CN103352584A - 一种外套式加固方法 - Google Patents
一种外套式加固方法 Download PDFInfo
- Publication number
- CN103352584A CN103352584A CN2013102886493A CN201310288649A CN103352584A CN 103352584 A CN103352584 A CN 103352584A CN 2013102886493 A CN2013102886493 A CN 2013102886493A CN 201310288649 A CN201310288649 A CN 201310288649A CN 103352584 A CN103352584 A CN 103352584A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- square steel
- concrete column
- bearing type
- newly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title abstract description 11
- 238000005728 strengthening Methods 0.000 title abstract 7
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 135
- 239000010959 steel Substances 0.000 claims abstract description 135
- 239000004567 concrete Substances 0.000 claims abstract description 94
- 230000002787 reinforcement Effects 0.000 claims abstract description 24
- 238000004873 anchoring Methods 0.000 claims abstract description 17
- 238000009434 installation Methods 0.000 claims abstract description 5
- 230000010412 perfusion Effects 0.000 claims description 3
- 230000002093 peripheral effect Effects 0.000 claims description 3
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 6
- 230000008901 benefit Effects 0.000 abstract description 5
- 230000021715 photosynthesis, light harvesting Effects 0.000 abstract 1
- 238000009417 prefabrication Methods 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
Description
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310288649.3A CN103352584B (zh) | 2013-07-09 | 2013-07-09 | 一种外套式加固方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310288649.3A CN103352584B (zh) | 2013-07-09 | 2013-07-09 | 一种外套式加固方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103352584A true CN103352584A (zh) | 2013-10-16 |
CN103352584B CN103352584B (zh) | 2015-10-14 |
Family
ID=49308992
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310288649.3A Expired - Fee Related CN103352584B (zh) | 2013-07-09 | 2013-07-09 | 一种外套式加固方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103352584B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669898A (zh) * | 2013-11-22 | 2014-03-26 | 江苏建筑职业技术学院 | 一种用环口套管加固钢管桁架相贯节点的方法 |
CN106088653A (zh) * | 2016-07-27 | 2016-11-09 | 姚攀峰 | 一种附加式空间约束高延性砌体改造结构及施工方法 |
CN106150119A (zh) * | 2016-07-27 | 2016-11-23 | 姚攀峰 | 一种工业化高延性空间约束砌体加固体系及其施工方法 |
CN106150121A (zh) * | 2016-08-26 | 2016-11-23 | 姚攀峰 | 一种仓储防爆改造结构体系及其施工方法 |
CN110056201A (zh) * | 2019-02-21 | 2019-07-26 | 北京筑福建筑科学研究院有限责任公司 | 一种老旧住宅采用外套式增面积结构加固及其施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101311479A (zh) * | 2007-05-25 | 2008-11-26 | 贵阳铝镁设计研究院 | 钢柱脚底板刚性横梁加固结构 |
US20100011680A1 (en) * | 2008-07-16 | 2010-01-21 | Oki Semiconductor Co., Ltd. | Aseismatic reinforcing structure of double flooring and aseismatic reinforcing method of double flooring |
CN201809873U (zh) * | 2009-10-31 | 2011-04-27 | 白风山 | 房屋加固抗震梁 |
CN103046789A (zh) * | 2013-01-14 | 2013-04-17 | 北京筑福建设工程有限责任公司 | 既有砌体结构外套避难仓结构及其施工方法 |
-
2013
- 2013-07-09 CN CN201310288649.3A patent/CN103352584B/zh not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101311479A (zh) * | 2007-05-25 | 2008-11-26 | 贵阳铝镁设计研究院 | 钢柱脚底板刚性横梁加固结构 |
US20100011680A1 (en) * | 2008-07-16 | 2010-01-21 | Oki Semiconductor Co., Ltd. | Aseismatic reinforcing structure of double flooring and aseismatic reinforcing method of double flooring |
CN201809873U (zh) * | 2009-10-31 | 2011-04-27 | 白风山 | 房屋加固抗震梁 |
CN103046789A (zh) * | 2013-01-14 | 2013-04-17 | 北京筑福建设工程有限责任公司 | 既有砌体结构外套避难仓结构及其施工方法 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669898A (zh) * | 2013-11-22 | 2014-03-26 | 江苏建筑职业技术学院 | 一种用环口套管加固钢管桁架相贯节点的方法 |
CN103669898B (zh) * | 2013-11-22 | 2015-09-30 | 江苏建筑职业技术学院 | 一种用环口套管加固钢管桁架相贯节点的方法 |
CN106088653A (zh) * | 2016-07-27 | 2016-11-09 | 姚攀峰 | 一种附加式空间约束高延性砌体改造结构及施工方法 |
CN106150119A (zh) * | 2016-07-27 | 2016-11-23 | 姚攀峰 | 一种工业化高延性空间约束砌体加固体系及其施工方法 |
CN106088653B (zh) * | 2016-07-27 | 2019-05-03 | 姚攀峰 | 一种附加式空间约束高延性砌体改造结构及施工方法 |
CN106150119B (zh) * | 2016-07-27 | 2019-09-20 | 姚攀峰 | 一种工业化高延性空间约束砌体加固体系及其施工方法 |
CN106150121A (zh) * | 2016-08-26 | 2016-11-23 | 姚攀峰 | 一种仓储防爆改造结构体系及其施工方法 |
CN110056201A (zh) * | 2019-02-21 | 2019-07-26 | 北京筑福建筑科学研究院有限责任公司 | 一种老旧住宅采用外套式增面积结构加固及其施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN103352584B (zh) | 2015-10-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102251607B (zh) | 钢筋混凝土叠合墙体节点连接结构及施工方法 | |
CN101691784B (zh) | 钢结构石膏墙体大开间节能住宅建筑及现场分层分段制作方法 | |
CN103046665B (zh) | 设马牙构造柱带钢丝网保温砂浆强化层空斗墙及作法 | |
CN103924797A (zh) | 农村装配式钢结构住宅体系及施工方法 | |
CN103835404B (zh) | 外包钢丝网砂浆板l形边框发泡混凝土承重墙体及作法 | |
CN103993679B (zh) | 低层装配式复合墙体房屋螺栓连接节点结构 | |
CN103343572B (zh) | 预制复合墙板抗震节能农居结构体系 | |
CN108301531B (zh) | 装配式内置保温层混凝土复合墙-轻钢框架-楼板连接节点 | |
CN103352584B (zh) | 一种外套式加固方法 | |
CN103835413A (zh) | 外包钢丝网砂浆板一字形边框发泡混凝土承重墙体及作法 | |
CN106245776A (zh) | 一种装配式混凝土房屋密柱体系 | |
CN106869567A (zh) | 一种耗能型冷弯薄壁钢管混凝土抗侧力体系 | |
CN103334497A (zh) | 一种世构体系框架柱钢筋的连接方法 | |
CN204475580U (zh) | 墙板组件及全装配式房屋 | |
CN103758248A (zh) | T形边框保温砌模单排配筋轻质混凝土墙体及制作方法 | |
CN203394091U (zh) | 一种外套式加固结构 | |
CN203334423U (zh) | 一种预制叠合阳台板与主体的钢筋拉结结构 | |
CN202081537U (zh) | 钢筋混凝土叠合墙体节点连接结构 | |
CN103835401A (zh) | 外包钢丝网砂浆板十字形边框发泡混凝土承重墙体及作法 | |
CN103741961A (zh) | 既有建筑预制圆孔板后增销键暗梁抗震加固方法 | |
CN108625491B (zh) | 装配式h型钢柱-独立基础-混凝土圈梁l形连接节点 | |
CN103015563B (zh) | 外砌模内砌体建筑结构体系 | |
CN203905531U (zh) | 农村装配式钢结构住宅体系 | |
CN108412036A (zh) | 装配式h型钢柱-独立基础-混凝土圈梁十字形连接节点 | |
Zhao | Features and construction of prefabricated buildings |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Du Lihong Inventor before: Dong You Inventor before: Ju Shusen Inventor before: Zhao Enping Inventor before: Xie Jianming Inventor before: Wan Zhao |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20171109 Address after: 102600, room 2, building 2212, center 3, 2 Xinghua street, Daxing District, Beijing Patentee after: Beijing Yong Bo Science and Technology Ltd. Address before: 100043, Beijing, Shijingshan District, 166 Fu Shi Road, two floor, Chak Yang Building Patentee before: Beijing Aeido International Engineering Technology Co., Ltd. |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20181102 Address after: 210008 Hankou Road, Drum Tower District, Nanjing, Jiangsu Province, No. 22 Patentee after: Wei Deying Address before: 102600 room 2212, 2 tower, Pope center 3, 2 Xinghua street, Daxing District, Beijing. Patentee before: Beijing Yong Bo Science and Technology Ltd. |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20190410 Address after: 419500 East Pioneer Road, Chenyang Town, Chenxi County, Huaihua City, Hunan Province - 13 # 13 Building 402 Patentee after: Hunan Junhong Construction Engineering Co., Ltd. Address before: 210008 Hankou Road, Drum Tower District, Nanjing, Jiangsu Province, No. 22 Patentee before: Wei Deying |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20151014 Termination date: 20190709 |