CN103046470A - Transverse positioning device for amplitude separation type steel box girder and application method of transverse positioning device - Google Patents
Transverse positioning device for amplitude separation type steel box girder and application method of transverse positioning device Download PDFInfo
- Publication number
- CN103046470A CN103046470A CN201210572459XA CN201210572459A CN103046470A CN 103046470 A CN103046470 A CN 103046470A CN 201210572459X A CN201210572459X A CN 201210572459XA CN 201210572459 A CN201210572459 A CN 201210572459A CN 103046470 A CN103046470 A CN 103046470A
- Authority
- CN
- China
- Prior art keywords
- type steel
- steel case
- framing type
- case beam
- positioning device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a transverse positioning device for an amplitude separation type steel box girder and an application method of the transverse positioning device and belongs to the field of bridge construction device. The transverse positioning device comprises a telescopic connecting girder, a hinge connector and a pushing device, wherein the telescopic connecting girder and the hinge connector are connected, and the pushing device is used for adjusting telescoping length of the telescopic connecting girder. The application method includes: fixing the positioning device in the middle of the amplitude separation type steel box girder which needs to be positioned; controlling pushing or contracting of the pushing device to push or contract the amplitude separation type steel box girder, stopping pushing or contracting of the pushing device when the position of the amplitude separation type steel box girder meets the requirement, and fixing current telescoping length of the telescopic connecting girder; when positioning and construction of the amplitude separation type steel box girder is completed, removing connection between a base and the amplitude separation type steel box girder, and removing fixation of the telescopic connecting girder. By the transverse positioning device which can be used repeatedly, accurate transverse positioning of the amplitude separation type steel box girder can be achieved simply, conveniently and fast.
Description
Technical field
The invention belongs to bridge construction device field, be applicable to the horizontal fine adjustment of framing type steel case beam.
Background technology
Framing type steel case beam generally by about width of cloth two parts steel case beam and middle connecting cross beam form.About after two width of cloth steel case beams lift by crane respectively because two width of cloth steel case beams are positioned in the air, and steel case beam weight is large, the horizontal spacing adjustment is comparatively difficult.Especially behind the inclined guy cable stretching, two width of cloth steel case beams laterally positioning are difficult to realize.Because two width of cloth steel case beams laterally positioning are difficult to realize that middle permanent connecting cross beam is installed difficulty, needs the connecting cross beam part to cut off.Totally unfavorable to steel box girder construction quality and integral bridge linearity.
Summary of the invention
The object of the invention is to: propose a kind of horizontal rackwork of framing type steel case beam and using method thereof, can realize simply, quickly and easily the aerial laterally fine adjustment of framing type steel case beam, and device can be reused.
The object of the invention realizes by following technical proposals:
The horizontal rackwork of a kind of framing type steel case beam comprises the scalable tie-beam and the articulated joint that are connected, and the thrustor of regulating described scalable tie-beam collapsing length.
As optimal way, described scalable tie-beam comprises telescoping member and the supporting member of movable nested connection, and described thrustor is located between described telescoping member and the supporting member, fixes with one, contacts with another.
As optimal way, described telescoping member activity is nested in the described supporting member, and described thrustor is located in the described supporting member for the positioning jack, and an end and described supporting member are fixed, and the other end contacts with described telescoping member.
The using method of the horizontal rackwork of a kind of aforementioned framing type steel case beam may further comprise the steps successively:
1) rackwork is positioned in the middle of the framing type steel case beam that needs positioning, its two ends are detachably fixing with a single width steel case beam respectively;
2) pushing tow or the contraction of control thrustor, framing type steel case back is opened or shunk, when framing type steel case beam position meets the demands, stop pushing tow or the contraction of thrustor, and fixing scalable tie-beam collapsing length at this moment, this moment, framing type steel case beam was adjusted to the right place;
3) when framing type steel case beam positioning put in place and construct finish after, remove its with framing type steel case beam between be connected, and remove fixing to scalable tie-beam, this moment framing type steel case beam fine adjustment and construct and finish.
Beneficial effect of the present invention: the horizontal rackwork of framing type steel case beam of the present invention and using method thereof, can realize simply, quickly and easily the aerial laterally fine adjustment of framing type steel case beam, and device can be reused, be fit to Practical Project and use, installing for large scale steel structure high altitude also has very strong reference.
Description of drawings
Fig. 1 is the elevational schematic view of the embodiment of the invention;
Fig. 2 is the floor map of the embodiment of the invention;
Wherein 1 is that articulated joint, 2 is that telescoping member, 3 is that supporting member, 4 is that positioning jack, 5 is single width steel case beam.
The specific embodiment
Following non-limiting examples is used for explanation the present invention.
As shown in Figure 1, 2, the horizontal rackwork of a kind of framing type steel case beam comprises the scalable tie-beam that is connected and the articulated joint 1 that is used for resisting two single width steel case beams, 5 unbalanced moments, and the thrustor of regulating scalable tie-beam collapsing length.As optimal way, as shown in this embodiment, scalable tie-beam comprises telescoping member 2 and the supporting member 3 of movable nested connection, telescoping member 2 activities are nested in the supporting member 3, thrustor is positioning jack 4, be located in the supporting member 3, an end and supporting member 3 are fixing, and the other end contacts with telescoping member 2.
The using method of the horizontal rackwork of aforementioned framing type steel case beam may further comprise the steps successively:
1) rackwork is positioned in the middle of the framing type steel case beam that needs positioning, its two ends are detachably fixing with a single width steel case beam 5 respectively, and namely telescoping member 2 and a single width steel case beam 5 are detachably fixing, and articulated joint 1 is detachably fixing with another single width steel case beam 5;
2) pushing tow or the contraction of control positioning jack 4, framing type steel case back is opened or shunk, framing type steel case beam separates relatively during positioning jack 4 pushing tow, when positioning jack 4 shrank, framing type steel case beam bounced back naturally relatively, when framing type steel case beam position meets the demands, pushing tow or the contraction of jack 4 stop to transpose, and fixing scalable tie-beam collapsing length at this moment, it is temporary fixed to be about to telescoping member 2 and 3 of supporting members, and this moment, framing type steel case beam was adjusted to the right place;
3) put in place when framing type steel case beam positioning, after finishing steel box beam Welding and permanent crossbeam and being in place, remove its with framing type steel case beam between be connected, and releasing fixing scalable tie-beam, namely remove the temporary fixed of 3 of telescoping member 2 and supporting members, this moment, the adjustment of framing type steel case beam was finished, and at this moment, rackwork can reuse.
The above only is preferred embodiment of the present invention, not in order to limiting the present invention, all any modifications of doing within the spirit and principles in the present invention, is equal to and replaces and improvement etc., all should be included within protection scope of the present invention.
Claims (4)
1. horizontal rackwork of framing type steel case beam is characterized in that: comprise the scalable tie-beam and the articulated joint that are connected, and the thrustor of regulating described scalable tie-beam collapsing length.
2. the horizontal rackwork of framing type steel case beam as claimed in claim 1, it is characterized in that: described scalable tie-beam comprises telescoping member and the supporting member of movable nested connection, described thrustor is located between described telescoping member and the supporting member, fixes with one, contacts with another.
3. the horizontal rackwork of framing type steel case beam as claimed in claim 2, it is characterized in that: described telescoping member activity is nested in the described supporting member, described thrustor is the positioning jack, be located in the described supporting member, one end and described supporting member are fixed, and the other end contacts with described telescoping member.
4. the using method of a claim 1, the horizontal rackwork of 2 or 3 described framing type steel case beams is characterized in that may further comprise the steps successively:
1) rackwork is positioned in the middle of the framing type steel case beam that needs positioning, its two ends are detachably fixing with a single width steel case beam respectively;
2) pushing tow or the contraction of control thrustor, framing type steel case back is opened or shunk, when framing type steel case beam position meets the demands, stop pushing tow or the contraction of thrustor, and fixing scalable tie-beam collapsing length at this moment, this moment, framing type steel case beam was adjusted to the right place;
3) when framing type steel case beam positioning put in place and construct finish after, remove its with framing type steel case beam between be connected, and remove fixing to scalable tie-beam, this moment framing type steel case beam fine adjustment and construct and finish.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210572459.XA CN103046470B (en) | 2012-12-26 | 2012-12-26 | Transverse positioning device for amplitude separation type steel box girder and application method of transverse positioning device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210572459.XA CN103046470B (en) | 2012-12-26 | 2012-12-26 | Transverse positioning device for amplitude separation type steel box girder and application method of transverse positioning device |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510002958.9A Division CN104631330B (en) | 2012-12-26 | 2012-12-26 | A kind of using method of framing type steel box-girder transverse direction rackwork |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103046470A true CN103046470A (en) | 2013-04-17 |
CN103046470B CN103046470B (en) | 2015-02-11 |
Family
ID=48059308
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210572459.XA Active CN103046470B (en) | 2012-12-26 | 2012-12-26 | Transverse positioning device for amplitude separation type steel box girder and application method of transverse positioning device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103046470B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108643353A (en) * | 2018-05-30 | 2018-10-12 | 中国建筑第八工程局有限公司 | A kind of the box beam connecting node and its construction method of adjustable length |
CN109853391A (en) * | 2019-02-19 | 2019-06-07 | 中交二航局第四工程有限公司 | A kind of combination unit for head tower structural stress deformation active accommodation |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4306040A1 (en) * | 1993-02-26 | 1994-09-01 | Walter Dipl Ing Komm | Method and device for transverse displacement of bridge construction elements produced with a camber |
JP2008144472A (en) * | 2006-12-11 | 2008-06-26 | Yokogawa Bridge Holdings Corp | Position adjustment method and device for connection of bridge girder |
CN201695342U (en) * | 2010-06-28 | 2011-01-05 | 中铁二十局集团有限公司 | Adjustable inner support rod for arch rib tilting construction |
CN202116984U (en) * | 2011-05-11 | 2012-01-18 | 天津城市建设学院 | Dragging-adjustable cross-brace device for continuous beams of spatial steel pipe trusses |
CN202323727U (en) * | 2011-11-16 | 2012-07-11 | 中铁十三局集团电务工程有限公司 | Device for adjusting horizontal position of steel box girder |
CN203034376U (en) * | 2012-12-26 | 2013-07-03 | 中交二航局第四工程有限公司 | Framing steel box beam lateral position-adjusting device |
-
2012
- 2012-12-26 CN CN201210572459.XA patent/CN103046470B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4306040A1 (en) * | 1993-02-26 | 1994-09-01 | Walter Dipl Ing Komm | Method and device for transverse displacement of bridge construction elements produced with a camber |
JP2008144472A (en) * | 2006-12-11 | 2008-06-26 | Yokogawa Bridge Holdings Corp | Position adjustment method and device for connection of bridge girder |
CN201695342U (en) * | 2010-06-28 | 2011-01-05 | 中铁二十局集团有限公司 | Adjustable inner support rod for arch rib tilting construction |
CN202116984U (en) * | 2011-05-11 | 2012-01-18 | 天津城市建设学院 | Dragging-adjustable cross-brace device for continuous beams of spatial steel pipe trusses |
CN202323727U (en) * | 2011-11-16 | 2012-07-11 | 中铁十三局集团电务工程有限公司 | Device for adjusting horizontal position of steel box girder |
CN203034376U (en) * | 2012-12-26 | 2013-07-03 | 中交二航局第四工程有限公司 | Framing steel box beam lateral position-adjusting device |
Non-Patent Citations (2)
Title |
---|
宋微: "多塔钢箱梁斜拉桥的优化施工方法及架设过程的关键力学问题研究", 《中国优秀硕士学位论文全文数据库•工程科技II辑C034-26》 * |
宋微: "多塔钢箱梁斜拉桥的优化施工方法及架设过程的关键力学问题研究", 《中国优秀硕士学位论文全文数据库•工程科技II辑C034-26》, 15 November 2012 (2012-11-15) * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108643353A (en) * | 2018-05-30 | 2018-10-12 | 中国建筑第八工程局有限公司 | A kind of the box beam connecting node and its construction method of adjustable length |
CN109853391A (en) * | 2019-02-19 | 2019-06-07 | 中交二航局第四工程有限公司 | A kind of combination unit for head tower structural stress deformation active accommodation |
CN109853391B (en) * | 2019-02-19 | 2023-09-19 | 中交二航局第四工程有限公司 | Combined device for actively adjusting stress deformation of steel tower structure |
Also Published As
Publication number | Publication date |
---|---|
CN103046470B (en) | 2015-02-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2013179549A1 (en) | Method for swapping stay cable, and temporary hanger for replacing stay cable | |
CN104234200A (en) | Ring-by-ring lifting mounting method for suspendome cable-bar system | |
CN105275253A (en) | Equal-diameter rod erecting device and application method thereof | |
CN103266799B (en) | Mast and installation technology thereof | |
CN204552054U (en) | A kind of telescopic work high above the ground hanger bracket | |
CN103046470A (en) | Transverse positioning device for amplitude separation type steel box girder and application method of transverse positioning device | |
CN203514212U (en) | Device for disassembling cross Bailey beam | |
CN105040591A (en) | Positioning device for waveform steel web and positioning method thereof | |
CN104631330B (en) | A kind of using method of framing type steel box-girder transverse direction rackwork | |
CN203034376U (en) | Framing steel box beam lateral position-adjusting device | |
CN105016220B (en) | A kind of pole guide support adding device | |
CN203143970U (en) | Tower crane standard joint introduction system | |
CN201635014U (en) | Cable-stayed movable suspended scaffolding provided with long platform and free from cable force adjustment | |
CN204238556U (en) | Adjustable overhanging type discharging platform | |
CN205170234U (en) | Cantilever crane | |
CN202787087U (en) | Hook-shaped cable saddle and support structure of track cable | |
KR20170001054U (en) | Apparatus for replacing insulator | |
CN205387943U (en) | Tunnel lining trolley | |
CN103982049A (en) | Wall body assembling straightening device for shear wall | |
CN203402858U (en) | Adjustable attachment device of tower crane | |
KR101339362B1 (en) | Method for loading pre-flex load | |
CN204000641U (en) | A kind of large-scale pier stud concrete vertical reinforcement locating rack | |
CN204038917U (en) | Detachable external hanging type operating platform | |
CN104818675A (en) | Assembling method of rebar segments | |
CN203613461U (en) | Slip form construction lifting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |