CN103215950B - 回填区桩基接长施工方法 - Google Patents
回填区桩基接长施工方法 Download PDFInfo
- Publication number
- CN103215950B CN103215950B CN201310163114.3A CN201310163114A CN103215950B CN 103215950 B CN103215950 B CN 103215950B CN 201310163114 A CN201310163114 A CN 201310163114A CN 103215950 B CN103215950 B CN 103215950B
- Authority
- CN
- China
- Prior art keywords
- pile
- pile foundation
- construction
- backfilling
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Foundations (AREA)
Abstract
本发明公开了一种回填区桩基接长施工方法,包括以下步骤:a.完成地面以下部分的桩基的施工,并预留桩基钢筋接头;b.于地面以下部分的桩基上砌筑地面以上部分的桩基的护壁;c.于相邻两根桩基的护壁之间进行桩间回填,并同时于钢筋接头上完成桩基钢筋的接长工作;d.继续桩间回填完成至指定高度;e.于护壁内浇筑完成桩基混凝土;f.循环步骤b~e,直至施工至桩基设计标高。本发明采用边成孔、边回填,后浇筑桩基混凝土的工艺,成孔采用砖砌护壁,不仅缩短了施工工期,节约了建设成本,而且还有效解决了回填区接桩后进行回填时,回填施工时给桩身造成的碰撞破坏,并消除了回填料施加给桩身的负摩擦阻力,保证了桩身质量。
Description
技术领域
本发明涉及一种桩基施工,尤其是一种自然地面标高低于桩基顶标高的回填区桩基接长施工方法。
背景技术
贵阳龙洞堡国际机场扩建工程,航站楼地下一层,底板底标高为-10.45米,基础为桩基础,场地自然地面标高最低处为-33.44米,需回填土石方的深度约23米。该23米范围内采用接桩工艺施工。现有的接桩技术为先采用模板将桩基施工完成,后进行桩间回填,该技术方案的缺点是:
1)不能满足工期要求:一个接桩周期需要11天时间(考虑架子模板钢筋施工2天,夜间浇筑混凝土,待早强混凝土上强度3天,拆除模板架子1天;桩间分层回填土每天一层,需要5天)。
2)不能满足设计要求:成桩后进行回填,不能有效解决负摩阻问题,加大了桩身荷载,需重新设计桩径等参数。
3)不能满足质量要求:桩间回填时,碰撞、侧向挤压对桩身产生影响,产生不可预见的破坏。
4)成本较高:采用定型模板进行施工,将带来加工制作费,采购费,机械吊装费等较多费用。
发明内容
本发明所要解决的技术问题是提供一种安全高效、节省施工时间,不会对桩身造成影响及破坏的回填区桩基接长施工方法。
为实现上述技术效果,本发明公开了一种回填区桩基接长施工方法,所述施工方法包括以下步骤:
a.完成地面以下部分的桩基的施工,并预留桩基钢筋接头;
b.于所述地面以下部分的桩基上砌筑地面以上部分的桩基的护壁;
c.于相邻两根桩基的护壁之间进行桩间回填,并同时于所述钢筋接头上完成桩基钢筋的接长工作;
d.继续桩间回填完成至指定高度;
e.于所述护壁内浇筑完成桩基混凝土;
f.循环步骤b~e,直至施工至桩基设计标高。
所述施工方法进一步的改进在于,在施工所述地面以下部分的桩基前包括步骤:
进行地面平整;
进行所述地面以下部分的桩基成孔施工;
于所述成孔内施工所述地面以下部分的桩基。
所述施工方法进一步的改进在于,所述地面以下部分的桩基混凝土高于地面500mm。
所述施工方法进一步的改进在于,所述护壁采用砖模砌筑,所述砖模的厚度为240,每1.5米高处设置一道圈梁。
所述施工方法进一步的改进在于,在进行桩间回填施工时,先回填所述护壁的周身,待完成所述护壁内的所述桩基钢筋接长后,再继续回填相邻两根所述护壁之间。
所述施工方法进一步的改进在于,采用山皮石进行分层回填,分层厚度为0.5m,振动碾压8遍,分层检测达到96%的压实度后,进行下一层回填。
所述施工方法进一步的改进在于,在浇筑所述桩基混凝土前,预先在已硬化的混凝土施工缝处铺一层水泥浆或与所述混凝土内成分相同的水泥砂浆。
本发明由于采用了以上技术方案,使其具有以下有益效果是:采用边成孔、边回填,后浇筑桩基混凝土的工艺,成孔采用砖砌护壁,不仅缩短了施工工期,节约了建设成本,而且还有效解决了回填区接桩后进行回填时,回填施工时给桩身造成的碰撞破坏,并消除了回填料施加给桩身的负摩擦阻力,保证了桩身质量。
附图说明
图1是本发明回填区桩基接长施工方法的施工示意图。
图2是本发明回填区桩基接长施工方法的施工示意图。
图3是本发明回填区桩基接长施工方法的施工示意图。
图4是本发明回填区桩基接长施工方法的施工示意图。
图5是本发明回填区桩基接长施工方法的施工示意图。
图6是本发明回填区桩基接长施工方法的施工示意图。
图7是本发明回填区桩基接长施工方法的施工示意图。
具体实施方式
下面结合附图和具体实施方式对本发明作进一步详细的说明。
参阅图1~7所示,是本发明回填区桩基接长施工方法的施工示意图。主要包括以下步骤:
1、进行地面10平整
现场根据地形,将地面10场平至便于机械布置,采取高挖低填的方法,现场形成“梯田”状地貌,设临时便道,利于材料的运输,如图1所示。
2、进行地面以下部分的桩基11成孔施工,成孔12如图2所示。
3、完成地面以下桩基11的施工,并预留桩基钢筋15的钢筋接头13
于成孔12内施工地面以下桩基11,地面以下桩基11的钢筋15安装时,预留钢筋接头13,其中,桩基中50%的钢筋接头13高于地面600mm,位于同一截面上另外50%的钢筋接头错开35倍的钢筋直径,高于地面1500mm,桩基11混凝土浇筑的施工缝,高于地面500mm,如图3所示。
4、砌筑地面以上部分的桩基护壁14
于地面以下桩基11上采用砖模砌筑地面以上部分的桩基的护壁14,砖模采用M7.5水泥砂浆,长度为240mm水泥砖,C25强度等级的混凝土浇筑圈梁,内配4根Φ12mm三级钢,箍筋Φ8mm,间距200mm,砖模厚度为240mm,每1.5米高处设置圈梁一道,如图4所示。
5、进行桩间回填,并同时完成桩基钢筋15的接长工作
以堆填方式先回填护壁14的周身,形成山丘形状16,回填时采用当地的山皮石进行分层回填,分层厚度0.5m,振动碾压8遍,分层检测达到96%的压实度后,进行第二层回填,如图5所示。
6、待完成护壁14内的桩基钢筋15接长后,再继续回填相邻两根护壁14之间的倒三角形状17的回填区域,回填完成至指定高度,如图6所示。
7、浇筑完成地面以上部分的桩基混凝土
在已硬化的混凝土表面上,清除水泥薄膜和松动的石子以及软弱的混凝土层,同时加以凿毛,用水冲洗干净并充分湿润不少于24h,残留在混凝土表面的积水应予清除,并在施工缝处铺一层水泥浆或与已硬化的混凝土内成分相同的水泥砂浆,如图7所示。
8、循环步骤4~步骤7,直至施工至桩基设计标高,完成施工。
以上结合附图实施例对本发明进行了详细说明,本领域中普通技术人员可根据上述说明对本发明做出种种变化例。因而,实施例中的某些细节不应构成对本发明的限定,本发明将以所附权利要求书界定的范围作为本发明的保护范围。
Claims (6)
1.一种回填区桩基接长施工方法,其特征在于所述施工方法包括以下步骤:
a.完成地面以下部分的桩基的施工,并预留桩基钢筋接头;
b.于所述地面以下部分的桩基上砌筑地面以上部分的桩基的护壁;
c.于相邻两根桩基的护壁之间进行桩间回填,并同时于所述钢筋接头上完成桩基钢筋的接长工作;在进行桩间回填施工时,先回填所述护壁的周身,待完成所述护壁内的所述桩基钢筋接长后,再继续回填相邻两根所述护壁之间的回填区域;
d.继续桩间回填完成至指定高度;
e.于所述护壁内浇筑完成桩基混凝土;
f.循环步骤b~e,直至施工至桩基设计标高。
2.如权利要求1所述的施工方法,其特征在于:在施工所述地面以下部分的桩基前包括步骤:
进行地面平整;
进行所述地面以下部分的桩基成孔施工;
于所述成孔内施工所述地面以下部分的桩基。
3.如权利要求2所述的施工方法,其特征在于:所述地面以下部分的桩基中的混凝土高于地面500mm。
4.如权利要求3所述的施工方法,其特征在于:所述护壁采用砖模砌筑,所述砖模的厚度为240mm,每1.5米高处设置一道圈梁。
5.如权利要求4所述的施工方法,其特征在于:采用山皮石进行分层回填所述护壁的周身,分层厚度为0.5m,振动碾压8遍,分层检测达到96%的压实度后,进行下一层回填。
6.如权利要求5所述的施工方法,其特征在于:在浇筑所述桩基混凝土前,预先在已硬化的混凝土施工缝处铺一层水泥浆。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310163114.3A CN103215950B (zh) | 2013-05-06 | 2013-05-06 | 回填区桩基接长施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310163114.3A CN103215950B (zh) | 2013-05-06 | 2013-05-06 | 回填区桩基接长施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103215950A CN103215950A (zh) | 2013-07-24 |
CN103215950B true CN103215950B (zh) | 2015-04-29 |
Family
ID=48814075
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310163114.3A Active CN103215950B (zh) | 2013-05-06 | 2013-05-06 | 回填区桩基接长施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103215950B (zh) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836221A (zh) * | 2017-01-03 | 2017-06-13 | 江苏工程职业技术学院 | 一种沉井振冲桩复合地基施工工艺 |
CN106836220A (zh) * | 2017-01-03 | 2017-06-13 | 江苏工程职业技术学院 | 一种沉井振冲式型钢‑混凝土桩复合地基施工工艺 |
CN108978697B (zh) * | 2018-08-02 | 2020-08-21 | 五冶集团上海有限公司 | 地坪模板系统及施工方法 |
CN110284432B (zh) * | 2019-06-04 | 2021-06-08 | 中交路桥建设有限公司 | 一种高填方区先施后填桥台施工方法 |
CN110952453B (zh) * | 2019-11-25 | 2021-11-12 | 通号建设集团有限公司 | 一种桥台结构的施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101294384A (zh) * | 2008-07-01 | 2008-10-29 | 北京住总集团有限责任公司 | 桩、柱接口定位装置及其施工方法 |
CN102400470A (zh) * | 2011-08-03 | 2012-04-04 | 中国建筑第二工程局有限公司 | 坡地高层建筑物多平台深基础施工方法 |
CN202865875U (zh) * | 2012-09-06 | 2013-04-10 | 中铁二院工程集团有限责任公司 | 既有加筋土挡墙修复加固构造 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08158360A (ja) * | 1994-12-07 | 1996-06-18 | Nissan Kensetsu Kk | 現場造成杭の余盛コンクリート処理工法 |
JP5181288B2 (ja) * | 2008-11-20 | 2013-04-10 | 清水建設株式会社 | 既存杭と既存基礎とを利用した新設構造物の構造および既存杭と既存基礎とを利用した新設構造物の構築方法 |
-
2013
- 2013-05-06 CN CN201310163114.3A patent/CN103215950B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101294384A (zh) * | 2008-07-01 | 2008-10-29 | 北京住总集团有限责任公司 | 桩、柱接口定位装置及其施工方法 |
CN102400470A (zh) * | 2011-08-03 | 2012-04-04 | 中国建筑第二工程局有限公司 | 坡地高层建筑物多平台深基础施工方法 |
CN202865875U (zh) * | 2012-09-06 | 2013-04-10 | 中铁二院工程集团有限责任公司 | 既有加筋土挡墙修复加固构造 |
Also Published As
Publication number | Publication date |
---|---|
CN103215950A (zh) | 2013-07-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102444142B (zh) | 一种群桩改柱扩建地下室及其施工工法 | |
CN204059124U (zh) | 一种砂桩排水强夯后注浆地基加固结构 | |
CN103215950B (zh) | 回填区桩基接长施工方法 | |
CN105350559B (zh) | 一种适用于大型厂房的金刚砂结构地面的施工方法 | |
CN102966114A (zh) | 塔机基础结构及其施工方法 | |
CN101245602A (zh) | 坑中坑支护体系的施工工艺 | |
CN102071698B (zh) | 基础下翻梁、承台垫层的施工方法 | |
CN104532957B (zh) | 原有建筑增设地下室逆作施工方法 | |
CN102505709A (zh) | 基础预制混凝土模板施工方法 | |
CN109648696A (zh) | 钢筋连接的边坡预制格构梁及其制作方法和施工方法 | |
CN214993554U (zh) | 一种水利工程的边坡加固结构 | |
CN110004991A (zh) | 基于外凸式翼脚板的地下结构抗浮体系及构建方法 | |
CN107816056A (zh) | 填充式混凝土重力挡土墙及其施工工艺 | |
CN109680671A (zh) | 一种基于建筑垃圾的液化地基处理方法 | |
CN109706952A (zh) | 大型沉井施工方法 | |
CN111676987A (zh) | 振冲浆夯法建筑肥槽回填施工方法 | |
CN104328790A (zh) | 现浇喷射混凝土暗承台及暗地梁胎模 | |
CN104963348B (zh) | 一种软土地区塔吊基础施工支护结构及其施工方法 | |
CN204000848U (zh) | 一种用于水下施工的嵌岩桩 | |
CN102359101A (zh) | 一种湿陷性土的地基处理方法 | |
CN104563497A (zh) | 一种新型有梁板支撑施工方法 | |
CN102535493B (zh) | 一种倒置式基础梁的施工方法 | |
CN205975653U (zh) | 一种土胎模施工的独立承台结构 | |
CN103821149A (zh) | 大型深基坑留坡挖土及坑中坑混凝土后浇施工工法 | |
CN204370463U (zh) | 超软土砖胎模辅助承台结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |