CN103166230B - Device for realizing fast interchange of capacitor bank and reactor group - Google Patents

Device for realizing fast interchange of capacitor bank and reactor group Download PDF

Info

Publication number
CN103166230B
CN103166230B CN201110415943.7A CN201110415943A CN103166230B CN 103166230 B CN103166230 B CN 103166230B CN 201110415943 A CN201110415943 A CN 201110415943A CN 103166230 B CN103166230 B CN 103166230B
Authority
CN
China
Prior art keywords
steel plate
foundation
banks
reactor
flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201110415943.7A
Other languages
Chinese (zh)
Other versions
CN103166230A (en
Inventor
顾尔重
连辉
杨光
冯蕾
曹志民
耿建风
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cao Zhimin
Geng Jianfeng
Gu Erzhong
PowerChina Henan Electric Power Survey and Design Institute Co Ltd
Original Assignee
Hennan Electric Power Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hennan Electric Power Survey and Design Institute filed Critical Hennan Electric Power Survey and Design Institute
Priority to CN201110415943.7A priority Critical patent/CN103166230B/en
Publication of CN103166230A publication Critical patent/CN103166230A/en
Application granted granted Critical
Publication of CN103166230B publication Critical patent/CN103166230B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/30Reactive power compensation

Abstract

A foundation for realizing fast exchange of a capacitor bank and a reactor group comprises a rail, a uniform foundation arranged in the rail, a supporting insulator fast connection device and a support fast connection device, and the uniform foundation can be used for realizing interchange of the capacitor bank and the reactor group in the same field. The uniform foundation is a mixed foundation which simultaneously comprises a capacitor bank foundation and a reactor group foundation, and a reinforcing rib is arranged in the mixed foundation and made of a grounding lead wire and glass reinforced plastics. All buried iron of the mixed foundation is connected with a main grounding net through the non-closed grounding lead wire. By means of the foundation, the requirement on interchange of the capacitor bank and the reactor group in the same field is satisfied, and the foundation can not only satisfy mounting requirements of different devices, but also can satisfy requirements on bearing capacity of foundation soil under the effect of different device loads.

