The preparation method of intubator
Technical field
The present invention relates to a kind of preparation method of carrying out plants planter in concrete revetment structure body.
Background technology
Protection water and soil resources, improving climatic environment, building conservation culture is international research theme.China's slope bulk area is large, and soil property is complicated, collapses serious under the body of existing slope, and slope body function is not good enough; Planting plants how on the body of concrete slope, adopting which kind of instrument is a difficult problem all the time.
Summary of the invention
The object of the present invention is to provide the preparation method of a kind of convenience intubator of planting plants in concrete revetment.
Technical solution of the present invention is:
A preparation method for intubator, is characterized in that: intubator is comprised of egative film, fixture, crab-bolt, four parts of capable ring; It is 1 group that egative film is 2, and 2 ~ 10 groups of plane combinations are 1 frame; Egative film adopts stainless-steel sheet, and length is 10m, and width is 0.5m, thickness is 1cm, on egative film, press 1m spacing, be polished into respectively half circular hole, hole diameter equals kind of a pipe diameter, 2 egative films are 1 group, be spliced to form the circular hole that inserts kind of pipe, every frame surrounding wafer type clamp clamps, the left and right two halves of fixture are fixed by crab-bolt, with the capable boxing that φ 10-15 reinforcing bar is made, be connected on fixture upper end, form intubator.
Described kind pipe is PVC plastic film tube, and diameter is 1.5cm-2cm, and length is >=slope protection concrete structure body thickness+4cm that end 4cm is coniform; First soil is poured in kind of pipe to a part, plant the space of the reserved 0.5cm height in pipe top, then pour into and plant, 2-4 grain, after seed pours into, then row grave mound, grave mound thickness is 0.5cm.
The present invention is easy to make, makes in concrete revetment planting plants very convenient, effective.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described.
Fig. 1 is the structural representation of egative film.
Fig. 2 is the structural representation of kind of pipe.
Embodiment
A preparation method for intubator, intubator is comprised of egative film 1, fixture, crab-bolt, four parts of capable ring; It is 1 group that egative film is 2, and 2 ~ 10 groups of plane combinations are 1 frame; Egative film adopts stainless-steel sheet, and length is 10m, and width is 0.5m, thickness is 1cm, on egative film, press 1m spacing, be polished into respectively half circular hole, hole diameter equals kind of a pipe diameter, 2 egative films are 1 group, be spliced to form the circular hole that inserts kind of pipe, every frame surrounding wafer type clamp clamps, the left and right two halves of fixture are fixed by crab-bolt, with the capable boxing that φ 10-15 reinforcing bar is made, be connected on fixture upper end, form intubator.
Described kind pipe is PVC plastic film tube 2, and diameter is 1.5cm-2cm, and length is >=slope protection concrete structure body thickness+4cm that end 4cm is coniform; First soil 3 is poured in kind of pipe to a part, plant the space of the reserved 0.5cm height in pipe top, then pour into and plant 4,2-4 grain, after seed pours into, then row grave mound, grave mound thickness is 0.5cm.
Planting: after concrete structure body forms, before initial set, after building among 24 hours, the intubator that kind of pipe is housed is inserted in concrete with hammering kind pipe on concrete surface, then dismantle crab-bolt and remove intubator, because kind of a pipe still has head, stay concrete surface surface, so again at kind of a pipe upper surface, cover and press beam slab, with vibrator, vibrate, make in the whole implantation of plant species pipe concrete.