CN103321148A - Bridge guardrail base split bolt hole plugging structure and process - Google Patents

Bridge guardrail base split bolt hole plugging structure and process Download PDF

Info

Publication number
CN103321148A
CN103321148A CN2013103071767A CN201310307176A CN103321148A CN 103321148 A CN103321148 A CN 103321148A CN 2013103071767 A CN2013103071767 A CN 2013103071767A CN 201310307176 A CN201310307176 A CN 201310307176A CN 103321148 A CN103321148 A CN 103321148A
Authority
CN
China
Prior art keywords
hole
rod
split bolt
bridge guardrail
millimeters
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013103071767A
Other languages
Chinese (zh)
Other versions
CN103321148B (en
Inventor
郭宗杰
李君强
魏树国
韩作新
纪续
冯子强
刘志民
彭洪涛
冉维彬
曹磊
牛伟
袁凯
林占胜
李竹志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JI'NAN CITY HIGHWAY BUREAU
JINAN JINYU HIGHWAY INDUSTRY DEVELOPMENT Co Ltd
Jinan Kingyue Highway Engineering Co Ltd
Original Assignee
JI'NAN CITY HIGHWAY BUREAU
JINAN JINYU HIGHWAY INDUSTRY DEVELOPMENT Co Ltd
Jinan Kingyue Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JI'NAN CITY HIGHWAY BUREAU, JINAN JINYU HIGHWAY INDUSTRY DEVELOPMENT Co Ltd, Jinan Kingyue Highway Engineering Co Ltd filed Critical JI'NAN CITY HIGHWAY BUREAU
Priority to CN201310307176.7A priority Critical patent/CN103321148B/en
Publication of CN103321148A publication Critical patent/CN103321148A/en
Application granted granted Critical
Publication of CN103321148B publication Critical patent/CN103321148B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a bridge guardrail base split bolt hole plugging structure which is used for solving the problems of water seepage and water leakage of split bolt hole plugging. The bridge guardrail base split bolt hole plugging structure comprises a guardrail base, wherein a hole is formed in the guardrail base, and is remained by a split bolt in the pouring process. The bridge guardrail base split bolt hole plugging structure is characterized in that a nylon plastic rod which is in excessively tight fit with the hole is embedded in the hole, an adhering agent is coated between the nylon plastic rod and the hole to form a watertight full-sealing structure. The invention also discloses a construction process of the bridge guardrail base split bolt hole plugging structure. The plugged hole does not seep and leak, and thus the problems of water seepage and water leakage of the bridge guardrail base to the split bolt hole are well solved.

Description

Bridge guardrail pedestal split bolt holes blocking structure and plugging technology
Technical field
This scheme is mainly used in the cast-in-place guardrail of bridge water cement concrete field, specifically a kind of structure and plugging technology that carries out shutoff for the split bolt hole in the Bridge guardrail pedestal.
Background technology
All be provided with the cast-in-place anticollision barrier of cement concrete in the bridge both sides, such as Fig. 1, in building forming process, need to use template to finalize the design, template in the general civil engineering need to use split bolt 11 that the template 12 of both sides is tightened up, play the effect of fixed form, then inside casting cement concrete.Behind the coagulation forming, again split bolt is extracted out, will be formed a hole in the position of interspersed split bolt, can be with reference to the Template Location scheme among the CN201962608U.At present, for the processing mode of split bolt hole be, use mortar with the simple shutoff of hole, this shutoff mode is suitable at general building, but has potential safety hazard for bridge and guardrail, is mainly reflected in:
In the winter time, the infiltration on road surface can progressively be accumulated in the hole, then progressively effluxes, and freeze to form the ice scraper-trough conveyer in the process that effluxes, and has caused security threat to pedestrian and the vehicle of dealing under the bridge.
Simultaneously, because the water that oozes out in the hole can form washmarking on the surface of bridge, affect the attractive in appearance of city, need to carry out thoroughly shutoff, had no at present effective shutoff scheme.
Summary of the invention
In order to solve the deficiencies in the prior art, the invention provides a kind of Bridge guardrail pedestal split bolt holes blocking structure and plugging technology, one of its purpose is carried out complete shutoff to the split bolt hole, and another purpose is to satisfy long-term non-maintaining military service.
The technical solution adopted for the present invention to solve the technical problems is: Bridge guardrail pedestal split bolt holes blocking structure, comprise Guard fence base, in described Guard fence base, be reserved with hole, this hole split bolt in casting process stays, it is characterized in that, in described hole, embed one and cross friction tight nylon plastic(s) rod, and between described nylon plastic(s) rod and hole, scribble cementing agent, form a watertight complete hermetically-sealed construction.
Described cementing agent is the neutral silicone weather-resistant glue.
Described nylon plastic(s) rod comprises straight rod section and cone rod section, and cone rod section wherein can conveniently be inserted hole, and straight rod section is crossed tight fit with hole formation.
Described nylon rod length is 150 millimeters, and is boring the rod section near making 15 millimeters to 18 millimeters gradual changes of diameter in 50 millimeters scopes of inner face.
Bridge guardrail pedestal split bolt holes blocking technique, according to the following steps operation in tandem:
Step 1 is made nylon rod, and described nylon rod has following architectural feature: described nylon rod comprises the straight rod section of outer end and inner cone rod section, and the described straight rod section of outer end matches with the size of hole;
Step 2 is cleaned out hole with hairbrush, air gun;
Step 3, injection neutral silicone weather-resistant glue in the hole after the cleaning, and smear the neutral silicone weather-resistant glue at the corresponding surface of nylon rod;
Step 4 uses hammer rapidly nylon rod to be wedged in the hole, until the nylon rod outer face is concordant with the pedestal external surface.
After step 4, also comprise a step of the hole mouth of wedging nylon rod being smeared the neutral silicone weather-resistant glue.
Detailed, described nylon rod length is 150 millimeters, and is boring the rod section near making 15 millimeters to 18 millimeters gradual changes of diameter in 50 millimeters scopes of inner face.
The invention has the beneficial effects as follows: the nylon plastic(s) rod has that good toughness, tear resistance are strong, oil resistant, antidetonation, stretching, bending strength are good, and have characteristics such as water imbibition is little, good stability of the dimension, the needs of the outdoor adverse circumstances of viaduct can be satisfied fully, hundred-percent shutoff can be realized.Hole after the shutoff no longer seeps water, leaks, and has well solved Bridge guardrail pedestal split bolt hole seepy question.
Description of drawings
Fig. 1 is Guard fence base cast in situs moulding figure;
Fig. 2 is the Guard fence base structural representation;
Fig. 3 is the stereogram of nylon plastic(s) rod.
Among the figure: 11 split bolts, 12 templates, 2 nylon plastic(s)s rod, 21 straight rod sections, 22 cone rod sections, 3 holes, 4 Guard fence bases.
The specific embodiment
As shown in Figure 2 to Figure 3,
The Bridge guardrail pedestal split bolt hole plugging technology that leaks was carried out the fishing expedition work in early stage before beginning to construct, mainly comprise and be familiar with design document, and carry out highway condition investigation at the scene comprehensively.Clear and definite Guard fence base split bolt hole location, quantity are also carried out detailed observed and recorded.
Then track of sealing utilizes crane gear the constructor to be delivered to guardrail outside pedestal split bolt hole location, then according to the following steps operation in tandem as construction area below bridge floor:
Step 1, make nylon plastic(s) rod 2, described nylon rod has following architectural feature: nylon rod comprises the straight rod section 21 of outer end and inner cone rod section 22, the straight rod section of outer end matches with the size of hole 3, nylon rod length is 150 millimeters, and is boring the rod section near making 15 millimeters to 18 millimeters gradual changes of diameter in 50 millimeters scopes of inner face.
Step 2 is cleaned out hole 3 with hairbrush, air gun, thoroughly removes the foreign material in the hole clean.
Step 3, the hole 3 interior injection neutral silicone weather-resistant glue after the cleaning, and smear the neutral silicone weather-resistant glue at the corresponding surface of nylon rod;
Step 4 uses the hammer instrument rapidly nylon rod to be wedged in the hole, until the nylon rod outer face is concordant with the pedestal external surface, the neutral silicone weather-resistant glue can form effective shutoff after solidifying.
Step 5 is smeared the neutral silicone weather-resistant glue to the hole mouth of wedging nylon rod 2.
Require Guard fence base maintenance to carry out quality inspection and evaluation according to job specfication after construction is finished, and in time the test evaluation situation is fed back to quality examination section, the problem of appearance is in time solved.
Final a kind of urban viaduct Guard fence base hole plugging structure that leaks that forms, comprise Guard fence base 4, in Guard fence base, be reserved with hole 3, in hole, embed one and cross friction tight nylon rod 2, nylon rod length is 150 millimeters, and is boring rod section 22 near making 15 millimeters to 18 millimeters gradual changes of diameter in 50 millimeters scopes of inner face.Scribble the neutral silicone weather-resistant glue between nylon rod and the hole.Form a kind of totally enclosed structure.
Nylon rod itself has mechanical strength, rigidity, hardness, toughness is high, ageing-resistant performance good, mechanical damping capacity is good, good sliding, excellent abrasion resistance, machining property is good, abrasion resistance is good, the feature of good stability of the dimension.In machine, filling operation, all have good characteristic, and can satisfy sealing performance and later stage weatherability requirement.
Embodiment recited above is described preferred embodiment of the present invention; be not that scope of the present invention is limited; design under the prerequisite of spirit not breaking away from the present invention; the relevant technical staff in the field all should expand as in the determined protection domain of claims of the present invention various distortion of the present invention and improvement.

Claims (7)

1. Bridge guardrail pedestal split bolt holes blocking structure, comprise Guard fence base, in described Guard fence base, be reserved with hole, it is characterized in that, in described hole, embed one and cross friction tight nylon plastic(s) rod, and between described nylon plastic(s) rod and hole, scribble cementing agent.
2. Bridge guardrail pedestal split bolt holes blocking structure according to claim 1 is characterized in that, described cementing agent is the neutral silicone weather-resistant glue.
3. Bridge guardrail pedestal split bolt holes blocking structure according to claim 1 and 2 is characterized in that, described nylon rod comprises straight rod section and cone rod section.
4. Bridge guardrail pedestal split bolt holes blocking structure according to claim 3 is characterized in that, described nylon rod length is 150 millimeters, and is boring the rod section near making 15 millimeters to 18 millimeters gradual changes of diameter in 50 millimeters scopes of inner face.
5. Bridge guardrail pedestal split bolt holes blocking technique, according to the following steps operation in tandem:
Step 1 is made nylon rod, and described nylon rod has following architectural feature: described nylon rod comprises the straight rod section of outer end and inner cone rod section, and the described straight rod section of outer end matches with the size of hole,
Step 2 will be cleaned out in the hole with hairbrush, air gun,
Step 3, injection neutral silicone weather-resistant glue in the hole after the cleaning, and smear the neutral silicone weather-resistant glue at the corresponding surface of nylon rod;
Step 4 uses the hammer instrument rapidly nylon rod to be wedged in the hole, until the nylon rod outer face is concordant with the pedestal external surface.
6. Bridge guardrail pedestal split bolt holes blocking technique according to claim 5 is characterized in that, also comprises a step of the hole mouth of wedging nylon rod being smeared the neutral silicone weather-resistant glue after step 4.
7. Bridge guardrail pedestal split bolt holes blocking technique according to claim 5 is characterized in that, described nylon rod length is 150 millimeters, and is boring the rod section near making 15 millimeters to 18 millimeters gradual changes of diameter in 50 millimeters scopes of inner face.
CN201310307176.7A 2013-07-19 2013-07-19 Bridge guardrail base split bolt holes blocking structure and plugging technology Active CN103321148B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310307176.7A CN103321148B (en) 2013-07-19 2013-07-19 Bridge guardrail base split bolt holes blocking structure and plugging technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310307176.7A CN103321148B (en) 2013-07-19 2013-07-19 Bridge guardrail base split bolt holes blocking structure and plugging technology

Publications (2)

Publication Number Publication Date
CN103321148A true CN103321148A (en) 2013-09-25
CN103321148B CN103321148B (en) 2015-08-19

Family

ID=49190172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310307176.7A Active CN103321148B (en) 2013-07-19 2013-07-19 Bridge guardrail base split bolt holes blocking structure and plugging technology

Country Status (1)

Country Link
CN (1) CN103321148B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867306A (en) * 2017-05-10 2018-11-23 镇江长城重工科技有限公司 A kind of S-shaped steel structure bridge
CN109013166A (en) * 2018-09-05 2018-12-18 中国航发动力股份有限公司 A kind of fabrication hole sealant coated tool and sealant coating method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004176400A (en) * 2002-11-27 2004-06-24 Sho Bond Constr Co Ltd Width expansion member for road and its installation method
CN1769611A (en) * 2004-11-02 2006-05-10 邱则有 Cast in situ reinforcing steel bar concrete hollow board
CN101016756A (en) * 2006-02-06 2007-08-15 朱新伟 Cast-in-situ concrete structure non-hole construction method
CN201074404Y (en) * 2007-07-16 2008-06-18 莱西市建筑总公司 Plugging tool
JP2008266910A (en) * 2007-04-17 2008-11-06 Kajima Corp Projection structure of anchorage or deviator of tendon, and construction method therefor
CN203361017U (en) * 2013-07-19 2013-12-25 济南金曰公路工程有限公司 Bridge guardrail base split bolt hole plugging structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004176400A (en) * 2002-11-27 2004-06-24 Sho Bond Constr Co Ltd Width expansion member for road and its installation method
CN1769611A (en) * 2004-11-02 2006-05-10 邱则有 Cast in situ reinforcing steel bar concrete hollow board
CN101016756A (en) * 2006-02-06 2007-08-15 朱新伟 Cast-in-situ concrete structure non-hole construction method
JP2008266910A (en) * 2007-04-17 2008-11-06 Kajima Corp Projection structure of anchorage or deviator of tendon, and construction method therefor
CN201074404Y (en) * 2007-07-16 2008-06-18 莱西市建筑总公司 Plugging tool
CN203361017U (en) * 2013-07-19 2013-12-25 济南金曰公路工程有限公司 Bridge guardrail base split bolt hole plugging structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867306A (en) * 2017-05-10 2018-11-23 镇江长城重工科技有限公司 A kind of S-shaped steel structure bridge
CN109013166A (en) * 2018-09-05 2018-12-18 中国航发动力股份有限公司 A kind of fabrication hole sealant coated tool and sealant coating method

Also Published As

Publication number Publication date
CN103321148B (en) 2015-08-19

Similar Documents

Publication Publication Date Title
CN103422868B (en) The structure of a kind of Super-void Water Pressure that dissipates, reinforcing shield tunnel soil body and method
CN104594199B (en) A kind of Reinforced Concrete Bridge longitudinally connected construction method of framing longitudinal joint
CN202187415U (en) Sidewalk drainage structure
CN103321148A (en) Bridge guardrail base split bolt hole plugging structure and process
CN104846849A (en) Method for preventing basement bottom plate post-cast strip from leaking
CN203361017U (en) Bridge guardrail base split bolt hole plugging structure
CN105463986A (en) Construction method of bridge expansion joint
CN106592378A (en) T-shaped collector pipe
CN207143920U (en) Water-stopping system between novel pile under a kind of complicated circumstance of flowing water
CN110593894B (en) Novel shield tunnel concrete pipe piece miniature reinforcing pile
CN109138116A (en) Concrete expires packet drainage pipeline tubine construction method
CN107587434A (en) Culvert of reinforced concrete percolating water prevention and disposition method
CN202500153U (en) Integral ribbed plastic inspection well
DE102013109594A1 (en) Tubing with a cast protective layer and method for producing such a tubbing
DD254750A5 (en) METHOD FOR RECONSTRUCTING IMMEDIATE RIVER CHANNELS, IN PARTICULAR PROFILED CANNULARS
CN104963294B (en) A kind of railway Thin-wall Hollow Pier circulation drip irrigation curing system
CN107165198A (en) Underground project waterproof systematical working construction method and waterproof material used
CN204370319U (en) Road and bridge crack bracing means
CN107542170A (en) A kind of cast in situ ferroconcrete wall or beam construction joint surface construction method
CN204530357U (en) Cliff side slope plank road
CN204326072U (en) A kind of anti-float anchor rod node
CN208423702U (en) The cable penetration cannula structure of slip casting sealing
CN208455457U (en) A kind of assembled bridge pier that drainpipe is embedded
CN207003605U (en) Reinforced buried concrete pumping equipment
CN105804008A (en) Anti-scour, heat-insulation and anti-seepage structure for box culvert and inverted siphon

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant