Publication number
CN103084316B
CN103084316B CN201110334928.XA CN201110334928A CN103084316B CN 103084316 B CN103084316 B CN 103084316B CN 201110334928 A CN201110334928 A CN 201110334928A CN 103084316 B CN103084316 B CN 103084316B
Authority
CN
China
Prior art keywords
dacroment
flow structure
concurrent flow
temperature
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110334928.XA
Other languages
Chinese (zh)
Other versions
CN103084316A (en
Inventor
黄汉涛
麻更新
张红豪
谷涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Kelin Motor Vehicle Air Conditioning Co Ltd
Original Assignee
Zhengzhou Kelin Motor Vehicle Air Conditioning Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Kelin Motor Vehicle Air Conditioning Co Ltd filed Critical Zhengzhou Kelin Motor Vehicle Air Conditioning Co Ltd
Priority to CN201110334928.XA priority Critical patent/CN103084316B/en
Publication of CN103084316A publication Critical patent/CN103084316A/en
Application granted granted Critical
Publication of CN103084316B publication Critical patent/CN103084316B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Application Of Or Painting With Fluid Materials (AREA)

Abstract

A manufacture method for air conditioning condenser for vehicle, it comprises the steps: 1. to sinter oil removing: heat concurrent flow structure condenser core in heating furnace, is warmed up to 200 ~ 300 degree of high temperature; 2. mechanical ball blast method is adopted to clean: the diameter range of the shot that shot-blasting machine uses is 0.1-0.6mm, then uses compressed air dedusting; Concurrent flow structure condenser core surface impurity, up to about 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C; 3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface; 4. toast: temperature controlling range is toasted between 200 ~ 300 degree, 10 ~ 15 minutes time; 5. secondary spraying: the Dacroment zinc-base prepared met coating solution with spray gun and again to uniformly spray at each position, concurrent flow structure chiller core surface one time; 6. secondary baking, Dacroment technique baking temperature is in 250 ~ 350 scopes, and 20 ~ 40 minutes time, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm; 7. adopt air blast to carry out cooling, dry.

Description

A kind of manufacture method of air conditioning condenser for vehicle
Technical field
The present invention relates to a kind of manufacture method of parallel-flow condenser used in automobile air conditioners.
Background technology
Along with the development of air conditioning for automobiles industry, traditional tube-fin condenser cannot adapt to the demand in market because of high in cost of production reason, and people be more concerned about be adopt aluminum serpentine condenser, parallel flow condenser application and research application thereof on.But adopt merely hot spray painted zinc or surperficial electrophoresis plastic-blasting all not to reach desirable effect for a long time.Simple aluminium flat conduit hot spray painted zinc can't resolve NOLOCK soldering opening Anticorrosion; Surface electrophoresis plastic-blasting considerably reduces the heat exchange efficiency of condenser, and megathermal climate effect is poor, and air-conditioning system efficiency reduces.Industry is badly in need of will needing to look for a kind of anticorrosion treatment technology technology, meets the need of market.
Summary of the invention
The object of this invention is to provide a kind of manufacture method of air conditioning condenser for vehicle, after adopting the method, parallel-flow condenser used in automobile air conditioners has high antiseptic property, according to ASTM/G85-1998 " modification salt fog test method " test, anticorrosion grade can reach 10/5vsA level.
For achieving the above object, the technical scheme of patent employing of the present invention:
The present invention adopts hot spray painted zinc flat tube to be processed into concurrent flow structure condenser core by NOCLOK solder technology, and adopt the process of Dacroment surface spraying to described concurrent flow structure condenser core, it comprises the steps:
1. sinter oil removing: in heating furnace, concurrent flow structure condenser core is heated, be warmed up to 200 ~ 300 degree of high temperature;
2. mechanical ball blast method is adopted to clean: the diameter range of the shot that shot-blasting machine uses is 0.1-0.6mm, then uses compressed air dedusting; Concurrent flow structure condenser core surface impurity, up to about 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C;
3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface;
4. toast: temperature controlling range is toasted between 200 ~ 300 degree, 10 ~ 15 minutes time;
5. secondary spraying: the Dacroment zinc-base prepared met coating solution with spray gun and again to uniformly spray at each position, concurrent flow structure chiller core surface one time;
6. secondary baking, Dacroment technique baking temperature is in 250 ~ 350 scopes, and 20 ~ 40 minutes time, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm;
7. adopt air blast to carry out cooling, dry.
Described step 3., 5. in adopt the coating procedure of Dacroment all to carry out in indoor.
In step bake process 4., temperature controls between 230 ~ 280 degree; In step secondary baking process 6., temperature controls between 280 ~ 320 degree.
Adopt the present invention of technique scheme, adopt the surperficial Dacroment processing method after improving, make anticorrosion grade reach 10/5vsA level.Test that its effect is shown in " modification salt fog test method ".
(1) test specimen
1, PLIA-001 concurrent flow core body (common)
1, PLIA-001 concurrent flow core body (surperficial Dacroment process)
(2) test requirements document and test method
By the requirement of GB/T2423.17-2008 standard, salt spray test is carried out to 2 of test specimen PLIA-011 concurrent flow core bodys.Concrete test requirements document is as follows: concentration of salt solution is (5+1) %, and the pH value of solution is 6.5 ~ 7.2, and test temperature is (35+2) DEG C, and the test period is 500 hours.After off-test, the presentation quality of test exemplar is checked, the salt fog resistance performance of GB/T6461-2002 standard to exemplar is installed and evaluates, and the air-tightness of exemplar is tested.
(3) result of the test
1) presentation quality inspection and salt fog resistance assessment of performance
A) PLIA-001 concurrent flow core body (common): sample about has the gross area of 1.2% occur parent metal corrosion (R p=5) and residual area there is approximately being less than the moderate dot etching (R of the gross area 10% a, and the tectal mild corrosion of positive polarity being less than the gross area 1.5% appears in surface: 5/3mA, 5SC=3);
B) PLIA-001 concurrent flow core body (surperficial Dacroment process): the parent metal corrosion (R being less than the gross area 0.1% appears in sample p=9), there is being less than the tectal mild corrosion (R of positive polarity of the gross area 0.25% in surface a=8): 9/8SC.
2) airtight test result
After test, check the sealing of two cover PLIA-001 concurrent flow core bodys, the sealing of exemplar is intact, does not find to let out gas leak phenomenon.
Detailed description of the invention
Embodiment 1
A manufacture method for air conditioning condenser for vehicle, it adopts hot spray painted zinc flat tube to be processed into concurrent flow structure condenser core by NOCLOK solder technology, and adopt the process of Dacroment surface spraying to concurrent flow structure condenser core, it comprises the steps:
1. sinter oil removing: in heating furnace, concurrent flow structure condenser core is heated, be warmed up to 200 ~ 300 degree of high temperature.
2. adopt mechanical ball blast method to clean: the diameter range of the shot that shot-blasting machine uses is 0.1-0.6mm, then uses compressed air dedusting, the dust of removing focuses on after special powder collector is collected; Concurrent flow structure condenser core surface impurity, up to about 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C.
3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface.The above-mentioned Dacroment Zinc Based Comples Coatings solution prepared is commercial products.
4. toast: temperature controlling range is toasted between 200 ~ 300 degree, 10 ~ 15 minutes time.
5. secondary spraying: the Dacroment zinc-base prepared met coating solution with spray gun and again to uniformly spray at each position, concurrent flow structure chiller core surface one time.
6. secondary baking, Dacroment technique baking temperature is in 250 ~ 350 scopes, and too low, the too high Dacroment that will all can make of temperature loses antiseptic power, and baking time 20 ~ 40 minutes, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm.
7. adopt that air blast carries out cooling, drying has air blast cooling effect simultaneously, within one hour, be cooled to normal temperature.
Above-mentioned steps 3., 5. in adopt the coating procedure of Dacroment all to carry out in indoor, avoiding spray solution to meet illumination can be aging rapidly.
Embodiment 2
A manufacture method for air conditioning condenser for vehicle, it adopts hot spray painted zinc flat tube to be processed into concurrent flow structure condenser core by NOCLOK solder technology, and adopt the process of Dacroment surface spraying to concurrent flow structure condenser core, it comprises the steps:
1. sinter oil removing: in heating furnace, concurrent flow structure condenser core is heated, be warmed up to 130 ~ 270 degree of high temperature.
2. adopt mechanical ball blast method to clean: the diameter range of the shot that shot-blasting machine uses is 0.2-0.5mm, then uses compressed air dedusting, the dust of removing focuses on after special powder collector is collected; Concurrent flow structure condenser core surface impurity, up to about 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C.
3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface.
4. toast: temperature controlling range is toasted between 230 ~ 280 degree, 12 ~ 14 minutes time.
5. secondary spraying: the Dacroment zinc-base prepared met coating solution with spray gun and again to uniformly spray at each position, concurrent flow structure chiller core surface one time.
6. secondary baking, Dacroment technique baking temperature is in 280 ~ 320 scopes, and too low, the too high Dacroment that will all can make of temperature loses antiseptic power, and baking time 25 ~ 35 minutes, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm.
7. adopt that air blast carries out cooling, drying has air blast cooling effect simultaneously, within one hour, be cooled to normal temperature.
Other technologies feature is identical with embodiment 1.
Embodiment 3
A manufacture method for air conditioning condenser for vehicle, it adopts hot spray painted zinc flat tube to be processed into concurrent flow structure condenser core by NOCLOK solder technology, and adopt the process of Dacroment surface spraying to concurrent flow structure condenser core, it comprises the steps:
1. sinter oil removing: in heating furnace, concurrent flow structure condenser core is heated, be warmed up to 200 degree of high temperature.
2. adopt mechanical ball blast method to clean: the diameter range of the shot that shot-blasting machine uses is 0.1mm, then uses compressed air dedusting, the dust of removing focuses on after special powder collector is collected; Concurrent flow structure condenser core surface impurity, up to about 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C.
3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface.
4. toast: temperature controlling range is toasted at 200 degree, 15 minutes time.
5. secondary spraying: the Dacroment zinc-base prepared met coating solution with spray gun and again to uniformly spray at each position, concurrent flow structure chiller core surface one time.
6. secondary baking, Dacroment technique baking temperature is in 250 scopes, and too low, the too high Dacroment that will all can make of temperature loses antiseptic power, and baking time 40 minutes, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm.
7. adopt that air blast carries out cooling, drying has air blast cooling effect simultaneously, within one hour, be cooled to normal temperature.
Embodiment 4
A manufacture method for air conditioning condenser for vehicle, it adopts hot spray painted zinc flat tube to be processed into concurrent flow structure condenser core by NOCLOK solder technology, and adopt the process of Dacroment surface spraying to concurrent flow structure condenser core, it comprises the steps:
1. sinter oil removing: in heating furnace, concurrent flow structure condenser core is heated, be warmed up to 300 degree of high temperature.
2. adopt mechanical ball blast method to clean: the diameter range of the shot that shot-blasting machine uses is 0.6mm, then uses compressed air dedusting, the dust of removing focuses on after special powder collector is collected; Concurrent flow structure condenser core surface impurity, up to about 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C.
3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface.
4. toast: temperature controlling range is toasted between 300 degree, 10 minutes time.
5. secondary spraying: the Dacroment zinc-base prepared met coating solution with spray gun and again to uniformly spray at each position, concurrent flow structure chiller core surface one time.
6. secondary baking, Dacroment technique baking temperature is in 350 scopes, and too low, the too high Dacroment that will all can make of temperature loses antiseptic power, and baking time 20 minutes, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm.
7. adopt that air blast carries out cooling, drying has air blast cooling effect simultaneously, within one hour, be cooled to normal temperature.
Embodiment 5
A manufacture method for air conditioning condenser for vehicle, it adopts hot spray painted zinc flat tube to be processed into concurrent flow structure condenser core by NOCLOK solder technology, and adopt the process of Dacroment surface spraying to concurrent flow structure condenser core, it comprises the steps:
1. sinter oil removing: in heating furnace, concurrent flow structure condenser core is heated, be warmed up to 240 degree of high temperature.
2. adopt mechanical ball blast method to clean: the diameter range of the shot that shot-blasting machine uses is 0.3mm, then uses compressed air dedusting, the dust of removing focuses on after special powder collector is collected; Concurrent flow structure condenser core surface impurity, up to about 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C.
3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface.
4. toast: temperature controlling range is toasted between 240 degree, 13 minutes time.
5. secondary spraying: the Dacroment zinc-base prepared met coating solution with spray gun and again to uniformly spray at each position, concurrent flow structure chiller core surface one time.
6. secondary baking, Dacroment technique baking temperature is in 280 scopes, and too low, the too high Dacroment that will all can make of temperature loses antiseptic power, and baking time 30 minutes, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm.
7. adopt that air blast carries out cooling, drying has air blast cooling effect simultaneously, within one hour, be cooled to normal temperature.
Embodiment 6
A manufacture method for air conditioning condenser for vehicle, it adopts hot spray painted zinc flat tube to be processed into concurrent flow structure condenser core by NOCLOK solder technology, and adopt the process of Dacroment surface spraying to concurrent flow structure condenser core, it comprises the steps:
1. sinter oil removing: in heating furnace, concurrent flow structure condenser core is heated, be warmed up to 270 degree of high temperature.
2. adopt mechanical ball blast method to clean: the diameter range of the shot that shot-blasting machine uses is 0.5mm, then uses compressed air dedusting, the dust of removing focuses on after special powder collector is collected; Concurrent flow structure condenser core surface impurity, up to about 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C.
3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface.
4. toast: temperature controlling range is toasted between 260 degree, 14 minutes time.
5. secondary spraying: the Dacroment zinc-base prepared met coating solution with spray gun and again to uniformly spray at each position, concurrent flow structure chiller core surface one time.
6. secondary baking, Dacroment technique baking temperature is in 320 scopes, and too low, the too high Dacroment that will all can make of temperature loses antiseptic power, and baking time 26 minutes, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm.
7. adopt that air blast carries out cooling, drying has air blast cooling effect simultaneously, within one hour, be cooled to normal temperature.

Claims (1)

1. the manufacture method of an air conditioning condenser for vehicle, it adopts hot spray painted zinc flat tube to be processed into concurrent flow structure condenser core by NOCLOK solder technology, it is characterized in that: adopt the process of Dacroment surface spraying to described concurrent flow structure condenser core, it is made up of following steps:
1. oil removing is sintered: in heating furnace, concurrent flow structure condenser core is heated, be warmed up to 200-300 DEG C of high temperature;
2. mechanical ball blast method is adopted to clean: the diameter range of the shot that shot-blasting machine uses is 0.1-0.6mm, then uses compressed air dedusting; Concurrent flow structure condenser core surface impurity, up to 60 DEG C, is removed, and is removed each position burr by the Part temperature after ball blast dedusting in time being down to 20 DEG C;
3. spray: with spray gun the Dacroment Zinc Based Comples Coatings dissolution homogeneity prepared is sprayed on each position, concurrent flow structure chiller core surface;
4. toast: temperature controlling range is toasted between 230--280 DEG C, time 10--15 minute;
5. secondary spraying: the Dacroment Zinc Based Comples Coatings solution prepared to be uniformly sprayed again at each position, concurrent flow structure chiller core surface one time with spray gun;
6. secondary baking, Dacroment technique baking temperature within the scope of 280--320 DEG C, time 20--40 minute, Dacroment Zinc Based Comples Coatings solution chemistry is reacted completely, and coating is firm;
7. adopt air blast to carry out cooling, dry;
Described step 3., 5. in adopt the coating procedure of Dacroment all to carry out in indoor.
CN201110334928.XA 2011-10-31 2011-10-31 A kind of manufacture method of air conditioning condenser for vehicle Active CN103084316B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110334928.XA CN103084316B (en) 2011-10-31 2011-10-31 A kind of manufacture method of air conditioning condenser for vehicle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110334928.XA CN103084316B (en) 2011-10-31 2011-10-31 A kind of manufacture method of air conditioning condenser for vehicle

Publications (2)

Publication Number Publication Date
CN103084316A CN103084316A (en) 2013-05-08
CN103084316B true CN103084316B (en) 2015-08-19

Family

ID=48197735

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110334928.XA Active CN103084316B (en) 2011-10-31 2011-10-31 A kind of manufacture method of air conditioning condenser for vehicle

Country Status (1)

Country Link
CN (1) CN103084316B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106196747A (en) * 2016-06-30 2016-12-07 浙江龙泉凯利达汽车空调有限公司 A kind of heat absorption plate core structure condenser and processing technology thereof
CN107138371A (en) * 2017-04-10 2017-09-08 青岛海尔空调器有限总公司 The processing method of evaporator surface
CN111947503B (en) * 2020-08-03 2022-03-25 湖北迪峰换热器股份有限公司 Heat exchanger core group used in acid-base corrosion environment and coating method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201434549Y (en) * 2009-06-25 2010-03-31 大洋昭和汽车空调(大连)有限公司 Condenser for Audi B8 platform vehicle

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201434549Y (en) * 2009-06-25 2010-03-31 大洋昭和汽车空调(大连)有限公司 Condenser for Audi B8 platform vehicle

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
达克罗(涂层)防腐新技术;沈志明;《电子机械工程》;20030725;第19卷(第3期);第4-6页 *

Also Published As

Publication number Publication date
CN103084316A (en) 2013-05-08

Similar Documents

Publication Publication Date Title
CN101480671B (en) Technique for producing double-layer copper brazing steel tube for air-conditioner
CN103084316B (en) A kind of manufacture method of air conditioning condenser for vehicle
CN113249726B (en) Method for preparing micron-sized spherical super-hydrophobic composite coating on surface of magnesium alloy
CN104919070A (en) Aluminum alloy brazing sheet for fin, heat exchanger, and method for producing heat exchanger
CN100463770C (en) Process for producing double-layer wrapped welding tube used for connecting indoor/outdoor units of air conditioner
CN102153696A (en) Water-soluble acrylic resin and preparation method thereof
CN112014133A (en) Method for confirming low-temperature optimal charging amount of refrigerant of heat pump air conditioner of pure electric vehicle
CN102626724B (en) Method for producing titanium alloy pipe
CN218179081U (en) Air return type low dew point dehumidifier based on finned tube adsorption coating
CN203007463U (en) Temperature control system for electroplating shop
CN201104155Y (en) Corrosion resistant enamel heat pipe
CN100507432C (en) Surface treatment process for heat sink of air conditioner
CN101113879A (en) Corrosion resistant enamel hot pipe
CN101966413B (en) Venturi scrubber valve body and manufacturing process thereof
CN101671828A (en) Method for processing automobile air conditioner evaporator surface
CN201974097U (en) Automobile air-conditioning spraying device
CN205066250U (en) Vapour vehicle air conditioner regenerator
CN106196747A (en) A kind of heat absorption plate core structure condenser and processing technology thereof
CN108138273A (en) For the high intensity and corrosion resisting alloy of HVAC & R systems
CN111921819A (en) Preparation method of super-hydrophobic coating for air source heat pump evaporator
CN216281794U (en) Sea side salt fog area is with directly expanding formula forced air cooling heat pump air treatment unit
CN217465492U (en) Anti-frosting base material, evaporator and refrigerator
CN112144001B (en) Pretreatment method for enhancing bonding strength of VW75 magnesium alloy thermal barrier coating and substrate
CN205505392U (en) Novel indirect hot -blast furnace
CN204350329U (en) A kind of PTC electric heater element of anti-oxidation dust

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant