CN103123715A - 220KV transformer substation electricity-using industry composition proportion online real-time counting method - Google Patents

220KV transformer substation electricity-using industry composition proportion online real-time counting method Download PDF

Info

Publication number
CN103123715A
CN103123715A CN2013100138464A CN201310013846A CN103123715A CN 103123715 A CN103123715 A CN 103123715A CN 2013100138464 A CN2013100138464 A CN 2013100138464A CN 201310013846 A CN201310013846 A CN 201310013846A CN 103123715 A CN103123715 A CN 103123715A
Authority
CN
China
Prior art keywords
real
electricity consumption
time
power
industry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100138464A
Other languages
Chinese (zh)
Other versions
CN103123715B (en
Inventor
宋军英
李欣然
刘永刚
朱琳
周帆
黄良刚
谢培元
姜新凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ELECTRIC POWER OF HUNAN
Hunan University
State Grid Corp of China SGCC
Original Assignee
ELECTRIC POWER OF HUNAN
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ELECTRIC POWER OF HUNAN, Hunan University filed Critical ELECTRIC POWER OF HUNAN
Priority to CN201310013846.4A priority Critical patent/CN103123715B/en
Publication of CN103123715A publication Critical patent/CN103123715A/en
Application granted granted Critical
Publication of CN103123715B publication Critical patent/CN103123715B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a 220KV transformer substation electricity-using industry composition proportion online real-time counting method. The method includes: step 1, counting related information of 10KV lines belonging in a power supply area of a 220KV transformer substation; step 2, calculating an electricity-using industry proportion of the 10KV lines; step 3, calculating real-time total electrical load in an online manner; and step 4, calculating an electricity-using industry composition proportion of the 220KV transformer substation in an online and real-time manner. By the method, the electricity-using industry composition proportion of the 220KV transformer substation can be counted in an online and real-time manner, so that problems of large denaturation and randomness and difficulty in knowing the electricity-using industry composition proportion when the 200KV transformer substation is loaded are solved, labor intensity is greatly reduced for personnel to manually count the transformer substation electricity-using industry composition proportion, cost is saved, counting errors caused by personal errors are reduced, and counting accuracy of the electricity-using industry composition proportion is greatly improved.

Description

The 220 online real-time statistical methods of kv substation electricity consumption industry composition
Technical field
The invention belongs to the statistical method of electric system, relate in particular to a kind of 220 online real-time statistical methods of kv substation electricity consumption industry composition, the method is applicable to instruct the operation of power networks analyst to grasp real-time and accurately 220 kv substation part throttle characteristics.
Background technology
It is the important process of management and running that electric system simulation calculates, and is the Main Basis of formulating power system operating mode and safe operation, therefore, reliable and accurately simulation result be the basic premise of management and running decision-making.Load is as one of critical elements of electric system, and the accuracy of its model parameter directly affects grid simulation result of calculation.How accurately to hold power system load model and seem particularly important.Transformer station's part throttle characteristics statistics is an important foundation sex work of Component Based load modeling, and can go out the required information of real reflection transformer station's load electricity consumption industry composition from the operation of power networks extracting data be the key that guarantees the success or not of Component Based load modeling.
Adding up the classic method of 220 kv substation electricity consumption industry compositions grasps by load is carried out investigation statistics, namely by power and the electricity consumption industry proportion thereof of its distribution line of statistics some special occasion of 220 kv substations (as large in the winter, the summer is large), transformer, last comprehensive these data draw the electricity consumption industry composition of this 220 kv substation.This method is a kind of campaign-styled manual research method, it is wide that it relates to the zone, employ personnel many, concern large (power administration, transformer station, the large-scale typical power consumer that comprise the urban district, various places) need to expend huge human and material resources and financial resources, and during the process of the investigation, the personnel arrangement difficulty, last the cycle long, the statistical poor efficiency, these all make whole fact-finding process be absorbed in greatly loaded down with trivial details among.In addition, the payload of 220 kv substation different times and electricity consumption consist of all, and the moment changes, be that it has stronger randomness and time variation, therefore, can not determine exactly transforming plant industry composition by certain investigation statistics once or several times.
Raising along with grid automation level, each department power administration energy management system is constantly updated development, realizing the 220 automatic collections that the affiliated 10 kilovolts of outlet switchs of kv substation service area reach and network source is exerted oneself, is that the online real-time statistics of 220 kv substation electricity consumption industry compositions is laid a good foundation.
Summary of the invention
The technical problem to be solved in the present invention is, have for load and distribute extensively, time variation is large, the problem that electricity consumption industry composition is difficult to grasp, a kind of 220 online real-time statistical methods of kv substation electricity consumption industry composition are proposed, in order to accurate, efficient, cheap online grasp in real time 220 kv substation electricity consumption industry compositions, load model lays the foundation for the dispatcher provides accurately.
Realize that the technology solution that the object of the invention adopts is:
The 220 online real-time statistical methods of kv substation electricity consumption industry composition, carry out according to the following steps:
Affiliated 10 KV relevant informations in step 1, statistics 220 kv substation service areas:
(1) 10 KVs under listing one by one in 220 kv substation service areas;
(2) the Online statistics 10 real-time burdens with power of KV outlet switch, the listed 10 real-time burdens with power of KV outlet switch in territory of use power administration this step of energy management system Online statistics (1), the real-time burden with power of wherein flowing out 10 kilovolts of buses on the occasion of, the real-time burden with power that flows into 10 kilovolts of buses is negative value;
(3) Online statistics is incorporated in real time total meritorious exerting oneself of 10 KV power supplys into, and territory of use power administration energy management system Online statistics is incorporated the listed 10 KV power supplys of this step (1) total meritorious exerting oneself in real time into, its size be on the occasion of;
(4) statistics 10 KV substation transformer titles, capacity and industry attribute, add up the distribution transformer capacity that is connected with listed 10 KVs in this step (1) by platform, and indicate the electricity consumption industry attribute of every station power distribution on-load that transformer supplies, namely every station power distribution on-load that transformer supplies is to belong to which kind of in 5 large electricity consumption industries (being heavy industry electricity consumption, light industry electricity consumption, agriculture electricity consumption, tertiary industry electricity consumption, municipal electricity consumption);
Step 2, calculating 10 KV electricity consumption industry ratios:
(1) calculate 10 KV electricity consumption industry distribution transformer capacities, at step 1(4) in choose arbitrarily 1 10 KV, to be connected with this circuit and distribution transformer capacity addition that electricity consumption industry attribute is identical, namely obtain this 10 KV electricity consumption industry distribution transformer capacity.Using such method obtains step 1(1) in listed 10 KV electricity consumption industry distribution transformer capacities;
(2) calculate 10 KV substation transformer total volumies, with step 1(4) in the distribution transformer capacity addition that is connected with a certain 10 KVs, namely obtain this 10 KV substation transformer total volume.Using such method obtains step 1(1) listed 10 KV substation transformer total volumies;
(3) calculate 10 KV electricity consumption industry ratios, utilize a certain 10 KV electricity consumption industry distribution transformer capacities that obtain in this step (1) divided by the same 10 KV substation transformer total volumies that obtain in this step (2), can calculate this 10 KV electricity consumption industry ratio.According to said method, but calculation procedure 1(1) listed 10 KV electricity consumption industry ratios;
Step 3, in the real-time total power load of line computation 220 kv substations:
(1) in the line computation 10 real-time power loads of KV, utilize step 1(2) in a certain the 10 real-time burdens with power of KV outlet switch add step 1(3) in real-time total meritorious the exerting oneself of same 10 KV power supplys, can be in the real-time power load of this 10 KV of line computation.Using such method, calculation procedure 1(1 online) the listed 10 real-time power loads of KV;
(2) in the in real time total power load of line computation 220 kv substations, with the 10 real-time power load of the KV additions one by one that obtain in this step (1), can be in the in real time total power load of line computation 220 kv substations;
Step 4, the online 220 kv substation electricity consumption industry compositions of calculating in real time:
(1) in the line computation 10 real-time burdens with power of KV electricity consumption industry, utilize step 2(3) in a certain 10 KV electricity consumption industry ratios obtaining multiply by step 3(1) in the same 10 real-time power loads of KV that obtain, namely obtain the real-time burden with power of this 10 KV electricity consumption industry.Using such method obtains step 1(1) the listed 10 real-time burdens with power of KV electricity consumption industry;
(2) in the line computation 220 real-time burdens with power of kv substation electricity consumption industry, with the identical real-time burden with power addition of electricity consumption industry attribute in whole 10 KVs that obtain in this step (1), can be in the line computation 220 real-time burdens with power of kv substation electricity consumption industry;
(3) the 220 online real-time statisticss of kv substation electricity consumption industry composition, utilize the 220 real-time burdens with power of kv substation electricity consumption industry that obtain in this step (2) divided by step 3(2) in the in real time total power load of 220 kv substations that obtain, can realize the 220 online real-time statisticss of kv substation electricity consumption industry composition.
The principle of the inventive method is: utilize the electricity consumption industry attribute of affiliated 10 kilovolts of outlets in 220 kv substation service areas and the circuit burden with power that the online real-time statistics of energy management system arrives, realize the 220 online real-time statisticss of kv substation electricity consumption industry composition.
The beneficial effect of the inventive method is:
1, use this method real-time statistics 220 kv substation electricity consumption industry compositions online, solved 220 kv substations load time variations and randomness large, and the electricity consumption industry composition problem that is difficult to grasp;
2, realize the 220 online real-time statisticss of kv substation electricity consumption industry composition by energy management system, greatly reduced personnel and added up by hand the labour intensity of transforming plant industry composition, saved cost;
3, use this method to reduce the statistical error that causes because of the personal error, greatly improved electricity consumption industry composition statistical accuracy.
Further illustrate technical scheme of the present invention below in conjunction with accompanying drawing.
Description of drawings
Fig. 1 is certain 220 kv substation service area schematic diagram.
Embodiment
See Fig. 1, existing take certain 220 kv substation service area as example, illustrate the inventive method.
The online real-time statistical method of this 220 kv substation electricity consumption industry composition, carry out according to the following steps:
Affiliated 10 KV relevant informations in step 1, statistics 220 kv substation service areas:
(1) 10 KVs under listing one by one in 220 kv substation service areas, under in 220 kilovolts of gulf service areas of Xiao transformer station of family there be 10 KVs: mountain bridge line 322, Alpinia japonica line 412, river, mountain II line 326, mountain town line 324, mountain nitrogen line 408 and circuit 1, Above Transmission Lines title see Table the 1st row in 1;
(2) the Online statistics 10 real-time burdens with power of KV outlet switch, the listed 10 real-time burdens with power of KV outlet switch in territory of use power administration this step of energy management system Online statistics (1), the real-time burden with power of wherein flowing out 10 kilovolts of buses on the occasion of, the real-time burden with power that flows into 10 kilovolts of buses is negative value, each 10 real-time burdens with power of KV outlet switch see Table 1 the 2nd row, it is mountain bridge line 322, Alpinia japonica line 412, mountain spring II line 326, mountain town line 324, mountain nitrogen line 408 and circuit 1 each 10 real-time burdens with power of KV outlet switch are respectively 1.04 megawatts, 2.63 megawatt, 0 megawatt, 1.35 megawatt, 0.06 megawatt, 4.06 megawatt,
(3) Online statistics is incorporated 10 KV power supplys total meritorious exerting oneself in real time into, territory of use power administration energy management system Online statistics is incorporated the listed 10 KV power supplys of this step (1) total meritorious exerting oneself in real time into, its size be on the occasion of, incorporate into 10 KV power supplys in real time total meritorious exerting oneself see Table 1 the 3rd row; Namely incorporate 10 kilovolts of mountain bridge lines 322, Alpinia japonica line 412, mountain spring II line 326, mountain town line 324, mountain nitrogen line 408 and circuit 1 each line power total meritorious be respectively 1.46 megawatts, 1.51 megawatts, 3.70 megawatts, 2.07 megawatts, 4.87 megawatts, 0.0 megawatt in real time into;
(4) statistics 10 KV substation transformer titles, capacity and industry attribute, add up the substation transformer title that is connected with listed 10 KVs in this step (1) by platform, capacity, and the electricity consumption industry attribute of dated every station power distribution on-load that transformer supplies, be that every station power distribution on-load that transformer supplies is that to belong to 5 large electricity consumption industries (be the heavy industry electricity consumption, the light industry electricity consumption, the agricultural electricity consumption, tertiary industry electricity consumption, the municipal administration electricity consumption) in which kind of, take 10 KV mountain bridge lines 322 as example, this circuit is respectively distribution transforming 11 for the substation transformer title of band, distribution transforming 12, distribution transforming 13, distribution transforming 14, distribution transforming 15, distribution transforming 16, distribution transforming 17(sees Table 1 the 4th row), every station power distribution transformer capacity is respectively 0.8 megavolt-ampere, 1 megavolt-ampere, 0.63 megavolt-ampere, 0.8 megavolt-ampere, 0.63 megavolt-ampere, 1.25 megavolt-amperes, 1.25 megavolt-amperes (seeing Table 1 the 5th row), the electricity consumption industry attribute of every station power distribution on-load that transformer supplies is respectively light industry, light industry, agricultural, agricultural, the tertiary industry, the tertiary industry, the tertiary industry (seeing Table 1 the 6th row) can obtain by similar method substation transformer title, capacity and the industry attribute that in this step (1), listed other 10 KV confession is with,
Step 2, calculating 10 KV electricity consumption industry ratios:
(1) calculate 10 KV electricity consumption industry distribution transformer capacities, at step 1(4) in choose arbitrarily 1 10 KV, to be connected with this circuit and distribution transformer capacity addition that electricity consumption industry attribute is identical, namely obtain this 10 KV electricity consumption industry distribution transformer capacity.Using such method, obtain step 1(1) in listed 10 KV electricity consumption industry distribution transformer capacities, 10 KV mountain bridge lines 322 are as example in the table 1, this circuit supplies the substation transformer of band without heavy industry electricity consumption industry, so the capacity of this 10 KV heavy industry electricity consumption industry substation transformer is 0 megavolt-ampere (i.e. table 1 the 7th row " heavy industry "); Mountain bridge line 322 is light industry for the electricity consumption industry of distribution transforming 11 and distribution transforming 12 in the substation transformer of band, therefore, with the capacity addition of distribution transforming 11 and distribution transforming 12, namely obtaining this 10 KV light industry electricity consumption industry distribution transformer capacity is 1.80 megavolt-amperes (i.e. table 1 the 7th row " light industry "); Mountain bridge line 322 is agricultural for the industry attribute of distribution transforming 13 and distribution transforming 14 in the substation transformer of band, therefore, with the capacity addition of distribution transforming 13 and distribution transforming 14, namely obtaining this 10 KV agricultural electricity consumption industry distribution transformer capacity is 1.43 megavolt-amperes (i.e. table 1 the 7th row " agricultural "); In like manner, mountain bridge line 322 is the tertiary industry for the electricity consumption industry of distribution transforming 15 in the substation transformer of band, distribution transforming 16 and distribution transforming 17, therefore, with the capacity addition of distribution transforming 15, distribution transforming 16 and distribution transforming 17, namely obtaining this 10 KV tertiary industry electricity consumption industry distribution transformer capacity is 3.13 megavolt-amperes; 10 KV mountain bridge lines 322 in the substation transformer of band without municipal household electricity industry, so this 10 KV municipal administration household electricity industry distribution transformer capacity is 0 megavolt-ampere (i.e. table 1 the 7th row " municipal administration is lived ").According to above method, can obtain step 1(1) the electricity consumption industry distribution transformer capacity of listed other 10 KV Alpinia japonica lines 412, mountain spring II line 326, mountain town line 324, mountain nitrogen line 408 and circuit 1;
(2) calculate 10 KV substation transformer total volumies, with step 1(4) in the distribution transformer capacity addition that is connected with a certain 10 KVs, namely obtain this 10 KV substation transformer total volume, Using such method, obtain step 1(1) listed 10 KV substation transformer total volumies, take 10 KV mountain bridge lines 322 as example, with the substation transformer (distribution transforming 11 of this 10 KV for band, distribution transforming 12, distribution transforming 13, distribution transforming 14, distribution transforming 15, distribution transforming 16, distribution transforming 17) capacity addition, namely obtaining this 10 KV is 6.36 megavolt-amperes for the substation transformer total volume of being with.According to said method, can obtain step 1(1) in listed other 10 KV Alpinia japonica lines 412, mountain spring II line 326, mountain town line 324, mountain nitrogen line 408 and circuit 1 electricity consumption industry distribution transformer capacity be respectively 9.45 megavolt-amperes, 11.60 megavolt-ampere, 9.68 megavolt-ampere, 13.90 megavolt-ampere, 12.30 megavolt-ampere, 10 KV substation transformer total volume result of calculations see Table 1 the 8th row;
(3) calculate 10 KV electricity consumption industry ratios, utilize a certain 10 KV electricity consumption industry distribution transformer capacities that obtain in this step (1) divided by the same 10 KV substation transformer total volumies that obtain in this step (2), can calculate this 10 KV electricity consumption industry ratio.According to said method, but calculation procedure 1(1) listed 10 KV electricity consumption industry ratios, take mountain bridge line 322 as example, utilize to obtain this 10 KV heavy industry electricity consumption industry distribution transformer capacity (0 megavolt-ampere) in step (1) divided by the substation transformer total volume (6.36 megavolt-ampere) of this 10 KV that obtains in this step (2) for band, can calculate this 10 KV heavy industry electricity consumption industry ratio is 0%.In like manner, can calculate 10 kilovolts of mountain bridge line 322 light industry, agricultural, the tertiary industry and municipal household electricity industry ratio and be respectively 0.00%, 28.30%, 22.48%, 49.21%, 0.00%.According to said method, but calculation procedure 1(1) in the electricity consumption industry ratio of listed other 10 KV Alpinia japonica lines 412, mountain spring II line 326, mountain town line 324, mountain nitrogen line 408 and circuit 1,10 KV electricity consumption industry ratio result of calculations see Table 1 the 9th row;
Step 3, in the real-time total power load of line computation 220 kv substations:
(1) in the line computation 10 real-time power loads of KV, utilize step 1(2) in a certain the 10 real-time burdens with power of KV outlet switch add step 1(3) in real-time total meritorious the exerting oneself of same 10 KV power supplys, can be in the real-time power load of this 10 KV of line computation.Using such method, calculation procedure 1(1 online) the listed 10 real-time power loads of KV, take 10 KV mountain bridge lines as example, utilize step 1(2) in the real-time burden with power of this 10 KV outlet switch (1.04 megawatt) add step 1(3) in real-time total meritorious the exerting oneself (1.46 megawatt) of this line power, can be 2.5 megawatts in the real-time power load of this 10 KV of line computation.In like manner, can obtain step 1(1) listed other 10 KV Alpinia japonica lines 412, mountain spring II line 326, mountain town line 324, mountain nitrogen line 408 and the real-time power load of circuit 1 be respectively 4.14 megawatts, 3.70 megawatt, 3.42,4.93 megawatt, 4.07 megawatt, the 10 real-time Calculation of electric charge results of KV are table 1 the 1st row and the 2nd row addition, the results are shown in Table 1 the 10th row;
(2) in the in real time total power load of line computation 220 kv substations, with the 10 real-time power load of the KV additions one by one that obtain in this step (1), can be 22.76 megawatts in the in real time total power load of line computation 220 kv substations, be about to table 1 the 10th each row addition of row, result of calculation sees Table 1 the 11st row;
Step 4, the online 220 kv substation electricity consumption industry compositions of calculating in real time:
(1) in the line computation 10 real-time burdens with power of KV electricity consumption industry, utilize step 2(3) in a certain 10 KV electricity consumption industry ratios obtaining multiply by step 3(1) in the same 10 real-time power loads of KV that obtain, namely obtain the real-time burden with power of this 10 KV electricity consumption industry, Using such method, obtain step 1(1) the listed 10 real-time burdens with power of KV electricity consumption industry, take 10 kilovolts of mountain bridge lines 322 as example, utilize step 2(3) in this 10 KV heavy industry electricity consumption industry ratio (0%) of obtaining multiply by step 3(1) in the real-time power load of this 10 KV (2.5 megawatt) that obtains, namely obtain real-time burden with power 0.00 megawatt of this 10 KV heavy industry electricity consumption industry, in like manner, can obtain this 10 KV light industry, agricultural, the tertiary industry and the real-time burden with power of municipal household electricity industry are respectively 0.71 megawatt, 0.56 megawatt, 1.23 megawatt, 0.00 megawatt, with the method, can arrive step 1(1) the real-time burden with power of listed other 10 KV electricity consumption industries, the ratio that the 10 real-time burdens with power of KV electricity consumption industry namely equal table 1 the 9th corresponding 10 KV electricity consumption industries of row multiply by the 10th row, result of calculation sees Table 1 the 12nd row,
(2) in the line computation 220 real-time burdens with power of kv substation electricity consumption industry, with the identical real-time burden with power addition of electricity consumption industry attribute in whole 10 KVs that obtain in this step (1), can be in the line computation 220 real-time burdens with power of kv substation electricity consumption industry, be about to the identical real-time burden with power addition of electricity consumption industry attribute in the 12nd row in table 1, obtain the 220 real-time burdens with power of kv substation electricity consumption industry, result of calculation sees Table 1 the 13rd row;
For example with the real-time burden with power addition of heavy industry electricity consumption industry in whole 10 KVs that obtain in this step (1), can be 6.87 megawatts in the line computation 220 real-time burdens with power of kv substation heavy industry electricity consumption industry, in like manner, can obtain 220 kv substation light industry, agricultural, the tertiary industry and the real-time burden with power of municipal household electricity industry and be respectively 4.39 megawatts, 1.81 megawatt, 7.15 megawatt, 2.54 megawatts;
(3) online real-time statistics 220 kv substation electricity consumption industry compositions, utilize the 220 real-time burdens with power of kv substation electricity consumption industry that obtain in this step (2) divided by step 3(2) in the in real time total power load of 220 kv substations that obtain, be about to the in real time total power load of 220 kv substations that in table 1, the 12nd real-time burden with power of row electricity consumption industry obtains divided by table 1 the 11st row, can realize the 220 online real-time statisticss of kv substation electricity consumption industry composition, result of calculation sees Table 1 the 14th row, for example utilize the 220 real-time burdens with power of kv substation heavy industry electricity consumption industry (6.87 megawatt) that obtain in this step (2) divided by step 3(2) in the in real time total power load (22.76 megawatt) of 220 kv substations that obtain, can obtain 220 kv substation heavy industry electricity consumption industry compositions is 30.18%, in like manner, can obtain 220 kv substation light industry, agricultural, the tertiary industry and municipal household electricity industry composition are respectively 19.29%, 7.96%, 31.43%, 11.14%.
The table 1 220 online real-time statistics tables of kv substation electricity consumption industry composition
Figure DEST_PATH_DEST_PATH_IMAGE001

Claims (1)

1. online real-time statistical method of kv substation electricity consumption industry composition is characterized in that carrying out according to the following steps:
Affiliated 10 KV relevant informations in step 1, statistics 220 kv substation service areas:
(1) 10 KVs under listing one by one in 220 kv substation service areas;
(2) the Online statistics 10 real-time burdens with power of KV outlet switch, the listed 10 real-time burdens with power of KV outlet switch in territory of use power administration this step of energy management system Online statistics (1), the real-time burden with power of wherein flowing out 10 kilovolts of buses on the occasion of, the real-time burden with power that flows into 10 kilovolts of buses is negative value;
(3) Online statistics is incorporated in real time total meritorious exerting oneself of 10 KV power supplys into, and territory of use power administration energy management system Online statistics is incorporated the listed 10 KV power supplys of this step (1) total meritorious exerting oneself in real time into, its size be on the occasion of;
(4) statistics 10 KV substation transformer titles, capacity and industry attribute, add up the distribution transformer capacity that is connected with listed 10 KVs in this step (1) by platform, and indicate the electricity consumption industry attribute of every station power distribution on-load that transformer supplies, namely every station power distribution on-load that transformer supplies is to belong to which kind of in 5 large electricity consumption industries (being heavy industry electricity consumption, light industry electricity consumption, agriculture electricity consumption, tertiary industry electricity consumption, municipal electricity consumption);
Step 2, calculating 10 KV electricity consumption industry ratios:
(1) calculate 10 KV electricity consumption industry distribution transformer capacities, at step 1(4) in choose arbitrarily 1 10 KV, to be connected with this circuit and distribution transformer capacity addition that electricity consumption industry attribute is identical, namely obtain this 10 KV electricity consumption industry distribution transformer capacity.Using such method obtains step 1(1) in listed 10 KV electricity consumption industry distribution transformer capacities;
(2) calculate 10 KV substation transformer total volumies, with step 1(4) in the distribution transformer capacity addition that is connected with a certain 10 KVs, namely obtain this 10 KV substation transformer total volume.Using such method obtains step 1(1) listed 10 KV substation transformer total volumies;
(3) calculate 10 KV electricity consumption industry ratios, utilize a certain 10 KV electricity consumption industry distribution transformer capacities that obtain in this step (1) divided by the same 10 KV substation transformer total volumies that obtain in this step (2), can calculate this 10 KV electricity consumption industry ratio.According to said method, but calculation procedure 1(1) listed 10 KV electricity consumption industry ratios;
Step 3, in the real-time total power load of line computation 220 kv substations:
(1) in the line computation 10 real-time power loads of KV, utilize step 1(2) in a certain the 10 real-time burdens with power of KV outlet switch add step 1(3) in real-time total meritorious the exerting oneself of same 10 KV power supplys, can be in the real-time power load of this 10 KV of line computation.Using such method, calculation procedure 1(1 online) the listed 10 real-time power loads of KV;
(2) in the in real time total power load of line computation 220 kv substations, with the 10 real-time power load of the KV additions one by one that obtain in this step (1), can be in the in real time total power load of line computation 220 kv substations;
Step 4, the online 220 kv substation electricity consumption industry compositions of calculating in real time:
(1) in the line computation 10 real-time burdens with power of KV electricity consumption industry, utilize step 2(3) in a certain 10 KV electricity consumption industry ratios obtaining multiply by step 3(1) in the same 10 real-time power loads of KV that obtain, namely obtain the real-time burden with power of this 10 KV electricity consumption industry.Using such method obtains step 1(1) the listed 10 real-time burdens with power of KV electricity consumption industry;
(2) in the line computation 220 real-time burdens with power of kv substation electricity consumption industry, with the identical real-time burden with power addition of electricity consumption industry attribute in whole 10 KVs that obtain in this step (1), can be in the line computation 220 real-time burdens with power of kv substation electricity consumption industry;
(3) the 220 online real-time statisticss of kv substation electricity consumption industry composition, utilize the 220 real-time burdens with power of kv substation electricity consumption industry that obtain in this step (2) divided by step 3(2) in the in real time total power load of 220 kv substations that obtain, can realize the 220 online real-time statisticss of kv substation electricity consumption industry composition.
CN201310013846.4A 2013-01-15 2013-01-15 220KV transformer substation electricity-using industry composition proportion online real-time counting method Active CN103123715B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310013846.4A CN103123715B (en) 2013-01-15 2013-01-15 220KV transformer substation electricity-using industry composition proportion online real-time counting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310013846.4A CN103123715B (en) 2013-01-15 2013-01-15 220KV transformer substation electricity-using industry composition proportion online real-time counting method

Publications (2)

Publication Number Publication Date
CN103123715A true CN103123715A (en) 2013-05-29
CN103123715B CN103123715B (en) 2014-04-09

Family

ID=48454681

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310013846.4A Active CN103123715B (en) 2013-01-15 2013-01-15 220KV transformer substation electricity-using industry composition proportion online real-time counting method

Country Status (1)

Country Link
CN (1) CN103123715B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104750994A (en) * 2015-04-03 2015-07-01 国家电网公司 Method for judging transient instability dominance based on outer region power ratio
CN108429253A (en) * 2018-02-12 2018-08-21 中国南方电网有限责任公司 The construction method of the load user property model of multi-level collaborative
CN111162523A (en) * 2020-01-08 2020-05-15 国网湖南省电力有限公司 Method for calculating proportion of induction motor in transformer substation load model
CN112561259A (en) * 2020-12-02 2021-03-26 国网湖南省电力有限公司 Intelligent online load modeling method for transformer substation

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101282040A (en) * 2008-05-09 2008-10-08 天津大学 Method for real time sorting non-intrusion type electric load
CN101777765A (en) * 2010-01-27 2010-07-14 中国电力科学研究院 On-line load simulation method of power system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101282040A (en) * 2008-05-09 2008-10-08 天津大学 Method for real time sorting non-intrusion type electric load
CN101777765A (en) * 2010-01-27 2010-07-14 中国电力科学研究院 On-line load simulation method of power system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张磊等: "统计综合法电力系统负荷建模平台的开发", 《电力系统及其自动化学报》, vol. 22, no. 1, 28 February 2010 (2010-02-28), pages 120 - 125 *
邱丽萍等: "华北电网综合负荷建模研究", 《电网技术》, vol. 34, no. 3, 31 March 2010 (2010-03-31), pages 72 - 78 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104750994A (en) * 2015-04-03 2015-07-01 国家电网公司 Method for judging transient instability dominance based on outer region power ratio
CN104750994B (en) * 2015-04-03 2017-05-17 国家电网公司 Method for judging transient instability dominance based on outer region power ratio
CN108429253A (en) * 2018-02-12 2018-08-21 中国南方电网有限责任公司 The construction method of the load user property model of multi-level collaborative
CN111162523A (en) * 2020-01-08 2020-05-15 国网湖南省电力有限公司 Method for calculating proportion of induction motor in transformer substation load model
CN112561259A (en) * 2020-12-02 2021-03-26 国网湖南省电力有限公司 Intelligent online load modeling method for transformer substation

Also Published As

Publication number Publication date
CN103123715B (en) 2014-04-09

Similar Documents

Publication Publication Date Title
CN105096207B (en) Important power user power supply reliability assessment method based on analytic hierarchy process
CN109286188B (en) 10kV power distribution network theoretical line loss calculation method based on multi-source data set
CN105375477A (en) Rural power distribution network line loss calculation method and system
CN102651049B (en) Method for calculating loss reducing rate of newly built transformer station of electric power system
CN102593839A (en) Difference adjustment coefficient setting method of generator excitation system considering all operating manners of power grid
CN103123715B (en) 220KV transformer substation electricity-using industry composition proportion online real-time counting method
CN105046584A (en) K-MEANS algorithm-based ideal line loss rate calculation method
CN104375035A (en) Method for testing energy efficiency of energy-saving device
CN103532136A (en) On-line computation and aid decision making system and on-line computation and aid decision making method for province-prefecture-country integrated network loss
CN103887792B (en) A kind of low-voltage distribution network modeling method containing distributed power source
CN103632031B (en) A kind of rural area based on load curve decomposition load type load modeling method
CN105893714B (en) Based on the detection of automatic voltage control system closed loop and appraisal procedure under Bulk power system simulation system
CN102856896A (en) On-line analytical method for direct-current transmission loss
CN103679551A (en) Method for on-line calculation of power flow of power distribution network
CN104158177B (en) Day operation average eguivalent for calculating 10kV Calculating Network Theoretical Line Loss loads methodology
CN109840646A (en) Voltage monitoring method based on big data processing
CN104134167A (en) Power-distribution-network state simulation and evaluation system based on mesh topology structure
Bie et al. Smart Grid in China: a promising solution to China’s energy and environmental issues
CN110688619A (en) Theoretical line loss calculation system and method for power distribution network
CN106203742A (en) A kind of grid equipment Energy efficiency evaluation based on energy-conservation return rate and selection method
CN104166767A (en) Method for converting transformer zero-sequence test data into zero-sequence parameters used for computation
CN102663159B (en) Layered automatic configuration and optimization method of single line diagram outside power distribution network
CN105046583A (en) Power grid model partitioning method suitable for distributed real-time data processing
CN201417948Y (en) Distribution network status and operating mode optimizing system based on DSCADA system
CN104135077A (en) Power-distribution-network state simulation and evaluation system based on tree topology structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: HUNAN ELECTRIC POWER COMPANY HUNAN UNIVERSITY

Free format text: FORMER OWNER: HUNAN UNIVERSITY

Effective date: 20130819

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: HUNAN ELECTRIC POWER COMPANY

Effective date: 20130819

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 410007 CHANGSHA, HUNAN PROVINCE TO: 100031 DONGCHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20130819

Address after: 100031 West Chang'an Avenue, Beijing, No. 86

Applicant after: State Grid Corporation of China

Applicant after: Electric Power of Hunan

Applicant after: Hunan University

Address before: 410007 No. 388 North Shaoshan Road, Yuhua District, Hunan, Changsha

Applicant before: Electric Power of Hunan

Applicant before: Hunan University

C14 Grant of patent or utility model
GR01 Patent grant