CN103321154A - Integral hoisting construction method for long-span steel truss girder - Google Patents

Integral hoisting construction method for long-span steel truss girder Download PDF

Info

Publication number
CN103321154A
CN103321154A CN2013102618790A CN201310261879A CN103321154A CN 103321154 A CN103321154 A CN 103321154A CN 2013102618790 A CN2013102618790 A CN 2013102618790A CN 201310261879 A CN201310261879 A CN 201310261879A CN 103321154 A CN103321154 A CN 103321154A
Authority
CN
China
Prior art keywords
hoisting
steel truss
construction
steel
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102618790A
Other languages
Chinese (zh)
Other versions
CN103321154B (en
Inventor
侯宇飞
钱有伟
欧阳石
赵飞
陈辉
吴曙光
汤彬伟
谢志华
房玉环
万欢欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
China Railway Group Ltd CREC
Second Engineering Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
China Railway Group Ltd CREC
Second Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, China Railway Group Ltd CREC, Second Engineering Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201310261879.0A priority Critical patent/CN103321154B/en
Publication of CN103321154A publication Critical patent/CN103321154A/en
Application granted granted Critical
Publication of CN103321154B publication Critical patent/CN103321154B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种大跨径钢桁梁整体吊装的施工方法,本施工方法包括以下步骤:(1)钢桁梁整体吊装吊点选择,(2)吊具设计与施工,(3)整体吊装施工,本发明有以下优点:在通航条件下采用整体吊装的方法架设钢桁梁,与少支架分段拼装、浮托法施工钢桁梁相比,操作相对简单,精度控制相对容易;同时减少了水上作业的安全风险,缩短了施工工期,减少了施工成本。

Figure 201310261879

The invention discloses a construction method for the overall hoisting of large-span steel truss girders. The construction method includes the following steps: (1) selection of hoisting points for the overall hoisting of steel truss girders, (2) design and construction of slings, (3) overall For hoisting construction, the present invention has the following advantages: the overall hoisting method is adopted to erect the steel truss girder under the navigational condition, compared with the steel truss girder constructed by segmental assembly with few supports and float-over method, the operation is relatively simple, and the precision control is relatively easy; at the same time The safety risk of water operations is reduced, the construction period is shortened, and the construction cost is reduced.

Figure 201310261879

Description

一种大跨径钢桁梁整体吊装施工方法A construction method for overall hoisting of long-span steel truss girders

技术领域 technical field

  本发明涉及桥梁制造领域,特别涉及一种大跨径钢桁梁整体吊装施工方法。  The present invention relates to the field of bridge manufacturing, in particular to a construction method for integral hoisting of large-span steel truss girders. the

背景技术 Background technique

目前钢桁梁整体吊装施工作为一种新发展起来的桥梁施工方法,由于对航道正常通航的影响很小、变高空作业为地面作业、施工快速、技术和经济效益高,在船舶流量大的航道区域施工中有很大的应用优势和应用前景。在这一领域有所突破,就意味着站在新的制高点上,其经济价值和应用前景非常好。  At present, the overall hoisting construction of steel truss girders is a newly developed bridge construction method. Because it has little impact on the normal navigation of the channel, the high-altitude operation is changed to ground operation, the construction is fast, and the technical and economic benefits are high. There are great application advantages and application prospects in regional construction. A breakthrough in this field means standing on a new commanding height, and its economic value and application prospects are very good. the

我国河道中不少河流过往的千吨级的船舶及拖挂船队很多,在桥梁施工期间不得断航。按照海事部门要求,航道内若设置支架,其净跨度不得小于45m,通航限高不得小于7m,若采用少支架法施工,在航道内设置的支架难免受到过往船只碰撞,危机船舶航运安全,同时支架自身的安全隐患很大,采用浮托法施工,施工工艺复杂,施工投入成本较大,安全风险高。  There are many thousand-ton ships and trailer fleets passing by many rivers in our country, and they must not stop sailing during bridge construction. According to the requirements of the maritime department, if supports are installed in the channel, the net span shall not be less than 45m, and the navigation height limit shall not be less than 7m. The safety hazard of the support itself is very large. The float-over method is used for construction, the construction process is complicated, the construction investment cost is large, and the safety risk is high. the

发明内容 Contents of the invention

本发明的目的是为了解决上述技术问题,提供一种操作简单,投入成本相对较低的大跨径钢桁梁整体吊装施工方法。  The object of the present invention is to solve the above-mentioned technical problems and provide a construction method for integral hoisting of large-span steel truss girders with simple operation and relatively low investment cost. the

本发明的技术方案:一种大跨径钢桁梁整体吊装施工方法,本施工方法包括以下步骤:  The technical scheme of the present invention: a construction method for integral hoisting of large-span steel truss girders, the construction method includes the following steps:

(1)吊点选择:根据现有浮吊设备的参数,选择合理的吊点位置;采取500吨和300吨的两台浮吊抬吊法进行吊装,根据两台浮吊设备的起重性能,合理选择钢桁梁吊点位置,设置不对称吊点以满足吊装设备不统一的问题,保证不同型号浮吊设备充分发挥性能。吊点位置应选在桁梁节点处,通过计算钢桁梁在吊装过程中吊点处的支点反力,同时根据现场吊装作业的实际情况,查阅两台浮吊的起重参数表,比较计算的反力是否符合浮吊参数表中的数值,进而确定合适吊点位置; (1) Selection of lifting points: According to the parameters of the existing floating cranes, select a reasonable lifting point position; use two floating cranes of 500 tons and 300 tons for lifting, and according to the lifting performance of the two floating cranes , Reasonably select the location of the steel truss girder lifting points, set asymmetrical lifting points to meet the problem of non-uniform lifting equipment, and ensure that different types of floating cranes can give full play to their performance. The position of the lifting point should be selected at the node of the truss girder. By calculating the fulcrum reaction force at the lifting point of the steel truss girder during the hoisting process, and according to the actual situation of the on-site hoisting operation, refer to the lifting parameter table of the two floating cranes, and compare and calculate Check whether the reaction force conforms to the value in the floating crane parameter table, and then determine the appropriate lifting point position;

(2)吊具设计与施工:本钢桁梁吊装,通过利用上弦节点A2、A4、A3、A5处既有螺栓孔群,在节点内外侧通过M24螺栓各加贴一块30mm厚的Q370qE钢板,连接钢板均高出钢桁梁上弦杆顶面50cm,并在其上焊接一块720*800*30mm的Q370qE盖板,将节点内外侧加贴的连接钢板连接起来,并按间距20cm设置16mm厚度加劲板加固内外侧加贴连接板,钢桁梁吊装时,为有效减少吊索对钢桁梁的横向压力,在同节点上平联横杆上安装一根φ426*8mm钢管作横撑,将左右两吊点相连,以抵抗吊装过程中产生的横桥向水平力;为便于钢丝绳栓结,在节点处连接盖板顶焊接销轴,销轴采用直径10cm,材质为40Cr,耳板采用500*420*30mm的Q235钢板,在销轴位置处开孔,并在开孔处内外侧各加贴一块16mm厚,外径200,内径100mm的环形加强钢板;  (2) Design and construction of hangers: For the hoisting of the steel truss girder, by using the existing bolt hole groups at the upper chord nodes A2, A4, A3, and A5, a 30mm-thick Q370qE steel plate is attached to the inner and outer sides of the nodes through M24 bolts. The connecting steel plates are all 50cm higher than the top surface of the upper chord of the steel truss girder, and a 720*800*30mm Q370qE cover plate is welded on it to connect the connecting steel plates attached to the inner and outer sides of the nodes, and a 16mm thick reinforcement is set at a distance of 20cm When the steel truss girder is hoisted, in order to effectively reduce the lateral pressure of the sling on the steel truss girder, a φ426*8mm steel pipe is installed on the parallel cross bar at the same node as a cross brace, and the left and right The two lifting points are connected to resist the horizontal force of the transverse bridge generated during the hoisting process; in order to facilitate the fastening of the steel wire rope, a welding pin is connected to the top of the cover plate at the joint. 420*30mm Q235 steel plate, make a hole at the position of the pin shaft, and add a 16mm thick, 200 outer diameter, and 100mm inner diameter ring-shaped reinforced steel plate on the inside and outside of the hole;

(3)整体吊装施工过程:钢梁在预拼场地全部拼装,采用500t和300t浮吊浮吊整体吊装架设就位,主要施工步骤如下: (3) Overall hoisting construction process: steel girders are fully assembled at the pre-assembled site, and 500t and 300t floating cranes are used for overall hoisting and erection. The main construction steps are as follows:

①完成基础、主墩及盖梁施工; ① Complete the foundation, main pier and cap beam construction;

②规划拼装场地,以满足钢桁梁拼装和整体吊装需要;为保证拼装后的钢桁梁在浮吊的起重半径范围内,根据现场实际条件,将钢桁梁拼装场地选在新桥下游5.0m的河岸边稻田地,拼装区域距离航道既有驳岸2.0m,以满足浮吊的作业半径,便于整体吊装; ② Plan the assembly site to meet the steel truss girder assembly and overall hoisting needs; in order to ensure that the assembled steel truss girder is within the lifting radius of the floating crane, according to the actual conditions on site, the steel truss girder assembly site is selected at the downstream of the new bridge 5.0m of rice field on the river bank, the assembly area is 2.0m away from the existing revetment of the channel to meet the operating radius of the floating crane and facilitate the overall hoisting;

③利用汽车吊在拼装场地将钢桁梁拼装成为成桥状态; ③Use truck cranes to assemble the steel truss girders into a bridge state at the assembly site;

④进行吊具安装; ④ Install the spreader;

⑤利用浮吊整体吊装钢桁梁,移至桥位处完成钢桁梁架设; ⑤The steel truss girder is hoisted as a whole by the floating crane, and moved to the bridge position to complete the erection of the steel truss girder;

⑥钢梁就位后,从桥梁两端向中间安装混凝土预制桥面板,并浇筑各桥面板的纵缝; ⑥ After the steel girders are in place, install the concrete prefabricated bridge deck from both ends of the bridge to the middle, and pour the longitudinal joints of each bridge deck;

⑦待纵缝达到100%强度后,再分批按次序浇注横缝,每批龄期相差4天; ⑦ After the longitudinal joints reach 100% strength, pour the transverse joints in batches in order, with a difference of 4 days in age between each batch;

⑧进行桥面系施工。  ⑧ Carry out bridge deck system construction. the

本发明的有益效果是:⑴提供一种钢桁梁架设的施工方法,与少支架分段吊装、浮托法架设钢桁梁相比,此法操作相对简单,精度控制相对容易;(2)降低了水上作业施工安全风险;(3)缩短了施工工期;(4)降低施工人员和机械资源的占用,减少施工成本。  The beneficial effects of the present invention are: (1) a construction method for erecting steel truss beams is provided, which is relatively simple in operation and relatively easy in accuracy control compared with segmental hoisting with less supports and erection of steel truss beams by the float-over method; (2) The construction safety risks of water operations are reduced; (3) the construction period is shortened; (4) the occupation of construction personnel and mechanical resources is reduced, and construction costs are reduced. the

附图说明 Description of drawings

图1是本发明的金溧河桥立面简图  ;  Fig. 1 is a simplified diagram of the facade of Jinli River Bridge of the present invention;

图2是本发明吊点连接平面布置图; Fig. 2 is a planar layout diagram of the connection of the suspension points of the present invention;

图3是本发明连接板平面图; Fig. 3 is a plane view of the connecting plate of the present invention;

图4是本发明连接板横桥向立面图; Fig. 4 is the vertical elevation view of the cross bridge of the connecting plate of the present invention;

图5是本发明连接板纵桥向立面图; Fig. 5 is the longitudinal bridge elevation view of the connecting plate of the present invention;

图6是本发明临时横撑截面图; Fig. 6 is a cross-sectional view of a temporary cross brace of the present invention;

图7是本发明节点处连接板栓接图; Fig. 7 is a bolted connection diagram of the connecting plate at the node of the present invention;

图8是本发明吊具耳板构造图; Fig. 8 is a structure diagram of the lug plate of the spreader of the present invention;

图9是本发明步骤一示意图; Fig. 9 is a schematic diagram of Step 1 of the present invention;

图10是本发明步骤三示意图; Fig. 10 is a schematic diagram of Step 3 of the present invention;

图11是本发明步骤四示意图; Fig. 11 is a schematic diagram of Step 4 of the present invention;