Description

A kind of device realizing Capacitor banks and Reactor banks rapid interchangeable
Technical field
The present invention relates to a kind of device of power equipment, specifically required when Same Site exchanges Capacitor banks and Reactor banks uniform based.
Background technology
500kV transformer station of China adopts 500kV/220kV/35(66) kV tertiary voltage, main transformer low-pressure side access reactive power compensator and station become, and are the important component parts of transformer station.The wherein Shunt Capacitor Unit of reactive power compensator many employings grouping switching and shunt reactor.
Research shows, adopts in the 500kV transformer station of compact device at high, medium voltage side, and main transformer low-pressure side is taken up an area can reach 26 ~ 31% of the full station gross area.In the case low voltage parallel capacitor group needed for transformer station is once gone up neat way to shunt reactor and add the occupation of land in main transformer low-pressure side region and corresponding equipment investment, cause the uneconomical of transformer substation construction, there is the larger wasting of resources.
Summary of the invention
The object of this invention is to provide a kind of uniform based, Capacitor banks can be installed on this basis, Reactor banks can be installed again, laying the foundation for realizing carrying out exchange at Same Site to Capacitor banks and Reactor banks.
For achieving the above object, the present invention is by the following technical solutions:
The present invention includes fence and be arranged on and realize uniform based, post insulator Quick Connect Kit and the support Quick Connect Kit that Capacitor banks and Reactor banks carry out at Same Site exchanging in fence; Wherein, described uniform based refers to the mixed base simultaneously comprising Capacitor banks basis and Reactor banks basis, and arranges arrangement of reinforcement in this mixed base, and described arrangement of reinforcement is made up of grounding lead wiring and fiberglass; Described mixed base all are buried Tie Tong and are crossed inc grounding lead wiring and be connected with main grounding grid.
Described post insulator Quick Connect Kit comprises and is arranged on plant bottom case and post insulator reserves the U-shaped steel plate buried between iron, the sealing baffle that this U-shaped steel plate comprises upper strata flange steel plate, lower floor's flange steel plate and is positioned at therebetween; Its at the middle and upper levels flange steel plate be connected with plant bottom case by bolt, lower floor's flange steel plate and post insulator be reserved to be buried iron and welds.
Between described upper strata flange steel plate and lower floor's flange steel plate, be also provided with stiffener, stiffener is vertically arranged relative to sealing baffle.
The installing hole that described support Quick Connect Kit comprises housing apparatus support and the steel plate be positioned at bottom equipment supporter, bury between iron at steel plate and support and flange component is set, flange component top is connected with steel plate by construction bolt, buries iron weld bottom flange component with support; And cover plate is set between equipment supporter and installing hole.
In described flange component, floor is set.
Described fence is 5m × 12m.
Adopt the present invention of technique scheme, for the exchange realizing Capacitor banks and Reactor banks is laid a good foundation, specifically comprise following advantage:
(1) uniform based, achieves the requirement of exchanging Capacitor banks and Reactor banks at Same Site, and this basis can not meet the installation requirement of distinct device, and meets the requirement of foundation bearing capacity under the effect of distinct device load.
(2) post insulator Quick Connect Kit and support Quick Connect Kit, achieve the fast assembling-disassembling of post insulator and equipment supporter respectively, easy construction, and construction precision is high, adopts simple measure to safeguard.
Accompanying drawing explanation
Fig. 1 realizes Capacitor banks and Reactor banks carry out the uniform based exchanged layout plan at Same Site in the present invention.
Fig. 2 is the ground network layout plan of uniform based of the present invention.
Fig. 3 is the structure chart of B-C post insulator Quick Connect Kit of the present invention.
Fig. 4 is the A place enlarged diagram in Fig. 3.
Fig. 5 is the structure chart of medium-height trestle Quick Connect Kit of the present invention.
Fig. 6 is B-B direction view in Fig. 5.
Embodiment
Due in the operation of transformer station, at synchronization, it is no matter the low-pressure side of same transformer or in same transformer station, low voltage parallel capacitor group and high and low pressure shunt reactor can not drop into simultaneously.Generally, the transformer substation construction initial stage due to duty ratio comparatively light, the charge power of 500kV is relatively large, often drops into shunt reactor in this stage.Along with transformer station's load increases, transformer reactive loss increases gradually, and shunt reactor exits, and the number of units that capacitor drops into increases gradually.
In each interval of main transformer low-pressure side reactive power compensator, partial separation is transform as the special interval not only capacitor can installed but also reactor can be installed.Drop into shunt reactor at the first stage of construction of transformer station, and along with the increase of substation's on-load, need reactor to be changed to capacitor according to operation.If this capacity reactance exchanges interval and can realize dismounting exchange capacity reactance equipment easily and fast and can meet service requirement, the reactive power compensator then often organizing main transformer once can be gone up together at first stage of construction, thus effectively can save the occupation of land scale of transformer station and invest accordingly, better economic benefit can be obtained.
Consider construction scale be often organize the transformer station that main transformer configures 3 groups of electric capacity and 2 groups of reactance, do not need 5 intervals of once go up needed for neat capacitor and reactor, but arrange 4 power distribution equipments power up perhaps reactance occupation of land interval.Wherein, capacitor is only installed in 2 intervals, and reactor is only installed in 1 interval, and 1 interval can be installed capacitor and also can be installed reactor, and equipment detachably exchanges.Three groups of electric capacity or two groups of reactance can be run at most as required under every platform main transformer.
For realizing the exchange of above-mentioned Capacitor banks and Reactor banks, needing basis, fence and earth mat for the two to make improvements, the present invention is based on this and propose a kind of uniform based.
As shown in Figure 1, the present invention includes fence 100 and be arranged on and realize uniform based, post insulator Quick Connect Kit and the support Quick Connect Kit that Capacitor banks and Reactor banks carry out at Same Site exchanging in fence, three jointly forms and exchanges basis.Capacitor installation fence is of a size of 5m × 12m, and reactor fence is of a size of 5m × 10m, and in equipment interchange process, fence 100 should adopt unified specification, and therefore, fence 100 size as selection gist, should should adopt 5m × 12m specification using comparatively large equipment size.
Wherein, as shown in Figure 1 and Figure 2, uniform based refers to the mixed base simultaneously comprising Capacitor banks basis 2 and Reactor banks basis 1.Because this mixed base is larger, and there is different sedimentations, cause basis easily to split, therefore need in mixed base, arrange arrangement of reinforcement 3; Simultaneously due to the existence of reactor, require can not there is thick hardware in antimagnetic distance, and the reinforcing bar or other metals formation that form closed circuit in basis, can not be had, so arrangement of reinforcement 3 of the present invention is made up of grounding lead wiring and fiberglass, fiberglass is nonmagnetic substance, and there is higher intensity, original reinforcing bar can be avoided to generate heat and to cause the generation of basic crack situation, improve the mechanical property of mixed base preferably; And this mixed base all are buried Tie Tong and are crossed inc grounding lead wiring and be connected with main grounding grid 4.
As shown in Figure 3, Figure 4, post insulator Quick Connect Kit comprises and is arranged on plant bottom case 5 and post insulator reserves the U-shaped steel plate 7 buried between iron 6, the sealing baffle 11 that this U-shaped steel plate 7 comprises upper strata flange steel plate 9, lower floor's flange steel plate 10 and is positioned at therebetween; Its at the middle and upper levels flange steel plate 9 be connected with plant bottom case 5 by bolt 8, lower floor's flange steel plate 10 and post insulator be reserved to be buried iron 6 and welds.Like this, when removing bolt 8, the post insulator on top can be removed, conveniently realize Fast Installation and dismounting.In addition, for the purpose of firmly, between upper strata flange steel plate 9 and lower floor's flange steel plate 10, be also provided with stiffener 13, stiffener 13 is vertically arranged relative to sealing baffle 11.
As shown in Figure 5, Figure 6, the installing hole 16 that support Quick Connect Kit comprises housing apparatus support 14 and the steel plate 18 be positioned at bottom equipment supporter, bury between iron 15 at steel plate 18 and support and flange component 17 is set, above-mentioned flange component 17 also can be U-shaped steel plate, and flange component 17 top is connected with steel plate 18 by construction bolt 19, buries iron 15 bottom flange component 17 with support and weld, like this, remove construction bolt 19, Fast Installation and the dismounting of equipment supporter 14 can be realized.In addition, floor 22 is set in flange component 17, to strengthen its fastness.Cover plate 20 can also be set between equipment supporter 14 and installing hole 16.

