CN103174130B - A kind of layer of sand anti-collapse method of Punching Borehole Cast-in-place Concrete Pile - Google Patents
A kind of layer of sand anti-collapse method of Punching Borehole Cast-in-place Concrete Pile Download PDFInfo
- Publication number
- CN103174130B CN103174130B CN201110430984.3A CN201110430984A CN103174130B CN 103174130 B CN103174130 B CN 103174130B CN 201110430984 A CN201110430984 A CN 201110430984A CN 103174130 B CN103174130 B CN 103174130B
- Authority
- CN
- China
- Prior art keywords
- hole
- sand
- serosity
- layer
- hole wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses the anti-collapse method of the layer of sand of a kind of Punching Borehole Cast-in-place Concrete Pile。The mud of stock tank mix cement and is sufficiently mixed, making serosity;In the process of punched hole construction, by the slurry filling made in hole;After the bonding of the serosity bottom hole and sand grains, its pumping is entered sedimentation tank filter sand, and send into stock tank and again make;Enforcement is circulated continuously according to above-mentioned steps。The present invention takes full advantage of the bonding capacity of cement, on the one hand by penetrating into the serosity of hole wall, adds the bond between the granule of hole wall layer of sand, makes the stability of hole wall significantly be strengthened, effectively prevent hole wall collapse during punched hole construction;On the other hand, the sandstone bonding effect bottom serosity and hole is better, can all be taken out of by bottom sandstone, it is ensured that construction quality。It addition, the present invention selects to adopt cement to improve conventional mud performance, have and draw materials conveniently, lower-cost advantage;And the serosity made has the advantages such as easy to make, good stability, viscosity are easily controllable。
Description
Technical field
The present invention relates to technical field of buildings, particularly the anti-collapse method of the layer of sand of a kind of Punching Borehole Cast-in-place Concrete Pile。
Background technology
Along with the development of national economy, urban construction is advanced by leaps and bounds, and Development of High-rise Buildings is rapid, and the concrete pouring of punched hole piles of many ultra-deep is arisen at the historic moment。According to its construction characteristic, there is shortage cementing power, the problem that during punched hole construction, hole wall easily caves between the granule of layer of sand。At present, adopting the anti-collapse method of perfusion conventional mud in construction, effect is extremely undesirable, it is easy to causes hole wall collapse, necking down, expansion neck, directly affects the construction quality of pile foundation, the Stability Analysis of Structures of whole building certainly will be caused tremendous influence。
Summary of the invention
The technical problem to be solved in the present invention is: provides one to increase layer of sand intergrain bond power, strengthens wall stability, it is ensured that the anti-collapse method of layer of sand of the Punching Borehole Cast-in-place Concrete Pile of construction quality, to overcome the deficiencies in the prior art。
First the present invention is achieved in that, mixes cement and is sufficiently mixed, make serosity in the mud of stock tank;Then, in the process of punched hole construction, by the slurry filling made in hole;Finally, after the bonding of the serosity bottom hole and sandstone, its pumping is entered sedimentation tank filter sand, and send into stock tank and again make;Enforcement is circulated continuously, it is prevented that in punched hole construction, hole wall layer of sand caves according to above-mentioned steps。
In the anti-collapse method of layer of sand of above-mentioned Punching Borehole Cast-in-place Concrete Pile, described cement weight accounts for the 2%~5% of mud weight。
In the anti-collapse method of layer of sand of aforesaid Punching Borehole Cast-in-place Concrete Pile, being equipped with steel pile casting in aperture, steel pile casting is above the ground level more than 0.8m。
Owing to have employed technique scheme, compared with the prior art, the present invention takes full advantage of the bonding capacity of cement, mixes cement production systD serosity in conventional mud。On the one hand by penetrating into the serosity of hole wall, add the bond between the granule of hole wall layer of sand, make the stability of hole wall significantly be strengthened, effectively prevent hole wall collapse during punched hole construction;On the other hand, the sandstone bonding effect bottom serosity and hole is better, can all be taken out of by bottom sandstone, it is ensured that construction quality。It addition, the present invention selects to adopt cement to improve conventional mud performance, relative to the method that routine uses additive, have and draw materials conveniently, lower-cost advantage;And the serosity made has the advantages such as easy to make, good stability, viscosity are easily controllable。
Accompanying drawing illustrates:
Fig. 1 is the schematic diagram implementing the present invention;
Being labeled as of accompanying drawing: 1-punching apparatus, 2-hole wall, 3-sedimentation tank, 4-stock tank。
Detailed description of the invention:
Embodiments of the invention: the present invention implement time as it is shown in figure 1, build at least one sedimentation tank 3 and stock tank 4 by the stake holes of Punching Borehole Cast-in-place Concrete Pile。First, mixing existing commercially available cement in the mud of stock tank 4 and be sufficiently mixed, making serosity, the slurry viscosity produced can reach 25~30S。Then, adopting existing commercially available punching apparatus 1 to be punched out in the process of construction, by the slurry filling made in hole;Finally, after the bonding of the serosity bottom hole and sandstone, its pumping is entered sedimentation tank 3 filter sand, and send into stock tank 4 and again make;(serosity in hole must keep circulation continuously, it is to avoid the sand sedimentation in serosity, solidification) enforcement is circulated continuously, it is prevented that in punched hole construction, hole wall layer of sand caves according to above-mentioned steps。In order to make the serosity bonding effect made better, it is adapted in use to, cement weight can be accounted for the 2%~5% of mud weight and make。In order to make serosity to forming enough pressure in hole, prevent hole wall layer of sand in punched hole construction from caving in further, existing commercially available steel pile casting can be installed in aperture, steel pile casting is installed beyond ground more than 0.8m。
Claims (2)
1. the anti-collapse method of the layer of sand of a Punching Borehole Cast-in-place Concrete Pile, it is characterised in that: first, mixing cement and be sufficiently mixed in the mud of stock tank, making serosity, described cement weight accounts for the 2%~5% of mud weight;Then, in the process of punched hole construction, by the slurry filling made in hole;Finally, after the bonding of the serosity bottom hole and sandstone, its pumping is entered sedimentation tank filter sand, and send into stock tank and again make;Enforcement is circulated continuously, it is prevented that in punched hole construction, hole wall layer of sand caves according to above-mentioned steps。
2. the anti-collapse method of the layer of sand of Punching Borehole Cast-in-place Concrete Pile according to claim 1, it is characterised in that: be equipped with steel pile casting in aperture, steel pile casting is above the ground level more than 0.8m。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110430984.3A CN103174130B (en) | 2011-12-21 | 2011-12-21 | A kind of layer of sand anti-collapse method of Punching Borehole Cast-in-place Concrete Pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110430984.3A CN103174130B (en) | 2011-12-21 | 2011-12-21 | A kind of layer of sand anti-collapse method of Punching Borehole Cast-in-place Concrete Pile |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103174130A CN103174130A (en) | 2013-06-26 |
CN103174130B true CN103174130B (en) | 2016-06-22 |
Family
ID=48634285
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110430984.3A Active CN103174130B (en) | 2011-12-21 | 2011-12-21 | A kind of layer of sand anti-collapse method of Punching Borehole Cast-in-place Concrete Pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103174130B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107489143A (en) * | 2017-08-30 | 2017-12-19 | 中建四局第建筑工程有限公司 | A kind of concrete pouring of punched hole piles structure and its plain fill layer leakproof paste-making method |
CN108301403A (en) * | 2018-01-04 | 2018-07-20 | 中国建筑第八工程局有限公司 | Subway drilling cast-in-place pile construction method |
CN109113056A (en) * | 2018-09-04 | 2019-01-01 | 中铁大桥局集团有限公司 | A method of preventing bored pile construction process middle hole wall and collapses |
CN111302710A (en) * | 2020-03-03 | 2020-06-19 | 中国五冶集团有限公司 | Large-diameter overlong punching slurry in dense pebble bed area |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1075521A (en) * | 1993-02-23 | 1993-08-25 | 何庆林 | Pile-making method of concrete-cast drillhole |
CN1101392A (en) * | 1993-10-06 | 1995-04-12 | 刘孝先 | Pouring process for reinforced concrete piles |
CN1274788A (en) * | 2000-05-24 | 2000-11-29 | 王平 | Continuous wall constructing method including drilling holes and late grouting |
RU2270899C2 (en) * | 2004-04-22 | 2006-02-27 | Общество с ограниченной ответственностью "Магнит" | Method and device for concrete mix treatment during bored pile erection |
-
2011
- 2011-12-21 CN CN201110430984.3A patent/CN103174130B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1075521A (en) * | 1993-02-23 | 1993-08-25 | 何庆林 | Pile-making method of concrete-cast drillhole |
CN1101392A (en) * | 1993-10-06 | 1995-04-12 | 刘孝先 | Pouring process for reinforced concrete piles |
CN1274788A (en) * | 2000-05-24 | 2000-11-29 | 王平 | Continuous wall constructing method including drilling holes and late grouting |
RU2270899C2 (en) * | 2004-04-22 | 2006-02-27 | Общество с ограниченной ответственностью "Магнит" | Method and device for concrete mix treatment during bored pile erection |
Non-Patent Citations (1)
Title |
---|
"水泥粘土浆在地下的固结与硬化";李东 等;《水利技术监督》;19990228;第7卷(第2期);第15-第16页 * |
Also Published As
Publication number | Publication date |
---|---|
CN103174130A (en) | 2013-06-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2018184254A1 (en) | Carbonization mixing pile-ventilating pipe pile composite foundation and construction method thereof | |
CN103174130B (en) | A kind of layer of sand anti-collapse method of Punching Borehole Cast-in-place Concrete Pile | |
CN103485345A (en) | Construction method for covering layer closed porthole high-pressure curtain grouting | |
CN102011399A (en) | PHC pile-based multiple high jet pedestal pile construction method | |
CN102900079A (en) | High-frequency hydraulic vibratory construction method for cement-soil core-inserted combined pile | |
CN103437348A (en) | Construction device and method of pile peripheral cemented soil cast-in-place stiffness core pile | |
CN105297710A (en) | High-pressure-jetting cement soil twist drill and reamed reinforced concrete grouting combined pile and manufacturing method | |
CN110230314B (en) | Pile foundation structure and construction method thereof | |
CN201660880U (en) | Double-shaft stirring pile envelop enclosure structure with cast-in place piles driven internally | |
CN201321614Y (en) | Retaining structure of precast reinforced concrete beam cement-soil piling wall | |
CN110130836B (en) | Double-tube spiral drill bit for cast-in-situ cement soil composite foundation and construction method thereof | |
CN202123569U (en) | Device for recycling residual slurry of pretensioning prestressed concrete pipe piles | |
CN101250885A (en) | Construction method for reinforcing subway station side soil body | |
CN205100208U (en) | Crowded, reaming reinforced concrete bored concrete pile composite pile of high water spray earth anger | |
CN204278207U (en) | Concrete tubular pile material filling system | |
CN103603345B (en) | Cement mixing grouting pile foundations and forming method | |
CN202644518U (en) | Post-inserted reinforcement cage cement fly ash gravel pile | |
CN210087248U (en) | Double-pipe spiral drill bit for cast-in-situ cement soil composite foundation | |
CN102605775B (en) | Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method | |
CN105507338B (en) | A kind of campshed grafting rubble formula supporting water blockoff diaphragm wall is molded engineering method | |
CN205205811U (en) | Drilling bit of deep submerged agitation pile | |
CN104831706B (en) | A kind of reinforcement means of red mud dump | |
CN103171021A (en) | Method for enhancing concrete strength, improving volume stability and reducing cracking | |
CN204401614U (en) | A kind of MC stiff composite pile | |
CN201738324U (en) | Project pile deflection prevention structure used on soft soil foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180314 Address after: 523000 Guangdong city of Dongguan Province East Industrial Park City Park Jiangnan Avenue East Patentee after: Guangdong Zhongjian new type building component Co., Ltd. Address before: Ganping Gan Yin Tong Road 550006 Guizhou city of Guiyang province No. 4 Patentee before: China Construction Fourth Engineering Bureau Ltd. |