CN103149346A - Detection and analysis system of tunnel concrete and detection and analysis method thereof - Google Patents

Detection and analysis system of tunnel concrete and detection and analysis method thereof Download PDF

Info

Publication number
CN103149346A
CN103149346A CN2012105728020A CN201210572802A CN103149346A CN 103149346 A CN103149346 A CN 103149346A CN 2012105728020 A CN2012105728020 A CN 2012105728020A CN 201210572802 A CN201210572802 A CN 201210572802A CN 103149346 A CN103149346 A CN 103149346A
Authority
CN
China
Prior art keywords
qualitative data
data
concrete
threshold range
detection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012105728020A
Other languages
Chinese (zh)
Other versions
CN103149346B (en
Inventor
李友田
徐青
刘庆贺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shenhua Energy Co Ltd
Shenhua Ganquan Railway Co Ltd
Original Assignee
China Shenhua Energy Co Ltd
Shenhua Ganquan Railway Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shenhua Energy Co Ltd, Shenhua Ganquan Railway Co Ltd filed Critical China Shenhua Energy Co Ltd
Priority to CN201210572802.0A priority Critical patent/CN103149346B/en
Publication of CN103149346A publication Critical patent/CN103149346A/en
Application granted granted Critical
Publication of CN103149346B publication Critical patent/CN103149346B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a detection and analysis system of tunnel concrete and a detection and analysis method of the tunnel concrete. The detection and analysis system of the tunnel concrete comprises a data collection device, a judging device and an analysis device, wherein the data collection device is used for collecting quality data of tunnel concrete, the judging device is used for comparing the quality data with a preset value data threshold range, the quality data and an alarm notification are output under the condition that the quality data is beyond the quality data threshold range, the analysis device is used for comparing the quality data with the stored historical data according to the alarm notification, and a quality analysis report is generated according to the comparing result. The detection and analysis system of the tunnel concrete and the detection and analysis method of the tunnel concrete have the advantages that the whole detection and analysis procedure can be achieved without human intervention, and the efficiency of the detection and the analysis and accuracy of the analysis result can be improved.

Description

Tunnel concrete detects analytic system and method
Technical field
The present invention relates to a kind of tunnel concrete and detect analytic system and a kind of tunnel concrete determination method.
Background technology
Need to regularly detect analysis for the railway tunnel xoncrete structure, guarantee the safe passing of train in the tunnel in time to carry out maintenance and repair in the in-problem situation of xoncrete structure.In the prior art, the realization of said process usually needs artificial the participation, for example, after some parameter to the tunnel concrete structure detects collection, is analyzed by experienced operating personnel and judges and provide solution.But this artificial participation method is not only strong to the dependence that the experience operating personnel are arranged, and it is lower to detect analysis efficiency, and analysis result is also not accurate enough.
Summary of the invention
The purpose of this invention is to provide a kind of tunnel concrete and detect analytic system and a kind of tunnel concrete determination method, this detection analytic system and method can make whole detection analytic process need not artificial participation, have improved detection analysis efficiency and precision of analysis.
To achieve these goals, the invention provides a kind of tunnel concrete and detect analytic system, this system comprises: data collector, for the qualitative data that gathers tunnel concrete; Judgment means is used for qualitative data and default qualitative data threshold range are compared, at qualitative data in the situation that outside default qualitative data threshold range, output quality data and alarm; Analytical equipment is used for comparing according to the historical data of alarm with qualitative data and storage, and generates Quality Analysis Report according to comparative result.
Preferably, this system also comprises memory storage, is used for storage qualitative data, historical data and Quality Analysis Report.
Preferably, qualitative data comprises with lower at least one: the crooked radian of the bow member in the loading of the number of steel bars in concrete density, concrete thickness, xoncrete structure, bar bending degree, inverted arch, out break amount and xoncrete structure.
The present invention also provides a kind of tunnel concrete determination method, and the method comprises: utilize data collector to gather the qualitative data of tunnel concrete; Utilize judgment means that qualitative data and default qualitative data threshold range are compared and at qualitative data in the situation that output quality data and alarm outside default qualitative data threshold range; And utilize analytical equipment compare and generate Quality Analysis Report according to comparative result according to the historical data of alarm to qualitative data and storage.
Preferably, the method also comprises and utilizes memory device stores qualitative data, historical data and Quality Analysis Report.
Preferably, qualitative data comprises with lower at least one: the crooked radian of the bow member in the loading of the number of steel bars in concrete density, concrete thickness, xoncrete structure, bar bending degree, inverted arch, out break amount and xoncrete structure.
By gathering the qualitative data of tunnel concrete, qualitative data and the qualitative data threshold range of presetting are compared, at qualitative data in the situation that output quality data and alarm outside default qualitative data threshold range, and compare according to the historical data of described alarm with qualitative data and storage, and generate Quality Analysis Report according to comparative result, can make whole detection analytic process need not artificial participation, and improve detection analysis efficiency and precision of analysis.
Other features and advantages of the present invention will partly be described in detail in embodiment subsequently.
Description of drawings
Accompanying drawing is to be used to provide a further understanding of the present invention, and consists of the part of instructions, is used from explanation the present invention with following embodiment one, but is not construed as limiting the invention.In the accompanying drawings:
Fig. 1 detects the block diagram of analytic system according to the tunnel concrete of the embodiment of the present invention; And
Fig. 2 detects the process flow diagram of analytic system according to the tunnel concrete of the embodiment of the present invention.
Embodiment
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is elaborated.Should be understood that, embodiment described herein only is used for description and interpretation the present invention, is not limited to the present invention.
Fig. 1 detects the block diagram of analytic system according to the tunnel concrete of the embodiment of the present invention.
As shown in Figure 1, this system comprises: data collector 12, for the qualitative data that gathers tunnel concrete; Judgment means 14 is used for qualitative data and default qualitative data threshold range are compared, at qualitative data in the situation that outside default qualitative data threshold range, output quality data and alarm; Analytical equipment 16 is used for comparing according to the historical data of alarm with qualitative data and storage, and generates Quality Analysis Report according to comparative result.
This system can also comprise memory storage 18, is used for storing described qualitative data, described historical data and described Quality Analysis Report.By memory storage 18 is set, is convenient to the preservation of data and repeats to call.
According to technical scheme of the present invention, can be by the qualitative data of data collector 12 input tunnel concretes, described qualitative data comprises with lower at least one: the crooked radian of the bow member in the loading of the number of steel bars in concrete density, concrete thickness, xoncrete structure, bar bending degree, inverted arch, out break amount and xoncrete structure.
judgment means 14 is connected with data collector 12, described qualitative data (is respectively arranged with its corresponding qualitative data threshold range for different qualitative datas from the qualitative data threshold range of presetting, this qualitative data threshold range can be set according to construction quality standard and requirement, the present invention does not limit it) compare, judgment means 14 at qualitative data in the situation that outside default qualitative data threshold range, disease appears in the judgement concrete, export thus described qualitative data and alarm (for example text prompt or the Notes of Key Data), concrete disease is informed the supvr straightforwardly, according to this alarm, the supvr can wait until that Quality Analysis Report is completed and just make the Disease Processing decision-making, improved work efficiency.
According to technical scheme of the present invention, when the qualitative data that gathers comprises when multiple, as long as wherein a kind of outside its corresponding qualitative data threshold range determines that this qualitative data exceeds default qualitative data threshold range.
analytical equipment 16 is connected with judgment means 14, after receiving the disease prompting, (described historical data for example is qualitative data empirical value before with the historical data of storing of extracting from memory storage 18 with described qualitative data, perhaps qualitative data optimal value, the present invention does not limit it) compare, and (this Quality Analysis Report can be that the disease grade that analytical equipment 16 generates according to comparative result according to the program of setting is judged report and corresponding treatment measures to generate Quality Analysis Report according to comparative result, it can be also the pre-stored historical Quality Analysis Report for different comparative results (historical defective for example, safeguard, maintenance policy etc.), analytical equipment 16 can be transferred corresponding Quality Analysis Report according to comparative result according to the program of setting, to increase work efficiency, the present invention does not limit it).
Judgment means 14 also is used at qualitative data in the situation that within default qualitative data threshold range, export this qualitative data, and analytical equipment 16 also is used for generating Quality Analysis Report based on this qualitative data.Namely, at qualitative data in the situation that within default qualitative data threshold range, concrete quality meets the requirement of technical standard, and directly the output quality data reach based on this qualitative data and generate Quality Analysis Report, and store by memory storage 18.
According to technical scheme of the present invention, this system can also comprise the display device (not shown), and this display device is connected with analytical equipment 16, is used for showing the Quality Analysis Report that generates.By this display device is set, can provide more intuitively Quality Analysis Report for the operator, so that the operator carries out maintenance or maintenance to tunnel concrete quickly and easily.
Fig. 2 detects the process flow diagram of analytic system according to the tunnel concrete of the embodiment of the present invention.
As shown in Figure 2, the method comprises:
S200 utilizes data collector 12 to gather the qualitative data of tunnel concrete;
S202 utilizes 14 pairs of qualitative datas of judgment means and default qualitative data threshold range to compare, and at qualitative data in the situation that outside default qualitative data threshold range, go to step S204;
S204, judgment means 14 output quality data and alarms; And
S206 utilizes analytical equipment 16 to compare according to the historical data of described alarm to described qualitative data and storage, and generates Quality Analysis Report according to comparative result.
In step S202, at qualitative data in the situation that within default qualitative data threshold range, go to step S208;
S208, judgment means 14 is directly exported this qualitative data;
S210, analytical equipment 16 generates Quality Analysis Report based on this qualitative data.
The method also comprises utilizes memory device stores qualitative data, historical data and Quality Analysis Report.
According to technical scheme of the present invention, the method can be utilized the qualitative data of data collector 12 input tunnel concretes, and described qualitative data comprises with lower at least one: the crooked radian of the bow member in the loading of the number of steel bars in concrete density, concrete thickness, xoncrete structure, bar bending degree, inverted arch, out break amount and xoncrete structure.
by judgment means 14, described qualitative data (is respectively arranged with its corresponding qualitative data threshold range for different qualitative datas from the qualitative data threshold range of presetting, this qualitative data threshold range can be set according to construction quality standard and requirement, the present invention does not limit it) compare, judgment means 14 at qualitative data in the situation that outside default qualitative data threshold range, disease appears in the judgement concrete, export thus described qualitative data and alarm (for example text prompt or the Notes of Key Data), concrete disease is informed the supvr straightforwardly, according to this alarm, the supvr can wait until that Quality Analysis Report is completed and just make the Disease Processing decision-making, improved work efficiency.
According to technical scheme of the present invention, when the qualitative data that gathers comprises when multiple, as long as wherein a kind of outside its corresponding qualitative data threshold range determines that this qualitative data exceeds default qualitative data threshold range.
analytical equipment 16 is after receiving the disease prompting, (described historical data for example is qualitative data empirical value before with the historical data of storing of extracting from memory storage 18 with described qualitative data, perhaps qualitative data optimal value, the present invention does not limit it) compare, and (this Quality Analysis Report can be that the disease grade that analytical equipment 16 generates according to comparative result according to the program of setting is judged report and corresponding treatment measures to generate Quality Analysis Report according to comparative result, it can be also the pre-stored historical Quality Analysis Report for different comparative results (historical defective for example, safeguard, maintenance policy etc.), analytical equipment 16 can be transferred corresponding Quality Analysis Report according to comparative result according to the program of setting, to increase work efficiency, the present invention does not limit it).
According to technical scheme of the present invention, the method can also show the Quality Analysis Report that generates by display device.Like this, can provide more intuitively Quality Analysis Report for the operator, so that the operator carries out maintenance or maintenance to tunnel concrete quickly and easily.
Can find out from above-described embodiment, by gathering the qualitative data of tunnel concrete, qualitative data and the qualitative data threshold range of presetting are compared, at qualitative data in the situation that output quality data and alarm outside default qualitative data threshold range, and compare according to the historical data of described alarm with qualitative data and storage, and generate Quality Analysis Report according to comparative result, can make whole detection analytic process need not artificial participation, and improve detection analysis efficiency and precision of analysis.
Below describe by reference to the accompanying drawings the preferred embodiment of the present invention in detail; but; the present invention is not limited to the detail in above-mentioned embodiment; in technical conceive scope of the present invention; can carry out multiple simple variant to technical scheme of the present invention, these simple variant all belong to protection scope of the present invention.
Need to prove that in addition each the concrete technical characterictic described in above-mentioned embodiment in reconcilable situation, can make up by any suitable mode.For fear of unnecessary repetition, the present invention is to the explanation no longer separately of various possible array modes.
In addition, also can carry out combination in any between various embodiment of the present invention, as long as it is without prejudice to thought of the present invention, it should be considered as content disclosed in this invention equally.

Claims (6)

1. a tunnel concrete detects analytic system, and wherein, this system comprises:
Data collector is for the qualitative data that gathers tunnel concrete;
Judgment means is used for described qualitative data and default qualitative data threshold range are compared, at described qualitative data in the situation that outside described default qualitative data threshold range, export described qualitative data and alarm;
Analytical equipment is used for comparing according to the historical data of described alarm with described qualitative data and storage, and generates Quality Analysis Report according to comparative result.
2. system according to claim 1, wherein, this system also comprises memory storage, is used for storing described qualitative data, described historical data and described Quality Analysis Report.
3. system according to claim 1 and 2, wherein, described qualitative data comprises with lower at least one: the crooked radian of the bow member in the loading of the number of steel bars in concrete density, concrete thickness, xoncrete structure, bar bending degree, inverted arch, out break amount and xoncrete structure.
4. tunnel concrete determination method, wherein, the method comprises:
Utilize data collector to gather the qualitative data of tunnel concrete;
Utilize judgment means that described qualitative data and default qualitative data threshold range are compared and at described qualitative data in the situation that the described qualitative data of output and alarm outside described default qualitative data threshold range; And
Utilize analytical equipment compare and generate Quality Analysis Report according to comparative result according to the historical data of described alarm to described qualitative data and storage.
5. method according to claim 4, wherein, the method also comprises utilizes the described qualitative data of memory device stores, described historical data and described Quality Analysis Report.
6. according to claim 4 or 5 described methods, wherein, described qualitative data comprises with lower at least one: the crooked radian of the bow member in the loading of the number of steel bars in concrete density, concrete thickness, xoncrete structure, bar bending degree, inverted arch, out break amount and xoncrete structure.
CN201210572802.0A 2012-12-25 2012-12-25 Tunnel concrete testing and analysis system and method Active CN103149346B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210572802.0A CN103149346B (en) 2012-12-25 2012-12-25 Tunnel concrete testing and analysis system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210572802.0A CN103149346B (en) 2012-12-25 2012-12-25 Tunnel concrete testing and analysis system and method

Publications (2)

Publication Number Publication Date
CN103149346A true CN103149346A (en) 2013-06-12
CN103149346B CN103149346B (en) 2015-09-23

Family

ID=48547549

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210572802.0A Active CN103149346B (en) 2012-12-25 2012-12-25 Tunnel concrete testing and analysis system and method

Country Status (1)

Country Link
CN (1) CN103149346B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104131500A (en) * 2014-07-01 2014-11-05 昆明理工大学 Detection method for compactness of granular ballast bed and using device
CN104794148A (en) * 2014-12-31 2015-07-22 远光共创智能科技股份有限公司 Automatic cola type test data compliance monitored control system and method
CN105807007A (en) * 2016-05-04 2016-07-27 广州建设工程质量安全检测中心有限公司 Drilled core method detection system and detection method thereof
CN112014413A (en) * 2020-08-04 2020-12-01 贵州乐道科技有限公司 Mobile phone glass cover plate window area defect detection method based on machine vision
CN112710815A (en) * 2020-11-27 2021-04-27 重庆交通大学 Concrete carbonization degree evaluation method and device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005291881A (en) * 2004-03-31 2005-10-20 Univ Of Tokyo Apparatus and method for detecting degradation of concrete structure
GB2427918B (en) * 2005-07-01 2009-01-28 David Richard Andrews A monitoring system
JP2010271062A (en) * 2009-05-19 2010-12-02 Ihi Infrastructure Systems Co Ltd Concrete diagnosis system
CN102587986A (en) * 2012-03-12 2012-07-18 西安建筑科技大学 Tunnel construction informatization dynamic monitoring system and monitoring method thereof
CN102608963A (en) * 2011-12-28 2012-07-25 北京工业大学 Summarized information monitoring system of tunnel
CN202548621U (en) * 2012-03-23 2012-11-21 上海市电力公司 Automatic remote monitoring system for power grid tunnel

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005291881A (en) * 2004-03-31 2005-10-20 Univ Of Tokyo Apparatus and method for detecting degradation of concrete structure
GB2427918B (en) * 2005-07-01 2009-01-28 David Richard Andrews A monitoring system
JP2010271062A (en) * 2009-05-19 2010-12-02 Ihi Infrastructure Systems Co Ltd Concrete diagnosis system
CN102608963A (en) * 2011-12-28 2012-07-25 北京工业大学 Summarized information monitoring system of tunnel
CN102587986A (en) * 2012-03-12 2012-07-18 西安建筑科技大学 Tunnel construction informatization dynamic monitoring system and monitoring method thereof
CN202548621U (en) * 2012-03-23 2012-11-21 上海市电力公司 Automatic remote monitoring system for power grid tunnel

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘胜春等: "大型盾构隧道结构健康监测系统设计研究", 《地下空间与工程学报》, vol. 7, no. 4, 15 August 2011 (2011-08-15) *
王军等: "南京长江隧道管片结构健康监测系统设计与应用", 《地下工程与隧道》, no. 3, 30 September 2009 (2009-09-30) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104131500A (en) * 2014-07-01 2014-11-05 昆明理工大学 Detection method for compactness of granular ballast bed and using device
CN104131500B (en) * 2014-07-01 2016-01-13 昆明理工大学 A kind of prose style free from parallelism ballast track bed compactness inspection method and application apparatus
CN104794148A (en) * 2014-12-31 2015-07-22 远光共创智能科技股份有限公司 Automatic cola type test data compliance monitored control system and method
CN104794148B (en) * 2014-12-31 2018-06-05 远光共创智能科技股份有限公司 Coal analysis data compliance automatic monitored control system and method
CN105807007A (en) * 2016-05-04 2016-07-27 广州建设工程质量安全检测中心有限公司 Drilled core method detection system and detection method thereof
CN112014413A (en) * 2020-08-04 2020-12-01 贵州乐道科技有限公司 Mobile phone glass cover plate window area defect detection method based on machine vision
CN112710815A (en) * 2020-11-27 2021-04-27 重庆交通大学 Concrete carbonization degree evaluation method and device
CN112710815B (en) * 2020-11-27 2024-04-12 重庆交通大学 Concrete carbonization degree evaluation method and device

Also Published As

Publication number Publication date
CN103149346B (en) 2015-09-23

Similar Documents

Publication Publication Date Title
CN103149346A (en) Detection and analysis system of tunnel concrete and detection and analysis method thereof
JP5792654B2 (en) Security monitoring system and security monitoring method
US9177139B2 (en) Control system cyber security
CN102955914A (en) Method and device for detecting security flaws of source files
CN101741633A (en) Association analysis method and system for massive logs
CN101883017A (en) System and method for evaluating network safe state
CN103439933A (en) System and method for production process self-adaption monitoring using OCSVM
CN103921761B (en) A kind of fuel burglarproof control method and device
CN110472851A (en) A kind of power distribution network risk hidden danger dynamic evaluation model building method neural network based
EA201401091A1 (en) METHOD OF MANAGEMENT MONITORING SYSTEM AND SYSTEM FOR ITS IMPLEMENTATION
CN102180170A (en) Device for collecting, storing, analyzing and displaying vehicle data
CN110865625A (en) Process data anomaly detection method based on time series
CN104895610A (en) Novel tunnel condition analyzer
CN105676077A (en) High-voltage cable partial discharge on-line monitoring alarm method, device and system
CN103148889A (en) Bridge detection analysis system and bridge detection analysis method
CN109278794B (en) Train track abnormity detection system
CN204044340U (en) A kind of light fault detection system
CN103337169B (en) Based on the highway tunnel traffic intelligent radio prior-warning device of Doppler's autodetector
CN205449522U (en) Track structure operating condition monitoring system
JP2017072420A5 (en) Structure monitoring system
CN102288911A (en) System and method for monitoring and diagnosing thermal generator set
CN115691075B (en) Early warning system based on coal mine temperature and humidity detection
CN101585485B (en) Determination and reconstruction of load changes in lifting devices
CN202189272U (en) Monitoring and diagnosing system of a thermal generator set
CN112257516B (en) Method and device for monitoring collapse of fan support rod

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant