CN102587289A - Automatic control pre-assembly device and method for steel box girders - Google Patents
Automatic control pre-assembly device and method for steel box girders Download PDFInfo
- Publication number
- CN102587289A CN102587289A CN201210101981XA CN201210101981A CN102587289A CN 102587289 A CN102587289 A CN 102587289A CN 201210101981X A CN201210101981X A CN 201210101981XA CN 201210101981 A CN201210101981 A CN 201210101981A CN 102587289 A CN102587289 A CN 102587289A
- Authority
- CN
- China
- Prior art keywords
- steel box
- steel case
- case beam
- box girders
- hydraulic jack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses an automatic control pre-assembly device for steel box girders. The automatic control pre-assembly device for the steel box girders comprises a plurality of vertically arranged hydraulic jacks which are connected with a hydraulic control console. According to the automatic control pre-assembly device for the steel box girders, springing parameters of the steel box girders can be controlled precisely, the assembly efficiency is high, and an effect of spatial three-dimensional curve springing of the steel box girders can be achieved. The invention also discloses a method for assembling the steel box girders by adopting the automatic control pre-assembly device for the steel box girders. The method comprises the following steps of: calculating rational pivot positions of the steel box girders through stress analysis software; arranging a plurality of hydraulic jacks below each steel box girder according to the rational pivot; controlling the hydraulic jacks by using the hydraulic control console to adjust the heights as well as the longitudinal and transverse directions of the steel box girders to achieve a steel box girder bridging linear effect; and arranging bridge matching pieces. The method is convenient to implement, suitable for industrial production and high in control precision.
Description
Technical field
The present invention relates to a kind of assembly unit device of steel case beam, relate in particular to a kind of steel case beam preparatory assembly unit device of control automatically; The invention still further relates to the said steel case beam method of the preparatory assembly unit device jointing steel box beam of control automatically of utilizing.
Background technology
The preparatory assembly unit of domestic and international existing steel case beam is divided into and utilizes moulding bed arch camber technology to realize steel case beam arch camber and utilize steel case beam length and the arch camber of matching parts thickness realization steel case beam.The moulding bed arch camber comparatively bothers, and efficiency of construction is low, and cost is big.Utilize steel case beam length and matching parts arch camber, precision is low, and it is linear to react the bridge location steel box beam erection more really.Daxie, the Zhejiang second bridge steel case beam is divided into straightway, the section of broadening and relaxes three kinds of forms of curved section; Bridge axis shape is the space three-dimensional curve that vertical curve and horizontal curve constitute; Adopt preparatory assembly unit moulding bed to make steel case beam, when assembly unit different segment in advance, need each transformation of the way moulding bed, and can not design moulding bed accurately; Cause steel case beam making error big, the size Control inaccuracy.
Summary of the invention
Goal of the invention: the objective of the invention is to the deficiency to prior art, provide a kind of and can accurately control steel case beam arch camber parameter, assembly unit efficient is high, can realize that the steel case beam of steel case beam space three-dimensional curve arch camber is controlled preparatory assembly unit device automatically.Another object of the present invention is to provide a kind of said steel case beam method of the preparatory assembly unit device jointing steel box beam of control automatically of utilizing.
Technical scheme: in order to realize the foregoing invention purpose, the technical scheme that the present invention adopted is:
A kind of steel case beam is the preparatory assembly unit device of control automatically, comprises the hydraulic jack that plurality of vertical is arranged, described hydraulic jack is connected with hydraulic control panel.
The hydraulic jack of described vertical layout per four as one group, each group is connected with hydraulic control panel respectively.
A kind of big shaped steel case beam is controlled pre-assembly method automatically; Adopt the reasonable position of the fulcrum of force analysis computed in software tapping case beam; Under each steel case beam, arrange several hydraulic jack according to reasonable fulcrum; Utilize hydraulic control panel control hydraulic jack to carry out steel case deck-molding journey and vertical and horizontal adjustment, it is linear to reach steel box beam erection, and the bridge location matching parts is installed then.
Calculate four reasonable fulcrums of each steel case beam, arrange four hydraulic jack according to reasonable fulcrum below each steel case beam.
Adopt the reasonable position of the fulcrum of force analysis computed in software tapping case beam; Under each steel case beam, arrange four hydraulic jack; Utilize hydraulic control panel to carry out steel case deck-molding journey and vertical and horizontal adjustment; It is linear to reach steel box beam erection, and the bridge location matching parts is installed then, when bridge location sets up, utilizes the bridge location matching parts to reset and sets up.
Beneficial effect: the present invention compared with prior art, its beneficial effect is:
Hydraulic jack is arranged on the reasonable position of the fulcrum of steel case beam, through the rise drawdown parameter of hydraulic control panel control hydraulic jack, accurately controls each strong point height, has promptly guaranteed the arch camber parameter of steel case beam; The hydraulic jack scalable data is controlled, is convenient to regulate the position of each strong point of steel case beam; Adopt hydraulic system can support heavy weight steel case beam, be fit to the preparatory assembly unit of big shaped steel case beam; Hydraulic control panel is easy to operate, and assembly unit efficient is high, has removed complicated internal model making from, has reduced cost of production; The method of the big shaped steel case of assembly unit of the present invention beam is convenient to implement, and be fit to suitability for industrialized production, and control accuracy is high.
Description of drawings
Fig. 1 is a structural representation of the present invention.
The specific embodiment
Below in conjunction with accompanying drawing, through a most preferred embodiment, technical scheme of the present invention is elaborated, but protection scope of the present invention is not limited to said embodiment.
As shown in Figure 1; A kind of steel case beam is the preparatory assembly unit device of control automatically; Comprise the hydraulic jack 1 that plurality of vertical is arranged, confirm to be provided with the quantity of hydraulic jack according to quantity, quality and the size of steel case beam, described hydraulic jack 1 is connected with hydraulic control panel 2; The hydraulic jack of described vertical layout per four as one group, each group is connected with hydraulic control panel respectively.Adopt the reasonable position of the fulcrum of ansys force analysis computed in software tapping case beam 3; Under each steel case beam, arrange four hydraulic jack according to reasonable fulcrum; With flat car for transport of sills steel case beam is placed on the hydraulic jack position piecemeal, utilizes hydraulic control panel to carry out steel case deck-molding journey and vertical and horizontal adjustment, it is linear to reach steel box beam erection; Detect linear qualified back bridge location matching parts 4 is installed, when bridge location sets up, utilize bridge location matching parts 4 to reset and set up.
Claims (4)
1. a steel case beam is controlled preparatory assembly unit device automatically, and it is characterized in that: comprise the hydraulic jack that plurality of vertical is arranged, described hydraulic jack is connected with hydraulic control panel.
2. steel case beam according to claim 1 is the preparatory assembly unit device of control automatically, it is characterized in that: the hydraulic jack of described vertical layout per four as one group, each group is connected with hydraulic control panel respectively.
3. a steel case beam is controlled pre-assembly method automatically; It is characterized in that: the reasonable position of the fulcrum that adopts force analysis computed in software tapping case beam; Under each steel case beam, arrange several hydraulic jack according to reasonable fulcrum; Utilize hydraulic control panel control hydraulic jack to carry out steel case deck-molding journey and vertical and horizontal adjustment, it is linear to reach steel box beam erection, and the bridge location matching parts is installed then.
4. steel case beam according to claim 3 is controlled pre-assembly method automatically, it is characterized in that: calculate four reasonable fulcrums of each steel case beam, arrange four hydraulic jack according to reasonable fulcrum below each steel case beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210101981XA CN102587289A (en) | 2012-03-31 | 2012-03-31 | Automatic control pre-assembly device and method for steel box girders |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210101981XA CN102587289A (en) | 2012-03-31 | 2012-03-31 | Automatic control pre-assembly device and method for steel box girders |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102587289A true CN102587289A (en) | 2012-07-18 |
Family
ID=46476483
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210101981XA Pending CN102587289A (en) | 2012-03-31 | 2012-03-31 | Automatic control pre-assembly device and method for steel box girders |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102587289A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103741602A (en) * | 2013-12-19 | 2014-04-23 | 中铁宝桥集团有限公司 | Steel box girder computer simulation flat arch camber preassembling method |
CN104607815A (en) * | 2014-12-18 | 2015-05-13 | 大连船舶重工集团装备制造有限公司 | Method for manufacturing and controlling camber of crane main girder |
CN105499927A (en) * | 2015-12-24 | 2016-04-20 | 中铁宝桥集团有限公司 | Manufacturing method of space curve profile steel component |
CN111501559A (en) * | 2020-04-07 | 2020-08-07 | 中铁大桥科学研究院有限公司 | System for assembling steel box girder of swivel cable-stayed bridge and adjusting method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1077609A (en) * | 1996-09-02 | 1998-03-24 | Kawada Kogyo Kk | Steel member manufacturing method |
CN1415040A (en) * | 1999-12-31 | 2003-04-30 | 奥特玛尔·法里昂 | Unit for production of track elements |
CN1978305A (en) * | 2005-12-07 | 2007-06-13 | 因温特奥股份公司 | Transportation system cradle, intermediate product, assembly plant, and method for manufacturing assembly |
CN101623820A (en) * | 2009-08-05 | 2010-01-13 | 中铁宝桥集团有限公司 | Horizontal preassembling method of large-sized bridge steel tower |
CN201534280U (en) * | 2009-08-05 | 2010-07-28 | 中铁宝桥集团有限公司 | Horizontal pre-assembly system for steel tower of large-scale bridge |
CN202519584U (en) * | 2012-03-31 | 2012-11-07 | 中铁宝桥(扬州)有限公司 | Automatic control pre-framing device for steel box girder |
-
2012
- 2012-03-31 CN CN201210101981XA patent/CN102587289A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1077609A (en) * | 1996-09-02 | 1998-03-24 | Kawada Kogyo Kk | Steel member manufacturing method |
CN1415040A (en) * | 1999-12-31 | 2003-04-30 | 奥特玛尔·法里昂 | Unit for production of track elements |
CN1978305A (en) * | 2005-12-07 | 2007-06-13 | 因温特奥股份公司 | Transportation system cradle, intermediate product, assembly plant, and method for manufacturing assembly |
CN101623820A (en) * | 2009-08-05 | 2010-01-13 | 中铁宝桥集团有限公司 | Horizontal preassembling method of large-sized bridge steel tower |
CN201534280U (en) * | 2009-08-05 | 2010-07-28 | 中铁宝桥集团有限公司 | Horizontal pre-assembly system for steel tower of large-scale bridge |
CN202519584U (en) * | 2012-03-31 | 2012-11-07 | 中铁宝桥(扬州)有限公司 | Automatic control pre-framing device for steel box girder |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103741602A (en) * | 2013-12-19 | 2014-04-23 | 中铁宝桥集团有限公司 | Steel box girder computer simulation flat arch camber preassembling method |
CN104607815A (en) * | 2014-12-18 | 2015-05-13 | 大连船舶重工集团装备制造有限公司 | Method for manufacturing and controlling camber of crane main girder |
CN105499927A (en) * | 2015-12-24 | 2016-04-20 | 中铁宝桥集团有限公司 | Manufacturing method of space curve profile steel component |
CN105499927B (en) * | 2015-12-24 | 2017-12-12 | 中铁宝桥集团有限公司 | A kind of manufacture method of space curve Steel section member |
CN111501559A (en) * | 2020-04-07 | 2020-08-07 | 中铁大桥科学研究院有限公司 | System for assembling steel box girder of swivel cable-stayed bridge and adjusting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102322071B (en) | Universal base structure of main transformer of 220kV substation | |
CN102500979A (en) | Method for forming and assembling four faces of bridge crane box type girder | |
CN102587289A (en) | Automatic control pre-assembly device and method for steel box girders | |
CN203793390U (en) | Mobile car for mounting guide rail rack | |
CN203783165U (en) | Multi-directional accurate adjusting device for embedded part | |
CN103643667A (en) | Ship lift nut column installation auxiliary adjustment method | |
CN105013899B (en) | Bending component forming method based on BIM technology | |
CN202519584U (en) | Automatic control pre-framing device for steel box girder | |
CN201738597U (en) | Sectional steel and steel pipe combined type support system of beam with high and large cross section | |
CN203772858U (en) | Loadable mobile side wall for roadbed slope three-dimensional mould test platform | |
CN102501198A (en) | Method for adjusting flexibility of assembly fixture of car body | |
CN202164623U (en) | Universal foundation structure of 220 kV transformer substation main transformer | |
CN204295412U (en) | Longmen machine tool crossbeam relief arrangement | |
CN102505863B (en) | Wireless laser synchronous control device for multi-rail slide construction | |
CN204531180U (en) | Control the stiff skeleton of large-scale component reinforcing bar binding precision | |
CN202540273U (en) | Support for inclined stay bar | |
CN203156332U (en) | Off-line assembling platform for flattener | |
CN203513176U (en) | Four-column car lifting machine | |
CN203108983U (en) | Gate embedded part correcting device | |
CN201437587U (en) | Steel-casing assembling platform suitable for marine construction | |
CN201433074Y (en) | Height positioning mechanism of lifting machine | |
CN203383515U (en) | Displacer | |
CN202763337U (en) | Flange connecting pipe height marking tool | |
CN102879074B (en) | Method for trail weighing of anchor machine sensor | |
CN201778495U (en) | Jig frame for overhead assembly of large-span truss |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20120718 |