其中:1、金溧河桥,2、钢桁梁,3、盖梁,4、6#主墩,5、7#主墩,6、航道驳岸,7、承台,8、航道河床底,9、桩基,10、吊具,11、钢桁梁上弦杆,12、临时钢管横撑,13、A3节点,14、A5节点,15、销轴,16、盖板,17、耳板,18、加劲板,19、连接钢板,20、销轴孔,21、高强螺栓,22、主桁上弦杆,23、脚手架,24、混凝土支墩。 Among them: 1. Jinli River Bridge, 2. Steel truss girder, 3. Cover beam, 4. 6# main pier, 5. 7# main pier, 6. Waterway revetment, 7. Capping platform, 8. Channel bottom, 9. Pile foundation, 10. Spreader, 11. Steel truss beam upper chord, 12. Temporary steel pipe cross brace, 13. A3 node, 14. A5 node, 15. Pin shaft, 16. Cover plate, 17. Ear plate, 18. Stiffeners, 19. Connecting steel plates, 20. Pin holes, 21. High-strength bolts, 22. Main truss top chords, 23. Scaffolding, 24. Concrete piers.

具体实施方式 Detailed ways

金溧河桥1于丹金溧漕河常州辖区金坛段,由于丹金溧漕河航道由五级整治为三级而新建的一座桥梁。新建桥梁位于老桥下游14m处,是一座主跨81.96m的下承式钢桁梁2主桁采用带竖杆的华伦式三角形腹杆体系,节间长度6.75m,主桁高度11m,高跨比为1/7.36。两片主桁中心距为13.2m,宽跨比为1/6.14,桥面宽度为12.0m。钢桁梁2重600余吨。  Jinli River Bridge 1 is a newly built bridge at the Jintan section of the Danjin Licao River Changzhou jurisdiction because the waterway of the Danjin Licao River has been renovated from five levels to three levels. The new bridge is located 14m downstream of the old bridge. It is an under-supported steel truss girder with a main span of 81.96m. The span ratio is 1/7.36. The distance between the centers of the two main trusses is 13.2m, the width-span ratio is 1/6.14, and the bridge deck width is 12.0m. The steel truss girder 2 weighs more than 600 tons. the

大跨径钢桁梁整体吊装施工方法包括以下步骤:  The overall hoisting construction method of large-span steel truss girders includes the following steps:

(1)吊点选择:根据现有浮吊设备,采取500吨和300吨的两台浮吊抬吊法进行吊装;根据两台浮吊设备的起重性能,合理选择钢梁吊点位置,设置不对称吊点以满足吊装设备不统一的问题,保证不同型号浮吊设备充分发挥性能,完成吊装任务。 (1) Selection of lifting points: According to the existing floating crane equipment, two floating cranes of 500 tons and 300 tons are used for hoisting; according to the lifting performance of the two floating cranes, the location of the steel beam lifting point is reasonably selected. Set up asymmetric lifting points to meet the problem of non-uniform hoisting equipment, to ensure that different types of floating cranes can give full play to their performance and complete the hoisting task.

为了保证钢桁梁2吊装过程中结构自身安全,吊点位置应选在桁梁节点处。为保证吊装作业的进行,通过计算钢桁梁2在吊装过程中吊点处的支点反力,同时根据现场吊装作业的实际情况,查阅两台浮吊的起重参数表,比较计算的反力是否符合浮吊参数表中的数值,这样就可以选择出吊点的合适位置。  In order to ensure the safety of the structure itself during the hoisting of the steel truss girder 2, the lifting point should be selected at the node of the truss girder. In order to ensure the hoisting operation, by calculating the fulcrum reaction force at the hoisting point of the steel truss girder 2 during the hoisting process, and according to the actual situation of the on-site hoisting operation, refer to the lifting parameter table of the two floating cranes, and compare the calculated reaction force Whether it conforms to the value in the floating crane parameter table, so that the appropriate position of the lifting point can be selected. the

例如本工程采取500吨和300吨的两台浮吊抬吊法进行吊装,浮吊水平仰角为600。本钢桁梁2拟将将吊点设置在上弦节点A2、A4、A3、A5位置。  For example, this project adopts two floating cranes of 500 tons and 300 tons for hoisting, and the horizontal elevation angle of the floating cranes is 60 0 . The steel truss girder 2 plans to set the lifting points at the upper chord nodes A2, A4, A3, and A5.

通过计算钢桁梁吊装支反力分别为239.98t,359.96t。  Through the calculation of steel truss girder hoisting reaction forces were 239.98t, 359.96t. the

同时根据两台浮吊的起重参数表可知,水平仰角为600 时,300t浮吊起吊重量为280t,500t浮吊起吊重量为380t,大于计算的吊装支反力,吊装节点选择合理。  At the same time, according to the lifting parameter table of the two floating cranes, it can be known that when the horizontal elevation angle is 60 ° , the lifting weight of the 300t floating crane is 280t, and the lifting weight of the 500t floating crane is 380t, which is greater than the calculated lifting support reaction force, and the selection of lifting nodes is reasonable. 

300t/500t浮吊起重负荷表(主扒杆长度40m)300t/500t floating crane lifting load table (main pole length 40m)

Figure 193386DEST_PATH_IMAGE001
Figure 193386DEST_PATH_IMAGE001

(2)吊具设计与施工:本钢桁梁吊装,通过利用上弦节点A2、A4、A3、A5处既有高强螺栓21孔群,在节点内外侧通过M24螺栓各加贴一块30mm厚的Q370qE钢板,连接钢板19均高出钢桁梁上弦杆11顶面50cm,并在其上焊接一块720*800*30mm的Q370qE盖板16,将节点内外侧加贴的连接钢板19连接起来,并按间距20cm设置16mm厚度加劲板18加固内外侧加贴连接板,钢桁梁2吊装时,为有效减少吊索对钢桁梁2的横向压力,在同节点上平联横杆上安装一根φ426*8mm临时钢管横撑12,将左右两吊点相连,以抵抗吊装过程中产生的横桥向水平力;为便于钢丝绳栓结,在节点处连接盖板顶焊接销轴15,销轴15采用直径10cm,材质为40Cr,耳板17采用500*420*30mm的Q235钢板,在销轴位置处开孔即销轴孔20,并在销轴孔20处内外侧各加贴一块16mm厚,外径200,内径100mm的环形钢板;  (2) Design and construction of the spreader: For the hoisting of the steel truss girder, a 30mm-thick Q370qE is attached to the inner and outer sides of the nodes through M24 bolts by using the 21 hole groups of high-strength bolts at the upper chord nodes A2, A4, A3, and A5. The steel plates, the connecting steel plates 19 are all 50cm higher than the top surface of the steel truss girder upper chord 11, and a Q370qE cover plate 16 of 720*800*30mm is welded on it, and the connecting steel plates 19 attached to the inner and outer sides of the nodes are connected together, and press Set 16mm thick stiffeners 18 at a distance of 20cm to strengthen the inner and outer sides and attach connecting plates. When the steel truss girder 2 is hoisted, in order to effectively reduce the lateral pressure of the sling on the steel truss girder 2, a φ426 *8mm temporary steel pipe cross brace 12, connecting the left and right lifting points to resist the horizontal force of the bridge generated during the hoisting process; in order to facilitate the bolting of the steel wire rope, the welding pin 15 is connected to the top of the cover plate at the node, and the pin 15 adopts The diameter is 10cm, and the material is 40Cr. The ear plate 17 is made of 500*420*30mm Q235 steel plate. A hole is opened at the position of the pin shaft, that is, the pin shaft hole 20, and a 16mm thick piece is attached to the inside and outside of the pin shaft hole 20, and the outer Circular steel plate with a diameter of 200mm and an inner diameter of 100mm;

(3)整体吊装施工过程:钢梁在预拼场地全部拼装,采用500t和300t浮吊浮吊整体吊装架设就位,主要施工步骤如下: (3) Overall hoisting construction process: steel girders are fully assembled at the pre-assembled site, and 500t and 300t floating cranes are used for overall hoisting and erection. The main construction steps are as follows:

步骤一:完成基础、6#主墩4、7#主墩5及盖梁3施工;如图9所示。 Step 1: Complete the construction of the foundation, 6# main pier 4, 7# main pier 5 and cover beam 3; as shown in Figure 9.

步骤二:规划拼装场地,以满足整体吊装需要;采用整体吊装法施工,为保证拼装后的钢桁梁2在浮吊的起重半径范围内,根据现场实际条件,将钢桁梁2拼装场地选在新桥下游5.0m的河岸边稻田地,拼装区域距离航道既有驳岸2.0m,以满足浮吊的作业半径,便于整体吊装;  Step 2: Plan the assembly site to meet the overall hoisting needs; use the overall hoisting method for construction, in order to ensure that the assembled steel truss girder 2 is within the lifting radius of the floating crane, according to the actual conditions on site, assemble the steel truss girder 2 The paddy field on the river bank 5.0m downstream of the new bridge is selected, and the assembly area is 2.0m away from the existing revetment of the channel to meet the operating radius of the floating crane and facilitate overall hoisting; 

步骤三:利用汽车吊在预拼场拼装钢桁梁主桁、上下平联、横梁、纵梁、桥门架及横联;如图10所示。 Step 3: Use the truck crane to assemble the steel truss girder main truss, upper and lower parallel joints, beams, longitudinal beams, bridge girders and cross joints in the pre-assembled field; as shown in Figure 10.

步骤四:进行吊具安装;  Step 4: Install the spreader;

步骤五:利用浮吊整体吊装钢桁梁2,移至桥位处完成钢桁梁2架设;如图11所示。 Step 5: Lift the steel truss girder 2 as a whole by using the floating crane, and move to the bridge position to complete the erection of the steel truss girder 2; as shown in Figure 11.

步骤六:钢桁梁2就位后,从两端向中间安装预制桥面板,并浇筑各桥面板的纵缝;  Step 6: After the steel truss girder 2 is in place, install the prefabricated bridge deck from both ends to the middle, and pour the longitudinal joints of each bridge deck;

步骤七:待纵缝达到100%强度后,再分批按次序浇注横缝,每批龄期相差4天; Step 7: After the longitudinal joints reach 100% strength, pour the transverse joints in batches in order, and the age difference of each batch is 4 days;

步骤八:进行桥面系施工。 Step 8: Carry out bridge deck system construction.

Claims (2)

1.一种大跨径钢桁梁整体吊装施工方法,其特征是本施工方法包括以下步骤: 1. A construction method for integral hoisting of large-span steel truss girders, characterized in that the construction method comprises the following steps: 1)吊点选择:根据现有浮吊设备的参数,选择合理的吊点位置;采取500吨和300吨的两台浮吊抬吊法进行吊装,根据两台浮吊设备的起重性能,合理选择钢桁梁吊点位置;吊点位置应选在桁梁节点处,通过计算钢桁梁在吊装过程中吊点处的支点反力,同时根据现场吊装作业的实际情况,查阅两台浮吊的起重参数表,比较计算的反力是否符合浮吊参数表中的数值,进而确定合适吊点位置; 1) Selection of lifting point: According to the parameters of the existing floating crane equipment, select a reasonable lifting point position; use two floating cranes of 500 tons and 300 tons for hoisting, and according to the lifting performance of the two floating cranes, Reasonably select the position of the lifting point of the steel truss girder; Check the lifting parameter table of the floating crane, compare the calculated reaction force with the value in the floating crane parameter table, and then determine the appropriate lifting point position; 2)吊具设计与施工:本钢桁梁吊装,通过利用上弦节点处设有的螺栓孔群,在节点内外两侧各加贴一块30mm厚的Q370qE连接钢板,连接钢板高出钢桁梁上弦杆顶面50cm,并在其上焊接一块720*800*30mm的Q370qE盖板,将节点内外侧加贴的连接钢板连接起来;并设置间距20cm,厚度16mm的加劲板用以加固内外侧加贴连接板;钢桁梁吊装时,在横桥向两个吊装节点上安装一根φ426*8mm钢管作横撑,将左右两吊点相连,以平衡在吊装时吊点处的横桥向水平力; 2) Design and construction of the spreader: For the hoisting of the steel truss girder, a 30mm thick Q370qE connecting steel plate is attached to the inner and outer sides of the node by using the bolt hole group at the upper chord node, and the connecting steel plate is higher than the upper chord of the steel truss girder The top surface of the rod is 50cm, and a 720*800*30mm Q370qE cover plate is welded on it to connect the connecting steel plates on the inner and outer sides of the node; and a stiffening plate with a spacing of 20cm and a thickness of 16mm is used to reinforce the inner and outer sides. Connecting plate; when hoisting the steel truss girder, a φ426*8mm steel pipe is installed on the two hoisting nodes of the cross bridge as a cross brace, and the left and right hoisting points are connected to balance the horizontal force of the cross bridge at the hoisting point during hoisting ; 3)整体吊装施工过程:将钢桁梁在拼装场地拼装成为成桥状态,在吊点处的节点安装吊具,采用500t和300t浮吊整体吊装,移至桥位处架设就位;主要施工步骤如下: 3) Overall hoisting construction process: Assemble the steel truss girders at the assembly site into a bridge state, install spreaders at the nodes at the lifting points, use 500t and 300t floating cranes for overall hoisting, move to the bridge site and erect it in place; the main construction Proceed as follows: ①完成桥梁基础、主墩及盖梁施工; ①Complete the construction of bridge foundation, main pier and cap beam; ②规划钢桁梁拼装场地,进行钢桁梁拼装作业; ② Plan steel truss girder assembly site and carry out steel truss girder assembly operation; ③利用汽车吊在拼装场地将钢桁梁拼装成为成桥状态; ③Use truck cranes to assemble the steel truss girders into a bridge state at the assembly site; ④进行吊具安装; ④ Install the spreader; ⑤利用浮吊整体吊装钢桁梁,移至桥位处完成钢桁梁架设; ⑤The steel truss girder is hoisted as a whole by the floating crane, and moved to the bridge position to complete the erection of the steel truss girder; ⑥钢桁梁就位后,从桥梁两端向中间安装混凝土预制桥面板,并浇筑各桥面板的纵缝; ⑥ After the steel trusses are in place, install the prefabricated concrete bridge deck from both ends of the bridge to the middle, and pour the longitudinal joints of each bridge deck; ⑦待纵缝达到100%强度后,再分批按次序浇注横缝,每批龄期相差4天; ⑦ After the longitudinal joints reach 100% strength, pour the transverse joints in batches in order, with a difference of 4 days in age between each batch; ⑧进行桥面系施工。 ⑧ Carry out bridge deck system construction. 2.根据权利要求书1所述的大跨径钢桁梁整体吊装施工方法,其特征是所述的吊具设计与施工,吊具节点处连接盖板顶部焊接耳板,耳板采用500*420*30mm的Q235钢板,在销轴位置处开孔,并在开孔处内外侧各加贴一块16mm厚,外径200,内径100mm的环形加强钢板,吊装时,将销轴插入耳板上的销轴孔,并将钢丝绳挂在销轴上,销轴采用直径10cm,材质为40Cr。 2. The overall hoisting construction method of large-span steel truss girders according to claim 1, characterized in that the design and construction of the spreader, the joints of the spreader are connected to the top of the cover to weld the lugs, and the lugs are 500* 420*30mm Q235 steel plate, open a hole at the position of the pin shaft, and affix a 16mm thick, 200 outer diameter, and 100mm inner diameter ring-shaped reinforced steel plate on the inside and outside of the opening. When hoisting, insert the pin shaft into the ear plate pin hole, and hang the steel wire rope on the pin shaft, the pin shaft adopts a diameter of 10cm, and the material is 40Cr.
CN201310261879.0A 2013-06-27 2013-06-27 Integral hoisting construction method for long-span steel truss girder Active CN103321154B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310261879.0A CN103321154B (en) 2013-06-27 2013-06-27 Integral hoisting construction method for long-span steel truss girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310261879.0A CN103321154B (en) 2013-06-27 2013-06-27 Integral hoisting construction method for long-span steel truss girder

Publications (2)

Publication Number Publication Date
CN103321154A true CN103321154A (en) 2013-09-25
CN103321154B CN103321154B (en) 2015-11-18

Family

ID=49190178

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310261879.0A Active CN103321154B (en) 2013-06-27 2013-06-27 Integral hoisting construction method for long-span steel truss girder

Country Status (1)

Country Link
CN (1) CN103321154B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452599A (en) * 2014-12-04 2015-03-25 中铁大桥局集团有限公司 Method for constructing large-span continuous steel trussed girder bridge under low height limit condition
CN106638320A (en) * 2016-12-12 2017-05-10 中铁山桥集团有限公司 Steel truss section assembling method by using ship positions
CN109081235A (en) * 2018-09-30 2018-12-25 中交二公局第二工程有限公司 A hoisting method of steel truss girder unit applied in single hoisting point hoisting mode
CN111254796A (en) * 2020-01-20 2020-06-09 中铁三局集团建筑安装工程有限公司 Single-side integral hoisting long-span overbridge for multiple railway business lines and construction method
CN115559554A (en) * 2022-12-01 2023-01-03 北京市第三建筑工程有限公司 Construction method for installing newly-added beam colliding with existing beam when supporting structure is excessive

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3885584B2 (en) * 2001-12-28 2007-02-21 鹿島建設株式会社 Construction method of composite truss bridge
CN201351084Y (en) * 2009-01-23 2009-11-25 柳州欧维姆机械股份有限公司 Dual-machine load walking type hydraulic numerical control cross cable crane
CN102352604A (en) * 2011-08-05 2012-02-15 中铁大桥局股份有限公司 Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof
CN102979033A (en) * 2012-11-16 2013-03-20 中铁大桥勘测设计院集团有限公司 Steel truss girder all-welded joist slice and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3885584B2 (en) * 2001-12-28 2007-02-21 鹿島建設株式会社 Construction method of composite truss bridge
CN201351084Y (en) * 2009-01-23 2009-11-25 柳州欧维姆机械股份有限公司 Dual-machine load walking type hydraulic numerical control cross cable crane
CN102352604A (en) * 2011-08-05 2012-02-15 中铁大桥局股份有限公司 Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof
CN102979033A (en) * 2012-11-16 2013-03-20 中铁大桥勘测设计院集团有限公司 Steel truss girder all-welded joist slice and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘雄: ""大跨度钢桁梁整体吊装施工关键技术"", 《城市建设理论研究(电子版)》, 28 February 2013 (2013-02-28), pages 1 - 5 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452599A (en) * 2014-12-04 2015-03-25 中铁大桥局集团有限公司 Method for constructing large-span continuous steel trussed girder bridge under low height limit condition
CN106638320A (en) * 2016-12-12 2017-05-10 中铁山桥集团有限公司 Steel truss section assembling method by using ship positions
CN106638320B (en) * 2016-12-12 2018-07-06 中铁山桥集团有限公司 A kind of steel truss girder segment accommodation assembling method
CN109081235A (en) * 2018-09-30 2018-12-25 中交二公局第二工程有限公司 A hoisting method of steel truss girder unit applied in single hoisting point hoisting mode
CN111254796A (en) * 2020-01-20 2020-06-09 中铁三局集团建筑安装工程有限公司 Single-side integral hoisting long-span overbridge for multiple railway business lines and construction method
CN111254796B (en) * 2020-01-20 2021-11-09 中铁三局集团建筑安装工程有限公司 Single-side integral hoisting long-span overbridge for multiple railway business lines and construction method
CN115559554A (en) * 2022-12-01 2023-01-03 北京市第三建筑工程有限公司 Construction method for installing newly-added beam colliding with existing beam when supporting structure is excessive

Also Published As

Publication number Publication date
CN103321154B (en) 2015-11-18

Similar Documents

Publication Publication Date Title
CN208072213U (en) A kind of steel box-girder installation temporary support
CN104499413B (en) Modularity punching block concrete combination arch bridge and suspension cable hanging construction method thereof
CN103321154B (en) Integral hoisting construction method for long-span steel truss girder
CN103410101B (en) Tower crane conversion method for construction of parabola-shaped ultrahigh pier
CN111364350A (en) A light-weight steel-concrete composite cover beam with quick installation of large cantilever arm
CN111663449A (en) Combined cast-in-place box girder support system and construction method
CN202466845U (en) Middle-layer node connecting structure for steel tube concrete column and steel reinforced concrete beam
CN103866693B (en) A kind of mounting method of steel concrete bowstring arch bridge arch rib
CN209128866U (en) Bridge structure of river course is striden to low-angle one side
CN106149572A (en) A kind of beam bridge ruggedized construction and reinforcement means
CN110863417A (en) A fast-installed steel-concrete composite girder bridge and its construction method
CN113914223A (en) High-pier arc-shaped upper cross beam light-weight bracket system and mounting method thereof
CN209652741U (en) A long-span viaduct across railway stations
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN102979033A (en) Steel truss girder all-welded joist slice and construction method thereof
CN109653517B (en) Multidirectional unloading system and construction method for assembling steel corridor by using same
CN110820519A (en) Tunnel arch bridge convenient for rapid construction and construction method thereof
CN215715459U (en) Offshore wind power assembled steel structure fan cushion cap
CN108589512B (en) A steel-concrete combined beam structure suitable for heavy-duty railways
CN110373990A (en) The double-deck whole hole of Combined steel truss beam manufactures and erection construction method
CN207228330U (en) A kind of prefabricated assembled frame combined using steel core concrete column and girder steel
CN111809654A (en) An assembled pressure-weight tower crane base structure
CN101368369B (en) Penetration type inhaul cable anchorage structure
CN204643604U (en) Door-shaped hanging bracket waterborne
CN111851307A (en) Construction method of large-span prefabricated corrugated web composite box girder transport frame

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant