CN103233742A - Treatment measure of bad geological section for long distance pipeline coal conveying - Google Patents

Treatment measure of bad geological section for long distance pipeline coal conveying Download PDF

Info

Publication number
CN103233742A
CN103233742A CN2013101739514A CN201310173951A CN103233742A CN 103233742 A CN103233742 A CN 103233742A CN 2013101739514 A CN2013101739514 A CN 2013101739514A CN 201310173951 A CN201310173951 A CN 201310173951A CN 103233742 A CN103233742 A CN 103233742A
Authority
CN
China
Prior art keywords
measure
water
measures
tunnel
treatment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101739514A
Other languages
Chinese (zh)
Inventor
张卫东
苏华
黎武
赵畅
卫桢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Original Assignee
Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Design and Research Institute of China Coal Technology and Engineering Group filed Critical Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Priority to CN2013101739514A priority Critical patent/CN103233742A/en
Publication of CN103233742A publication Critical patent/CN103233742A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a treatment measure of a bad geological section for long distance pipeline coal conveying. The treatment measure includes the following measures: 1) fault fracture zone treatment measure: measures of forepoling or grouting and water plugging and the like are adopted, preliminary bracing and permanent lining are performed in time, the forepoling can adopt the measures of an advanced anchor bolt, an advanced small pipe or small pipe shed + steel arch and the like; 2) inrush (flooding) accident treatment measure: for a surrounding rock section which may have inrush (flooding) accidents, an advanced hole probing forecast measure is adopted to perform advanced grouting and water plugging. A karst water discharge area is close to a karst water discharge port, and a drainage measure is used for treatment. When water seepage amount on the sprayed concrete surface in a tunnel is large, or stranded inrush exists, a technical measure with drainage as a main measure can be adopted. Through technical treatment of the bad geological section, the treatment measure reduces difficulty in a construction process, improves construction speed and efficiency, and guarantees smooth construction and safe late project operation.

Description

Long-distance pipe is failed coal bad geological section treatment measures
Technical field
The present invention relates to the defeated coal bad geological section treatment measures of a kind of pipeline coal transporting bad geological section treatment measures, especially long-distance pipe.
Background technology
Object of construction production is built in bad geological section, itself just exists various danger, in order to deal with problems, by small-sized simulated experiment, this method can reasonablely be handled the generation of fault belt and prominent (gushing) water accident well, coal slurry pipeline is carried under relatively safer condition moved.
Summary of the invention
The purpose of this invention is to provide the defeated coal bad geological section treatment measures of a kind of long-distance pipe.
For overcoming the prior art deficiency, the present invention solves like this: the unfavorable geology that this engineering tunnel may run into is mainly situations such as fault belt and prominent (gushing) water, in conjunction with convey coal pipe construction of tunnel characteristics and other similar engineering experience, propose the defeated coal bad geological section treatment measures of long-distance pipe, this measure is carried out according to the following steps:
(1) fault belt treatment measures
Poor at the zone of fracture geological conditions, cause tunnel roof, abutment wall to occur caving in easily behind the country rock excavation, fall piece, the cavitation condition is poor, short from the steady time, even accident such as roof fall, design is considered to carry out leading inspecting hole before excavation, finds out fault zone zone of fracture geological condition and underground water, according to the geological conditions after finding out, groundwater condition, take measures such as advance support or grouting for water blocking, in time apply preliminary bracing and permanent lining, secondary lining.Advance support can adopt advance anchor bolt, leading ductule or tubule canopy+measures such as steel bow member.
(2) prominent (gushing) water accident treatment measure
In construction of tunnel, when the tunnel by IV level, V level country rock Fu Shui location, as deal with improperly, prominent (gushing) water accident very easily takes place.Prominent (gushing) water accident is administered and must be suited measures to local conditions, based on row, and stifled row combination.At first should to the country rock location of (gushing) water phenomenon of may dashing forward, take the forecast measure of leading inspecting hole according to the tunnel geology exploration report in the construction, carry out the pre-grouting water reinforcement.When the tunnel is in the karst water discharge area, and nearer apart from its scavenge port, adopt drainage measure to handle.Sprayed mortar sweat amount is bigger in the tunnel, or when strand shape water burst is arranged into, can the row of taking be main technical measures also.
Beneficial effect of the present invention: by the technical finesse to bad location, not only reduced the difficulty in the work progress, and improved speed and the efficient of construction, guaranteed the safety of the smooth of construction and end item operation.
The specific embodiment
According to the tunnel geology data, the unfavorable geology that this engineering tunnel may run into is mainly situations such as fault belt and prominent (gushing) water, in conjunction with convey coal pipe construction of tunnel characteristics and other similar engineering experience, at several unfavorable geology phenomenons, take following treatment measures respectively:
(1) fault belt treatment measures
Poor at the zone of fracture geological conditions, cause tunnel roof, abutment wall to occur caving in easily behind the country rock excavation, fall piece, the cavitation condition is poor, short from the steady time, even accident such as roof fall, design is considered to carry out leading inspecting hole before excavation, finds out fault zone zone of fracture geological condition and underground water, according to the geological conditions after finding out, groundwater condition, take measures such as advance support or grouting for water blocking, in time apply preliminary bracing and permanent lining, secondary lining.Advance support can adopt advance anchor bolt, leading ductule or tubule canopy+measures such as steel bow member.
(2) prominent (gushing) water accident treatment measure
In construction of tunnel, when the tunnel by IV level, V level country rock Fu Shui location, as deal with improperly, prominent (gushing) water accident very easily takes place.Prominent (gushing) water accident is administered and must be suited measures to local conditions, based on row, and stifled row combination.At first should to the country rock location of (gushing) water phenomenon of may dashing forward, take the forecast measure of leading inspecting hole according to the tunnel geology exploration report in the construction, carry out the pre-grouting water reinforcement.When the tunnel is in the karst water discharge area, and nearer apart from its scavenge port, adopt drainage measure to handle.Sprayed mortar sweat amount is bigger in the tunnel, or when strand shape water burst is arranged into, can the row of taking be main technical measures also.

Claims (1)

1. a long-distance pipe is failed coal bad geological section treatment measures, it is characterized in that being undertaken by following step:
(1) fault belt treatment measures
Poor at the zone of fracture geological conditions, cause tunnel roof, abutment wall to occur caving in easily behind the country rock excavation, fall piece, the cavitation condition is poor, short from the steady time, even accident such as roof fall, design is considered to carry out leading inspecting hole before excavation, finds out fault zone zone of fracture geological condition and underground water, according to the geological conditions after finding out, groundwater condition, take measures such as advance support or grouting for water blocking, in time apply preliminary bracing and permanent lining, secondary lining; Advance support can adopt advance anchor bolt, leading ductule or tubule canopy+measures such as steel bow member;
(2) prominent (gushing) water accident treatment measure
In construction of tunnel, when the tunnel by IV level, V level country rock Fu Shui location, as deal with improperly, prominent (gushing) water accident very easily takes place.Prominent (gushing) water accident is administered and must be suited measures to local conditions, based on row, and stifled row combination; At first should to the country rock location of (gushing) water phenomenon of may dashing forward, take the forecast measure of leading inspecting hole according to the tunnel geology exploration report in the construction, carry out the pre-grouting water reinforcement; When the tunnel is in the karst water discharge area, and nearer apart from its scavenge port, adopt drainage measure to handle; Sprayed mortar sweat amount is bigger in the tunnel, or when strand shape water burst is arranged into, can the row of taking be main technical measures also.
CN2013101739514A 2013-05-11 2013-05-11 Treatment measure of bad geological section for long distance pipeline coal conveying Pending CN103233742A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101739514A CN103233742A (en) 2013-05-11 2013-05-11 Treatment measure of bad geological section for long distance pipeline coal conveying

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101739514A CN103233742A (en) 2013-05-11 2013-05-11 Treatment measure of bad geological section for long distance pipeline coal conveying

Publications (1)

Publication Number Publication Date
CN103233742A true CN103233742A (en) 2013-08-07

Family

ID=48881805

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101739514A Pending CN103233742A (en) 2013-05-11 2013-05-11 Treatment measure of bad geological section for long distance pipeline coal conveying

Country Status (1)

Country Link
CN (1) CN103233742A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103775126A (en) * 2014-01-09 2014-05-07 安徽水安建设集团股份有限公司 Grotto preliminary bracing construction method adopted when underground water seeps
CN103850688A (en) * 2014-03-24 2014-06-11 昆明理工大学 Method for dynamically superimposing coupling support on large-section roadway in complicated fault fracture zone
CN105888693A (en) * 2016-06-01 2016-08-24 中国云南路建集团股份公司 Treating construction method for water burst of small underground river of highway tunnel
CN112610227A (en) * 2020-12-14 2021-04-06 山东大学 Rapid construction method for open TBM to penetrate through unfavorable geology

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0633474A (en) * 1992-07-15 1994-02-08 Nisshin Kogyo Kk Headrace pipe and collection and drainage headrace pipe method
JP2003239687A (en) * 2002-02-21 2003-08-27 Watanabegumi:Kk Drainage structure of shaft in pipe jacking method
CN101691842A (en) * 2009-07-15 2010-04-07 中铁隧道股份有限公司 Three-arm hydraulic wagon drill and tunnel drilling and grouting construction method
CN201502401U (en) * 2009-01-06 2010-06-09 牡丹江电业局 Automatic drainage system of cable tunnel
CN101761346A (en) * 2009-12-30 2010-06-30 中铁十二局集团第二工程有限公司 Method for constructing metamorphic rock confined water tunnel
CN101994513A (en) * 2010-10-30 2011-03-30 中铁十二局集团第二工程有限公司 Method for constructing tunnel by finishing full section curtain grouting from upper-half section
CN102619560A (en) * 2012-04-17 2012-08-01 中铁十六局集团有限公司 Drainage and drainage method for long-distance reverse-slope tunnels
CN102705006A (en) * 2012-06-07 2012-10-03 中铁十一局集团第四工程有限公司 Method for governing operating tunnel flood by adopting wellpoint dewatering method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0633474A (en) * 1992-07-15 1994-02-08 Nisshin Kogyo Kk Headrace pipe and collection and drainage headrace pipe method
JP2003239687A (en) * 2002-02-21 2003-08-27 Watanabegumi:Kk Drainage structure of shaft in pipe jacking method
CN201502401U (en) * 2009-01-06 2010-06-09 牡丹江电业局 Automatic drainage system of cable tunnel
CN101691842A (en) * 2009-07-15 2010-04-07 中铁隧道股份有限公司 Three-arm hydraulic wagon drill and tunnel drilling and grouting construction method
CN101761346A (en) * 2009-12-30 2010-06-30 中铁十二局集团第二工程有限公司 Method for constructing metamorphic rock confined water tunnel
CN101994513A (en) * 2010-10-30 2011-03-30 中铁十二局集团第二工程有限公司 Method for constructing tunnel by finishing full section curtain grouting from upper-half section
CN102619560A (en) * 2012-04-17 2012-08-01 中铁十六局集团有限公司 Drainage and drainage method for long-distance reverse-slope tunnels
CN102705006A (en) * 2012-06-07 2012-10-03 中铁十一局集团第四工程有限公司 Method for governing operating tunnel flood by adopting wellpoint dewatering method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王振学: "鹅步岭隧道施工超前地质与不良地质处治方案", 《企业技术开发》, vol. 29, no. 1, 31 January 2010 (2010-01-31) *
詹卫荣: "巷道在强风化泥灰岩中的施工技术", 《江西煤炭科技》, no. 4, 31 December 2011 (2011-12-31) *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103775126A (en) * 2014-01-09 2014-05-07 安徽水安建设集团股份有限公司 Grotto preliminary bracing construction method adopted when underground water seeps
CN103775126B (en) * 2014-01-09 2015-12-30 安徽水安建设集团股份有限公司 A kind of cavern's preliminary bracing construction method when having underground water to ooze out
CN103850688A (en) * 2014-03-24 2014-06-11 昆明理工大学 Method for dynamically superimposing coupling support on large-section roadway in complicated fault fracture zone
CN105888693A (en) * 2016-06-01 2016-08-24 中国云南路建集团股份公司 Treating construction method for water burst of small underground river of highway tunnel
CN112610227A (en) * 2020-12-14 2021-04-06 山东大学 Rapid construction method for open TBM to penetrate through unfavorable geology

Similar Documents

Publication Publication Date Title
CN102493822B (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN102383828B (en) Refection reducing and outburst eliminating method for deep-hole hydraulic fracture driving gas shallow hole extraction
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN103306714B (en) Coal seam group with near interval Di Chou holes in lane the mash gas harnessing method in a hole three
CN103510957B (en) A kind of combined type coal uncovering method
CN102787846B (en) Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
CN101915105B (en) United method for tunneling super-strong or strong rock burst hole section of TBM construction tunnel
CN103306713B (en) A kind of high prominent coal seam layer-through drilling networking reinforcement means
CN105221168B (en) Shield method tunnel construction portal Water sealing method under the conditions of a kind of rich water is buried
US20180195386A1 (en) Parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence
CN102877857B (en) Deep hole pre-grouting top plate reinforcement method for large-mining height working face under special geological conditions
CN103233742A (en) Treatment measure of bad geological section for long distance pipeline coal conveying
CN203847129U (en) Supporting device used for tunnel construction in weak, fractured and uneven stratum
CN108386193A (en) A kind of hard integrality top plate chemically expansible pressure break pressure relief method in end
CN103089277A (en) Space reinforcing construction technology of sand layer roadway
CN203700978U (en) Box culvert pilot tubal curtain device
AU2015377002A1 (en) Non-coal-pillar gob-side entry retaining method having filling-wall self-elimination
CN103291312A (en) Shield tunneling machine capable of realizing three-dimensional grouting
CN111005740A (en) Method for controlling surrounding rock of upper and lower walls of stope by medium-length hole pre-grouting
CN104179511A (en) Novel hole arrangement grouting method for enabling ground pre-grouting reinforcing roadway to penetrate through surrounding rocks at fault fracture zone
CN104018474B (en) The method in a working tunnel backfill reconstruction maintenance hole
Liu Pillarless mining technology of fully-mechanized top coal caving mining face with retained gateways along goaf
CN204457781U (en) TBM tunnels tunnel fracture slide type rockburst risk relief structure
CN104265329B (en) For steel pipe truss grouting and reinforcing and the supporting and protection structure of heavily stressed weak broken wall rock
CN203130097U (en) Small guide pipe for grouting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Applicant after: Wuhan Design and Research Institute Co., Ltd. pf China Coal Technology & Engineering Group

Address before: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Applicant before: Wuhan Design and Research Institute of China Coal Technology & Engineering Group

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: WUHAN DESIGN AND RESEARCH INSTITUTE OF CHINA COAL TECHNOLOGY + ENGINEERING GROUP TO: WUHAN DESIGN AND RESEARCH INSTITUTE CO., LTD. PF CHINA COAL TECHNOLOGY + ENGINEERING GROUP

C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130807