CN103065213A - 一种基于工作流引擎的变电站标准化验收辅助方法 - Google Patents

一种基于工作流引擎的变电站标准化验收辅助方法 Download PDF

Info

Publication number
CN103065213A
CN103065213A CN2012105420857A CN201210542085A CN103065213A CN 103065213 A CN103065213 A CN 103065213A CN 2012105420857 A CN2012105420857 A CN 2012105420857A CN 201210542085 A CN201210542085 A CN 201210542085A CN 103065213 A CN103065213 A CN 103065213A
Authority
CN
China
Prior art keywords
acceptance
inspection
document
workflow engine
converting station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012105420857A
Other languages
English (en)
Inventor
王亚非
刘斌
贾占岭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Xuchang Power Supply Co of Henan Electric Power Co
Original Assignee
State Grid Corp of China SGCC
Xuchang Power Supply Co of Henan Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Xuchang Power Supply Co of Henan Electric Power Co filed Critical State Grid Corp of China SGCC
Priority to CN2012105420857A priority Critical patent/CN103065213A/zh
Publication of CN103065213A publication Critical patent/CN103065213A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明公开了一种基于工作流引擎的变电站标准化验收辅助方法,包括以下步骤:(1)施工单位完工后通过客户端向系统端提交验收申请,系统端按照计算机的预定规则流程自动传递验收文档保存在数据库中;(2)系统端通过根据不同专业不同部门定制的预制模板对验收申请进行逐项预验收(3)组织相关专家对验收申请进行进一步专业验收,并对问题进行记录,提出专家意见:若专家意见是未通过,则提出整改方案,申请人整改后重新申请;若专家意见是通过但有缺陷,则进行消缺处理后出最终验收报告并归档。本发明能够实现变电站验收的规范化管理;为变电站验收工作提供辅助决策手段;提高变电站验收工作质量和效率,避免人为因素造成变电站验收信息的缺漏。

Description

一种基于工作流引擎的变电站标准化验收辅助方法
技术领域
本发明涉及变电站标准化验收领域,尤其涉及一种基于工作流引擎的变电站标准化验收辅助方法。
背景技术
变电站验收工作的质量直接关系到投运后变电站的运行水平。尤其是随着数字化和智能化变电站的建设,变电站的验收项目和内容越来越多,涉及到得部门、专业、人员越来越多,要求越来越高,如何提高验收质量和效率是摆在各相关专业面前的紧迫而重要的问题之一。目前的变电站自动化系统验收采用厂站侧负责制,由项目主管部门召集各相关专业人员一起进行现场验收,由于各专业的验收规范不同,各自携带本专业的相关验收表单在现场测试打勾、记录存在的问题,回去在整理打印领导审核。通常变电站的验收要经过初验、复验、投运前验收,每一次的都要进行整体验收既要重点检验上次的遗留问题,还要兼顾整改结果是否会引出新的潜在安全隐患。这样给验收人员带来了很大的工作量,在加上项目验收周期比较长,容易造成信息遗漏。而且各部门、各专业之间的信息沟通主要通过纸张或邮件的方式进行信息传递,没有一个统一的信息共享互动平台。
发明内容
 本发明要解决的技术问题是提供一种基于工作流引擎的变电站标准化验收辅助方法,提高变电站验收工作质量和效率。
     本发明采用的技术方案:一种基于工作流引擎的变电站标准化验收辅助方法,包括以下步骤:(1)、施工单位完工后通过客户端向系统端提交验收申请,系统端按照计算机的预定规则流程自动传递验收文档并生成符合验收规范的标准化验收申请保存在数据库中;
(2)、系统端通过根据不同专业不同部门定制的预制模板对验收申请进行逐项预验收,若预审通过,进入下一步;若预审未通过,则建议申请人提出整改方案后重新申请;
(3)、组织相关专家对验收申请进行进一步专业验收,并对问题进行记录,提出专家意见:若专家意见是未通过,则提出整改方案,申请人整改后重新申请;若专家意见是通过但有缺陷,则进行消缺处理后进入下一步;若专家意见是通过,则直接进入下一步;
(4)、验收完成,出最终验收报告并归档。
所述的系统端设置有客户端查看的专家库,专家库存储有对验收过程中的常见验收问题、相应的整改方案的汇总。
所述的步骤(1)中自动传递验收文档是通过加密方式传递的。
所述的步骤(1)中的验收文档为CAD文档、office文档、PDF文档或JPG文档 。
本发明改变目前的验收模式,结合工作流引擎,实现了变电站验收申请、初验、复验、运行验收等日常工作的计算机化流程管理,用户可在客户端提交申请,相关专业人员对相关专业验收内容进行验收,并对问题进行记录,形成整改意见,并可对常见问题进行汇总,形成专家库,从而有效的加强和提高变电站项目验收管理水平,提高验收效率、推进缺陷整改进度,减少工程施工时间。提高公司的管理水平。自动生成变电站标准验收大纲;实现变电站验收的规范化管理;为变电站验收工作提供辅助决策手段;提高变电站验收工作质量和效率,避免人为因素造成变电站验收信息的缺漏。
附图说明
图1为本发明的方法流程图。
具体实施方式
如图1所示,本发明一种基于工作流引擎的变电站标准化验收辅助方法,包括以下步骤:
(1)、施工单位完工后通过客户端向系统端提交验收申请,系统端按照计算机的预定规则流程自动传递验收文档并生成符合验收规范的标准化验收申请保存在数据库中;所述的步骤(1)中的验收文档为CAD文档、office文档、PDF文档或JPG文档 。自动传递验收文档是通过加密方式传递的,有效杜绝了泄密和窃密的发生;
(2)、系统端通过根据不同专业不同部门定制的预制模板对验收申请进行逐项预验收,若预审通过,进入下一步;若预审未通过,则建议申请人提出整改方案后重新申请;
(3)、组织相关专家对验收申请进行进一步专业验收,并对问题进行记录,提出专家意见:若专家意见是未通过,则提出整改方案,申请人整改后重新申请;若专家意见是通过但有缺陷,则进行消缺处理后进入下一步;若专家意见是通过,则直接进入下一步;
(4)、验收完成,出最终验收报告并归档。
其中所述的系统端设置有客户端查看的专家库,专家库存储有对验收过程中的常见验收问题、相应的整改方案的汇总。
本发明以变电站验收整体过程为研究对象,分部门、分专业设计一套信息化流程管理系统,实现对变电站自动化项目验收的全过程流程化管理。基于变电站验收工作跨越部门多、验收文档多的特点,利用计算机按预定规则自动传递文档、信息或者任务,以不同颜色和不同方向的箭头作为工作进度标志,并显示报文的收发时间,方便报文数据查询及通信故障源的追溯,还可以根据验收的实际需求灵活设置测试条件,自动形成事件记录,以备事后查询。模板定制标准验收内容,供用户逐项验证,让验收项目无漏网之鱼,系统还提供验收资料图书馆,用户可将本变电站的所有资料、版本号、电子文档说明书等置于验收资料图书馆里,方便以后查询。支持文档的批量上传、下载,支持档案柜、文件夹、文档的属性查询, 支持文档内容的全文检索。利于人员的考核和事件追踪。并且能够监督站端被控设备厂商技术人员的远程维护。

Claims (4)

1.一种基于工作流引擎的变电站标准化验收辅助方法,其特征在于:包括以下步骤:(1)、施工单位完工后通过客户端向系统端提交验收申请,系统端按照计算机的预定规则流程自动传递验收文档并生成符合验收规范的标准化验收申请保存在数据库中;
(2)、系统端通过根据不同专业不同部门定制的预制模板对验收申请进行逐项预验收,若预审通过,进入下一步;若预审未通过,则建议申请人提出整改方案后重新申请;
(3)、组织相关专家对验收申请进行进一步专业验收,并对问题进行记录,提出专家意见:若专家意见是未通过,则提出整改方案,申请人整改后重新申请;若专家意见是通过但有缺陷,则进行消缺处理后进入下一步;若专家意见是通过,则直接进入下一步;
(4)、验收完成,出最终验收报告并归档。
2.根据权利要求1所述的基于工作流引擎的变电站标准化验收辅助方法,其特征在于:所述的系统端设置有客户端查看的专家库,专家库存储有对验收过程中的常见验收问题、相应的整改方案的汇总。
3.根据权利要求1所述的基于工作流引擎的变电站标准化验收辅助方法,其特征在于:所述的步骤(1)中自动传递验收文档是通过加密方式传递的。
4.根据权利要求1所述的一种基于工作流引擎的变电站标准化验收辅助方法,其特征在于:所述的步骤(1)中的验收文档为CAD文档、office文档、PDF文档或JPG文档 。
CN2012105420857A 2012-12-14 2012-12-14 一种基于工作流引擎的变电站标准化验收辅助方法 Pending CN103065213A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012105420857A CN103065213A (zh) 2012-12-14 2012-12-14 一种基于工作流引擎的变电站标准化验收辅助方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012105420857A CN103065213A (zh) 2012-12-14 2012-12-14 一种基于工作流引擎的变电站标准化验收辅助方法

Publications (1)

Publication Number Publication Date
CN103065213A true CN103065213A (zh) 2013-04-24

Family

ID=48107834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012105420857A Pending CN103065213A (zh) 2012-12-14 2012-12-14 一种基于工作流引擎的变电站标准化验收辅助方法

Country Status (1)

Country Link
CN (1) CN103065213A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103279832A (zh) * 2013-06-04 2013-09-04 国家电网公司 变电站工程建设质量监督分析系统
CN103390217A (zh) * 2013-07-16 2013-11-13 嘉兴市恒光电力建设有限责任公司华创分公司 变电设备异动管理操作系统
CN104680322A (zh) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 一种基于bim的工程验收系统及方法
CN106803155A (zh) * 2017-01-25 2017-06-06 深圳市万科房地产有限公司 施工质量管控方法及系统
CN108364113A (zh) * 2017-12-26 2018-08-03 中国移动通信集团广东有限公司 基站验收系统及计算机可读存储介质
CN113836887A (zh) * 2021-09-15 2021-12-24 国网江苏省电力有限公司无锡供电分公司 一种智能变电站配置文件的校核验收方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030182172A1 (en) * 2002-03-25 2003-09-25 Claggett Stuart Lee System and method to build project management processes
CN102749549A (zh) * 2012-06-21 2012-10-24 云南电力试验研究院(集团)有限公司电力研究院 一种变电站交流电流电压二次回路智能检验系统
CN202600765U (zh) * 2012-01-20 2012-12-12 安徽省电力公司合肥供电公司 智能化供电系统数据综合管理系统

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030182172A1 (en) * 2002-03-25 2003-09-25 Claggett Stuart Lee System and method to build project management processes
CN202600765U (zh) * 2012-01-20 2012-12-12 安徽省电力公司合肥供电公司 智能化供电系统数据综合管理系统
CN102749549A (zh) * 2012-06-21 2012-10-24 云南电力试验研究院(集团)有限公司电力研究院 一种变电站交流电流电压二次回路智能检验系统

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张益林: "工作流技术的研究及在工程项目管理中的设计与实现", 《中国优秀硕士学位论文全文数据库(信息科技辑)》 *
赵丽叶等: "基于WEB技术的科研项目验收管理系统的设计与实现", 《科技创新导报》 *
郝伟等: "变电站自动化辅助验收系统应用研究", 《科技创新与应用》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103279832A (zh) * 2013-06-04 2013-09-04 国家电网公司 变电站工程建设质量监督分析系统
CN103279832B (zh) * 2013-06-04 2017-06-06 国家电网公司 变电站工程建设质量监督分析系统
CN103390217A (zh) * 2013-07-16 2013-11-13 嘉兴市恒光电力建设有限责任公司华创分公司 变电设备异动管理操作系统
CN103390217B (zh) * 2013-07-16 2016-08-10 嘉兴市恒光电力建设有限责任公司华创分公司 变电设备异动管理操作系统
CN104680322A (zh) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 一种基于bim的工程验收系统及方法
CN106803155A (zh) * 2017-01-25 2017-06-06 深圳市万科房地产有限公司 施工质量管控方法及系统
CN108364113A (zh) * 2017-12-26 2018-08-03 中国移动通信集团广东有限公司 基站验收系统及计算机可读存储介质
CN113836887A (zh) * 2021-09-15 2021-12-24 国网江苏省电力有限公司无锡供电分公司 一种智能变电站配置文件的校核验收方法

Similar Documents

Publication Publication Date Title
CN103065213A (zh) 一种基于工作流引擎的变电站标准化验收辅助方法
CN108229782B (zh) 一种基于云的可视化生产管理平台
CN105868936B (zh) 一种应用于变电设备一体化运维检修的智能运检系统
CN105447627A (zh) 设计评审过程管控模式研究方法
CN106127608A (zh) 一种电力营销线上办电方法
CN101364284A (zh) 一种用于电力系统的生产管理系统
CN109377180A (zh) 一种电力系统业扩流程信息管控系统
CN110555609A (zh) 一种水电站现场标准化作业管控系统及方法
CN102142108A (zh) 适用于电力系统的物料与设备对应关系信息的处理方法
CN102880790A (zh) 基于pda模式的现场标准化作业系统及作业流程
CN111353787A (zh) 一种基于云平台的装备综合保障系统
CN111950846A (zh) 一种智能工厂用排班系统
Faizrakhmanov et al. Sustainable energy consumption control using the MY-JEVIS energy management data system
CN114417255B (zh) 一种碳排放量化平台和碳排放量化系统
CN114677044A (zh) 一种面向智慧建筑监理工程项目的管理系统及方法
CN112862242A (zh) 用于变电站基建工程的生产全过程验收工具
CN103605866A (zh) 一种配电网工程设计仿真培训系统及方法
CN108647793B (zh) 一种安装检修质量智能管控平台
KR100584903B1 (ko) 발전소 운전정보 실시간 관리 시스템
Wang et al. Development and application of MES based on cloud platform for steel structure enterprises
Jing et al. Development of BIM-Sensor integrated platform for MEP piping maintenance
CN103390217A (zh) 变电设备异动管理操作系统
CN201732392U (zh) 适用于电力系统物料与设备对应关系信息的处理装置
Ali et al. Fast Track Implementation of Energy Management System 2018 Using Sequential Approach
Nakafuji et al. Distributed resource energy analysis and management system (DREAMS) development for real-time grid operations

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130424