CN201635014U - Cable-stayed movable suspended scaffolding provided with long platform and free from cable force adjustment - Google Patents

Cable-stayed movable suspended scaffolding provided with long platform and free from cable force adjustment Download PDF

Info

Publication number
CN201635014U
CN201635014U CN2010201194105U CN201020119410U CN201635014U CN 201635014 U CN201635014 U CN 201635014U CN 2010201194105 U CN2010201194105 U CN 2010201194105U CN 201020119410 U CN201020119410 U CN 201020119410U CN 201635014 U CN201635014 U CN 201635014U
Authority
CN
China
Prior art keywords
cable
head connector
anchor
anchor head
pull rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010201194105U
Other languages
Chinese (zh)
Inventor
钟剑锋
苏慈
钱亮
吴存全
王晓佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Changda Highway Engineering Co Ltd
Original Assignee
Guangdong Changda Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Changda Highway Engineering Co Ltd filed Critical Guangdong Changda Highway Engineering Co Ltd
Priority to CN2010201194105U priority Critical patent/CN201635014U/en
Application granted granted Critical
Publication of CN201635014U publication Critical patent/CN201635014U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a cable-stayed movable suspended scaffolding provided with a long platform and free from cable force adjustment. The movable suspended scaffolding comprises the loading platform, wherein a stretching system is arranged at the front end of the loading platform and includes an anchor head connector, a cable staying pull rod, an anchor beam and a piercing lifting jack; the anchor head connector is connected with a stayed cable; one end of the cable staying pull rod is connected with the anchor head connector, the other end of the cable staying pull rod penetrates a stretching groove of a loading platform main longitudinal beam, the anchor beam and the lifting jack, and the tail end of the cable staying pull rod is fixed through a pull rod nut. The utility model is free from the cable force adjustment from the pouring construction, thereby reducing the construction control difficulty.

Description

Exempt to transfer the rope long platform tiltedly to draw Hanging Basket
Technical field
The utility model relates to a kind of construction equipment that concrete deck cable stayed bridge kingpost cantalever pouring construction is used, and especially a kind ofly exempts to transfer the rope long platform tiltedly to draw Hanging Basket.
Background technology
In the cantilever pouring work progress of cable stayed bridge concrete girder, linear control is primary often.In construction control process in the past, in order to improve construction equipment (Hanging Basket) global stiffness and to reduce distortion, usually need English truss be set or must during the process of building, repeatedly adjust Suo Li at bridge floor, so just increase the control difficulty of work progress, be unfavorable for linear control on the contrary.
The utility model content
The utility model purpose be to provide a kind of in the process of building, do not need to adjust Suo Li exempt from transfer the rope long platform tiltedly to draw Hanging Basket.
For achieving the above object, the technical solution adopted in the utility model is: a kind ofly exempt to transfer the rope long platform tiltedly to draw Hanging Basket to comprise plummer, front end at plummer is provided with tensioning system, this tensioning system is made up of anchor head connector, guy rope pull bar, anchor beam, punching jack, the anchor head connector is connected with suspension cable, guy rope pull bar one end is connected with the anchor head connector, and the other end passes stretch-draw groove, anchor beam and the jack of plummer main longitudinal grider successively, and end is fixed by pull-rod nut.
The rear end of described plummer main longitudinal grider is provided with the suspension cable thrust brake.
After the utility model adopts said structure, by front end tensioning system is set at plummer, this tensioning system is made up of anchor head connector, guy rope pull bar, anchor beam, punching jack, the anchor head connector is connected with suspension cable, guy rope pull bar one end is connected with the anchor head connector, the other end passes stretch-draw groove, anchor beam and the jack of plummer main longitudinal grider successively, and end is fixed by pull-rod nut; Because anchor beam is the front fulcrum of Hanging Basket, can slide up and down and lock along the circular arc bearing surface, thereby the position of front fulcrum is adjustable, to adapt to the variation of suspension cable angle.During the system conversion, pretensioning guy rope pull bar loosens pull-rod nut, jack slowly loosens then, the drag-line nut is stressed to be compressed, and the anchor head connector is removed in the system conversion at last, Hanging Basket separates with suspension cable, so by tensioning system of the present utility model is suspension cable and Hanging Basket to be coupled together when the Hanging Basket cantilever casting construction formation front fulcrum, applies certain tensile stress to suspension cable, with the internal force that reduces main longitudinal grider in the construction with reduce front end and be out of shape; After cantilever is finished, suspension cable is separated with Hanging Basket, realize the Suo Li conversion, avoided in the pouring construction process, adjusting Suo Li.
Description of drawings
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail:
Fig. 1 is the utility model longitudinal plane structure schematic diagram;
Fig. 2 is the utility model tensioning system structural representation.
Among the figure: 1 plummer, 11 through holes, 12 annular lip, 2 tensioning systems, 21 anchor head connectors, 22 guy rope pull bars, 23 anchor beams, 24 jack, 25 pull-rod nuts, 3 suspension cables, 4 suspension cable thrust brakes.
The specific embodiment
Shown in Fig. 1 and 2, of the present utility modelly exempt to transfer the rope long platform tiltedly to draw Hanging Basket to comprise plummer 1, front end at plummer 1 is provided with tensioning system 2, this tensioning system 2 is made up of anchor head connector 21, guy rope pull bar 22, anchor beam 23, punching jack 24, anchor head connector 21 is connected with suspension cable 3, guy rope pull bar 22 1 ends are connected with anchor head connector 21, and the other end passes stretch-draw groove, anchor beam 23 and the jack 24 of plummer main longitudinal grider 11 successively, and are terminal fixing by pull-rod nut 25; Rear end at plummer main longitudinal grider 11 also is provided with suspension cable thrust brake 4.The tensioning system 2 of plummer 1 front end is suspension cable 3 and Hanging Basket to be coupled together the formation front fulcrum when the Hanging Basket cantilever casting construction, applies certain tensile stress for suspension cable 3, with the internal force that reduces main longitudinal grider 11 in the construction with reduce the front end distortion; After cantilever is finished, suspension cable 3 is separated with Hanging Basket, realize the Suo Li conversion, avoided in the pouring construction process, adjusting Suo Li; Anchor beam 23 is front fulcrums of Hanging Basket, can slide up and down and lock along the circular arc bearing surface, thereby the position of front fulcrum is adjustable, to adapt to the variation of suspension cable 3 angles.During the system conversion, pretensioning guy rope pull bar 22 loosens pull-rod nut 25, and jack 24 slowly loosens then, drag-line nut 25 stressed compressing, and anchor head connector 21 is removed in the system conversion at last, and Hanging Basket separates with suspension cable 3.

Claims (2)

1. exempt to transfer the rope long platform tiltedly to draw Hanging Basket for one kind, it comprises plummer (1), it is characterized in that: the front end at plummer (1) is provided with tensioning system (2), this tensioning system (2) is made up of anchor head connector (21), guy rope pull bar (22), anchor beam (23), punching jack (24), anchor head connector (21) is connected with suspension cable (3), guy rope pull bar (22) one ends are connected with anchor head connector (21), the other end passes stretch-draw groove, anchor beam (23) and the jack (24) of plummer main longitudinal grider (11) successively, and is terminal fixing by pull-rod nut (25).
2. according to claim 1ly exempt to transfer the rope long platform tiltedly to draw Hanging Basket, it is characterized in that: be provided with suspension cable thrust brake (4) in the rear end of described plummer main longitudinal grider (11).
CN2010201194105U 2010-02-26 2010-02-26 Cable-stayed movable suspended scaffolding provided with long platform and free from cable force adjustment Expired - Lifetime CN201635014U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201194105U CN201635014U (en) 2010-02-26 2010-02-26 Cable-stayed movable suspended scaffolding provided with long platform and free from cable force adjustment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201194105U CN201635014U (en) 2010-02-26 2010-02-26 Cable-stayed movable suspended scaffolding provided with long platform and free from cable force adjustment

Publications (1)

Publication Number Publication Date
CN201635014U true CN201635014U (en) 2010-11-17

Family

ID=43079500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201194105U Expired - Lifetime CN201635014U (en) 2010-02-26 2010-02-26 Cable-stayed movable suspended scaffolding provided with long platform and free from cable force adjustment

Country Status (1)

Country Link
CN (1) CN201635014U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103074854A (en) * 2013-01-23 2013-05-01 中交四航局第一工程有限公司 Rear supporting point triangular bracket hanging basket and bridge construction method using same
CN103866691A (en) * 2014-03-27 2014-06-18 中交一公局第一工程有限公司 Anchor group device of large-sized cable hoisting system track cables
CN109295859A (en) * 2018-10-18 2019-02-01 柳州欧维姆机械股份有限公司 A kind of front fulcrum hangs the tensioning equipment and its stretch-draw construction method of blue construction
CN112942133A (en) * 2021-04-01 2021-06-11 中交二航局第二工程有限公司 Tensioning and positioning device and method for front fulcrum hanging basket

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103074854A (en) * 2013-01-23 2013-05-01 中交四航局第一工程有限公司 Rear supporting point triangular bracket hanging basket and bridge construction method using same
CN103866691A (en) * 2014-03-27 2014-06-18 中交一公局第一工程有限公司 Anchor group device of large-sized cable hoisting system track cables
CN103866691B (en) * 2014-03-27 2015-09-09 中交一公局第一工程有限公司 A kind of Large scale cable crane track cable group anchor device
CN109295859A (en) * 2018-10-18 2019-02-01 柳州欧维姆机械股份有限公司 A kind of front fulcrum hangs the tensioning equipment and its stretch-draw construction method of blue construction
CN109295859B (en) * 2018-10-18 2023-12-19 柳州欧维姆机械股份有限公司 Tensioning device for front supporting point hanging construction and tensioning construction method thereof
CN112942133A (en) * 2021-04-01 2021-06-11 中交二航局第二工程有限公司 Tensioning and positioning device and method for front fulcrum hanging basket

Similar Documents

Publication Publication Date Title
CN101280630B (en) Network frame house cap integral lifting construction method
JP5572668B2 (en) Replacement method of oblique cable and temporary hanger for replacing oblique cable
CN201635014U (en) Cable-stayed movable suspended scaffolding provided with long platform and free from cable force adjustment
CN102444086A (en) Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge
CN101672011A (en) Steel tube arch rib vertical lifting method
CN101446074B (en) Installation and closure construction method for steel sliding roadway arch on top surface of steel trussed beam bridge
CN101845795B (en) Cable-stayed cradle of adjustment-free cable tension long platform in construction of cable-stayed bridge
CN103437298A (en) Concrete precast box girder hoisting method and hoisting device
CN104847122B (en) Device assembly for tensioning fork ear type stay rope or steel pull rod and tensioning construction method of device assembly
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN105088970A (en) Construction method of corrugated steel web PC box girder cable-stayed bridge
CN202380390U (en) Flexible arch support frame with vault pushing steel truss girder
CN101818479A (en) Construction process for overhead back-up movement and dismantlement of movable shuttering form
CN112942132B (en) Front supporting point composite hanging basket and shifting method thereof
CN203173749U (en) Assembled integral type vertical self-jacking device of hydraulic double-type crane tower
CN104594206A (en) Suspended type dragging anchor socket and method for steel trussed beam longitudinal displacement
CN104120659A (en) Descending type suspended scaffold
CN110820566A (en) Corrugated steel web part bearing type hanging basket suspension casting construction method
CN201458544U (en) Carrying pole for mounting component
CN101831872B (en) Front and rear fulcrum combined cradle
CN110820567A (en) Bearing type hanging basket for PC box girder part with corrugated steel web plate
CN204151695U (en) Be applicable to the combination Hanging Basket system of continuous rigid frame bridge or the full beam section construction of continuous girder bridge
CN204079226U (en) A kind of movable beam string hanging apparatus that can increase rigidity when tubular truss lifts
CN214656451U (en) Front supporting point composite hanging basket
CN205772893U (en) A kind of king-tower function at most lifting traction apparatus

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20101117