CN103267181A - 平口混凝土管连接方法 - Google Patents

平口混凝土管连接方法 Download PDF

Info

Publication number
CN103267181A
CN103267181A CN2013102221362A CN201310222136A CN103267181A CN 103267181 A CN103267181 A CN 103267181A CN 2013102221362 A CN2013102221362 A CN 2013102221362A CN 201310222136 A CN201310222136 A CN 201310222136A CN 103267181 A CN103267181 A CN 103267181A
Authority
CN
China
Prior art keywords
pipeline
concrete
cement slurry
cement
coil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102221362A
Other languages
English (en)
Other versions
CN103267181B (zh
Inventor
闫勇
卜祥英
王珺彤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Tianjin Corp Ltd
Original Assignee
Tianjin MCC20 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin MCC20 Construction Co Ltd filed Critical Tianjin MCC20 Construction Co Ltd
Priority to CN201310222136.2A priority Critical patent/CN103267181B/zh
Publication of CN103267181A publication Critical patent/CN103267181A/zh
Application granted granted Critical
Publication of CN103267181B publication Critical patent/CN103267181B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Sewage (AREA)

Abstract

本发明公开了一种平口混凝土管连接方法,包括以下步骤:(1)把混凝土平口管端部位凿毛,把高分子防水卷材裁剪,粘合剂用水、107胶和水泥搅匀的水泥浆;(2)将平口混凝土管道按放线位置排放到位,把高分子防水卷材在接口处从管底穿过,将水泥浆浇到卷材和管道的连接面处,然后用水泥浆将卷材一头粘到管道,另外一头压在上面;(3)重复步骤(2)再粘贴一层高分子防水卷材。本发明利用高分子防水卷材的柔韧性和防水性使管道接口能够适应管道施工和使用过程中产生的变形,更有效的避免因为地基不均匀沉降和上部不均匀压力等产生变形而出现开裂,进而造成的管道渗漏。

Description

平口混凝土管连接方法
技术领域
本发明涉及一种管道连接方法,具体的说涉及一种平口混凝土管道的接口连接方法。
背景技术
随着城市建设步伐的加快,在城市基础设施建设中,人们对市政工程的要求越来越高,要求城市排水工程要更趋于合理、完善。为此,无论从技术角度或从经济角度而言,都必须提高排水管道的使用周期。长期以来,在城市雨排水工程中,多选用混凝土排水管,混凝土管道主要有承插式和平口式,这里主要是介绍平口混凝土管道的接口连接方法。混土管道基础的不均匀沉降或上部压力的加大都可能会导致的接口渗漏。为了使混凝土排水管道能够在其使用过程中,充分发挥作用,得到合理使用,这就要求混凝土排水管本身和管道与管道的接口具有良好的防渗漏功能。因此,在城市排水管网中应用混凝土排水管道时,应该特别注意管道本身的质量与接口防渗漏处理这两方面的问题,从而才能保证水泥混凝土排水管的使用效果与使用周期。
混凝土管道的质量已经通过质量监督管理部门对生产厂家的管理进行控制,混凝土管道的接口却是要现场施工进行控制。图集《混凝土排水管道基础与接口》04S516中关于平口混凝土管道接口主要是用钢丝网4加水泥砂浆抹带5的方法进行连接,如图1所示。
这种连接方法对于地基的不均匀沉降和上部不均匀压力等造成的变形的适应能力较差,非常容易造成水泥砂浆开裂,从而导致排水管道渗漏水。
发明内容
为了解决现有技术中存在的问题,本发明提供一种平口雨排水混凝土管道和预留备用管道的连接方法,克服现有技术中因水泥砂浆容易开裂导致的平口雨排水管道容易渗漏的问题。
本发明的技术方案如下:一种平口混凝土管连接方法,包括以下步骤:
(1)把混凝土平口管端部位100-200mm范围内凿毛,把高分子防水卷材(像聚乙烯丙纶防水卷材等比较薄而且表面粗糙容易与粘合剂粘合的卷材均可)裁剪成宽为200-400mm,长度为混凝土管外径加200-400mm,粘合剂用水、107胶和水泥搅匀的水泥浆,水泥浆的比例根据天气、温度等条件适当调整,以水泥浆浇到管顶部能向两侧自流为宜;
(2)将平口混凝土管道按放线位置排放到位,将相邻两管口对齐顶紧,把高分子防水卷材在接口处从管底穿过,将水泥浆浇到卷材和管道的连接面处,管道两侧施工人员将卷材在接口处来回拉扯使水泥浆能均匀的分布,然后用水泥浆将卷材一头粘到管道,另外一头压在上面;
(3)重复步骤(2)再粘贴一层防水卷材,内外两层卷材的接头错开100mm以上。
所述粘合剂中水:107胶:水泥比例为1:3:6。
通过步骤(1)-(3)做完接口头以后可以再在接头处参照《混凝土排水管道基础与接口》04S516设置120度混凝土基础或其他形式基础,也可以根据实际情况先做基础后安装管道。
本发明的有益效果是:本发明利用高分子防水卷材的柔韧性和防水性使管道接口能够适应管道施工和使用过程中产生的变形,更有效的避免因为地基不均匀沉降和上部不均匀压力等产生变形而出现开裂,进而造成的管道渗漏。此外用107胶配的水泥浆使卷材与管道的粘合更牢固,不易被变形撕裂。这样的接口与管道连接牢固,接口还不易因为变形面被撕裂出现渗漏现象,从而提高了雨排水的使用效果和使用周期,保证了施工质量。在管道连接前处必须进行过凿毛处理,以保证管道的紧密结合,从而提高施工质量。
附图说明
图1是04S5516图集施工方法;
图2是本发明施工方法的断面图;
图3是图2的俯视图。
具体实施方式
下面结合附图对本发明作进一步详细描述。
以雨排水平口混凝土管道为例进行说明,本发明的施工步骤如下:
1、采用
Figure BDA00003308201300021
的雨排水平口混凝土管道;
2、把混凝土平口管头1处100-200mm范围内凿毛。把高分子防水卷材2裁剪成宽为200-400mm,长度为混凝土管外径加200-400mm。粘合剂用水:107胶:水泥搅匀的水泥浆3,水:107胶:水泥浆3比例为1:3:6,水泥浆3的比例也要根据天气、温度、湿度等条件适当调整,以水泥浆浇到管顶部能向两侧自流为宜。
3、将平口混凝土管道按放线位置排放到位,将相邻两管口对齐顶紧,把高分子防水卷材1在接口处从管底穿过,将水泥浆浇到卷材到管道的连接处,管道两侧施工人员将卷材在接口处来回拉扯两次,使水泥浆能均匀的分布。然后用水泥浆将卷材一头粘到管道,另外一头压在上面。
4、再重复第2步再粘贴一层高分子防水卷材。内外两层卷材的接头在错开100mm以上。两层都做完后进行养护。
5、做完接口头以后可以再在接头处参照《混凝土排水管道基础与接口》04S516设置120度混凝土基础或其他形式基础,也可以根据实际情况先做基础后安装管道。
这样施工完等水泥浆强度达到后,接口处很难被破坏,而且防渗漏效果良好。本发明应用到平口雨排水混凝土管道和预留备用管道的接口连接中,实施效果良好。
尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可以作出很多形式,这些均属于本发明的保护范围之内。

Claims (4)

1.一种平口混凝土管连接方法,其特征在于,包括以下步骤:
(1)把混凝土平口管端部位100-200mm范围内凿毛,把高分子防水卷材裁剪成宽为200-400mm,长度为混凝土管外径加200-400mm,粘合剂用水、107胶和水泥搅匀的水泥浆,水泥浆的比例根据天气、温度等条件适当调整,以水泥浆浇到管顶部能向两侧自流为宜;
(2)将平口混凝土管道按放线位置排放到位,将相邻两管口对齐顶紧,把高分子防水卷材在接口处从管底穿过,将水泥浆浇到卷材和管道的连接面处,管道两侧施工人员将卷材在接口处来回拉扯使水泥浆能均匀的分布,然后用水泥浆将卷材一头粘到管道,另外一头压在上面;(3)重复步骤(2)再粘贴一层高分子防水卷材,内外两层卷材的接头错开100mm以上。
2.根据权利要求1所述平口混凝土管连接方法,其特征在于,所述粘合剂中水:107胶:水泥比例为1:3:6。
3.根据权利要求1所述平口混凝土管连接方法,其特征在于,通过步骤(1)-(3)做完接口头以后再在接头处设置120度混凝土基础。
4.根据权利要求1所述平口混凝土管连接方法,其特征在于,所述步骤(1)高分子防水卷材为聚乙烯丙纶。
CN201310222136.2A 2013-06-05 2013-06-05 平口混凝土管连接方法 Active CN103267181B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310222136.2A CN103267181B (zh) 2013-06-05 2013-06-05 平口混凝土管连接方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310222136.2A CN103267181B (zh) 2013-06-05 2013-06-05 平口混凝土管连接方法

Publications (2)

Publication Number Publication Date
CN103267181A true CN103267181A (zh) 2013-08-28
CN103267181B CN103267181B (zh) 2015-03-11

Family

ID=49010825

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310222136.2A Active CN103267181B (zh) 2013-06-05 2013-06-05 平口混凝土管连接方法

Country Status (1)

Country Link
CN (1) CN103267181B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106985273A (zh) * 2017-04-21 2017-07-28 济南城建集团有限公司 一种混凝土平口管道接口水泥砂浆抹带工具
SE541235C2 (en) * 2016-07-11 2019-05-07 Tekniska Verken I Linkoeping Ab Method of providing a liquid proof joint between parts and structure comprising such joint
CN111795225A (zh) * 2020-07-22 2020-10-20 武汉市年华管业有限公司 一种水泥管道防水连接方法
CN111810732A (zh) * 2020-07-22 2020-10-23 武汉市年华管业有限公司 一种钢筋砼管企口管连接口防渗水的处理方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4499923A (en) * 1981-04-07 1985-02-19 Schlegel Lining Technology Gmbh Concrete pipe with an inner lining
DE3534965A1 (de) * 1984-10-12 1986-05-22 Kabelwerke Brugg AG, Brugg Fixpunkte von rohrleitungen
CN2174518Y (zh) * 1993-08-24 1994-08-17 叶一宁 建筑防水多层复合卷材
CN102691851A (zh) * 2012-06-15 2012-09-26 上海久坚加固工程有限公司 用纤维复合材料布加固管道的方法
CN202492975U (zh) * 2012-03-23 2012-10-17 上海市电力公司 一种伸出屋面的管道防水结构
CN102927364A (zh) * 2012-11-05 2013-02-13 济南城建集团有限公司 钢筋混凝土管安装施工方法及钢筋砼管道专用夹具

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4499923A (en) * 1981-04-07 1985-02-19 Schlegel Lining Technology Gmbh Concrete pipe with an inner lining
DE3534965A1 (de) * 1984-10-12 1986-05-22 Kabelwerke Brugg AG, Brugg Fixpunkte von rohrleitungen
DE3534965C2 (zh) * 1984-10-12 1987-10-15 Kabelwerke Brugg Ag, Brugg, Ch
CN2174518Y (zh) * 1993-08-24 1994-08-17 叶一宁 建筑防水多层复合卷材
CN202492975U (zh) * 2012-03-23 2012-10-17 上海市电力公司 一种伸出屋面的管道防水结构
CN102691851A (zh) * 2012-06-15 2012-09-26 上海久坚加固工程有限公司 用纤维复合材料布加固管道的方法
CN102927364A (zh) * 2012-11-05 2013-02-13 济南城建集团有限公司 钢筋混凝土管安装施工方法及钢筋砼管道专用夹具

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘以勇 等: "大口径低压混凝土平口管对接工艺探讨", 《山东水利》, no. 7, 15 July 2004 (2004-07-15), pages 38 *
北京市市政工程设计研究总院: "《04S516混凝土排水管基础及接口》", 1 March 2004, 中国建筑标准设计研究院出版, article "120°混凝土基础钢丝网水泥砂浆抹带接口", pages: 28 *
马国强: "柔性接口钢筋混凝土排水管在市政工程中的应用_马国强[1]", 《河南省土木建筑学会2009年学术大会论文集》, 1 May 2009 (2009-05-01), pages 4 - 6 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE541235C2 (en) * 2016-07-11 2019-05-07 Tekniska Verken I Linkoeping Ab Method of providing a liquid proof joint between parts and structure comprising such joint
CN106985273A (zh) * 2017-04-21 2017-07-28 济南城建集团有限公司 一种混凝土平口管道接口水泥砂浆抹带工具
CN106985273B (zh) * 2017-04-21 2023-09-01 济南城建集团有限公司 一种混凝土平口管道接口水泥砂浆抹带工具
CN111795225A (zh) * 2020-07-22 2020-10-20 武汉市年华管业有限公司 一种水泥管道防水连接方法
CN111810732A (zh) * 2020-07-22 2020-10-23 武汉市年华管业有限公司 一种钢筋砼管企口管连接口防渗水的处理方法
CN111810732B (zh) * 2020-07-22 2022-04-12 武汉市年华管业有限公司 一种钢筋砼管企口管连接口防渗水的处理方法

Also Published As

Publication number Publication date
CN103267181B (zh) 2015-03-11

Similar Documents

Publication Publication Date Title
CN106120873B (zh) 一种桩筏基础预铺反粘复合高分子防水卷材的施工方法
CN101787742B (zh) 一种种植屋面植土下变形缝构造方法
CN107859064B (zh) 一种预制管廊与现浇管廊衔接防水结构及施工方法
CN108832563A (zh) 一种预制电缆排管及其施工方法
CN107059946A (zh) 一种地下室排水板及其施工工法
CN103276858B (zh) 倒置式屋面排水结构及其施工方法
CN104482298B (zh) 一种hdpe钢塑复合螺旋缠绕排水管安装施工方法
CN105862873A (zh) 深基坑狭窄空间地下防水及外墙结构施工方法
CN103267181A (zh) 平口混凝土管连接方法
CN109944314B (zh) 一种无降水大口径缠绕管复合接口快速施工方法
CN106812219A (zh) 填充墙顶部塞缝施工方法
CN102776897A (zh) 一种散水防沉防裂施工方法及结构
CN105201025A (zh) 地下室防水构造及其施工方法
CN102912945B (zh) 一种屋面复式防渗排汽孔细部处理工艺
CN105442861B (zh) 卫生间排水管道渗漏水背水面修复方法
CN215291040U (zh) 一种使用定型化pc构件的女儿墙泛水护角
CN110541431A (zh) 一种管廊防水结构及其施工方法
CN110409600A (zh) 单元组合式污水池结构施工方法
CN204252414U (zh) 屋面防水结构
CN206429253U (zh) 隧道衬砌环向施工缝裂缝渗水处治结构
CN103206093B (zh) 房顶沉降缝的补防漏方法
CN112681624A (zh) 独立地下室顶板种植屋面的建造方法
CN202401561U (zh) 多功能环保型可移动水槽
CN208329409U (zh) 一种屋面女儿墙防漏水构造
CN109372030A (zh) 一种后浇带防水结构及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 300301 Dongli District, flawless Street Jintang Highway Bridge No. ten

Patentee after: MCC TIANGONG GROUP TIANJIN CO., LTD.

Address before: 300301, Dongli District, Tianjin, Tianjin twenty Street Construction Co., Ltd.

Patentee before: Tianjin MCC20 Construction Co., Ltd.