of secondary device, parameter, definite value, interface and unit can be embodied and connect topological relation etc..
The modeling method of Object -Oriented Model method and Information is combined by the present invention, in conjunction with IEC61850 mark Standard, sets up phantom by visualization means, makes the versatility of secondary device phantom higher.For this reason, adopting in the present invention With following technical step:
(1)Using visual modeling tool, draw power system main wiring diagram and the cross, straight flow graph of plant stand, according to power train The feature of system generates Training Simulation System flexible bus.
Here visual modeling tool can be that the powerWorld Simulator of University of Illinois of U.S. exploitation is soft Part Power World etc..As shown in Fig. 2 in this visual modeling tool, patrolling in secondary device phantom can be arranged Collect nodal community, data etc..In addition, equipment modeling instrument and power network modeling instrument etc. can be included in visual modeling tool, Wherein equipment modeling instrument can be used to produce the extended model of the IEC61850 standard shown in Fig. 3, and power network modeling instrument is permissible It is used for producing the primary system flexible bus shown in Fig. 4.Further, this Training Simulation System flexible bus can also include Fig. 5 institute DC power-supply system flexible bus showing etc..
(2)Using visual modeling tool, draw the outward appearance of secondary device.
(3)Analyze attribute and the function of secondary device by logical node.
(4)The input data of analysis secondary device and output data, and order secondary from Training Simulation System flexible bus The input data of equipment, defines output data.If it is necessary, being extended to Training Simulation System flexible bus.
(5)Using visual modeling tool, define the outward appearance logical node of secondary device.
(6)According to IEC61850 reference format, extend the incidence relation between secondary device phantom built-in attribute, table State the internal mechanism of model behavior, realize the definition of attribute and function.
(7)According to IEC61850 reference format, the secondary device phantom being generated in secondary device model library storage.
By collect and arrange electrical network in various secondary device models, secondary device model library will progressively be expanded with Abundant, ultimately form complete secondary device model library.User can be rapidly completed simulated grid by parameter setting In secondary device and loop instantiation.
Above-mentioned visualization, Componentized secondary device phantom construction method foundation IEC61850 standard, using artwork The visual modeling tool of one, and is carried out abstract for the inner member of secondary device according to actual electric loop for logical node Graphical combination is built, thus realizing the structure to the detailed phantom of secondary device and loop.This secondary device emulates mould Type not only can describe the internal physical functional attributes of secondary device, simultaneously accurately simulate all appearance attributes and action belongs to Property.This visual modeling method is by abstract for original copying realized by internal execution code function for patterned unit Part combination is built, simple and clear, and multiplexing is convenient, be also based on existing phantom carry out local directed complete set can be formed new Secondary device phantom, need not develop again, save construction cycle and cost it is ensured that the opening of Training Simulation System Property.
Above construction method for secondary equipment simulation model of electric power provided by the present invention is described in detail. To those skilled in the art, on the premise of without departing substantially from true spirit to it done any obvious Change, all will constitute to infringement of patent right of the present invention, corresponding legal responsibility will be undertaken.

Claims (3)

1. a kind of construction method for secondary equipment simulation model of electric power is it is characterised in that comprise the steps:
(1) use visual modeling tool, draw power system main wiring diagram and the cross, straight flow graph of plant stand, according to power system Feature generates Training Simulation System flexible bus;
(2) use visual modeling tool, draw the outward appearance of secondary device;
(3) attribute of secondary device and function are analyzed by logical node, described logical node comprise to embody secondary device state, Parameter, definite value, interface and unit connect attribute and the function of topological relation;
(4) input data of analysis secondary device and output data, and order secondary device from Training Simulation System flexible bus Input data, define output data;
(5) use visual modeling tool, define the outward appearance logical node of secondary device;
(6) according to IEC61850 reference format, extend the incidence relation between secondary device phantom built-in attribute, state mould The internal mechanism of type behavior, realizes the definition of attribute and function;
(7) according to IEC61850 reference format, the secondary device phantom that generated in secondary device model library storage;
(8) pass through parameter setting, be rapidly completed the instantiation in secondary device in simulated grid and loop.
2. construction method for secondary equipment simulation model of electric power as claimed in claim 1 it is characterised in that:
Described secondary device phantom is made up of logical node.
3. construction method for secondary equipment simulation model of electric power as claimed in claim 1 it is characterised in that:
Described visual modeling tool includes equipment modeling instrument and power network modeling instrument.
CN201210563811.3A 2011-12-21 2012-12-21 Construction method for secondary equipment simulation model of electric power system Expired - Fee Related CN103353902B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210563811.3A CN103353902B (en) 2011-12-21 2012-12-21 Construction method for secondary equipment simulation model of electric power system

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN201110432137.0 2011-12-21
CN201110432137 2011-12-21
CN2011104321370 2011-12-21
CN201210563811.3A CN103353902B (en) 2011-12-21 2012-12-21 Construction method for secondary equipment simulation model of electric power system

Publications (2)

Publication Number Publication Date
CN103353902A CN103353902A (en) 2013-10-16
CN103353902B true CN103353902B (en) 2017-02-22

Family

ID=49310274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210563811.3A Expired - Fee Related CN103353902B (en) 2011-12-21 2012-12-21 Construction method for secondary equipment simulation model of electric power system

Country Status (1)

Country Link
CN (1) CN103353902B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105762763A (en) * 2014-12-15 2016-07-13 成都交大运达电气有限公司 Railway traction power supply system main transformer differential protection model based on IEC61850 standard
CN105160119B (en) * 2015-09-16 2019-01-11 中国电力科学研究院 A kind of second power equipment emulation modelling method based on strategy file
CN105243196B (en) * 2015-09-18 2018-07-24 国网安徽省电力公司培训中心 Substation secondary circuit emulation modelling method
CN106789274B (en) * 2016-12-27 2020-06-16 上海科梁信息工程股份有限公司 Intelligent substation safety testing system and method
CN107971767B (en) * 2017-12-27 2023-08-29 圣辉(上海)能源科技有限公司 Intelligent control system of numerical control machine tool auxiliary device based on object-oriented technology
CN108646587B (en) * 2018-04-18 2021-08-17 许继电气股份有限公司 EMTDC parallel simulation method and system
CN110968546B (en) * 2018-09-30 2023-04-07 北京国双科技有限公司 Method for setting map node skipping probability and related equipment
CN109389326B (en) * 2018-11-05 2021-05-25 国网四川省电力公司 Monitoring event-oriented object modeling method, device and system
CN110705078B (en) * 2019-09-25 2023-04-21 哈尔滨工程大学 Simulation model development system and analysis method of nuclear power plant
CN114548001B (en) * 2022-02-27 2024-03-26 江苏中屹能源技术有限公司 Automatic generation primary wiring diagram method based on electric power intelligent operation and maintenance system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101894488A (en) * 2009-07-15 2010-11-24 上海市电力公司超高压输变电公司 Distributed three-dimensional simulation training system for regional power system transformer station
CN102081867A (en) * 2010-05-24 2011-06-01 北京科东电力控制系统有限责任公司 All-digital high-voltage direct current transmission training stimulation system
CN102209108A (en) * 2011-05-16 2011-10-05 广东电网公司深圳供电局 Method and system for realizing seamless communication between master scheduling station and substation of power grid

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101894488A (en) * 2009-07-15 2010-11-24 上海市电力公司超高压输变电公司 Distributed three-dimensional simulation training system for regional power system transformer station
CN102081867A (en) * 2010-05-24 2011-06-01 北京科东电力控制系统有限责任公司 All-digital high-voltage direct current transmission training stimulation system
CN102209108A (en) * 2011-05-16 2011-10-05 广东电网公司深圳供电局 Method and system for realizing seamless communication between master scheduling station and substation of power grid

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
"IEC 61850在继电保护故障信息系统中的应用研究";王睿;《中国优秀硕士学位论文全文数据库-工程科技Ⅱ辑》;20050815(第04期);C042-208,参见正文第13页4.4节"IEC61850中的几个重要术语",第16页4.6节"IEC61850建模方法",第19页第4.7节"IEC61850建模步骤",第26-27页5.2节"IEC61850名称空间的扩展",第29页5.3节"典型设备建模" *
"变电站数字物理混合仿真培训系统的研究与应用";周鑫;《中国优秀硕士学位论文全文数据库-工程科技Ⅱ辑》;20060815(第08期);C042-425 *
"基于IEC61850的继电保护通信系统仿真与设计";吴永超;《中国优秀硕士学位论文全文数据库-工程科技Ⅱ辑》;20091115(第11期);C042-416 *

Also Published As

Publication number Publication date
CN103353902A (en) 2013-10-16

Similar Documents

Publication Publication Date Title
CN103353902B (en) Construction method for secondary equipment simulation model of electric power system
CN103500249B (en) Visualization Relay Protection Setting Calculation System and method
CN107103113A (en) Towards the Automation Design method, device and the optimization method of neural network processor
CN102609991B (en) Volume-reduction optimization method for three-dimensional solid model
Vanfretti et al. Unambiguous power system dynamic modeling and simulation using modelica tools
CN103616825B (en) A kind of low cost semi-physical self-adaption clock virtual microgrid test platform
CN102360535A (en) Three-dimensional visual simulation training system and method
CN105159754B (en) In-circuit emulation method and device based on business intelligence cloud platform
CN109191591A (en) Substation Training Simulator construction method based on augmented reality
CN106681726B (en) Python model conversion is the method for Modelica model
CN207352604U (en) A kind of intelligent distribution transformer terminals automatization test system based on LUA scripts
CN112327745B (en) PLC program design method based on testable digital twin body
CN106326450B (en) A kind of exchange method for realizing that SCD file is checked out based on data integration
Cui et al. ANDES: A Python-based cyber-physical power system simulation tool
CN103280137A (en) Three-dimensional model system of 220KV power transformer
CN102968519A (en) Model of electronic current transformer with hollow coil in electrical system and modeling method thereof
CN108108403A (en) Based on bay device Logical Configuration Visualization Platform system and its construction method
Ebeid et al. Model-driven design of network aspects of distributed embedded systems
CN108153932A (en) The modeling of Table top type three-dimensional Maintenance Model
CN108920825A (en) A kind of SoC visual data manager based on IP kernel
CN107515966A (en) A kind of radar simulator system layering construction method based on DDS
CN103164545A (en) Visual editing method of virtual electronic components
CN101609614A (en) A kind of emulation platform of semi-matter simulating system reaches the method for goal systems being carried out online accent ginseng
CN106951593A (en) A kind of method and apparatus for the configuration file for generating protection supervisory equipment
CN109002645A (en) EMU subsystem modeling method and device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170222

Termination date: 20171221