CN103174124A - On-site overlapping lay-out method of vertical sand-protecting barriers - Google Patents

On-site overlapping lay-out method of vertical sand-protecting barriers Download PDF

Info

Publication number
CN103174124A
CN103174124A CN2012102325329A CN201210232532A CN103174124A CN 103174124 A CN103174124 A CN 103174124A CN 2012102325329 A CN2012102325329 A CN 2012102325329A CN 201210232532 A CN201210232532 A CN 201210232532A CN 103174124 A CN103174124 A CN 103174124A
Authority
CN
China
Prior art keywords
sand
continued access
foundation pile
barrier
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012102325329A
Other languages
Chinese (zh)
Other versions
CN103174124B (en
Inventor
李生宇
王海峰
谷峰
雷加强
徐新文
何志辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Institute of Ecology and Geography of CAS
Original Assignee
Xinjiang Institute of Ecology and Geography of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Institute of Ecology and Geography of CAS filed Critical Xinjiang Institute of Ecology and Geography of CAS
Priority to CN201210232532.9A priority Critical patent/CN103174124B/en
Publication of CN103174124A publication Critical patent/CN103174124A/en
Application granted granted Critical
Publication of CN103174124B publication Critical patent/CN103174124B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to an on-site overlapping lay-out method of vertical sand-protecting barriers. According to the on-site overlapping lay-out method of the vertical sand-protecting barriers, a foundation file laid out primarily and a continuing connection pile overlapped and laid out in a later period of the vertical sand-protecting barriers are connected together through a continuing connection sleeve barrel, the sand-protecting barriers are respectively fixed on the foundation pile and the continuing connection pile, the sand-protecting barrier matched with the foundation pile is higher, and the sand-protecting barrier matched with the continuing connection pile is lower. By means of the method, on-site vertical overlapping lay-out of the vertical sand-protecting barriers is realized, the protection benefits of the vertical sand-protecting barriers are fully utilized, the sand-blocking amount of the vertical sand-protecting barriers is multiplied, and the sand prevention cost is lowered. The on-site overlapping lay-out method of the vertical sand-protecting barriers can be widely applied to machinery sand prevention engineering in all areas, and largely improves the protection benefits.

Description

A kind of vertical sand barrier original place stack distribution method
Technical field
The present invention relates to a kind of sand control engineering method, be specifically related to a kind of vertical sand barrier original place stack distribution method.
Background technology
Defending and controlling sand is the important leverage of husky district socio-economic development.Compare with controlling sediment by plant and chemical sand control, the mechanical sand control measure has advantages of that one-time investment is little, does not need water resource, abominable, the remote area of suitable ambient conditions, the first-selected control measures of sand control engineering, as the measure in advance of dune-fixating forestation or sand damage severely afflicated area independently measures for sand prevention be widely used.
Sand-protecting barrier is important mechanical sand control measure, and according to height, sand-protecting barrier can be divided into vertical sand barrier, half concealed type sand-protecting barrier and concealed type sand-protecting barrier.Vertical sand barrier is important mechanical sand control measure, and the material of use has straw and plastic wire.Seriously regional in hazards of sand storms, mechanical measures for sand prevention must be laid in the original place again every several years, for vertical sand barrier, was mostly again to lay on the sand body of certain distance before and after original sand-protecting barrier spud pile.Learn principle according to geometry and aeolian landform, the husky amount of the resistance that the stack of vertical sand barrier original position is laid is maximum, and the protection life-span is long, and the engineering cost of the husky amount of unit resistance is corresponding significantly to be reduced.The various sand-protecting barrier spud piles that use at present can't connect each other, have simultaneously vertical sand barrier height all higher (1-1.2m) now, and when stack was laid with sand body top, wind resistance was too large, causes sand-protecting barrier unstable.
Lay the problem that exists for above vertical sand barrier, the invention provides a kind of vertical sand barrier original place stack distribution method.
Summary of the invention
The object of the invention is, a kind of vertical sand barrier original place stack distribution method is provided, the method is with the continued access stake of the first foundation pile of laying of sand-protecting barrier and later stage stack laying, by the continued access sleeve, both are coupled together, sand-protecting barrier is separately fixed in foundation pile and continued access stake, the sand-protecting barrier height that matches with foundation pile is higher, and the sand-protecting barrier height that matches with the continued access stake is less.Adopt the method can realize layings that vertically superpose of vertical sand barrier original position, can take full advantage of the protection benefit of the husky body of sand-protecting barrier resistance, husky the measuring of sand-protecting barrier resistance is multiplied, the sand prevention cost.The method can be widely used in the mechanical sediment control structure of all regions, can significantly improve protection benefit.
A kind of vertical sand barrier of the present invention original place stack distribution method, a kind of continued access vertical sand barrier spud pile that relates in the method is comprised of foundation pile, continued access stake, continued access sleeve, stator, sand-protecting barrier and screw, and concrete operations follow these steps to carry out:
A, insert underground (9) with foundation pile (1) is most advanced and sophisticated vertical, the degree of depth is 30-50cm, and between foundation pile, spacing distance is 4-8m;
B, sand-protecting barrier (6) is adjacent to foundation pile (1), compresses sand-protecting barrier with stator (4), pass hole (8) on stator (4) with screw (5), insert foundation pile (1) and go up hole (7), tighten;
Or sand-protecting barrier (6) two ends are arranged bagging, and be provided with hangnail on foundation pile (1) outer wall, the bagging on sand-protecting barrier (6) is enclosed within on foundation pile (1);
c, when sand-protecting barrier both sides amount of drift sand near after saturated, continued access sleeve (3) is inserted in foundation pile (1) top, rotation continued access sleeve (3), make hole (11) alignment of hole (7) and continued access sleeve (3) bottom on foundation pile (1) top, fixing by screw (5), again continued access stake (2) one ends are inserted in continued access sleeve (3), rotation continued access stake (2), make hole (11) alignment on hole (10) and continued access sleeve (3) top of continued access stake (2) bottom, fixing by screw (5), again sand-protecting barrier (6) is adjacent to continued access stake (2), compress sand-protecting barrier with stator (4), pass hole (8) on stator (4) with screw (5), tighten in the hole (10) of inserting in the upper hole (7) of foundation pile (1) and continued access stake (2), or the bagging of sand-protecting barrier (6) is enclosed within continued access stake (2),
D, after sand-protecting barrier collection sand reaches capacity again, again superposeing by step c gets final product.
One end of the foundation pile (1) in the continued access vertical sand barrier spud pile that relates in described method is cone-shaped, the other end is the flat-top shape, foundation pile (1) length be the sand-protecting barrier height 1.5-1.6 doubly, be provided with fixing hole (7) on foundation pile (1), foundation pile (1) outer wall is smooth or be provided with hangnail.
Continued access stake (2) two ends in the continued access vertical sand barrier spud pile that relates in described method are all the flat-top stake, are provided with fixing hole (10) in continued access stake (2), and the length of continued access stake (2) is the height of supporting installation sand-protecting barrier.
The long 10-15cm of continued access sleeve (3) in the continued access vertical sand barrier spud pile that relates in described method, continued access sleeve (3) is provided with fixing hole (11), by the corresponding connection of fixing hole (7) on screw (5) and foundation pile (1).
Stator (4) in the continued access vertical sand barrier spud pile that relates in described method is provided with fixing hole (8), is provided with the corresponding connection of fixing hole (7) by screw (5) and foundation pile (1).
Each fixing hole above foundation pile (1) in the continued access vertical sand barrier spud pile that relates in described method, continued access stake (2), continued access sleeve (3) and stator (4) is for being on the same line.
The sand-protecting barrier (6) that matches with foundation pile (1) in the continued access vertical sand barrier spud pile that relates in described method highly is 60-120cm, and the sand-protecting barrier height that matches with continued access stake (2) is 20-40cm.
The material of the foundation pile (1) in the continued access vertical sand barrier spud pile that relates in described method, continued access stake (2), continued access sleeve (3), stator (4) is wooden, irony, aluminium alloys, anti-aging organic material or metal/organic/inorganic mixed material, the profile of foundation pile (1), continued access stake (2), continued access sleeve (3) can for cylindrical, be square or other shape.
Method of the present invention can realize sand-protecting barrier original place stack laying, can take full advantage of the wind prevention and sand resistance benefit of sand-protecting barrier sand body, can increase exponentially the husky amount of sand-protecting barrier resistance, extends the application life of protection system, and reduction synthetical sand-prevention cost.
Description of drawings
Fig. 1 is structural representation of the present invention
Fig. 2 is foundation pile structural representation of the present invention;
Fig. 3 is continued access pilework schematic diagram of the present invention;
Fig. 4 is continued access tube-in-tube structure schematic diagram of the present invention;
Fig. 5 is sand-protecting barrier fixture structure schematic diagram of the present invention;
Fig. 6 is sand-protecting barrier spud pile continued access ideograph of the present invention.
The specific embodiment
Further describe below in conjunction with accompanying drawing, and provide embodiment.
Embodiment 1
A kind of vertical sand barrier of the present invention original place stack distribution method, a kind of continued access vertical sand barrier spud pile that relates in the method is comprised of foundation pile 1, continued access stake 2, continued access sleeve 3, stator 4, sand-protecting barrier 6 and screw 5, one end of foundation pile 1 is cone-shaped, the other end is the flat-top shape, foundation pile 1 length is 1.5 times of sand-protecting barrier height, is provided with fixing hole 7 on foundation pile 1; Continued access stake 2 two ends are all the flat-top shape, are provided with fixing hole 10 in continued access stake 2, and the length of continued access stake 2 is the height of supporting installation sand-protecting barrier; The long 15cm of continued access sleeve 3, continued access sleeve 3 is provided with fixing hole 11; By screw 5 and the corresponding connection of fixing hole 7 on foundation pile 1; Stator 4 is provided with fixing hole 8, the corresponding connection of fixing hole 10 on being provided with fixing hole 7 and the continued access stake is connected by screw 5 and foundation pile 1; The sand-protecting barrier 6 that matches with foundation pile 1 highly is 120cm, and the sand-protecting barrier height that matches with continued access stake 2 is 40cm, and concrete operations follow these steps to carry out:
A, vertically insert undergroundly 9 with foundation pile 1 is most advanced and sophisticated, its degree of depth is 50cm, and between foundation pile, spacing distance is 4m;
B, sand-protecting barrier 6 is adjacent to foundation pile 1, compresses sand-protecting barriers with stator 4, pass hole 8 on stator 4 with screw 5, on insertion foundation pile 1, fixing hole 7 is tightened;
C, when sand-protecting barrier both sides amount of drift sand near after saturated, continued access sleeve 3 is inserted in foundation pile 1 top, rotation continued access sleeve 3 makes the fixing hole 7 on foundation pile 1 top and fixing hole 11 alignment of continued access sleeve 3 bottoms, and is fixing by screw 5; Continued access stake 2 one ends are inserted in continued access sleeves 3, rotation continued access stake 2 makes the fixing hole 10 of continued access stake 2 bottoms and fixing hole 11 alignment on continued access sleeve 3 tops, and is fixing by screw 5 again; Again sand-protecting barrier 6 is adjacent to continued access stake 2, compresses sand-protecting barriers with stator 4, pass fixing hole 8 on stator 4 with screw 5, the fixing hole 10 on insertion foundation pile 1 in fixing hole 7 and continued access stake 2 is tightened;
D, after sand-protecting barrier collection sand reaches capacity again, again superposeing by step c gets final product.
Embodiment 2:
A kind of vertical sand barrier of the present invention original place stack distribution method, a kind of continued access vertical sand barrier spud pile that relates in the method is comprised of foundation pile 1, continued access stake 2, continued access sleeve 3, stator 4, sand-protecting barrier 6 and screw 5, one end of foundation pile 1 is cone-shaped, the other end is the flat-top shape, foundation pile 1 length is 1.6 times of sand-protecting barrier height, is provided with fixing hole 7 on foundation pile 1; Continued access stake 2 two ends are all the flat-top shape, are provided with fixing hole 10 in continued access stake 2, and the length of continued access stake 2 is the height of supporting installation sand-protecting barrier; The long 10cm of continued access sleeve 3, continued access sleeve 3 is provided with fixing hole 11, by screw 5 and the corresponding connection of fixing hole 7 on foundation pile 1; Stator 4 is provided with fixing hole 8, is provided with the corresponding connection of fixing hole 7 by screw 5 and foundation pile 1, and the sand-protecting barrier 6 that matches with foundation pile 1 highly is 60cm, and the sand-protecting barrier height that matches with continued access stake 2 is 20cm, and concrete operations follow these steps to carry out:
A, vertically insert undergroundly 9 with foundation pile 1 is most advanced and sophisticated, its degree of depth is 30cm, and between foundation pile, spacing distance is 8m;
B, sand-protecting barrier 6 is adjacent to foundation pile 1, compresses sand-protecting barriers with stator 4, pass hole 8 on stator 4 with screw 5, on insertion foundation pile 1, fixing hole 7 is tightened;
c, when sand-protecting barrier both sides amount of drift sand near after saturated, continued access sleeve 3 is inserted in foundation pile 1 top, rotation continued access sleeve 3, make the fixing hole 7 on foundation pile 1 top and fixing hole 11 alignment of continued access sleeve 3 bottoms, fixing by screw 5, continued access stake 2 one ends are inserted in continued access sleeve 3, rotation continued access stake 2, make the fixing hole 10 of continued access stake 2 bottoms and fixing hole 11 alignment on continued access sleeve 3 tops, fixing by screw 5, again sand-protecting barrier 6 two ends are adjacent to continued access stake 2, compress sand-protecting barrier with stator 4, pass fixing hole 8 on stator 4 with screw 5, fixing hole 10 on insertion foundation pile 1 in fixing hole 7 and continued access stake 2 is tightened,
D, after sand-protecting barrier collection sand reaches capacity again, again superposeing by step c gets final product.
Embodiment 3:
a kind of vertical sand barrier of the present invention original place stack distribution method, a kind of continued access vertical sand barrier spud pile that relates in the method is by foundation pile 1, continued access stake 2, continued access sleeve 3, stator 4, sand-protecting barrier 6 and screw 5 form, one end of foundation pile 1 is cone-shaped, the other end is the flat-top shape, foundation pile 1 length is 1.6 times of sand-protecting barrier height, be provided with fixing hole 7 on foundation pile 1, continued access stake 2 two ends are all the flat-top shape, be provided with fixing hole 10 in continued access stake 2, the length of continued access stake 2 is the height of supporting installation sand-protecting barrier, the long 10cm of continued access sleeve 3, continued access sleeve 3 is provided with fixing hole 11, by screw 5 and the corresponding connection of fixing hole 7 on foundation pile 1, stator 4 is provided with fixing hole 8, be provided with the corresponding connection of fixing hole 7 by screw 5 and foundation pile 1, the sand-protecting barrier 6 that matches with foundation pile 1 highly is 100cm, the sand-protecting barrier height that matches with continued access stake 2 is 30cm, concrete operations follow these steps to carry out:
A, vertically insert undergroundly 9 with foundation pile 1 is most advanced and sophisticated, its degree of depth is 40cm, and between foundation pile, spacing distance is 6m;
B, the two ends of sand-protecting barrier 6 are arranged the installation bagging, be provided with hangnail (preventing the sand-protecting barrier slippage) on foundation pile 1 outer wall, the bagging on sand-protecting barrier 6 is enclosed within on foundation pile 1;
C, when sand-protecting barrier both sides amount of drift sand near after saturated, continued access sleeve 3 is inserted in foundation pile 1 top, rotation continued access sleeve 3, make the fixing hole 7 on foundation pile 1 top and fixing hole 11 alignment of continued access sleeve 3 bottoms, fixing by screw 5, then continued access stake 2 one ends are inserted in continued access sleeves 3, rotation continued access stake 2, make the fixing hole 10 of continued access stake 2 bottoms and fixing hole 11 alignment on continued access sleeve 3 tops, fixing by screw 5, then the bagging on sand-protecting barrier 6 is enclosed within continued access stake (2);
D, after sand-protecting barrier collection sand reaches capacity again, again superposeing by step c gets final product.
Foundation pile 1 in the continued access vertical sand barrier spud pile that relates in the method for the invention, continued access stake 2, continued access sleeve 3 and each fixing hole above stator 4 all are on the same line; The material of foundation pile 1, continued access stake 2, continued access sleeve 3, stator 4 is wooden, irony, aluminium alloys, anti-aging organic material or metal/organic/inorganic mixed material, the profile of foundation pile 1, continued access stake 2, continued access sleeve 3 can for cylindrical, be square or other shape.

Claims (8)

1. a vertical sand barrier original place stack distribution method, is characterized in that a kind of continued access vertical sand barrier spud pile that relates in the method is comprised of foundation pile, continued access stake, continued access sleeve, stator, sand-protecting barrier and screw, and concrete operations follow these steps to carry out:
A, insert underground (9) with foundation pile (1) is most advanced and sophisticated vertical, the degree of depth is 30-50cm, and between foundation pile, spacing distance is 4-8m;
B, sand-protecting barrier (6) is adjacent to foundation pile (1), compresses sand-protecting barrier with stator (4), pass hole (8) on stator (4) with screw (5), insert foundation pile (1) and go up hole (7), tighten;
Or the two ends of sand-protecting barrier (6) are arranged bagging, and be provided with hangnail on foundation pile (1) outer wall, the bagging at sand-protecting barrier (6) two ends is enclosed within on foundation pile (1);
c, when sand-protecting barrier both sides amount of drift sand near after saturated, continued access sleeve (3) is inserted in foundation pile (1) top, rotation continued access sleeve (3), make hole (11) alignment of hole (7) and continued access sleeve (3) bottom on foundation pile (1) top, fixing by screw (5), again continued access stake (2) one ends are inserted in continued access sleeve (3), rotation continued access stake (2), make hole (11) alignment on hole (10) and continued access sleeve (3) top of continued access stake (2) bottom, fixing by screw (5), again sand-protecting barrier (6) is adjacent to continued access stake (2), compress sand-protecting barrier with stator (4), pass hole (8) on stator (4) with screw (5), insert the hole (10) on the upper hole (7) of foundation pile (1) and continued access stake (2) top, tighten, or the installation bagging of sand-protecting barrier (6) is enclosed within continued access stake (2),
D, after sand-protecting barrier collection sand reaches capacity again, again superposeing by step c gets final product.
2. the method for claim 1, one end of the foundation pile (1) in the continued access vertical sand barrier spud pile that it is characterized in that relating in described method is cone-shaped, the other end is the flat-top shape, foundation pile (1) length is 1.5-1.6 times of sand-protecting barrier height, be provided with fixing hole (7) on foundation pile (1), foundation pile (1) outer wall is smooth or be provided with hangnail.
3. method as claimed in claim 2, continued access stake (2) two ends in the continued access vertical sand barrier spud pile that it is characterized in that relating in described method are all the flat-top stake, be provided with fixing hole (10) in continued access stake (2), the length of continued access stake (2) is the height of supporting installation sand-protecting barrier.
4. method as claimed in claim 3, the long 10-15cm of continued access sleeve (3) in the continued access vertical sand barrier spud pile that it is characterized in that relating in described method, continued access sleeve (3) is provided with fixing hole (11), by the corresponding connection of fixing hole (7) on screw (5) and foundation pile (1).
5. method as claimed in claim 4, the stator (4) in the continued access vertical sand barrier spud pile that it is characterized in that relating in described method is provided with fixing hole (8), is provided with the corresponding connection of fixing hole (7) by screw (5) and foundation pile (1).
6. each fixing hole above method as claimed in claim 5, the foundation pile (1) in the continued access vertical sand barrier spud pile that it is characterized in that relating in described method, continued access stake (2), continued access sleeve (3) and stator (4) all is on the same line.
7. method as claimed in claim 6, the sand-protecting barrier (6) that matches with foundation pile (1) in the continued access vertical sand barrier spud pile that it is characterized in that relating in described method highly are 60-120cm, and the sand-protecting barrier height that matches with continued access stake (2) is 20-40cm.
8. method as claimed in claim 7, the material of the foundation pile (1) in the continued access vertical sand barrier spud pile that it is characterized in that relating in described method, continued access stake (2), continued access sleeve (3), stator (4) is wooden, irony, aluminium alloys, anti-aging organic material or metal/organic/inorganic mixed material, the profile of foundation pile (1), continued access stake (2), continued access sleeve (3) can for cylindrical, be square or other shape.
CN201210232532.9A 2012-07-06 2012-07-06 On-site overlapping lay-out method of vertical sand-protecting barriers Active CN103174124B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210232532.9A CN103174124B (en) 2012-07-06 2012-07-06 On-site overlapping lay-out method of vertical sand-protecting barriers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210232532.9A CN103174124B (en) 2012-07-06 2012-07-06 On-site overlapping lay-out method of vertical sand-protecting barriers

Publications (2)

Publication Number Publication Date
CN103174124A true CN103174124A (en) 2013-06-26
CN103174124B CN103174124B (en) 2015-02-25

Family

ID=48634279

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210232532.9A Active CN103174124B (en) 2012-07-06 2012-07-06 On-site overlapping lay-out method of vertical sand-protecting barriers

Country Status (1)

Country Link
CN (1) CN103174124B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103541341A (en) * 2013-11-04 2014-01-29 中国科学院新疆生态与地理研究所 Repeatedly utilized grass grid sand fixing method
CN103835279A (en) * 2013-10-20 2014-06-04 娄志平 Construction method of hung-bag-shaped high vertical sediment retaining net fixing mobile dune
CN104060599A (en) * 2014-06-16 2014-09-24 娄志平 Overlapping splicing type sand blocking net and construction method thereof
CN105780674A (en) * 2016-02-02 2016-07-20 中国科学院寒区旱区环境与工程研究所 Lifting type wind prevention and sand resistance dike suitable for most leading edge of wind-sand protection system
CN110387835A (en) * 2019-08-06 2019-10-29 中铁西北科学研究院有限公司 Assembled dredges sand stop wall

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1150449A (en) * 1997-07-31 1999-02-23 Denki Kagaku Kogyo Kk Coupling method for steel pipe
CA2295788A1 (en) * 1999-01-15 2000-07-15 Richard D. Ruiz, Llc Pipe pier system
CN2672112Y (en) * 2004-01-05 2005-01-19 陈传标 Plastic sand blocking net
CN2709521Y (en) * 2004-06-24 2005-07-13 孙显科 Vertical string hanging sand-protecting barrier of 3D foldable connecting wide-strip polymer net piece
CN201933486U (en) * 2011-01-08 2011-08-17 常州市鹏腾土工复合材料工程有限公司 Wind-proof and sand-fixing pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1150449A (en) * 1997-07-31 1999-02-23 Denki Kagaku Kogyo Kk Coupling method for steel pipe
CA2295788A1 (en) * 1999-01-15 2000-07-15 Richard D. Ruiz, Llc Pipe pier system
CN2672112Y (en) * 2004-01-05 2005-01-19 陈传标 Plastic sand blocking net
CN2709521Y (en) * 2004-06-24 2005-07-13 孙显科 Vertical string hanging sand-protecting barrier of 3D foldable connecting wide-strip polymer net piece
CN201933486U (en) * 2011-01-08 2011-08-17 常州市鹏腾土工复合材料工程有限公司 Wind-proof and sand-fixing pile

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103835279A (en) * 2013-10-20 2014-06-04 娄志平 Construction method of hung-bag-shaped high vertical sediment retaining net fixing mobile dune
CN103835279B (en) * 2013-10-20 2017-03-29 娄志平 Outstanding pouch-shaped high vertical sediment trapping net fixes the construction method of moving dunes
CN103541341A (en) * 2013-11-04 2014-01-29 中国科学院新疆生态与地理研究所 Repeatedly utilized grass grid sand fixing method
CN104060599A (en) * 2014-06-16 2014-09-24 娄志平 Overlapping splicing type sand blocking net and construction method thereof
CN105780674A (en) * 2016-02-02 2016-07-20 中国科学院寒区旱区环境与工程研究所 Lifting type wind prevention and sand resistance dike suitable for most leading edge of wind-sand protection system
CN110387835A (en) * 2019-08-06 2019-10-29 中铁西北科学研究院有限公司 Assembled dredges sand stop wall
CN110387835B (en) * 2019-08-06 2021-12-28 中铁西北科学研究院有限公司 Assembled dredging sand blocking wall

Also Published As

Publication number Publication date
CN103174124B (en) 2015-02-25

Similar Documents

Publication Publication Date Title
CN103174124B (en) On-site overlapping lay-out method of vertical sand-protecting barriers
CN205276316U (en) Modular prefabricated piping lane
CN104993440A (en) Lightning-protection manual grounding system and construction method by utilizing structure steel bar externally-connected downlead wire
CN105350522A (en) Method for manufacturing and using prefabricated reinforced concrete energy pile system
CN103967011B (en) Callable umbrella pressure-bearing earth anchor in a kind of soft soil layer
CN103741708B (en) Prefabricated concrete rod sleeve basis
CN206376981U (en) Lattice tower and the wind power generating set including the lattice tower
CN202559382U (en) Concrete prefabricated combined duct with stepped conical spigot and socket
CN202954610U (en) Power pole heightening apparatus
CN202595756U (en) Piled raft foundation structure of narrow-base power transmission tower
CN204849774U (en) A simple and easy device for well casing sinks to be put
CN204370417U (en) A kind of for base pit engineering external corner or the road place of going along with sb. to guard him to drawing cable bolting structure
CN204089044U (en) Portable overhead conductor shift unit
CN201024584Y (en) Water heating ground heat pipeline pavement template
CN203393740U (en) Integral reinforced concrete foundation structure for assembling drainage pipelines
CN204825860U (en) Wolf's fang stake
CN103953058B (en) Coaxial steel cylinder basis
CN205604824U (en) Fastener that pole suitability is strong
CN203684258U (en) Prefabricated concrete rod sleeve foundation
CN204098024U (en) A kind of secondary grouting concrete pipe pile construction device
CN103809074A (en) Power cable safety identification device and method
CN206942282U (en) A kind of reinforcement type electric force pole tower
CN203160236U (en) Anti-floating anchor rod capable of collecting ground source heat energy
CN203256744U (en) Device for correcting perpendicularity of concrete-filled steel tubular column through reverse construction method
CN206157757U (en) Pre -embedded steel pipe formula photovoltaic trestle pile basis

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant