CN103162981B - 一种盾构隧道管片衬砌相似试验模型 - Google Patents

一种盾构隧道管片衬砌相似试验模型 Download PDF

Info

Publication number
CN103162981B
CN103162981B CN201310041535.9A CN201310041535A CN103162981B CN 103162981 B CN103162981 B CN 103162981B CN 201310041535 A CN201310041535 A CN 201310041535A CN 103162981 B CN103162981 B CN 103162981B
Authority
CN
China
Prior art keywords
section
jurisdiction ring
shield tunnel
area
jurisdiction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310041535.9A
Other languages
English (en)
Other versions
CN103162981A (zh
Inventor
王士民
何川
徐国文
张广超
马志刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUZHOU METRO GROUP Co.,Ltd.
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN201310041535.9A priority Critical patent/CN103162981B/zh
Publication of CN103162981A publication Critical patent/CN103162981A/zh
Application granted granted Critical
Publication of CN103162981B publication Critical patent/CN103162981B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明公开了一种盾构隧道管片衬砌相似试验模型,包括由相似材料整体浇注而成管片环、管片环上开有模拟管片接头刚度弱化效应的凹槽,其特征在于:所述的管片环分为上部区域(1a)、下部区域(1b)、左侧区域(1c)、右侧区域(1d),上部区域(1a)和下部区域(1b)的模拟管片接头刚度弱化效应的凹槽(2a)开在管片环的内侧,左侧、右侧区域的模拟管片接头刚度弱化效应的凹槽(2b)开在管片环的外侧。该种试验模型能够更好的模拟盾构隧道管片接头部位的力学特性,尤其可以很好的模拟盾构隧道管片衬砌的大变形及渐进性破坏过程;试验误差小,能对隧道的设计、施工及维护加固提供更加准确、可靠的试验数据。

Description

一种盾构隧道管片衬砌相似试验模型
技术领域
本发明涉及一种盾构隧道试验模型。
背景技术
目前,盾构隧道由于其自身的优点,在城市轨道交通、越江跨海通道以及市政管道等的建设中得到了越来越广泛的应用。盾构隧道主要采用环向接头将多个弧形的单层衬砌管片拼接成管片环,再通过纵向接头将管片环以通缝或错缝方式拼装成盾构隧道。由于工程水文地质条件的复杂性、隧道规模及细部构造的差异,以及盾构隧道对工程安全的高要求,通常需要通过模型试验研究揭示盾构隧道管片衬砌结构的力学特性。鉴于盾构隧道管片接头的复杂性,在实施盾构隧道模型试验过程中,如何考虑盾构隧道管片接头的力学效应是一个重要的问题。
通过对现有技术的文献检索发现,在已有的模型试验中,模拟盾构隧道的力学特性采用的相似试验模型主要有以下两种:
第一种相似试验模型以修正惯用法作为理论依据,用管片衬砌环整体抗弯刚度的降低等效盾构隧道管片接头部位抗弯刚度的降低,来考虑管片环向接头对盾构隧道管片衬砌结构力学特性的影响。从而采用材质均匀金属管、有机材料管等圆形结构作为相似试验模型材料,根据盾构隧道横向刚度等效原则,确定出相似试验模型衬砌厚度,该相似试验模型在试验过程中仅能近似模拟管片衬砌结构的整体力学特征,但是由于无法反映管片衬砌接头部位的局部应力集中效应及接头转动等力学特性,模型试验得到的隧道管片的内力和变形规律与原型隧道差别较大。
第二种相似试验模型为同济大学发明专利(公开号:CN101299008A),该模型管片采用配置的相似材料整体浇注而成,对于环向接头、纵向接头的刚度弱化效应,通过在对应于环向接头、纵向接头部位的管片环外侧切割出相应的凹槽予以实现,凹槽深度根据等效刚度原理通过计算进行确定。
上述两种模型中,第二种相似模型由于其在处理管片接头该模型在一定程度上保证了模型相似比的要求,与实际情况更为接近,因此被广泛接受并使用。但实际上管片环在以竖向荷载为主的外荷载作用下,其不同部位的变形及内力分布是有区别的:拱顶、拱底部位受正弯矩作用,位移指向管片内侧,该部位管片环内侧受拉;左拱腰、右拱腰部位受负弯矩作用,位移指向管片外侧,该部位管片环外侧受拉。实际管片环的接头(相邻管片的螺栓连接部位)应表现为管片环受拉侧张开,而该模型用于模拟管片接头的凹槽均开在管片环外侧,导致管片环位于拱顶及拱底的接头(内侧连续,无凹槽)无法张开,从而造成不该有的应力集中,其变形及受力状态与实际不相符合。试验数据误差大,尤其在模拟盾构隧道管片衬砌结构承受极限荷载发生大变形及渐进性破坏时,这种由于接头处理方式带来的误差更将会被放大。难以对隧道的设计、施工及维护提供准确、可靠的试验数据。
发明内容
本发明要解决的技术问题是提出一种盾构隧道管片衬砌相似试验模型,该种试验模型能够更好的模拟盾构隧道管片接头部位的力学特性,尤其可以很好的模拟盾构隧道管片衬砌的大变形及渐进性破坏过程;试验误差小,能对隧道的设计、施工及维护加固提供更加准确、可靠的试验数据。
本发明解决其技术问题所采用的技术方案是,一种盾构隧道管片衬砌相似试验模型,包括由相似材料整体浇注而成管片环、管片环上开有模拟管片接头刚度弱化效应的凹槽,其特征在于:所述的管片环分为上部区域、下部区域、左侧区域、右侧区域;上部区域和下部区域的模拟管片接头刚度弱化效应的凹槽开在管片环的内侧,左侧、右侧区域的模拟管片接头刚度弱化效应的凹槽开在管片环的外侧。
与现有技术相比,本发明的有益效果是:
本发明在采用凹槽模拟接头部位刚度弱化时,考虑了管片环不同部位在外荷载下的受力及变形特性,对整个管片环进行了分区处理:其中,上部、下部(拱顶、拱底)区域受正弯矩作用,位移指向管片内侧,该区域管片环内侧受拉,相应的凹槽开在管片环内侧;而左侧、右侧(左拱腰、右拱腰)区域受负弯矩作用,位移指向管片外侧,该区域管片环外侧受拉,相应的凹槽开在管片环外侧。从而实现了管片环在受拉侧开槽,在外荷载作用下可以正确模拟管片环所有接头的张开效应,消除不该有的应力集中,使其变形及受力状态与实际相符,进而减小试验数据误差。尤其在模拟盾构隧道管片衬砌结构承受极限荷载发生大变形及渐进性破坏时,这种接头处理方式使试验模型的变形、受力、破坏及失稳等更符合实际管片环相关特性,更为显著地减小试验数据误差。从而能对隧道的设计、施工及维护提供更准确、可靠的试验数据。
上述的管片环的上部区域、下部区域、左侧区域、右侧区域均分,即每个区域的弧度为90°。
下面结合附图和具体实施方式对本发明作进一步的详细说明。
附图说明
图1为本发明实施例的相似试验模型的结构示意图。图中,虚线为管片环的四个区域的分界线。
具体实施方式
实施例
图1示出,本发明的一种具体实施方式是,一种盾构隧道管片衬砌相似试验模型,包括由相似材料整体浇注而成管片环、管片环上开有模拟管片接头刚度弱化效应的凹槽。管片环分为上部区域1a、下部区域1b、左侧区域1c、右侧区域1d;上部区域1a和下部区域1b的模拟管片接头刚度弱化效应的凹槽2a开在管片环的内侧,左侧、右侧区域的模拟管片接头刚度弱化效应的凹槽2b开在管片环的外侧。
本例管片环的上部区域1a、下部区域1b、左侧区域1c、右侧区域1d均分,即每个区域的弧度为90°。
每个区域的具体位置为:上部区域1a和下部区域1b为沿管片环的垂直轴线±45°,左侧区域1c、右侧区域1d为沿管片环的水平轴线±45°。

Claims (2)

1.一种盾构隧道管片衬砌相似试验模型,包括由相似材料整体浇注而成管片环、管片环上开有模拟管片接头刚度弱化效应的凹槽,其特征在于:所述的管片环分为上部区域(1a)、下部区域(1b)、左侧区域(1c)、右侧区域(1d);上部区域(1a)和下部区域(1b)的模拟管片接头刚度弱化效应的凹槽(2a)开在管片环的内侧,左侧、右侧区域的模拟管片接头刚度弱化效应的凹槽(2b)开在管片环的外侧。
2.根据权利要求1所述的一种盾构隧道管片衬砌相似试验模型,其特征在于:所述的管片环的上部区域(1a)、下部区域(1b)、左侧区域(1c)、右侧区域(1d)均分,即每个区域的弧度为90°。
CN201310041535.9A 2013-02-01 2013-02-01 一种盾构隧道管片衬砌相似试验模型 Active CN103162981B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310041535.9A CN103162981B (zh) 2013-02-01 2013-02-01 一种盾构隧道管片衬砌相似试验模型

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310041535.9A CN103162981B (zh) 2013-02-01 2013-02-01 一种盾构隧道管片衬砌相似试验模型

Publications (2)

Publication Number Publication Date
CN103162981A CN103162981A (zh) 2013-06-19
CN103162981B true CN103162981B (zh) 2016-02-03

Family

ID=48586248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310041535.9A Active CN103162981B (zh) 2013-02-01 2013-02-01 一种盾构隧道管片衬砌相似试验模型

Country Status (1)

Country Link
CN (1) CN103162981B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108932902A (zh) * 2018-06-22 2018-12-04 同济大学 一种可模拟盾构隧道环向接头的衬砌环模型设计方法

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103471796B (zh) * 2013-09-18 2016-01-20 山东科技大学 隧道现浇砼衬砌抗震性能测试方法
CN103593558A (zh) * 2013-11-01 2014-02-19 中南大学 一种盾构隧道管片结构安全评估模型与方法
CN103758532B (zh) * 2014-01-28 2016-01-06 华南理工大学 一种地铁盾构隧道管片接头的短期主动加固方法
CN104533470B (zh) * 2014-11-03 2016-08-24 同济大学 一种站立式三环原型异形盾构管片力学加载装置
CN105787193A (zh) * 2016-03-16 2016-07-20 上海市城市建设设计研究总院 盾构隧道模型结构的三角形抗力荷载计算方法
CN105863734B (zh) * 2016-05-20 2017-10-10 天津大学 双线隧道开挖既有隧道模拟监测装置
CN106053110B (zh) * 2016-06-01 2018-08-24 同济大学 一种用于盾构隧道模型试验的管环模型设计方法
CN106017961A (zh) * 2016-07-01 2016-10-12 上海交通大学 一种模拟盾构隧道管片接头的试验模型
CN108444740B (zh) * 2018-03-11 2020-04-24 北京工业大学 一种可实现衬砌支护功能的土压平衡模型盾构试验机
CN108776033B (zh) * 2018-03-30 2023-09-22 西南交通大学 一种用于盾构隧道纵向模型试验的衬砌模型及制作方法
CN109118930B (zh) * 2018-07-20 2020-10-02 同济大学 一种盾构隧道拼装式管片结构模型及设计制作方法
CN110645015B (zh) * 2019-09-28 2020-10-02 同济大学 在正负弯矩作用下刚度不同的盾构隧道管片接头试验模型
CN113959750A (zh) * 2021-11-17 2022-01-21 北京市市政工程设计研究总院有限公司 一种用于离心模型试验的拼装式盾构隧道模型衬砌及其制作方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2132907C1 (ru) * 1998-06-04 1999-07-10 Дирекция строящегося метрополитена Обделка тоннеля
JP2001288992A (ja) * 2000-01-31 2001-10-19 Geostr Corp シールド工事用セグメントリング、セグメントおよびリング間継手
CN101299008A (zh) * 2008-06-13 2008-11-05 同济大学 可模拟盾构隧道管片接头的试验模型及其制作方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2132907C1 (ru) * 1998-06-04 1999-07-10 Дирекция строящегося метрополитена Обделка тоннеля
JP2001288992A (ja) * 2000-01-31 2001-10-19 Geostr Corp シールド工事用セグメントリング、セグメントおよびリング間継手
CN101299008A (zh) * 2008-06-13 2008-11-05 同济大学 可模拟盾构隧道管片接头的试验模型及其制作方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
圆形装配式衬砌结构力学模型研究;张厚美等;《建筑结构》;20010525;第31卷(第5期);第61-64页 *
盾构隧道施工期衬砌管片受力特性及其影响分析;叶飞等;《岩土力学》;20110610;第32卷(第6期);全文 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108932902A (zh) * 2018-06-22 2018-12-04 同济大学 一种可模拟盾构隧道环向接头的衬砌环模型设计方法

Also Published As

Publication number Publication date
CN103162981A (zh) 2013-06-19

Similar Documents

Publication Publication Date Title
CN103162981B (zh) 一种盾构隧道管片衬砌相似试验模型
CN104457572B (zh) 基于三维扫描技术提取盾构隧道错缝错台量的方法
CN203069393U (zh) 盾构隧道管片衬砌力学试验模型
CN106194206A (zh) 一种盾构隧道管片信息可视化建模方法
CN103956109B (zh) 一种衬砌结构接头刚度可变的隧道模型试验方法
CN108932902B (zh) 一种可模拟盾构隧道环向接头的衬砌环模型设计方法
CN107100645A (zh) 基于bim技术的盾构隧道曲线区段管片预拼装选型设计方法
Deng et al. Analysis of asymmetrical deformation of surface and oblique pipeline caused by shield tunneling along curved section
CN203741996U (zh) 一种用于逆作法基坑工程中梁柱节点
CN207685996U (zh) 一种钢管混凝土柱与梁主筋连接节点
CN102053027A (zh) 高速铁路预制箱梁收缩徐变仿真分析用模型梁的制作方法
CN106441758A (zh) 一种用于盾构隧道振动试验台的多尺度模型设计方法
CN203689815U (zh) 一种隧道微台阶法工艺教学仿真体
CN206960198U (zh) 一种适用于室内隧道模型试验的衬砌支护模具
CN105205228A (zh) 核电站水池不锈钢衬里薄壁对焊结构变形模拟方法
CN109488331A (zh) 成型盾构隧道管片及其受力测试方法
CN102140920B (zh) 一种隧道仿生加固桥
CN107675635A (zh) 一种对悬臂梁式桥体接合处进行加固的支撑结构
CN205908904U (zh) 用于复合式管节的连跨拱顶弧形板片间的连接结构
CN206721890U (zh) 箱型式平衡梁
CN107059628A (zh) 一种基于bim的单轨交通轨道梁桥线形控制技术
CN205421925U (zh) 钢大模
Wang et al. Numerical Stability Analysis of Large Section Tunnels Using the Double-Side Heading Method: A Case Study of Xiamen Haicang Evacuate-Channel
Dong et al. Study of the prevention method of±800 kV transmission tower foundation deviation
CN102444089B (zh) 大风区预制构件拼装式防风明洞及其接头拼装连接方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210810

Address after: 610000, No. two, section 111, North Ring Road, Jinniu District, Sichuan, Chengdu

Patentee after: SOUTHWEST JIAOTONG University

Patentee after: FUZHOU METRO GROUP Co.,Ltd.

Address before: 610031 No. two, section 111, ring road, Chengdu, Sichuan, China

Patentee before: SOUTHWEST JIAOTONG University

TR01 Transfer of patent right