CN103078285A - Nine-bundle conductor transmission line current circulation intelligent ice-melting device - Google Patents

Nine-bundle conductor transmission line current circulation intelligent ice-melting device Download PDF

Info

Publication number
CN103078285A
CN103078285A CN2013100210861A CN201310021086A CN103078285A CN 103078285 A CN103078285 A CN 103078285A CN 2013100210861 A CN2013100210861 A CN 2013100210861A CN 201310021086 A CN201310021086 A CN 201310021086A CN 103078285 A CN103078285 A CN 103078285A
Authority
CN
China
Prior art keywords
sub
conductor
ice
conductive plate
intelligent controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100210861A
Other languages
Chinese (zh)
Other versions
CN103078285B (en
Inventor
张志劲
洪敏�
蒋兴良
胡琴
洪伟
邵文峰
胡建林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Guangren Iron Tower Manufacture Co ltd
Chongqing University
Original Assignee
CHONGQING GUANGREN TOWER MANUFACTURING CO LTD
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING GUANGREN TOWER MANUFACTURING CO LTD, Chongqing University filed Critical CHONGQING GUANGREN TOWER MANUFACTURING CO LTD
Priority to CN201310021086.1A priority Critical patent/CN103078285B/en
Publication of CN103078285A publication Critical patent/CN103078285A/en
Application granted granted Critical
Publication of CN103078285B publication Critical patent/CN103078285B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Driving Mechanisms And Operating Circuits Of Arc-Extinguishing High-Tension Switches (AREA)
  • Distribution Board (AREA)

Abstract

The invention relates to a nine-bundle conductor transmission line current circulation intelligent ice-melting device which achieves the purpose of ice-melting in the way that the device judges if ice coating exists by monitoring external environmental conditions, the on-off of a breaker is controlled by an intelligent controller, and the total current transmitted by a nine-bundle conductor is respectively transferred to part of sub-conductors to increase the electric current density of the sub-conductors. The intelligent controller automatically computes time needed to melt ice by adopting the load current measured by an electric sensor, the ice coating conditions measured by an ice coating parameter monitoring unit, and the external environmental conditions, controls the breaker to transfer the current to the other part of the sub-conductors after ice-melting of the part of the sub-conductors is finished, and returns to the normal work state after ice layers on the nine sub-conductors are melted and fall off completely. When the nine-bundle conductor transmission line current circulation intelligent ice-melting device disclosed by the invention works, the intelligent controller is used for overall control, the work judgment standard of the intelligent controller is provided by the electric sensor, the ice coating parameter monitoring unit and the external environmental conditions, and the automatic ice-melting and deicing of the transmission lines without manual intervention are achieved.

Description

Nine bundle conductor transmission line current cycle intelligence deicing device
Technical field
The present invention relates to voltage technology of transmission of electricity field, particularly a kind of ultra-high-tension power transmission line deicing device for nine bundle conductors.
Background technology
In the winter time in the environment of low temperature, high humility, the icing phenomenon can occur in the high-tension electricity transmission line, serious icing causes that electric power line pole tower collapses, conductor cord disconnection etc. affects the major accident of power system security reliability service, cause electric grid large area power cut, have a strong impact on industrial and agricultural production and people's lives, and cause the tremendous economic loss.
Ultra-high-tension power transmission line is anti-icing, ice-melt and deicing are the focus of paying close attention to both at home and abroad always.The anti-icing technology of existing deicing high-voltage power transmission line is still immature, can not satisfy the requirement of large tracts of land anti-icing and deicing, though part deicing technology can be used in engineering, needs to carry out under additional equipment or manual operation guidance.Anti-icing transmission line such as the disclosed a kind of multiple conducting wires of Chinese invention patent Publication Specification of publication number CN101527442A, it is to increase the ice-melt switch at the two ends of multiple conducting wires transmission line, the equal normal power-up of each wire when not needing ice-melt, interruption of power supply when needing ice-melt behind the icing, take the mode of manual operation switch, make a wire transmission electric current, all the other wires disconnect, and manual operation progressively makes the ice sheet of each wire melt.The method need to be set up switching device, change the structure of transmission line, the necessary interruption of power supply of deicing processes, ice-melt exists potential safety hazard and operation extremely inconvenient, the ice-melt cost is high, and ice-melt starts and all needing to stop artificial Subjective Intervention, can not treat icing line segment in various degree with a certain discrimination and realize anti-icing in real time, infeasible with breaker deciliter wire for supertension line, particularly can not satisfy the anti-icing of ultra high voltage bundle conductor; The and for example disclosed a kind of automatic ice melting method for multiple division electricity transmission line of the Chinese invention patent of publication number CN101459327 and special switch thereof, it is to adopt in icing transmission line two ends transformer station special switch is installed, then manual remote control is sent instruction, make special switch that action occur and realize that the transmission line electric current all is transferred to the sub-conductor for the treatment of ice-melt, this sub-conductor heating, ice-melt, this patent of invention needs the on-the-spot circuit of artificial judgment whether to have icing, and need power scheduling department to cooperate the adjusting circuit load, manual remote control is sent the ice-melt instruction at the scene at last, can't realize dividing section and real-time intelligent ice-melt according to the needs of icing degree, be difficult to be on the scene for local icing section technical staff such as micro climate microclimates and observe the icing situation and send the ice-melt instruction.
Summary of the invention
The purpose of this invention is to provide a kind of current cycle intelligence deicing device that is applied to nine bundle conductor transmission lines, it is according to the measurement result of environmental condition and ice coating state, the auto-controlled circuit breaker opening and closing, the load current of nine bundle conductor Transmission Lines is transferred to respectively single sub-conductor, increases the sub-conductor current density and reach the ice-melt purpose.
The objective of the invention is to realize by such technical scheme, it includes nine current input terminal R, nine current output terminal S and be arranged on current input terminal and current output terminal between current cycle intelligence deicing device main body, described current cycle intelligence deicing device main body includes the conductive plate that confluxes, the shunting conductive plate, division board, reference voltage plate and the electric current output board that current output terminal is installed, nine current input terminal R are fixed on the conductive plate that confluxes, the conductive plate that confluxes is connected by the primary winding contact rod as electricity-getting mutual inductor between the conductive plate with shunting, be provided with nine conducting rods at the shunting conductive plate, nine conducting rods pass division board and are connected on the reference voltage plate, between electric current output board and division board, be provided with nine with the circuit breaker of by-pass switch, a corresponding current output terminal S is fixed and be connected to arc control device one end of each circuit breaker all with the electric current output board, the arc control device other end of circuit breaker passes the reference voltage plate, and be connected with the actuator of a circuit breaker, on the shunting conductive plate, also be provided with intelligent controller and built-in icing parameter monitoring unit, intelligent controller and built-in icing parameter monitoring unit are between division board and shunting conductive plate, and intelligent controller is electrically connected with built-in icing parameter monitoring unit and actuator respectively.
Further, described intelligent controller, actuator and built-in icing parameter monitoring unit are powered by the electricity-getting mutual inductor take the reference voltage plate as benchmark.
Further, described circuit breaker and by-pass switch all arrange independently actuator.
Further, described device also includes external icing parameter monitoring unit, external icing parameter monitoring unit is used for monitoring of environmental parameter, conductor temperature, current in wire and wire icing loading condition, and the data communication device that monitors is crossed radio communication and the wired connection dual mode is sent to intelligent controller.
Further, described shunting conductive plate includes insulation daughter board and conduction daughter board, and the conduction daughter board is embedded in the center of insulation daughter board, is provided with nine hole and holes that are used for installing electricity-getting mutual inductor that are used for passing conducting rod on the conduction daughter board.
Further, described device also includes two insulating bars that pass successively respectively the conductive plate that confluxes, shunting conductive plate, division board, reference voltage plate and electric current output board.
Further, described device also includes insulation crust, and the conductive plate that confluxes, shunting conductive plate, division board, reference voltage plate and electric current output board are installed in the insulation crust.
Owing to adopted technique scheme, the present invention to have following advantage:
The present invention can be by built-in and external two kinds of modes icing parameter monitoring unit inspection to external environment condition judge whether to occur the icing phenomenon, the folding of intelligent controller control circuit breaker, the load current of nine bundle conductor Transmission Lines is transferred on a part of sub-conductor, increase the sub-conductor current density and reach the ice-melt purpose, intelligent controller calculates the ice-melt time automatically according to load current and the external environment condition parameter of power taking sensor measurement, after the complete ice-melt of this parton wire, the control circuit breaker is transferred to electric current on another part sub-conductor successively, come off until nine root conductive line surfaces ice sheets all melt, then recover normal operating conditions.The present invention controls by intelligent controller is whole in the course of the work, and the criterion of intelligent controller work is provided by the icing parameter monitoring unit of electricity-getting mutual inductor and built-in and external two kinds of modes, can realize the transmission line ice-melt work that prosthetic is intervened.
Other advantages of the present invention, target and feature will be set forth to a certain extent in the following description, and to a certain extent, based on being apparent to those skilled in the art to investigating hereinafter, perhaps can obtain from the practice of the present invention instruction.Target of the present invention and other advantages can realize and obtain by following specification and claims.
Description of drawings
Description of drawings of the present invention is as follows.
Fig. 1 is structural representation of the present invention;
Fig. 2 is workflow diagram of the present invention;
Fig. 3 is the program control block diagram of intelligent controller;
Fig. 4 is shunting conductive plate structure schematic diagram.
Among the figure: 1. conductive plate confluxes; 2. electricity-getting mutual inductor; 3. shunting conductive plate; 4. division board; 5. reference voltage plate; 6. insulation output board; 7. conducting rod; 8. built-in icing parameter monitoring unit; 9. intelligent controller; 10. circuit breaker; 11. by-pass switch; 12. actuator; 13. conduction daughter board; 14. insulation daughter board; 15. insulation crust; 16. insulating bar.
Embodiment
The invention will be further described below in conjunction with drawings and Examples.
As shown in Figure 1, current input terminal R concentrates the transmission current of nine each sub-conductor of bundle conductor through the conductive plate 1 that confluxes, utilize electricity-getting mutual inductor 2 to measure nine bundle conductor Transmission Lines electric current total values, transfer to reference voltage plate 5 through shunting conductive plate 3 and conducting rod 7, reference voltage plate 5 is connecting an end of all circuit breakers 10 and by-pass switch in parallel 11, the other end that circuit breaker 10 is connected with by-pass switch is connecting respectively the sub-S of sub-conductor current output terminal that is fixed in insulation output board 6, and each root wire correspondence is connecting a circuit breaker 10 and a by-pass switch 11 in parallel, nine circuit breaker 10 initial conditions are closure state, and nine by-pass switch 11 initial conditions in parallel are in the state of cut-offfing.Intelligent controller 9 sends whether start the ice-melt instruction according to external icing parameter monitoring unit and built-in icing parameter monitoring unit 8 measurement results and built-in control program.Division board 4 is used for actuator 12 is carried out isolation and protection with intelligent controller 9, built-in icing parameter monitoring unit 8.Reference voltage plate 5 is supply voltage reference points of electricity-getting mutual inductor, and electricity-getting mutual inductor provides working power for actuator 12, built-in icing parameter monitoring unit 8 and intelligent controller 9.By-pass switch 11 provided current channel when circuit breaker 10 lost efficacy.Insulating bar 16 is connecting respectively the conductive plate 1 that confluxes, shunting conductive plate 3, division board 4, reference voltage plate 5 and insulation output board 6, is used for machinery and fixes and install the location.
As shown in Figure 4, shunting conductive plate 3 includes insulation daughter board 14 and conduction daughter board 13, conduction daughter board 13 is embedded in the center of insulation daughter board 3, is provided with nine holes that are used for passing conducting rod 7 on the conduction daughter board 13, and the heart arranges a hole that is used for installing electricity-getting mutual inductor 2 primary conductive rods therein.
Do not need to start ice-melt if intelligent controller 9 is judged, then intelligent controller 9 sends instruction to actuator 12, and actuator determines that circuit breaker 10 and by-pass switch 11 remain on initial condition, makes nine each sub-conductor of division by moving under the normal transmission current status.
When intelligent controller 9 judgements need to start ice-melt, by the switch of control respective circuit breakers, can carry out following ice-melting mode:
Ice-melting mode one:
1) intelligent controller 9 utilizes nine bundle conductor transmission line current cycle intelligence deicing device that the Transmission Lines electric current is automatically transferred to wherein sub-conductor according to the measurement result of the load current of device built-in and external environmental parameter, ice coating state and power taking sensor measurement
Figure 2013100210861100002DEST_PATH_IMAGE002
, on sub-conductor II and the sub-conductor III, make that this three roots current in wire increases, heating, automatically calculate the ice-melt time according to the load current of ice coating state and power taking sensor measurement, within the time of automatically calculating, melt the ice sheet of this three roots wire.Intelligent controller 9 sends instruction to actuator 12, then determines circuit breaker 10 actions " cut-offfing " that sub-conductor IV, sub-conductor V, sub-conductor VI, sub-conductor VII, sub-conductor VIII and sub-conductor IX are connected by actuator 12.Make nine bundle conductor Transmission Lines current transfer to sub-conductor , on sub-conductor II and the sub-conductor III, make sub-conductor
Figure 783226DEST_PATH_IMAGE002
, the heating of sub-conductor II and sub-conductor III, ice-melt, determine the ice-melt times by intelligent controller 9.
2) sub-conductor
Figure 562963DEST_PATH_IMAGE002
, sub-conductor II and sub-conductor III ice sheet melt finish after, nine bundle conductor transmission line current cycle deicing devices are transferred to the Transmission Lines current intelligent on sub-conductor IV, sub-conductor V and the sub-conductor VI automatically, make this three roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of three root wires within the time of automatically calculating.Step 1) in, if sub-conductor
Figure 519024DEST_PATH_IMAGE002
, sub-conductor II and the ice-melt of sub-conductor III finish, and sends instruction to actuator 12 by intelligent controller 9, circuit breaker 10 action " closure ", the then sub-conductors that wire IV, sub-conductor V and sub-conductor VI are connected
Figure 395713DEST_PATH_IMAGE002
, circuit breaker 10 actions " cut-offfing " that connected of sub-conductor II and sub-conductor III, then nine bundle conductor Transmission Lines current transfer are to sub-conductor IV, sub-conductor V and sub-conductor VI, make wire IV, sub-conductor V and the heating of sub-conductor VI, ice-melt, determine the ice-melt time by intelligent controller 9.
3) ice sheet of sub-conductor IV, sub-conductor V and sub-conductor VI melts end, nine bundle conductor transmission line current cycle deicing devices are transferred to the Transmission Lines current intelligent on sub-conductor VII, sub-conductor VIII and the sub-conductor IX automatically, make this three roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this three roots wire within the time of automatically calculating.Step 2) in, sub-conductor IV, sub-conductor V and the ice-melt of sub-conductor VI finish, send instruction to actuator 12 by intelligent controller 9, circuit breaker 10 actions " closure " that sub-conductor VII, sub-conductor VIII and sub-conductor IX are connected, then circuit breaker 10 action " cut-offfing " that connected of wire IV, sub-conductor V and sub-conductor VI, then nine bundle conductor Transmission Lines current transfer are to sub-conductor VII, sub-conductor VIII and sub-conductor IX, make sub-conductor VII, sub-conductor VIII and the heating of sub-conductor IX, ice-melt, determine the ice-melt time by intelligent controller 9.
Ice-melting mode two:
1) according to the measurement result of the load current of built-in and external environmental parameter, ice coating state and the power taking sensor measurement of device, utilize nine bundle conductor transmission line current cycle intelligence deicing device that the Transmission Lines electric current is automatically transferred to wherein on the sub-conductor I and sub-conductor II, make this two roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Intelligent controller 9 sends instruction to actuator 12, then determine that by actuator 12 circuit breaker 10 actions " cut-offfing " that sub-conductor III, sub-conductor IV, sub-conductor V, sub-conductor VI, sub-conductor VII, sub-conductor VIII, sub-conductor IX connect make nine bundle conductor Transmission Lines current transfer to sub-conductor I and sub-conductor II, make the heating of sub-conductor I and sub-conductor II, ice-melt, determine the ice-melt time by intelligent controller 9.
2) ice sheet of sub-conductor I and sub-conductor II melts end, measurement result according to the load current that installs built-in and external environmental parameter, ice coating state and power taking sensor measurement, the Transmission Lines electric current is automatically transferred to wherein on the sub-conductor III and sub-conductor IV, make this two roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Step 1) in, if sub-conductor I and the ice-melt of sub-conductor II finish, send instruction to actuator 12 by intelligent controller 9, circuit breaker 10 actions " closure " that sub-conductor III and sub-conductor IV are connected, then circuit breaker 10 actions " cut-offfing " that connected of sub-conductor I and sub-conductor II, then nine bundle conductor Transmission Lines current transfer make the heating of sub-conductor III and sub-conductor IV, ice-melt to sub-conductor III and sub-conductor IV, determine the ice-melt time by intelligent controller 9.
3) ice sheet of sub-conductor III and sub-conductor IV melts end, measurement result according to the load current that installs built-in and external environmental parameter, ice coating state and power taking sensor measurement, sharp the Transmission Lines electric current is automatically transferred to wherein on the sub-conductor V and sub-conductor VI, make this two roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Step 2) in, if sub-conductor III and the ice-melt of sub-conductor IV finish, send instruction to actuator 12 by intelligent controller 9, circuit breaker 10 actions " closure " that sub-conductor V and sub-conductor VI are connected, then circuit breaker 10 actions " cut-offfing " that connected of sub-conductor III and sub-conductor IV, then nine bundle conductor Transmission Lines current transfer make the heating of sub-conductor V and sub-conductor VI, ice-melt to sub-conductor V and sub-conductor VI, determine the ice-melt time by intelligent controller 9.
4) ice sheet of sub-conductor V and sub-conductor VI melts end, measurement result according to the load current that installs built-in and external environmental parameter, ice coating state and power taking sensor measurement, the Transmission Lines electric current is automatically transferred to wherein on the sub-conductor VII and sub-conductor VIII, make this two roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Step 3) in, if sub-conductor V and the ice-melt of sub-conductor VI finish, send instruction to actuator 12 by intelligent controller 9, circuit breaker 10 actions " closure " that sub-conductor VII and sub-conductor VIII are connected, then circuit breaker 10 actions " cut-offfing " that connected of sub-conductor V and sub-conductor VI, then nine bundle conductor Transmission Lines current transfer make the heating of sub-conductor VII and sub-conductor VIII, ice-melt to sub-conductor VII and sub-conductor VIII, determine the ice-melt time by intelligent controller 9
5) ice sheet of wire VII and sub-conductor VIII melts end, measurement result according to the load current that installs built-in and external environmental parameter, ice coating state and power taking sensor measurement, the Transmission Lines electric current is automatically transferred to wherein on the sub-conductor I and sub-conductor IX, make this two roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Step 4) in, if wire VII and the ice-melt of sub-conductor VIII finish, send instruction to actuator 12 by intelligent controller 9, circuit breaker 10 actions " closure " that sub-conductor I and sub-conductor IX are connected, then circuit breaker 10 actions " cut-offfing " that connected of wire VII and sub-conductor VIII, then nine bundle conductor Transmission Lines current transfer make the heating of sub-conductor I and sub-conductor IX, ice-melt to sub-conductor I and sub-conductor IX, determine the ice-melt time by intelligent controller 9.
6) when the whole ice-melts end of the ice sheet of 9 root wires, intelligent apparatus recovers the conducting state of normal transmission electric current, waits for next icing process and starts next time deicing processes.
Ice-melting mode three:
1) according to the measurement result of the load current of built-in and external environmental parameter, ice coating state and the power taking sensor measurement of device, the Transmission Lines electric current is automatically transferred to wherein on sub-conductor I, sub-conductor II, sub-conductor III and the sub-conductor IV, make this four roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Intelligent controller 9 sends instruction to actuator 12, then determine circuit breaker 10 actions " cut-offfing " that sub-conductor V, sub-conductor VI, sub-conductor VII, sub-conductor VIII, sub-conductor IX connect by actuator 12, make nine bundle conductor Transmission Lines current transfer to sub-conductor I, sub-conductor II, sub-conductor III and sub-conductor IV, make sub-conductor I, sub-conductor II, sub-conductor III and the heating of sub-conductor IV, ice-melt, determine the ice-melt time by intelligent controller 9
2) ice sheet of sub-conductor I, sub-conductor II, sub-conductor III and sub-conductor IV melts end, measurement result according to the load current that installs built-in and external environmental parameter, ice coating state and power taking sensor measurement, the Transmission Lines electric current is automatically transferred to wherein on sub-conductor V, sub-conductor VI, sub-conductor VII, sub-conductor VIII and the sub-conductor IX, make this five roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Step 1) in, if sub-conductor I, the sub-conductor II, sub-conductor III and the ice-melt of sub-conductor IV finish, send instruction to actuator 12 by intelligent controller 9, at first make the sub-conductor V, the sub-conductor VI, the sub-conductor VII, circuit breaker 10 actions " closure " that sub-conductor VIII and sub-conductor IX are connected, then sub-conductor I, the sub-conductor II, circuit breaker 10 actions " cut-offfing " that sub-conductor III and sub-conductor IV are connected, then nine bundle conductor Transmission Lines current transfer are to the sub-conductor V, the sub-conductor VI, the sub-conductor VII, on sub-conductor VIII and the sub-conductor IX, make the sub-conductor V, the sub-conductor VI, the sub-conductor VII, sub-conductor VIII and the heating of sub-conductor IX, ice-melt is determined the ice-melt time by intelligent controller 9.
3) when the whole ice-melts end of the ice sheet of 9 root wires, intelligent apparatus recovers the conducting state of normal transmission electric current, waits for next icing process and starts next time deicing processes.
Ice-melting mode four:
1) according to the measurement result of the load current of built-in and external environmental parameter, ice coating state and the power taking sensor measurement of device, sharp the Transmission Lines electric current is automatically transferred to wherein on sub-conductor I, sub-conductor II, sub-conductor III and the sub-conductor IV, make this four roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Intelligent controller 9 sends instruction to actuator 12, then determine that by actuator 12 circuit breaker 10 actions " cut-offfing " that sub-conductor V, sub-conductor VI, sub-conductor VII, sub-conductor VIII, sub-conductor IX connect make nine bundle conductor Transmission Lines current transfer to sub-conductor I, sub-conductor II, sub-conductor III and sub-conductor IV, make sub-conductor I, sub-conductor II, sub-conductor III and the heating of sub-conductor IV, ice-melt, determine the ice-melt time by intelligent controller 9.
2) ice sheet of sub-conductor I, sub-conductor II, sub-conductor III and sub-conductor IV melts end, measurement result according to the load current that installs built-in and external environmental parameter, ice coating state and power taking sensor measurement, the Transmission Lines electric current is automatically transferred to wherein on sub-conductor V, sub-conductor VI, sub-conductor VII and the sub-conductor VIII, make this four roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Step 1) in, if sub-conductor I, the sub-conductor II, sub-conductor III and the ice-melt of sub-conductor IV finish, send instruction to actuator 12 by intelligent controller 9, at first make the sub-conductor V, the sub-conductor VI, circuit breaker 10 actions " closure " that sub-conductor VII and sub-conductor VIII are connected, then sub-conductor I, the sub-conductor II, circuit breaker 10 actions " cut-offfing " that sub-conductor III and sub-conductor IV are connected, then nine bundle conductor Transmission Lines current transfer are to the sub-conductor V, the sub-conductor VI, on sub-conductor VII and the sub-conductor VIII, make the sub-conductor V, the sub-conductor VI, sub-conductor VII and the heating of sub-conductor VIII, ice-melt is determined the ice-melt time by intelligent controller 9.
3) ice sheet of sub-conductor V, sub-conductor VI, sub-conductor VII and sub-conductor VIII melts end, measurement result according to the load current that installs built-in and external environmental parameter, ice coating state and power taking sensor measurement, the Transmission Lines electric current is automatically transferred to wherein sub-conductor I, sub-conductor II, sub-conductor III and sub-conductor IX, make this four roots current in wire increase, generate heat, load current according to ice coating state and power taking sensor measurement calculates the ice-melt time automatically, melts the ice sheet of this sub-conductor within the time of automatically calculating.Step 2) in, if sub-conductor V, the sub-conductor VI, sub-conductor VII and the ice-melt of sub-conductor VIII finish, send instruction to actuator 12 by intelligent controller 9, at first make the sub-conductor I, the sub-conductor II, circuit breaker 10 actions " closure " that sub-conductor III and sub-conductor IX are connected, then sub-conductor V, the sub-conductor VI, circuit breaker 10 actions " cut-offfing " that sub-conductor VII and sub-conductor VIII are connected, then nine bundle conductor Transmission Lines current transfer are to the sub-conductor I, the sub-conductor II, on sub-conductor III and the sub-conductor IX, make the sub-conductor I, the sub-conductor II, sub-conductor III and the heating of sub-conductor IX, ice-melt is determined the ice-melt time by intelligent controller 9.
4) when the whole ice-melts end of the ice sheet of 9 root wires, intelligent apparatus recovers the conducting state of normal transmission electric current, waits for next icing process and starts next time deicing processes.
As shown in Figure 2, external icing parameter monitoring unit Real-Time Monitoring environmental parameter, conductor temperature, current in wire and wire icing loading condition, and with above-mentioned parameter by the wireless mode real-time Transmission to intelligent controller 9, built-in icing parameter monitoring unit 8 Real-Time Monitoring environmental parameters, conductor temperature, current in wire and wire icing loading condition, and with above-mentioned parameter by the wired mode real-time Transmission to intelligent controller 9, intelligent controller 9 is according to external icing parameter monitoring unit, the data that built-in icing parameter monitoring unit 8 and electricity-getting mutual inductor 2 provide are sent instruction determines circuit breaker 10 and by-pass switch in parallel 11 to actuator 12 operating state according to built-in control program.
Explanation is at last, above embodiment is only unrestricted in order to technical scheme of the present invention to be described, although with reference to preferred embodiment the present invention is had been described in detail, those of ordinary skill in the art is to be understood that, can make amendment or be equal to replacement technical scheme of the present invention, and not breaking away from aim and the scope of the technical program, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (7)

1. nine bundle conductor transmission line current cycle intelligence deicing device, it is characterized in that: described device includes nine current input terminal R, nine current output terminal S and be arranged on current input terminal and current output terminal between current cycle intelligence deicing device main body, described current cycle intelligence deicing device main body includes the conductive plate that confluxes, the shunting conductive plate, division board, reference voltage plate and the electric current output board that current output terminal is installed, nine current input terminal R are fixed on the conductive plate that confluxes, the conductive plate that confluxes is connected by the primary winding contact rod as electricity-getting mutual inductor between the conductive plate with shunting, be provided with nine conducting rods at the shunting conductive plate, nine conducting rods pass division board and are connected on the reference voltage plate, between electric current output board and division board, be provided with nine with the circuit breaker of by-pass switch, a corresponding current output terminal S is fixed and be connected to arc control device one end of each circuit breaker all with the electric current output board, the arc control device other end of circuit breaker passes the reference voltage plate, and be connected with the actuator of a circuit breaker, on the shunting conductive plate, also be provided with intelligent controller and built-in icing parameter monitoring unit, intelligent controller and built-in icing parameter monitoring unit are between division board and shunting conductive plate, and intelligent controller is electrically connected with built-in icing parameter monitoring unit and actuator respectively.
2. nine bundle conductor transmission line current cycle as claimed in claim 1 intelligence deicing device, it is characterized in that: described intelligent controller, actuator and built-in icing parameter monitoring unit are powered by the electricity-getting mutual inductor take the reference voltage plate as benchmark.
3. nine bundle conductor transmission line current cycle as claimed in claim 1 intelligence deicing device, it is characterized in that: described circuit breaker and by-pass switch all arrange independently actuator.
4. nine bundle conductor transmission line current cycle as claimed in claim 1 intelligence deicing device, it is characterized in that: described device also includes external icing parameter monitoring unit, external icing parameter monitoring unit is used for monitoring of environmental parameter, conductor temperature, current in wire and wire icing loading condition, and the data communication device that monitors is crossed radio communication and the wired connection dual mode is sent to intelligent controller.
5. nine bundle conductor transmission line current cycle as claimed in claim 1 intelligence deicing device, it is characterized in that: described shunting conductive plate includes insulation daughter board and conduction daughter board, the conduction daughter board is embedded in the center of insulation daughter board, is provided with nine hole and holes that are used for installing electricity-getting mutual inductor that are used for passing conducting rod on the conduction daughter board.
6. nine bundle conductor transmission line current cycle as claimed in claim 1 intelligence deicing device, it is characterized in that: described device also includes two insulating bars that pass successively respectively the conductive plate that confluxes, shunting conductive plate, division board, reference voltage plate and electric current output board.
7. nine bundle conductor transmission line current cycle as claimed in claim 1 intelligence deicing device, it is characterized in that: described device also includes insulation crust, and the conductive plate that confluxes, shunting conductive plate, division board, reference voltage plate and electric current output board are installed in the insulation crust.
CN201310021086.1A 2013-02-16 2013-02-16 Nine-bundle conductor transmission line current circulation intelligent ice-melting device Active CN103078285B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310021086.1A CN103078285B (en) 2013-02-16 2013-02-16 Nine-bundle conductor transmission line current circulation intelligent ice-melting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310021086.1A CN103078285B (en) 2013-02-16 2013-02-16 Nine-bundle conductor transmission line current circulation intelligent ice-melting device

Publications (2)

Publication Number Publication Date
CN103078285A true CN103078285A (en) 2013-05-01
CN103078285B CN103078285B (en) 2015-04-08

Family

ID=48154734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310021086.1A Active CN103078285B (en) 2013-02-16 2013-02-16 Nine-bundle conductor transmission line current circulation intelligent ice-melting device

Country Status (1)

Country Link
CN (1) CN103078285B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2253762A1 (en) * 1998-12-04 2000-06-04 Hydro-Quebec Apparatus and switching method for electric power transmission lines
JP2007166836A (en) * 2005-12-15 2007-06-28 Tokyo Electric Power Services Co Ltd Snow and ice falling-off prevention device
CN101431224A (en) * 2008-12-12 2009-05-13 武汉大学 De-icing technology for overhead transmission line
CN101710683A (en) * 2009-12-25 2010-05-19 重庆大学 Intelligent circulation anti-icing method for transmitting current by split lead

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2253762A1 (en) * 1998-12-04 2000-06-04 Hydro-Quebec Apparatus and switching method for electric power transmission lines
JP2007166836A (en) * 2005-12-15 2007-06-28 Tokyo Electric Power Services Co Ltd Snow and ice falling-off prevention device
CN101431224A (en) * 2008-12-12 2009-05-13 武汉大学 De-icing technology for overhead transmission line
CN101710683A (en) * 2009-12-25 2010-05-19 重庆大学 Intelligent circulation anti-icing method for transmitting current by split lead

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张志劲 等: ""四分裂导线运行电流分组融冰方法与现场试验"", 《电网技术》, vol. 36, no. 7, 31 July 2012 (2012-07-31), pages 54 - 59 *
舒立春 等: ""智能循环电流融冰方法及其临界融冰电流研究"", 《电工技术学报》, vol. 27, no. 10, 31 October 2012 (2012-10-31), pages 26 - 34 *

Also Published As

Publication number Publication date
CN103078285B (en) 2015-04-08

Similar Documents

Publication Publication Date Title
CN103023000B (en) Grid current limiting device and grid current limiting device and grid current limiting system
CN201570912U (en) 10kV subdistrict power supply intelligent system
WO2014107854A1 (en) Power grid current-limiting apparatus, power grid current limiter, and power grid current-limiting system
CN104518564A (en) Backup automatic switching apparatus with area automatic switching function, and backup automatic switching method
CN110994693A (en) Uninterrupted parallel operation grid-connected system and grid-connected method of medium-voltage power supply vehicle
CN104410165B (en) A kind of method and system of micro-internetworking
CN103378574A (en) Control protection method for achieving deicing function of direct-current deicing device
CN103050918B (en) Intelligent device for circularly melting ice on power transmission line with four split sub-conductors by current
CN103050920B (en) Binary fission wire transmission line current cycle intelligence deicing device
CN103094869B (en) Electric transmission line current circulation intelligent ice melting device of five divided conductors
CN103050917B (en) Intelligent device for circularly melting ice on power transmission line with twelve split sub-conductors by current
CN103066543B (en) Current circulating smart ice melting device of three-bundle-conductor electric transmission line
CN103050923B (en) Intelligent device for circularly melting ice on power transmission line with eight split sub-conductors by current
CN104577831A (en) Diverting tool and electrical equipment hotline maintenance method
CN103050921B (en) Intelligent device for circularly melting ice on power transmission line with six split sub-conductors by current
CN103078285B (en) Nine-bundle conductor transmission line current circulation intelligent ice-melting device
CN103050919B (en) Intelligent device for circularly melting ice on power transmission line with ten split sub-conductors by current
CN103078286B (en) Current-circulating intelligent ice-melting device for hepta-bundled conductor power transmission line
CN103050922B (en) Intelligent device for circularly melting ice on power transmission line with eleven split sub-conductors by current
CN211377605U (en) Uninterrupted parallel operation grid-connected system of medium-voltage power supply vehicle
CN102104278B (en) Power supply intelligent system of cell
CN107769363A (en) The apparatus and method that forced oil-circulation air-cooled transformer cooler is thrown by force
CN102136756B (en) 10kV power supply region intelligent control system
CN207530608U (en) The device that forced oil-circulation air-cooled transformer cooler is thrown by force
CN102280853B (en) Intelligent overcurrent phase-failure protector of distribution transformer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No. 6 Fengqi Road, Caijiagang Town, Beibei District, Chongqing, 400707

Patentee after: Chongqing Guangren Iron Tower Manufacture Co.,Ltd.

Patentee after: Chongqing University

Address before: No. 6 Fengqi Road, Caijiagang Town, Beibei District, Chongqing, 400707

Patentee before: CHONGQING GUANGREN TOWER MANUFACTURING Co.,Ltd.

Patentee before: Chongqing University

CP01 Change in the name or title of a patent holder