CN103290845A - 管桩桩头固定方法 - Google Patents

管桩桩头固定方法 Download PDF

Info

Publication number
CN103290845A
CN103290845A CN2013102729134A CN201310272913A CN103290845A CN 103290845 A CN103290845 A CN 103290845A CN 2013102729134 A CN2013102729134 A CN 2013102729134A CN 201310272913 A CN201310272913 A CN 201310272913A CN 103290845 A CN103290845 A CN 103290845A
Authority
CN
China
Prior art keywords
pile
pipe pile
steel pipe
head fixing
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013102729134A
Other languages
English (en)
Inventor
黄修振
曲建华
姚东森
朱文革
王滨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN CONSTRUCTION CO Ltd OF 22MCC GROUP
Original Assignee
TIANJIN CONSTRUCTION CO Ltd OF 22MCC GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN CONSTRUCTION CO Ltd OF 22MCC GROUP filed Critical TIANJIN CONSTRUCTION CO Ltd OF 22MCC GROUP
Priority to CN2013102729134A priority Critical patent/CN103290845A/zh
Publication of CN103290845A publication Critical patent/CN103290845A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及孤石群地质条件下预应力管桩施工方法,具体是一种管桩桩头固定方法。按下述方法进行:沉桩到设计标高后,保持桩身垂直、稳定,利用两台经纬仪纵横双向校正,待垂直度和水平位置均符合要求后,在桩孔孔口处通过钢管用扣件连接成的井字形固定架将桩头固定,井字形固定架与管桩外壁相吻合,井字形固定架两端采用八字形钢管支撑,钢管支撑上端用扣件连接井字形固定架,下端植入土层内,桩头固定完毕后,再进行一次管桩垂直度和水平位置的复核,确保管桩垂直精度。本发明方法简单,施工方便,增加了管桩的保护作用,既保证了管桩的垂直度,也有效地提高了预应力管桩的承载能力。

Description

管桩桩头固定方法
技术领域
本发明涉及孤石群地质条件下预应力管桩施工方法,具体是一种管桩桩头固定方法。
背景技术
管桩桩孔成孔验收合格后即进行沉桩施工,由于桩孔直径大于管桩直径、桩孔深度大于桩长,因此如何使沉桩后的管桩位置固定是需要解决的问题。目前,尚无有一种很好的方法来保证管桩位置,大多采用在孔壁与管桩之间填充小石块来固定,无法保证管桩位置及垂直精度,对管桩整体施工质量产生很大影响。
发明内容
本发明旨在解决上述管桩位置固定存在的问题,而提供一种能够防止桩头因为水平力的作用而产生位移的管桩桩头固定方法。
本发明解决所述问题采用的技术方案是:
一种管桩桩头固定方法,按下述方法进行:沉桩到设计标高后,保持桩身垂直、稳定,利用两台经纬仪纵横双向校正,待垂直度和水平位置均符合要求后,在桩孔孔口处通过钢管用扣件连接成的井字形固定架将桩头固定,井字形固定架与管桩外壁相吻合,井字形固定架两端采用八字形钢管支撑,钢管支撑上端用扣件连接井字形固定架,下端植入土层内,桩头固定完毕后,再进行一次管桩垂直度和水平位置的复核,确保管桩垂直精度。
采用上述技术方案的本发明,与现有技术相比具有下述优点和积极效果:
方法简单,施工方便,既保证了管桩的垂直度,也有效地提高了预应力管桩的承载能力。其作用有两个方面:一是起到稳定作用,确保了管桩的垂直精度,提高了管桩的水平载荷能力,同时增加桩周摩阻力;二是避免管桩周围地下复杂环境的侵蚀影响,增加了管桩的保护作用,延长了整体质量和寿命。
附图说明
图1是管桩桩头固定平面图。
图2是图1中A-A向视图。
图中:管桩1,钢管2,钢管支撑3,扣件4。
具体实施方式
下面结合附图及实施例对本发明作进一步说明,目的仅在于更好地理解本发明内容。因此,所举之例并不限制本发明的保护范围。
参见图1、图2,这种管桩桩头固定方法是:
桩孔成孔验收合格后,利用汽车吊、静力压桩机进行沉桩。沉桩到设计标高后,保持桩身垂直、稳定,利用两台经纬仪纵横双向校正,待垂直度和水平位置均符合要求后,在桩孔孔口处用钢管2与扣件4连接成的井字形固定架将管桩1的桩头固定,井字形固定架的钢管2与管桩1外壁相吻合。井字形固定架两端采用八字形钢管支撑3,钢管支撑3的上端用扣件4连接井字形固定架,下端植入土层内。固定完毕后,再进行一次复核,确保管桩1的垂直精度,静力压桩机方可摘钩、移位,管桩桩头固定完毕。

Claims (1)

1.一种管桩桩头固定方法,其特征在于,沉桩到设计标高后,保持桩身垂直、稳定,利用两台经纬仪纵横双向校正,待垂直度和水平位置均符合要求后,在桩孔孔口处通过钢管用扣件连接成的井字形固定架将桩头固定,井字形固定架与管桩外壁相吻合,井字形固定架两端采用八字形钢管支撑,钢管支撑上端用扣件连接井字形固定架,下端植入土层内,桩头固定完毕后,再进行一次管桩垂直度和水平位置的复核,确保管桩垂直精度。
CN2013102729134A 2013-07-02 2013-07-02 管桩桩头固定方法 Pending CN103290845A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013102729134A CN103290845A (zh) 2013-07-02 2013-07-02 管桩桩头固定方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013102729134A CN103290845A (zh) 2013-07-02 2013-07-02 管桩桩头固定方法

Publications (1)

Publication Number Publication Date
CN103290845A true CN103290845A (zh) 2013-09-11

Family

ID=49092335

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013102729134A Pending CN103290845A (zh) 2013-07-02 2013-07-02 管桩桩头固定方法

Country Status (1)

Country Link
CN (1) CN103290845A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106400802A (zh) * 2016-08-24 2017-02-15 中交公局厦门工程有限公司 一种钻孔桩桩头预埋免钻孔环切整体快速提吊方法
CN108252318A (zh) * 2018-03-07 2018-07-06 华北水利水电大学 一种管桩基础均衡传力装置及施工方法
CN110670490A (zh) * 2019-10-28 2020-01-10 中国葛洲坝集团第三工程有限公司 一种预应力管道的造孔装置及造孔方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100792130B1 (ko) * 2007-03-16 2008-01-04 이창남 압입강관말뚝 공법(PPP Pile 공법)
JP2010156191A (ja) * 2008-12-03 2010-07-15 Jfe Engineering Corp L形補強構造物、該l形補強構造物を設置した補強構造及び補強方法
CN102077777A (zh) * 2009-11-26 2011-06-01 上海德通能源环保科技有限公司 一种树杆加固架的改良结构
CN102425167A (zh) * 2011-11-25 2012-04-25 天津港航工程有限公司 潮间带施打大直径钢管桩沉桩方法
CN102535469A (zh) * 2012-02-17 2012-07-04 中交武汉港湾工程设计研究院有限公司 工具式导向沉桩装置
CN102587377A (zh) * 2012-02-21 2012-07-18 中交二航局第三工程有限公司 吊锤沉桩装置及沉桩方法
CN202745057U (zh) * 2012-09-14 2013-02-20 中国甘肃国际经济技术合作总公司 用于振动沉入钢桩的整体型钢导向架装置

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100792130B1 (ko) * 2007-03-16 2008-01-04 이창남 압입강관말뚝 공법(PPP Pile 공법)
JP2010156191A (ja) * 2008-12-03 2010-07-15 Jfe Engineering Corp L形補強構造物、該l形補強構造物を設置した補強構造及び補強方法
CN102077777A (zh) * 2009-11-26 2011-06-01 上海德通能源环保科技有限公司 一种树杆加固架的改良结构
CN102425167A (zh) * 2011-11-25 2012-04-25 天津港航工程有限公司 潮间带施打大直径钢管桩沉桩方法
CN102535469A (zh) * 2012-02-17 2012-07-04 中交武汉港湾工程设计研究院有限公司 工具式导向沉桩装置
CN102587377A (zh) * 2012-02-21 2012-07-18 中交二航局第三工程有限公司 吊锤沉桩装置及沉桩方法
CN202745057U (zh) * 2012-09-14 2013-02-20 中国甘肃国际经济技术合作总公司 用于振动沉入钢桩的整体型钢导向架装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王振军等: "深水基础预应力混凝土管桩沉桩技术", 《铁道建筑技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106400802A (zh) * 2016-08-24 2017-02-15 中交公局厦门工程有限公司 一种钻孔桩桩头预埋免钻孔环切整体快速提吊方法
CN108252318A (zh) * 2018-03-07 2018-07-06 华北水利水电大学 一种管桩基础均衡传力装置及施工方法
CN108252318B (zh) * 2018-03-07 2019-10-29 华北水利水电大学 一种管桩基础均衡传力装置及施工方法
CN110670490A (zh) * 2019-10-28 2020-01-10 中国葛洲坝集团第三工程有限公司 一种预应力管道的造孔装置及造孔方法

Similar Documents

Publication Publication Date Title
CN201794079U (zh) 一种基坑支撑系统
CN205296874U (zh) 桩柱一体化信息化施工监测定位装置
CN207244654U (zh) 桩托二层挡土墙结构
CN103290845A (zh) 管桩桩头固定方法
CN205089345U (zh) 一种锚索让压装置
CN205152971U (zh) 一种复合桩基桩顶抗震阻尼调节装置
CN205530394U (zh) 一种桩侧负摩阻力的测试装置
CN201687227U (zh) 一体化通信基站
CN202090352U (zh) 钢管桩-自钻式预应力锚杆深基坑支护系统
CN202041208U (zh) 一种稳固直埋式gps观测标志
CN207597754U (zh) 一种装配式楼梯连接装置
CN207405664U (zh) 一种土木工程中地桩用减震装置
CN211849400U (zh) 建筑工程用抗震型建筑桩
CN202266065U (zh) 一种定日镜立柱
CN203977418U (zh) 防止灌注桩混凝土流失装置
CN104153366A (zh) 一种海中强风浪高强度裸岩钢管桩基的方法
CN212537359U (zh) 一种用于土石坝测压管及测斜管安装埋设的固定装置
CN210564579U (zh) 一种隧道钢拱架阻尼变形支护装置
CN109137931B (zh) 一种适用于狭窄基坑的嵌固长度的计算方法
CN202865849U (zh) 框架逆作法中一柱一桩垂直度的反导向控制装置
CN203256752U (zh) 一种地铁基坑围护结构
CN206418859U (zh) 一种竖向可伸缩的基坑临边围护装置
CN203383523U (zh) 一种承重柱
CN202559366U (zh) 格构边坡生态支护结构
CN110130327A (zh) 组合桩基结构及其安装方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130911