CN103243748B - Application of foamed light soil in repairing of building foundation subsidence holes - Google Patents

Application of foamed light soil in repairing of building foundation subsidence holes Download PDF

Info

Publication number
CN103243748B
CN103243748B CN201310178529.8A CN201310178529A CN103243748B CN 103243748 B CN103243748 B CN 103243748B CN 201310178529 A CN201310178529 A CN 201310178529A CN 103243748 B CN103243748 B CN 103243748B
Authority
CN
China
Prior art keywords
lightweight soil
cavity
foam lightweight
holes
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310178529.8A
Other languages
Chinese (zh)
Other versions
CN103243748A (en
Inventor
陈忠平
汪建斌
陈俊霖
马元锦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Shengrui Technology Co ltd
Original Assignee
Guangdong Sheng Rui Civil Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Sheng Rui Civil Technology filed Critical Guangdong Sheng Rui Civil Technology
Priority to CN201310178529.8A priority Critical patent/CN103243748B/en
Publication of CN103243748A publication Critical patent/CN103243748A/en
Application granted granted Critical
Publication of CN103243748B publication Critical patent/CN103243748B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses an application of foamed light soil in repairing of building foundation subsidence holes. The application of the foamed light soil in repairing of building foundation subsidence holes includes the following steps: (1) density and strength of the foamed light soil to be used are determined according to height of a building above the subsidence holes; (2) waterproof geomembranes are paved on the bottom layers of the subsidence holes; (3) the foamed light soil with required density and strength is prepared at a construction site and poured in the building foundation subsidence holes, layered pouring is performed during pouring; and (4) the foamed light soil is used for filling the holes in a pouring mode, common surface soil is paved above the foamed light soil, and namely repairing operation is finished. The foamed light soil is used for repairing the building foundation subsidence holes, has the advantages of being high in fluidity and firmness rate, resistant to subsidence and the like, can fill the holes, and simultaneously is small in proportion. The problem of re-subsidence cannot occur after the holes are filled by the foamed light soil, and the foamed light soil is low in cost and suitable for popularization and application.

Description

Foam lightweight soil is repairing the application in structure foundation depression cavity
Technical field
The invention belongs to building engineering field, be specifically related to Foam lightweight soil and repairing the application in structure foundation depression cavity.
Background technology
Structure foundation depression due to soft foundation processing defective and cause, be because drive piles, banket, the measure such as compacting not (not) thoroughly can solve the problem of subgrade depression, thus cause the subsidence of foundations to occur the phenomenon in depression cavity.
For the depression cavity that structure foundation depression occurs, prior art is difficult to process, does not also process case reliably.According to conventional cement slurries filling, the setting percentage (owing to solidifying depression) of 58-65% can not ensure to be full of cavity completely on the one hand, in addition because obturation (conventional cement slurries) proportion is high, also again there is the problem of depression after cannot solving process, filling cost is also high simultaneously, and therefore this building just may be scrapped.
Summary of the invention
In order to overcome shortcoming existing for existing employing conventional cement slurries filling structure foundation depression cavity with not enough, Foam lightweight soil is the object of the present invention is to provide to repair the application in structure foundation depression cavity.Foam lightweight soil has the characteristics such as high fluidity, high setting percentage and anti-settling, can solve the deficiencies in the prior art preferably.
Object of the present invention is achieved through the following technical solutions:
Foam lightweight soil is repairing the application in structure foundation depression cavity, comprises the following steps:
(1) density and the intensity of the Foam lightweight soil that will use is determined according to the height of building above depression cavity; When above depression cavity, the height of building is lower than 20 meters, the density of Foam lightweight soil should be 550 kilograms/m 3, intensity is 0.6MPa; When above depression cavity, the height of building is 20-50 rice, the density of Foam lightweight soil should be 560-640 kilogram/m 3, intensity is 0.7-0.9MPa; When above depression cavity, the height of building is greater than 50 meters, the density of Foam lightweight soil should be 650 kilograms/m 3, intensity is 1.0MPa;
Construction of buildings on subgrade, process of generally will driving piles; The Main Load of building is born by pile foundation, and basement process Main Function is the deformation failure of anchor spike base horizontal direction, plays stabilization, and be exactly the attractive in appearance of guarantee ground in addition, walking is convenient.The subsidence of foundations can affect the supporting capacity of pile foundation, destroys ground attractive in appearance, and personnel pass in and out safety without guarantee, inconvenience.Light soil ground only need ensure that the intensity of original place base just can meet the requirement of intensity, in order to reliably, leaves certain allowance, fully ensures safety, so, according to height, suitably improve intensity;
(2) when starting to process, the soft mud in depression cavity is dug up make cavity reach at least 2 meters dark, then spread waterproofing geomembrane at the bottom in depression cavity; Foam lightweight soil is for a long time under the immersion of water, and its performance can be destroyed, and laying waterproofing geomembrane is exactly to prevent water logging, molding casting body.
(3) prepare the Foam lightweight soil of desired density and intensity at the construction field (site), and be poured in structure foundation depression cavity; Laminated pouring is wanted, every layer thickness 40-80cm during cast; Later layer be cast in after front one deck pours into a mould 20 hours, carry out when front one deck Foam lightweight soil initial setting strength is greater than more than 0.2Mpa;
If every layer thickness is lower than 40cm, the solidification effect after filling is poor, and intensity is difficult to ensure card, and construction times is many, increases cost.If higher than 80cm, easily occur segregation layering, the defects such as froth breaking after cast, the uniformity of pour mass performance can not get ensureing.
(4) by Foam lightweight soil cavity watered and fill, when its initial setting strength reaches more than 0.3Mpa, above Foam lightweight soil, spread normal surface soil again, namely complete reparation operation;
Described Foam lightweight soil can adopt the Foam lightweight soil of prior art, foam concrete disclosed in such as " People's Republic of China (PRC) construction industry industry standard-foam concrete JG/T266-2011 ".
The present invention has following advantage and effect relative to prior art:
Foam lightweight soil be applied to and repair structure foundation depression cavity, Foam lightweight soil has the characteristics such as high fluidity, high setting percentage and anti-settling, can fill full cavity; Foam lightweight soil proportion is little simultaneously, and the problem of sedimentation again can not occur after using Foam lightweight soil to fill; Moreover Foam lightweight soil cost is low, be applicable to promoting the use of.
Accompanying drawing explanation
Fig. 1 is building settlement cavity organigram before treatment.
Fig. 2 is the organigram in building settlement cavity after employing method process of the present invention.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing, the present invention is described in further detail, but embodiments of the present invention are not limited thereto.
Embodiment 1
Structure foundation depression cavity, one place, as shown in Figure 1, top, cavity building object height 30 meters, to dark about 2 meters of depression cavity during process for its structure.Adopt Foam lightweight soil to repair this structure foundation depression cavity, comprise the following steps:
(1) determine that the density of the Foam lightweight soil that will use is 580 kilograms/m according to the height of building above depression cavity 3, intensity is 0.8MPa;
(2), when starting to process, the soft mud in depression cavity is dug up, then the bottom in depression cavity spread waterproofing geomembrane (purchased from Dezhou Orient Geosynthetics Co., Ltd., specification 0.5-1.0mm; Lower same);
(3) prepare the Foam lightweight soil of desired density and intensity at the construction field (site), and be poured in structure foundation depression cavity; Laminated pouring is wanted, every layer thickness 60cm during cast; Later layer be cast in after front one deck pours into a mould 20 hours, carry out when front one deck Foam lightweight soil initial setting strength is greater than more than 0.2Mpa;
(4) by Foam lightweight soil cavity watered and fill, when its initial setting strength reaches more than 0.3Mpa, above Foam lightweight soil, spread normal surface soil again, namely complete reparation operation; Repair the structure of groundwork as shown in Figure 2.
After adopting above-mentioned process, no longer there is sedimentation in this place's ground, ground is attractive in appearance, and walking is convenient.
Embodiment 2
Structure foundation depression cavity, one place, as shown in Figure 1, top, cavity building object height 60 meters, to dark about 3 meters of depression cavity during process for its structure.Adopt Foam lightweight soil to repair this structure foundation depression cavity, comprise the following steps:
(1) determine that the density of the Foam lightweight soil that will use is 650 kilograms/m according to the height of building above depression cavity 3, intensity is 1.0MPa;
(2), when starting to process, the soft mud in depression cavity is dug up, then spreads waterproofing geomembrane at the bottom in depression cavity;
(3) prepare the Foam lightweight soil of desired density and intensity at the construction field (site), and be poured in structure foundation depression cavity; Laminated pouring is wanted, every layer thickness 80cm during cast; Later layer be cast in after front one deck pours into a mould 20 hours, carry out when front one deck Foam lightweight soil initial setting strength is greater than more than 0.2Mpa;
(4) by Foam lightweight soil cavity watered and fill, when its initial setting strength reaches more than 0.3Mpa, above Foam lightweight soil, spread normal surface soil again, namely complete reparation operation; Repair the structure of groundwork as shown in Figure 2.
After adopting above-mentioned process, no longer there is sedimentation in this place's ground, ground is attractive in appearance, and walking is convenient.
Embodiment 3
Structure foundation depression cavity, one place, as shown in Figure 1, top, cavity building object height 15 meters, to dark about 1.5 meters of depression cavity during process for its structure.Adopt Foam lightweight soil to repair this structure foundation depression cavity, comprise the following steps:
(1) determine that the density of the Foam lightweight soil that will use is 550 kilograms/m according to the height of building above depression cavity 3, intensity is 0.6MPa;
(2) when starting to process, the soft mud in depression cavity is dug up make cavity reach 2 meters dark, then spread waterproofing geomembrane at the bottom in depression cavity;
(3) prepare the Foam lightweight soil of desired density and intensity at the construction field (site), and be poured in structure foundation depression cavity; Laminated pouring is wanted, every layer thickness 50cm during cast; Later layer be cast in after front one deck pours into a mould 20 hours, carry out when front one deck Foam lightweight soil initial setting strength is greater than more than 0.2Mpa;
(4) by Foam lightweight soil cavity watered and fill, when its initial setting strength reaches more than 0.3Mpa, above Foam lightweight soil, spread normal surface soil again, namely complete reparation operation; Repair the structure of groundwork as shown in Figure 2.
After adopting above-mentioned process, no longer there is sedimentation in this place's ground, ground is attractive in appearance, and walking is convenient.
Above-described embodiment is the present invention's preferably embodiment; but embodiments of the present invention are not restricted to the described embodiments; change, the modification done under other any does not deviate from Spirit Essence of the present invention and principle, substitute, combine, simplify; all should be the substitute mode of equivalence, be included within protection scope of the present invention.

Claims (1)

1. Foam lightweight soil is repairing the application in structure foundation depression cavity, it is characterized in that comprising the following steps:
(1) density and the intensity of the Foam lightweight soil that will use is determined according to the height of building above depression cavity; When above depression cavity, the height of building is lower than 20 meters, the density of Foam lightweight soil should be 550 kilograms/m 3, intensity is 0.6MPa; When above depression cavity, the height of building is 20-50 rice, the density of Foam lightweight soil should be 560-640 kilogram/m 3, intensity is 0.7-0.9MPa; When above depression cavity, the height of building is greater than 50 meters, the density of Foam lightweight soil should be 650 kilograms/m 3, intensity is 1.0MPa;
(2) when starting to process, the soft mud in depression cavity is dug up make cavity reach at least 2 meters dark, then spread waterproofing geomembrane at the bottom in depression cavity;
(3) prepare the Foam lightweight soil of desired density and intensity at the construction field (site), and be poured in structure foundation depression cavity; Laminated pouring is wanted, every layer thickness 40-80cm during cast; Later layer be cast in after front one deck pours into a mould 20 hours, carry out when front one deck Foam lightweight soil initial setting strength is greater than 0.2Mpa;
(4) by Foam lightweight soil cavity watered and fill, when its initial setting strength reaches more than 0.3Mpa, above Foam lightweight soil, spread normal surface soil again, namely complete reparation operation.
CN201310178529.8A 2013-05-14 2013-05-14 Application of foamed light soil in repairing of building foundation subsidence holes Active CN103243748B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310178529.8A CN103243748B (en) 2013-05-14 2013-05-14 Application of foamed light soil in repairing of building foundation subsidence holes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310178529.8A CN103243748B (en) 2013-05-14 2013-05-14 Application of foamed light soil in repairing of building foundation subsidence holes

Publications (2)

Publication Number Publication Date
CN103243748A CN103243748A (en) 2013-08-14
CN103243748B true CN103243748B (en) 2015-03-11

Family

ID=48923600

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310178529.8A Active CN103243748B (en) 2013-05-14 2013-05-14 Application of foamed light soil in repairing of building foundation subsidence holes

Country Status (1)

Country Link
CN (1) CN103243748B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040100704A (en) * 2003-05-23 2004-12-02 한국해양연구원 A Light-Weighted Foam Soil Manufacturing Method and Soft Ground Improvement Method Using thereof
CN101391902A (en) * 2008-11-10 2009-03-25 梁林华 Foaming concrete made by waste and old concrete and production method thereof and use
JP2010180678A (en) * 2009-02-09 2010-08-19 Bridgestone Corp Load reducing configuration for structure
CN102261262A (en) * 2010-08-13 2011-11-30 深圳市中金岭南有色金属股份有限公司凡口铅锌矿 High-performance foam mortar filling method for mine stope
WO2013065229A1 (en) * 2011-11-04 2013-05-10 Jfeスチール株式会社 Filling material and ground-repairing method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040100704A (en) * 2003-05-23 2004-12-02 한국해양연구원 A Light-Weighted Foam Soil Manufacturing Method and Soft Ground Improvement Method Using thereof
CN101391902A (en) * 2008-11-10 2009-03-25 梁林华 Foaming concrete made by waste and old concrete and production method thereof and use
JP2010180678A (en) * 2009-02-09 2010-08-19 Bridgestone Corp Load reducing configuration for structure
CN102261262A (en) * 2010-08-13 2011-11-30 深圳市中金岭南有色金属股份有限公司凡口铅锌矿 High-performance foam mortar filling method for mine stope
WO2013065229A1 (en) * 2011-11-04 2013-05-10 Jfeスチール株式会社 Filling material and ground-repairing method

Also Published As

Publication number Publication date
CN103243748A (en) 2013-08-14

Similar Documents

Publication Publication Date Title
CN102852059A (en) Pavement structure based on water sand backfilling technology and construction method thereof
CN104652371B (en) The glue of crossing set up based on old dam coagulates rock-fill dams and construction method thereof
CN102080381B (en) Method for managing landslip of side slope landslide for transformer substation
CN108193648A (en) Plasticity panel homogeneous dam
CN207211362U (en) A kind of basement bottom board fish tail and waterproof layer
CN104652495A (en) Waterproof construction process for joint of inner support upright post of foundation pit and bottom plate
CN113431065A (en) Rapid construction method and structure of occlusive pile and steel sleeve combined cofferdam
CN103243748B (en) Application of foamed light soil in repairing of building foundation subsidence holes
CN106884436A (en) A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab
CN104404918B (en) Adopt composite geo-membrane and part to change and fill out the method that clay repairs clay through crack
CN203229927U (en) Treatment structure for dam body upstream face superficial layer temperature crack
CN108193706A (en) A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure
CN110512571B (en) Roller compacted concrete dam containing rock-fill concrete core wall and construction method thereof
CN210797245U (en) Structure is backfilled to bridgehead abutment back of body
CN208578025U (en) A kind of constructing device for the multi-functional tubular pole that can be drained for the island Tian Haizhu
CN206298874U (en) It is a kind of to prevent the structure that water buffer brake is destroyed in bedding material
CN203247604U (en) Composite foundation of mixture of port engineering riprap foundation bed and underwater non-dispersion concrete
CN202865712U (en) Pavement structure based on water-compacted sand backfilling technology
CN207228166U (en) A kind of town road heavy well cover walling crib ruggedized construction
CN206457856U (en) A kind of ground crack resistence structure
CN107217563B (en) A kind of renovation technique of bridge pavement
CN111455968A (en) Anti-settlement construction method for soft soil foundation
CN105735366B (en) Waterproof construction method based on concrete
CN205387721U (en) Highway retaining wall reinforced structure
CN114688347B (en) Method for embedding flexible pipeline by using controllable low-strength material prefabricated block

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: Tsinghua Science Park 511440 Guangdong city of Guangzhou province Panyu District Shilou town Guanqiao Village building five floor D District

Patentee after: GUANGDONG SHENGRUI TECHNOLOGY Co.,Ltd.

Address before: Tsinghua Science Park 511440 Guangdong city of Guangzhou province Panyu District Shilou town Guanqiao Village building five floor D District

Patentee before: GUANGDONG SHENGRUI CIVIL TECHNOLOGY CO.,LTD.

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Application of foamed light soil in repairing of building foundation subsidence holes

Effective date of registration: 20151125

Granted publication date: 20150311

Pledgee: China Co. truction Bank Corp Guangzhou Panyu branch

Pledgor: GUANGDONG SHENGRUI TECHNOLOGY Co.,Ltd.

Registration number: 2015990001064

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20170518

Granted publication date: 20150311

Pledgee: China Co. truction Bank Corp Guangzhou Panyu branch

Pledgor: GUANGDONG SHENGRUI TECHNOLOGY Co.,Ltd.

Registration number: 2015990001064

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Application of foamed light soil in repairing of building foundation subsidence holes

Effective date of registration: 20170525

Granted publication date: 20150311

Pledgee: China Co. truction Bank Corp Guangzhou Panyu branch

Pledgor: GUANGDONG SHENGRUI TECHNOLOGY Co.,Ltd.

Registration number: 2017990000425

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20180620

Granted publication date: 20150311

Pledgee: China Co. truction Bank Corp Guangzhou Panyu branch

Pledgor: GUANGDONG SHENGRUI TECHNOLOGY Co.,Ltd.

Registration number: 2017990000425

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Application of foamed light soil in repairing of building foundation subsidence holes

Effective date of registration: 20200617

Granted publication date: 20150311

Pledgee: Shunde Guangdong rural commercial bank Limited by Share Ltd. Daliang branch

Pledgor: GUANGDONG SHENGRUI TECHNOLOGY Co.,Ltd.

Registration number: Y2020980003164

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230704

Granted publication date: 20150311

Pledgee: Shunde Guangdong rural commercial bank Limited by Share Ltd. Daliang branch

Pledgor: GUANGDONG SHENGRUI TECHNOLOGY Co.,Ltd.

Registration number: Y2020980003164

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Application of foam light soil in repairing building foundation subsidence cavity

Effective date of registration: 20230825

Granted publication date: 20150311

Pledgee: Guangdong Shunde Rural Commercial Bank Co.,Ltd. science and technology innovation sub branch

Pledgor: GUANGDONG SHENGRUI TECHNOLOGY Co.,Ltd.

Registration number: Y2023980053840