CN103306681A - Tunneling sector rotation construction method - Google Patents

Tunneling sector rotation construction method Download PDF

Info

Publication number
CN103306681A
CN103306681A CN2013102468312A CN201310246831A CN103306681A CN 103306681 A CN103306681 A CN 103306681A CN 2013102468312 A CN2013102468312 A CN 2013102468312A CN 201310246831 A CN201310246831 A CN 201310246831A CN 103306681 A CN103306681 A CN 103306681A
Authority
CN
China
Prior art keywords
fan
meter
construction method
excavation
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102468312A
Other languages
Chinese (zh)
Other versions
CN103306681B (en
Inventor
戴兴民
董贤顺
郭建国
陈建
汪春生
马栋
郭秀琴
陈广亮
杨立伟
董君
周莉
郭希芹
戴兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd, Metro Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN201310246831.2A priority Critical patent/CN103306681B/en
Publication of CN103306681A publication Critical patent/CN103306681A/en
Application granted granted Critical
Publication of CN103306681B publication Critical patent/CN103306681B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a tunneling sector rotation construction method which comprises the following steps of 1) excavation and support: sector support design is conducted firstly, the inner side semidiameter of a sector support is more than 1.5 meters, and the clearance size during the excavation is controlled within a design scope; and 2) secondary lining: lining formworks are laid out according to a sector, and a side wall is provided with a curve steel molding plate. The method has the benefits that the problems that the other end of a stagger line tunnel cannot be excavated as a working plane, and a cross section of the main tunnel is widened and lengthened for opening turn to result in waste, discontinuous procedures, and a long construction period are solved; the method is simple in process flow, labor-saving, material-saving, short in construction period, and high in efficiency; a product of the method is linear and attractive, corresponds with a fluid motion rule; and the method has very significant economic and social benefits.

Description

The fan-shaped rotation swivel construction method of a kind of tunnel piercing
Technical field
The present invention relates to a kind of technical field of building construction, relate in particular to the fan-shaped rotation swivel construction method of a kind of tunnel piercing.
Background technology
In the work progress of the underground passages such as subway walkway, air channel, the urgency that usually can run into tunnel turnover 90 degree is turned round; No. eight line art museums of Beijing Metro station just runs into many places; Wherein between the plug-in device of northwest for satisfying the requirement that is open to traffic, set up place's Temporary Ventilation vertical shaft, the wide 4.4m of its main air duct, high 4.2m, with the wide 3.6m in inferior air channel of ventilating shaft opening part, high 2.5m.
If adopt traditional tunnel turnover job practices, working procedure is seen Fig. 5, and its concrete steps are: 1) excavate main tunnel; 2) lining cutting master tunnel (reserving time tunnel opening place); 3) excavation time tunnel; 4) lining cutting time tunnel; In order to satisfy time tunnel opening technique, need to strengthen, lengthen main tunnel cross-section, opening part need to arrange reinforcing ring.
The defective of conventional construction method is: traditional excavation method can only be excavated first main tunnel, rear excavation time tunnel; Can not solve because of the duration tight, main tunnel one side can't provide the scope of operation, opposite time tunnel one side shaft hoisting device resource is idle, but can't implement the contradiction of tunnel excavation.In addition: its main tunnel cross-section of traditional excavation method has carried out the unwanted increasing lengthening of use function, operation is discontinuous, long in time limit, can not satisfy construction period.
Summary of the invention
The purpose of this invention is to provide a kind of set of tunneling construction method, to overcome present prior art above shortcomings.
The objective of the invention is to be achieved through the following technical solutions:
The fan-shaped rotation swivel construction method of a kind of tunnel piercing may further comprise the steps:
1) excavation supporting: at first carry out fan-shaped design of its support, fan-shaped supporting inner radius should be more than 1.5 meters, digging process control headroom size in scope of design, inboard Grill space should about 0.4 meter or below; Outside Grill space is 0.6 meter ~ 0.8 meter; Add 1 ~ 2 half Pin grid between the whole Pin grid in the outside; Add the position of half Pin grid, vertically the dowel spacing is about 0.5 meter, vertically dowel arrange up and down put and with the grid firm welding; When the tunnel excavation headroom surpasses 5.5m, can select to arrange median septum according to field condition.Each Pin grid is numbered, according to the installation site of each Pin grid of numbering control, according to the installation site control excavation headroom size of grid; And
2) secondary lining: the lining cutting mould bases is by fan-shaped layout, and abutment wall arranges the curve steel template, and the inboard spacing of lining cutting mould bases is about 0.4 meter, and outside spacing is 0.6 meter ~ 0.8 meter, and the arch template of lining cutting mould bases adopts plank, and the plank upper surface is laid veneer.
Beneficial effect of the present invention is: having solved inflection threaded list road can not be that scope of operation excavation, main tunnel cause waste, an operation difficult problem discontinuous, long in time limit for the opening turnover makes its section strengthen lengthening from the other end; Its technological process is simple, saving of labor, material-saving, the duration is short, efficient is high; Its product is linear attractive in appearance, meets the fluid motion rule, and economical, societal benefits are very remarkable.
Description of drawings
The below is described in further detail the present invention with reference to the accompanying drawings.
Fig. 1 is the operation schematic diagram of the fan-shaped rotation swivel construction method of the described tunnel piercing of the embodiment of the invention;
Fig. 2 is the sectional view of A-A line among Fig. 1;
Fig. 3 is the grid arrangement diagram of the fan-shaped rotation swivel construction method of the described tunnel piercing of the embodiment of the invention;
Fig. 4 is the sectional view of B-B line among Fig. 3;
Fig. 5 is the construction operation schematic diagram in prior art 90 degree turnover tunnels.
Among the figure:
1, excavation supporting line; 2, secondary lining line; 3, stopping; 4, equipment room; 5, ventilating shaft; 6, construction direction; 7, whole Pin grid; 8, half Pin grid; 9, dowel; Four steps of the first step to the of working procedure in I ~ IV, the prior art.
The specific embodiment
Such as Fig. 1 ~ shown in Figure 4, the fan-shaped rotation swivel construction method of the described a kind of tunnel piercing of the embodiment of the invention, its concrete steps are as follows:
1, excavation supporting
Before excavation the preliminary bracing grid arranged and design, its main points are: the inner side of curve radius is suitable 〉=and 1.5m; Inboard Grill space ≈ 0.4m or as far as possible reduce; The outside Grill space 0.6 ~ 0.8m(or according to the actual conditions adjustment); Between the whole Pin grid 7 in the outside, add 1 ~ 2 half Pin grid 8; It adds the position of half Pin grid 8, and vertically dowel 9 spacing ≈ 0.5m are strengthened, and vertically dowel 9 is arranged up and down and put, and with the grid firm welding; When the tunnel excavation headroom surpasses 5.5m, consider to arrange median septum; Strict control headroom size in excavation, its main points are: each Pin grid is numbered, adopts coordinate method to control the installation site of each Pin grid.
2, secondary lining
The lining cutting mould bases is by fan-shaped layout, inboard spacing ≈ 0.4m, outside spacing 0.6 ~ 0.8m; Abutment wall arranges curve steel template, vertical array; The arch template adopts plank, and the plank upper surface is laid veneer, on-the-spot according to real size blanking install.Other method of operating is all by ripe construction technology.
The fan-shaped method job practices of turning of tunnel piercing provided by the invention has solved inflection threaded list road and can not cause waste, an operation difficult problem discontinuous, long in time limit for open section strengthens lengthening from other end scope of operation excavation, main tunnel.
The present invention is not limited to above-mentioned preferred forms; anyone can draw other various forms of products under enlightenment of the present invention; no matter but do any variation in its shape or structure; every have identical with a application or akin technical scheme, all drops within protection scope of the present invention.

Claims (5)

1. the fan-shaped rotation swivel construction method of tunnel piercing is characterized in that, may further comprise the steps:
1) excavation supporting: at first carry out fan-shaped design of its support, fan-shaped supporting inner radius should be more than 1.5 meters, and digging process control headroom size is in scope of design, and inboard Grill space should be no more than 0.4 meter; Outside Grill space is 0.6 meter ~ 0.8 meter; Add 1 ~ 2 half Pin grid between the whole Pin grid in the outside; And
2) secondary lining: the lining cutting mould bases is by fan-shaped layout, and abutment wall arranges the curve steel template, and the inboard spacing of lining cutting mould bases is 0.4 meter, and outside spacing is 0.6 meter ~ 0.8 meter.
2. the fan-shaped rotation swivel construction method of tunnel piercing according to claim 1, it is characterized in that: in the step 1), the vertical dowel spacing in position of adding half Pin grid is about 0.5 meter, vertically dowel arrange up and down put and with the grid firm welding.
3. the fan-shaped rotation swivel construction method of tunnel piercing according to claim 2 is characterized in that: in the step 1), when the tunnel excavation headroom surpasses 5.5m, can select to arrange median septum according to field condition.
4. the fan-shaped rotation swivel construction method of tunnel piercing according to claim 3 is characterized in that: in the step 1), each Pin grid is numbered, according to the installation site of each Pin grid of numbering control, according to the installation site control excavation headroom size of grid.
5. the fan-shaped rotation swivel construction method of tunnel piercing according to claim 4 is characterized in that: step 2) in, the arch template of lining cutting mould bases adopts plank, and the plank upper surface is laid veneer.
CN201310246831.2A 2013-06-20 2013-06-20 A kind of tunnel piercing sector rotation construction method Expired - Fee Related CN103306681B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310246831.2A CN103306681B (en) 2013-06-20 2013-06-20 A kind of tunnel piercing sector rotation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310246831.2A CN103306681B (en) 2013-06-20 2013-06-20 A kind of tunnel piercing sector rotation construction method

Publications (2)

Publication Number Publication Date
CN103306681A true CN103306681A (en) 2013-09-18
CN103306681B CN103306681B (en) 2015-09-09

Family

ID=49132356

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310246831.2A Expired - Fee Related CN103306681B (en) 2013-06-20 2013-06-20 A kind of tunnel piercing sector rotation construction method

Country Status (1)

Country Link
CN (1) CN103306681B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611115A (en) * 2018-12-14 2019-04-12 中铁北京工程局集团城市轨道交通工程有限公司 A kind of preliminary bracing engineering method for minor-circle turn
CN110374635A (en) * 2019-07-31 2019-10-25 中国三峡建设管理有限公司 A kind of big cross section different gradient dog-ear position concrete construction method
CN110566239A (en) * 2019-10-11 2019-12-13 中建八局轨道交通建设有限公司 mounting and positioning method for grid support at turning position of underground excavation tunnel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3001376A1 (en) * 1980-01-16 1981-07-23 Bochumer Eisenhütte Heintzmann GmbH & Co, 4630 Bochum Bend section for mine gallery support structure - has arched radiating from inner corner, with channels connected by intermediate adaptors
CN1242454A (en) * 1998-07-21 2000-01-26 陈建源 Road crossing design or layout for vehicles passing through and vehicles passing mode therefor
CN1952350A (en) * 2006-10-27 2007-04-25 中铁四局集团有限公司 Rapid construction method for small-section abrupt change tunnel to large-section tunnel
CN101586346A (en) * 2008-11-10 2009-11-25 郑州市市政工程总公司 Method for constructing multi-functional metro interchange station complex
CN102182465A (en) * 2011-04-01 2011-09-14 长安大学 Tunnel-entering construction method for tunnel
CN202851011U (en) * 2012-10-26 2013-04-03 中铁二十二局集团第六工程有限公司 Existing grate and novel grate connecting system in tunnel construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3001376A1 (en) * 1980-01-16 1981-07-23 Bochumer Eisenhütte Heintzmann GmbH & Co, 4630 Bochum Bend section for mine gallery support structure - has arched radiating from inner corner, with channels connected by intermediate adaptors
CN1242454A (en) * 1998-07-21 2000-01-26 陈建源 Road crossing design or layout for vehicles passing through and vehicles passing mode therefor
CN1952350A (en) * 2006-10-27 2007-04-25 中铁四局集团有限公司 Rapid construction method for small-section abrupt change tunnel to large-section tunnel
CN101586346A (en) * 2008-11-10 2009-11-25 郑州市市政工程总公司 Method for constructing multi-functional metro interchange station complex
CN102182465A (en) * 2011-04-01 2011-09-14 长安大学 Tunnel-entering construction method for tunnel
CN202851011U (en) * 2012-10-26 2013-04-03 中铁二十二局集团第六工程有限公司 Existing grate and novel grate connecting system in tunnel construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109611115A (en) * 2018-12-14 2019-04-12 中铁北京工程局集团城市轨道交通工程有限公司 A kind of preliminary bracing engineering method for minor-circle turn
CN110374635A (en) * 2019-07-31 2019-10-25 中国三峡建设管理有限公司 A kind of big cross section different gradient dog-ear position concrete construction method
CN110374635B (en) * 2019-07-31 2020-07-07 中国三峡建设管理有限公司 Concrete construction method for large-section different-gradient bevel part
CN110566239A (en) * 2019-10-11 2019-12-13 中建八局轨道交通建设有限公司 mounting and positioning method for grid support at turning position of underground excavation tunnel
CN110566239B (en) * 2019-10-11 2020-10-13 中建八局轨道交通建设有限公司 Mounting and positioning method for grid support at turning position of underground excavation tunnel

Also Published As

Publication number Publication date
CN103306681B (en) 2015-09-09

Similar Documents

Publication Publication Date Title
CN208073481U (en) Mountainous City Underground Subway Station vented construction
CN203307840U (en) Integral horizontal moving type formwork construction device for strip-shaped constant-cross-section concrete structure
CN102943678A (en) Arched subway station old and new building connection structure and construction method
CN108412500A (en) Mountainous City Underground Subway Station vented construction and its construction method
CN103244129B (en) Construction method for three-dimensional intersection concave-convex fulcrums
CN103306681B (en) A kind of tunnel piercing sector rotation construction method
CN102797500A (en) Gob sealing structure
CN203925523U (en) Close to repair to dividing and repair tunnel greatly across the asymmetric temporary lining structure of changeover portion
CN206539355U (en) Second lining of tunnel arch wall adjustable steel end mould
CN202745940U (en) Enclosing construction for gob
CN204327112U (en) Tunnel hole-exiting advance support system
CN109958443B (en) Parallel vertical shafts hidden in pipe gallery tunnel and construction method thereof
CN203835412U (en) Underwater-roadway leakage processing structure
CN203530990U (en) Deep foundation pit shoring retaining wall steel pipe concrete supporting structure
CN102953317B (en) Self-propelled road surface cutting device and construction method thereof
CN203346950U (en) Hidden laying structure for temporary water supply pipes of high-rise building
CN204059401U (en) Novel combined traffic tunnel
CN104405404B (en) A kind of gas in mine stay roadway method
CN204825820U (en) Pressure regulating well structure using traffic hole as upper chamber
CN204457784U (en) Large-diameter shield in a kind of tunneling air channel receives and starting well
CN202001022U (en) Movable lining arch center formwork
CN210195773U (en) Steel mould trolley grouting device for rock wall grouting
CN207348874U (en) A kind of tunnel trolley seaming die anti-crack device
CN105040649A (en) Pressure regulating well structure using traffic hole as upper chamber and construction method
CN102392459A (en) Construction method for straight manhole

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150909

CF01 Termination of patent right due to non-payment of annual fee