CN103324842A - Method for positioning temporary supporting point of large structure base layer deck piece - Google Patents
Method for positioning temporary supporting point of large structure base layer deck piece Download PDFInfo
- Publication number
- CN103324842A CN103324842A CN2013102291539A CN201310229153A CN103324842A CN 103324842 A CN103324842 A CN 103324842A CN 2013102291539 A CN2013102291539 A CN 2013102291539A CN 201310229153 A CN201310229153 A CN 201310229153A CN 103324842 A CN103324842 A CN 103324842A
- Authority
- CN
- China
- Prior art keywords
- supporting point
- temporary supporting
- point
- rectangular area
- rectangular region
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a method for positioning a temporary supporting point of a large structure base layer deck piece. The method comprises the following steps of (1) confirming a severely-deformed rectangular region required to be supported temporarily in the deck piece; (2) optionally selecting one point in the confirmed rectangular region and using the point as the one-time temporary supporting point, using position coordinates of the one-time temporary supporting point as design variables, and then adopting a zero-order optimization method to calculate position coordinates of an optimal supporting point in the rectangular region through iteration optimizing; (3) selecting a main beam cross point closest to the position coordinates of the optimal supporting point in the rectangular region and using the cross point as the final temporary supporting point. The method has the advantages that the settling volume of a structure can be remarkably decreased, improvement of the stability of a steel structure is facilitated, the design time is shortened, and the design is scientific and reasonable.
Description
Technical field
The present invention relates to the measurement and positioning method, particularly relate to large structure deck of cellar sheet temporary supporting independent positioning method.
Background technology
On the sheet of large structure deck of cellar, because the weight of steel construction large (one deck just has about the hundreds of ton usually), and build and normally carry out on the subgrade basis, so ground can produce sedimentation.Owing to reasons such as structures, the sedimentation of each spud leg also can be different simultaneously.If differential settlement is apart from excessive, just steel construction piece may produce the danger such as rollover between each spud leg.Engineering equipment is installed on the girder steel, and girder steel also can produce distortion, if surpassed the yield limit of steel, girder steel can produce plastic yield, and this is definitely unallowed, so be necessary distortion is optimized design, namely increases temporary supporting at deck plate.
Summary of the invention
The object of the invention is to overcome the deficiency of prior art, a kind of settling amount that can significantly reduce works is provided, be conducive to improve the large structure deck of cellar sheet temporary supporting independent positioning method of the steadiness of steel construction.
In order to achieve the above object, the technical solution used in the present invention is:
Large structure of the present invention deck of cellar sheet temporary supporting independent positioning method, it may further comprise the steps:
(1) determines the large rectangular area that needs to increase temporary supporting of distortion in the deck plate;
(2) in selected rectangular area, choose arbitrarily a bit as a temporary supporting point, with the position coordinates of a temporary supporting point as design variable, then adopt the zeroth order optimization method, by Optimized Iterative, calculate optimum supporting point position coordinate in the rectangular area;
(3) in the rectangular area, choose with the nearest girder point of crossing of optimum supporting point position coordinate as final temporary supporting point.
The invention has the advantages that: can significantly reduce the settling amount of works by this method, be conducive to improve the steadiness of steel construction, reduce design time, make the more science, reasonable that designs.
Description of drawings
Accompanying drawing is the schematic diagram of the deck plate that relates in the sheet temporary supporting independent positioning method of large structure of the present invention deck of cellar.
Embodiment
Describe the present invention below in conjunction with the drawings and specific embodiments.
This large structure deck of cellar sheet temporary supporting independent positioning method as shown in the figure, it may further comprise the steps: (1) determines the large rectangular area that needs to increase temporary supporting of distortion in the deck plate, the zone 5 that is represented by dotted lines among the figure; First, second, third, fourth girder point of crossing 1,2,3,4 is arranged in the rectangular area.(2) in selected rectangular area, choose arbitrarily a bit as a temporary supporting point, as design variable, then adopt the zeroth order algorithm with the position coordinates of a temporary supporting point, calculate optimum supporting point position coordinate in the rectangular area by Optimized Iterative; True origin among the figure is the lower-left point in the rectangular area.(3) in the rectangular area, choose with the nearest girder point of crossing of optimum supporting point position coordinate as final temporary supporting point.The principle of the zeroth order optimization method in the described step (2) is: the match objective function, then utilize penalty function to convert restricted minimization problem to unconstrained problem, in the approximate enterprising row iteration of penalty function, until objective function convergence, thereby obtain the optimal design variable, even the optimum supporting point position of works deflection minimum.
(1) analyzes the large structure deck plate is stressed by the ANSYS finite element analysis software, determine the large rectangular area that needs to increase temporary supporting of distortion in the deck plate;
(2) in selected rectangular area, choose arbitrarily a bit as a temporary supporting point, as design variable, then adopt the zeroth order optimization method to calculate optimum supporting point position coordinate in the rectangular area with the position coordinates of a temporary supporting point;
Concrete grammar is:
1. set up the mathematical model of optimal design
(1) determines design variable
Delimit the large rectangular area that needs to increase temporary supporting of distortion in the deck plate, set up rectangular coordinate system, as shown in Figure 1.1,2,3,4 girder point of crossing wherein, 5 is the rectangular area of delimiting.Distance is a between the setting border, the left and right sides, rectangular area, and distance is b between the up-and-down boundary.
Any selected point A is as a temporary supporting point in the zone, with the position coordinates of this point as design variable, that is:
X=[x
1,x
2]
T=[x,y]
T
In the formula, x
1---the horizontal ordinate of temporary supporting point A;
x
2---the ordinate of temporary supporting point A.
(2) determine the constraint function that A is ordered
A. performance constraints condition:
The node stress σ that temporary supporting is pointed out establishes σ in the allowable stress range of structure
cBe the structure permissible stress, then have:
σ≤σ
c
The mathematic(al) representation that obtains thus constraint function is:
g
1(x)=σ-σ
c≤0
B. range constraint condition:
The constraint of the design variable (position of a temporary supporting) that the present invention is selected just belongs to boundary constraint, and then the mathematic(al) representation of design variable boundary constraint function is:
g
5(x)=y-b≤0
G in the formula
2(x), g
3(x), g
4(x), g
5The position constraint of the upper and lower, left and right of (x) ordering for A.
(3) determine objective function minF (x)
Maximum deformation value δ is as objective function, and maximum distortion is minimum.
(4) set up optimized mathematical model
minF(x)
X=[x
1,x
2]
T=[x,y]
T
s.t.g
u(x)≤0 u=1,2,…,5
g
u(x) this function is changed lack bracket half, do not have other problems
3. optimization method.
(1) match objective function
In the deck module zone of choosing, choose n discrete temporary supporting point, the ANSYS finite element analysis is carried out in malformation after successively each temporary supporting point being increased, set up the model of the rammer soil base at large structure and place thereof, divide by grid, imposed load carries out FEM (finite element) calculation, and result of calculation carried out stress and deformation analysis, extract maximum deformation quantity δ.
According to principle of least square method match deflection expression formula, use objective function
The expression maximum deformation quantity then has:
Come Coefficient of determination a by the weighted least-squares error
iAnd b
IjThat is:
In the formula, the group number of n---design variable;
W
(j)---the weight relevant with j group design variable, desirable 1;
f
(j)---the j that is calculated by finite element method organizes maximum deformation quantity corresponding to temporary supporting position;
---the j that is calculated by formula (1) organizes maximum deformation quantity corresponding to temporary supporting position.
According to the principle of least square, ask E
2Minimal value, get system of equations:
Separate this system of equations, can get coefficient a
i, b
Ij, in generation, returned the objective function that equation can get the match form
In ensuing optimizing process, whenever carry out iteration one time, then obtain one group of a that upgrades
iAnd b
Ij
(2) be converted to unconstrained optimization problem
Adopt penalty function to remove constraint, that is:
In the formula, G (g
i) be the penalty function of state variable constrain;
p
kBe penalty function G (g
i) penalty factor, 0<p
k<1, get successively p
k=1,0.1,0.01 ... the penalty function form of constraint function is as follows:
To F (X, p
k) get ultimate value, to obtain the optimization solution X of this iteration
*=[x
1, x
2], that is:
(3) Optimized Iterative
A. choose initial temporary supporting position X
(0), substitution formula 1 upgrades maximum deformation quantity expression formula coefficient a according to formula 2,3
iAnd b
Ij, in generation, returns formula 1 and obtains match deflection expression formula
B. set initial penalty factor p
0, try to achieve constraint penalty function G (g
i).
C. will
And G (g
i) for returning formula 4 couples of F (X, p
0) ask ultimate value, obtain this iteration optimization solution X
* (0)And and X
* (0)Corresponding
And F
(0)
D. getting successively the k time iteration is: X
(k+1)=X
* (k), p
K+1=cp
k(c=0.1), proceed according to the method described above iteration, respectively must be corresponding in this
With F
(k+1)
4. set the cycle control parameter.
Set and work as
When (τ is the tolerance of objective function σ), reach convergence state, stop cycle calculations.
5. check the implementation sequence result, list the optimized design variable, be i.e. the position coordinates of optimum temporary supporting point.
6. in the rectangular area, choose with the nearest girder point of crossing of optimum supporting point position coordinate as final temporary supporting point.
Reduce the settling amount of works by this method, the steadiness of steel construction improves.
Claims (1)
1. large structure deck of cellar sheet temporary supporting independent positioning method is characterized in that it may further comprise the steps:
(1) determines the large rectangular area that needs to increase temporary supporting of distortion in the deck plate;
(2) in selected rectangular area, choose arbitrarily a bit as a temporary supporting point, with the position coordinates of a temporary supporting point as design variable, then adopt the zeroth order optimization method, by Optimized Iterative, calculate optimum supporting point position coordinate in the rectangular area;
(3) in the rectangular area, choose with the nearest girder point of crossing of optimum supporting point position coordinate as final temporary supporting point.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013102291539A CN103324842A (en) | 2013-06-08 | 2013-06-08 | Method for positioning temporary supporting point of large structure base layer deck piece |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013102291539A CN103324842A (en) | 2013-06-08 | 2013-06-08 | Method for positioning temporary supporting point of large structure base layer deck piece |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103324842A true CN103324842A (en) | 2013-09-25 |
Family
ID=49193581
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013102291539A Pending CN103324842A (en) | 2013-06-08 | 2013-06-08 | Method for positioning temporary supporting point of large structure base layer deck piece |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103324842A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106347577A (en) * | 2016-09-26 | 2017-01-25 | 中国海洋石油总公司 | Construction technology capable of shortening block slide way occupation and general assembly period |
CN108180878A (en) * | 2017-11-21 | 2018-06-19 | 博迈科海洋工程股份有限公司 | A kind of heavy die block structure middle deck piece installation error control method |
CN109446680A (en) * | 2018-11-05 | 2019-03-08 | 天津大学 | Plate detection device supporting pin position optimization design method and device |
CN112478082A (en) * | 2020-12-11 | 2021-03-12 | 天津博迈科海洋工程有限公司 | Construction precision control method for large ocean oil and gas module multilayer deck |
CN113914227A (en) * | 2021-11-11 | 2022-01-11 | 中国水利水电第五工程局有限公司 | Construction method for viaduct curved section steel box girder supporting system on existing bridge |
CN115240429A (en) * | 2022-08-11 | 2022-10-25 | 深圳市城市交通规划设计研究中心股份有限公司 | Pedestrian and vehicle flow statistical method, electronic equipment and storage medium |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1100498A (en) * | 1993-08-11 | 1995-03-22 | 约亨·科斯 | Bearing block |
JPH10219827A (en) * | 1997-01-31 | 1998-08-18 | V N Eng Kk | Framing structure of multistoried building |
JP2005022771A (en) * | 2003-06-30 | 2005-01-27 | Mitsubishi Juko Koji Kk | Lifting/lowering device for heavy article |
US20070295379A1 (en) * | 2004-05-13 | 2007-12-27 | Ipo L.L.C. | Modular boat lift canopy assembly and kit |
CN101566013A (en) * | 2009-06-03 | 2009-10-28 | 西安建筑科技大学 | Main factory building structure system for large-scale thermal power plant |
CN102733599A (en) * | 2012-06-08 | 2012-10-17 | 北京市第三建筑工程有限公司 | Fastener type steel pipe scaffold framework support applicable to steel reinforced concrete beam |
-
2013
- 2013-06-08 CN CN2013102291539A patent/CN103324842A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1100498A (en) * | 1993-08-11 | 1995-03-22 | 约亨·科斯 | Bearing block |
JPH10219827A (en) * | 1997-01-31 | 1998-08-18 | V N Eng Kk | Framing structure of multistoried building |
JP2005022771A (en) * | 2003-06-30 | 2005-01-27 | Mitsubishi Juko Koji Kk | Lifting/lowering device for heavy article |
US20070295379A1 (en) * | 2004-05-13 | 2007-12-27 | Ipo L.L.C. | Modular boat lift canopy assembly and kit |
CN101566013A (en) * | 2009-06-03 | 2009-10-28 | 西安建筑科技大学 | Main factory building structure system for large-scale thermal power plant |
CN102733599A (en) * | 2012-06-08 | 2012-10-17 | 北京市第三建筑工程有限公司 | Fastener type steel pipe scaffold framework support applicable to steel reinforced concrete beam |
Non-Patent Citations (3)
Title |
---|
张冰: "大跨度空间结构建造过程中吊点和支撑位置合理性研究", 《中国优秀硕士学位论文全文数据库(工程科技II辑)》 * |
方金苗: "基于ANSYS的导管架海洋平台的优化设计", 《中国优秀硕士学位论文全文数据库(工程科技II辑)》 * |
陈博文: "大跨度钢结构吊点优化研究", 《中国优秀硕士学位论文数据库(工程科技II辑)》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106347577A (en) * | 2016-09-26 | 2017-01-25 | 中国海洋石油总公司 | Construction technology capable of shortening block slide way occupation and general assembly period |
CN108180878A (en) * | 2017-11-21 | 2018-06-19 | 博迈科海洋工程股份有限公司 | A kind of heavy die block structure middle deck piece installation error control method |
CN109446680A (en) * | 2018-11-05 | 2019-03-08 | 天津大学 | Plate detection device supporting pin position optimization design method and device |
CN109446680B (en) * | 2018-11-05 | 2023-05-09 | 天津大学 | Method and device for optimally designing position of supporting pin of plate detection device |
CN112478082A (en) * | 2020-12-11 | 2021-03-12 | 天津博迈科海洋工程有限公司 | Construction precision control method for large ocean oil and gas module multilayer deck |
CN112478082B (en) * | 2020-12-11 | 2022-07-08 | 天津博迈科海洋工程有限公司 | Construction precision control method for large ocean oil and gas module multilayer deck |
CN113914227A (en) * | 2021-11-11 | 2022-01-11 | 中国水利水电第五工程局有限公司 | Construction method for viaduct curved section steel box girder supporting system on existing bridge |
CN115240429A (en) * | 2022-08-11 | 2022-10-25 | 深圳市城市交通规划设计研究中心股份有限公司 | Pedestrian and vehicle flow statistical method, electronic equipment and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103324842A (en) | Method for positioning temporary supporting point of large structure base layer deck piece | |
CN102243671B (en) | Method for analyzing temperature gradient effect of flat steel box girder of long-span steel bridge | |
CN105731262A (en) | Tower crane plane arranging system and method based on BIM (building information modeling) technology | |
CN104405054B (en) | A kind of construction design method that viscous damper is set | |
CN103106305A (en) | Space grid structure model step-by-step correction method based on actual measurement mode | |
CN101956476A (en) | Power characteristic-based power transmission tower structural failure early warning method | |
CN109056533B (en) | Method for determining bridge-forming cable force of cable cooperation system bridge | |
CN102375913B (en) | Method for generating wing by adopting active structure rigidity method | |
CN102493569B (en) | Seismic behavior based optimization method and system for building structure | |
CN103266570A (en) | Method for accurately installing and positioning suspension bridge main cable anchor system | |
CN102682175A (en) | Method for analyzing reliability of construction error of grid structure based on buckling mode combination | |
CN203420265U (en) | System for monitoring deformation of edge of foundation ditch | |
CN104458455A (en) | Spatial tower leg structure testing method of narrow-based power transmission steel pipe tower | |
CN105808802B (en) | A kind of lead core rubber support equivalent linearization modeling method and its isolation bridge application | |
CN104553660A (en) | Control method and control device of self-adaptive active suspension | |
CN103955603B (en) | Consider time effect and coefficient super-high building structure Calculation Methods for Internal Force | |
CN108166503A (en) | Supporting construction maximum distortion ability approximate calculation method and system | |
CN115323918B (en) | Installation pre-deflection adjusting and calculating method for large-section steel box girder support | |
CN209011214U (en) | A kind of TMD damping cisten mechanism | |
CN102587289A (en) | Automatic control pre-assembly device and method for steel box girders | |
CN102184316B (en) | Method for automatically selecting type of variable-force spring and determining type information | |
CN102034014B (en) | Method for establishing volute three-dimensional model of redial-axial flow turbine of hydropower station in all-parameter mode | |
CN105160091A (en) | Earthquake resistant design system based on structural integrity | |
CN105046324A (en) | Height anomaly fitting interpolation calculation method based on mobile neural network | |
Alaghmandan et al. | Modifying tall building form to reduce the along-wind effect |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130925 |