Claims (6)

1. realize a device for Capacitor banks and Reactor banks rapid interchangeable, it is characterized in that: it comprises fence (100) and be arranged on and realizes uniform based, post insulator Quick Connect Kit and the support Quick Connect Kit that Capacitor banks and Reactor banks carry out at Same Site exchanging in fence; Wherein, described uniform based refers to the mixed base simultaneously comprising Capacitor banks basis (2) and Reactor banks basis (1), and in this mixed base, arrange arrangement of reinforcement (3), and described arrangement of reinforcement (3) is made up of grounding lead wiring and fiberglass; Described mixed base all are buried Tie Tong and are crossed inc grounding lead wiring and be connected with main grounding grid (4).
2. the device realizing Capacitor banks and Reactor banks rapid interchangeable according to claim 1, it is characterized in that: described post insulator Quick Connect Kit comprises and is arranged on the reserved U-shaped steel plate (7) buried between iron (6) of plant bottom case (5) and post insulator, the sealing baffle (11) that this U-shaped steel plate (7) comprises upper strata flange steel plate (9), lower floor's flange steel plate (10) and is positioned at therebetween; Its at the middle and upper levels flange steel plate (9) be connected with plant bottom case (5) by bolt (8), lower floor's flange steel plate (10) and post insulator be reserved to be buried iron (6) and welds.
3. the device realizing Capacitor banks and Reactor banks rapid interchangeable according to claim 2, it is characterized in that: between described upper strata flange steel plate (9) and lower floor's flange steel plate (10), be also provided with stiffener (13), stiffener (13) is vertically arranged relative to sealing baffle (11).
4. the device realizing Capacitor banks and Reactor banks rapid interchangeable according to claim 1, it is characterized in that: the installing hole (16) that described support Quick Connect Kit comprises housing apparatus support (14) and the steel plate (18) be positioned at bottom equipment supporter, bury between iron (15) at steel plate (18) and support and flange component (17) is set, flange component (17) top is connected with steel plate (18) by construction bolt (19), and flange component (17) bottom is buried iron (15) with support and welded; And cover plate (20) is set between equipment supporter (14) and installing hole (16).
5. the device realizing Capacitor banks and Reactor banks rapid interchangeable according to claim 4, is characterized in that: in described flange component (17), arrange floor (22).
6. the device realizing Capacitor banks and Reactor banks rapid interchangeable according to claim 1, is characterized in that: described fence (100) wide length is 5m × 12m.
CN201110415943.7A 2011-12-14 2011-12-14 Device for realizing fast interchange of capacitor bank and reactor group Expired - Fee Related CN103166230B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110415943.7A CN103166230B (en) 2011-12-14 2011-12-14 Device for realizing fast interchange of capacitor bank and reactor group

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110415943.7A CN103166230B (en) 2011-12-14 2011-12-14 Device for realizing fast interchange of capacitor bank and reactor group

Publications (2)

Publication Number Publication Date
CN103166230A CN103166230A (en) 2013-06-19
CN103166230B true CN103166230B (en) 2015-05-20

Family

ID=48589075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110415943.7A Expired - Fee Related CN103166230B (en) 2011-12-14 2011-12-14 Device for realizing fast interchange of capacitor bank and reactor group

Country Status (1)

Country Link
CN (1) CN103166230B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061746A (en) * 2010-11-26 2011-05-18 宝业集团浙江建设产业研究院有限公司 Steel structure assembled embedded part and construction method thereof
CN201857620U (en) * 2010-11-05 2011-06-08 中国科学院武汉岩土力学研究所 Device for conducting vertical anti-pulling static loading experiment to pile and board foundation of electricity transmission tower

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4021312B2 (en) * 2002-12-06 2007-12-12 鹿島建設株式会社 Structure housing and grounding structure using structure housing

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201857620U (en) * 2010-11-05 2011-06-08 中国科学院武汉岩土力学研究所 Device for conducting vertical anti-pulling static loading experiment to pile and board foundation of electricity transmission tower
CN102061746A (en) * 2010-11-26 2011-05-18 宝业集团浙江建设产业研究院有限公司 Steel structure assembled embedded part and construction method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
±800kV平波电抗器安装工艺控制;曹邦标;《华东电力》;20110824;第39卷(第8期);第1364-1366页 *
交流特高压晋东南变电站GIS组合电器超长大体积混凝土基础冬期施工方法;贺虎等;《电网技术》;20090520;第33卷(第10期);第38-41页 *

Also Published As

Publication number Publication date
CN103166230A (en) 2013-06-19

Similar Documents

Publication Publication Date Title
CN101788636B (en) Resonance voltage resistant test system and voltage resistant test method of sample with large capacitance
CN104143834B (en) A kind of photovoltaic plant low-voltage ride through detection system of high altitude localities
CN103986152B (en) The method for arranging of flexible direct current converter station connection district and valve Room power distribution equipment
CN202978006U (en) Ultrahigh voltage intelligent substation medium-voltage side HGIS power distribution device
CN110130295A (en) Offshore wind power flexible DC power transmission converter station bridge arm valve tower layout and offshore platform
CN204349309U (en) Photovoltaic inversion boosting integrated box type transformer station
CN204045951U (en) A kind of arrangement of 220kV power distribution equipment
CN103166230B (en) Device for realizing fast interchange of capacitor bank and reactor group
CN205583475U (en) Integrated transformer substation of 110kV prepackage type
CN202353005U (en) Insulating platform for high-voltage direct current change-over switch
CN103166231B (en) A kind of method reducing land occupation of reactive compensation device layout
CN102891439A (en) Medium-voltage side hybrid gas insulated switchgear (HGIS) distribution device for ultrahigh voltage intelligent substation
CN201985528U (en) Series compensation system adopting line iron towers
CN204258114U (en) A kind of 500kV substation equipment arrangement
CN201352680Y (en) Portable power distribution cabinet
CN204088904U (en) A kind of multi-functional photovoltaic exchanges header box
CN202384114U (en) Quick connecting device for post insulator
CN202380472U (en) Unified foundation for implementing interchange of capacitor bank and reactor bank on same site
Mutluer et al. A unified relocatable SVC for open-cast lignite mining in Turkey
CN202466613U (en) Quick support connecting device
CN202034483U (en) Sea water direct current earth electrode device
CN201796053U (en) Movable supporting platform for withstand voltage test of current transformator
CN201846015U (en) GIS (global information system) power distribution unit adopting one and half breaker connection
CN201438638U (en) High-voltage parallel connection capacitor
CN202424187U (en) Movable static var generator

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 450007 Zhengzhou Zhongyuan Road, Henan, No. 212

Co-patentee after: Cao Zhimin

Patentee after: China Electric Power Construction Group Henan electric survey and Design Institute Co., Ltd.

Co-patentee after: Geng Jianfeng

Co-patentee after: Gu Erzhong

Address before: 450007 Zhengzhou Zhongyuan Road, Henan, No. 212

Co-patentee before: Cao Zhimin

Patentee before: Hennan Electric Power Survey & Design Institute

Co-patentee before: Geng Jianfeng

Co-patentee before: Gu Erzhong

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150520

Termination date: 20191214