CN103034918A - Electric power safe production management system operating method - Google Patents

Electric power safe production management system operating method Download PDF

Info

Publication number
CN103034918A
CN103034918A CN2011102982595A CN201110298259A CN103034918A CN 103034918 A CN103034918 A CN 103034918A CN 2011102982595 A CN2011102982595 A CN 2011102982595A CN 201110298259 A CN201110298259 A CN 201110298259A CN 103034918 A CN103034918 A CN 103034918A
Authority
CN
China
Prior art keywords
management system
ticket
work ticket
operation order
electric power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102982595A
Other languages
Chinese (zh)
Inventor
朱日君
吕孟东
俞宏群
彭礼平
钱国春
丁晓峰
曹梁
屠伟东
罗银兵
李鸿
王振团
徐芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUCHUNJIANG HYDROELECTRIC POWER STATION OF EAST CHINA GRID Co Ltd
STATE GRID XINYUAN HYDROPOWER CO Ltd
State Grid Corp of China SGCC
Original Assignee
FUCHUNJIANG HYDROELECTRIC POWER STATION OF EAST CHINA GRID Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUCHUNJIANG HYDROELECTRIC POWER STATION OF EAST CHINA GRID Co Ltd filed Critical FUCHUNJIANG HYDROELECTRIC POWER STATION OF EAST CHINA GRID Co Ltd
Priority to CN2011102982595A priority Critical patent/CN103034918A/en
Publication of CN103034918A publication Critical patent/CN103034918A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides an electric power safe production management system operating method. The method comprises the following steps: creating an electronic operation ticket and a work ticket in a management system, downloading the operation ticket and the work ticket to a handheld computer and changing a management state of the operation ticket and the work ticket; executing the operation ticket and the work ticket on the handheld computer and synchronously performing sound recording and operation and locking operation processes; and transmitting the operation ticket and the work ticket finishing execution back to the management system and changing the management state of the operation ticket and the work ticket. The electric power safe production management system operating method achieves whole 'double tickets' closed -loop management including ticket drafting, examination and verifying, permission and execution by the aid of a handheld personal digital assistant (PDA) device, really and completely eradicates potential safety hazards in item hopping and item omitting operation during 'double tickets' execution technically, ensures the safety of 'double tickets' execution and improves the work efficiency of the 'double tickets' execution.

Description

A kind of electric power safety production management system method of operating
Technical field
The present invention relates to the production safety management technical field, relate in particular to a kind of electric power safety production management system method of operating.
Background technology
Safety is the eternal theme of electrical production, grab safety management and at first will catch the principal risk point, the dangerous matter sources of electrical production maximum is: the staff is strict implement work ticket and operation order system not, jumps item, leaks an operation, causes equipment or personal injury thereby maloperation occurs.The most basic drawback of traditional papery operation order and work ticket (being called for short " two tickets ") is to monitor the quality of staff's implementation.The quality of carrying out in order to improve " two tickets ", the way of in the past usually taking is to realize from ideological education and organiztion measure.By ideological education, strengthen awareness of safety, make the staff be reluctant to jump item, leak an operation.By perfecting system, strict punishment makes the staff dare not jump item, leaks an operation.Except tighten security education and perfecting system, can in the jumping item that guarantees in technical measures to avoid artificial, a leakage operation, be exactly the problem that the method will solve.
Palm PC PDA electronic operational ticket and work ticket are the implementations about " two tickets " with no paper office.After examining by " two tickets " flow process of KXG is complete, " two tickets " of needs operation downloaded on the PDA, operating personnel operate according to the prompting of PDA, pda system can carry out logic blocking to operation steps, the operation that does not namely allow the user to carry out spanned item, get over item and leak item, thereby prevent that the operating personnel is habitual violating the regulations, avoid the generation of power equipment accident or human casualty accident.
Summary of the invention
The present invention proposes a kind of electric power safety production management system method of operating, by hand-held PDA equipment, realized that " two tickets " is from intending ticket, audit, approval, execution to the closed loop management of closing overall process, really stopped technically to jump during " two tickets " carried out the potential safety hazard of item, a leakage operation, guarantee the safety that " two tickets " carried out, improved the work efficiency that " two tickets " carried out.
In order to achieve the above object, the present invention proposes a kind of electric power safety production management system method of operating, comprises the following steps:
In management system, create electronic operational ticket and work ticket;
Described operation order and work ticket are downloaded on the palm PC, and change the supervisor status of described operation order and work ticket;
Carry out operation order and work ticket on the described palm PC, record synchronously and operate, and operating process is carried out locking;
The operation order and the work ticket that are finished are passed back in the management system, and change the supervisor status of described operation order and work ticket.
Further, the data of described operation order and work ticket comprise operation item, operation steps and order, and operating personnel, dangerous point, the content of control measure and order, and permit on-stream time.
Further, if recording operation is not opened or suspended, then described operation order and work ticket do not allow operation.
Further, must first dangerous point and control measure be finished, just can carry out the execution of operation order and work ticket.
Further, after operation order and work ticket are finished, then automatically generate recording file.
Further, described management system provides operation order and work ticket inquiry, by the key word of ticket title, and page number, the personnel that make out an invoice, the responsible official, perhaps guardian's information is carried out the inquiry of operation order and work ticket.
Further, described management system provides statistical computation, adds up current personnel, operator's item number, guardian's item number, person approving's item number, and total umber information of operation order and work ticket.
Further, described management system is that the recording file of operation order and work ticket arranges administration authority.
Beneficial effect of the present invention is as follows:
(1) direct loss and the indirect loss of the national economy brought of power system accident generally all will reach thousands of units, the application in hydroelectric power plant's safety in production by palm PC PDA electronic operational ticket and work ticket, equipment breakdown and the human casualty accident that can reduce or avoid people from hydroelectric power plant to cause for maloperation, it guaranteeing that the economic benefit on the power plant safety is difficult to the appraisal.Utilize this system can greatly improve the security of power plant, avoid or reduce the generation of Power Plant Accident, thereby produce significant economic benefit.
(2) stopping the operating personnel in technical measures jumps item or leaks a behavior of operation.Sound-recording function and the software logic locking flow process function of utilizing palm PC PDA to have realize that operation is recorded and operation steps is carried out synchronously, and the operation recording is closed, and operation steps can't be carried out, and improves operations staff's operational quality.
(3) managerial personnel's subsequent supervision, inspection and inquiry are convenient.Managerial personnel can be in management system with the implementation status of overall monitor operation order and work ticket: the contents such as operator, guardian, operation start time, EO time, operation execution in step and operation recording.Foregoing generates automatically by the palm PC pda system, and the operating personnel can't revise, the authenticity of mirror operation.
(4) " two tickets " carries out content and recording passback same system, managerial personnel can see " two tickets " content on one side in system, one side playback content, check whether operation order and work ticket content and recording operation whether corresponding, the operating personnel have situations such as whether jumping and operate standard, overcome the disadvantage that former playback is not known the concrete operation step of " two tickets ".
(5) " two tickets " realizes electronization, saved paper, thus the expense of minimizing equipment operation.Solved simultaneously papery on rainy day " two tickets " problem smudgy or that damage that is moistened by rain.
(6) operating personnel need not to carry other taping tools.Because PDA has sound-recording function, do not need to purchase in addition again recording pen as the taping tool of operations staff's operation.
(7) the operation recording is carried out synchronously with operation steps, and the operation recording is closed, and operation steps can't be carried out, and reduces original recording deviant circumstance.
(8) has the statement prompting function, prompting operating personnel implementation status.
Description of drawings
Figure 1 shows that the electric power safety production management system flow chart of preferred embodiment of the present invention.
Embodiment
Please refer to Fig. 1, Figure 1 shows that the electric power safety production management system flow chart of preferred embodiment of the present invention.The present invention proposes a kind of electric power safety production management system method of operating, comprises the following steps:
Step S100: in management system, create electronic operational ticket and work ticket;
Step S200: described operation order and work ticket are downloaded on the palm PC, and change the supervisor status of described operation order and work ticket;
Step S300: carry out operation order and work ticket on the described palm PC, record synchronously and operate, and operating process is carried out locking;
Step S300: the operation order and the work ticket that are finished are passed back in the management system, and change the supervisor status of described operation order and work ticket.
PDA electronic operational ticket and work ticket are about the implementation of the with no paper office of operation order in the KXG.After the creation operation ticket, enter after the relevant flow process in management system, download " two tickets " that need operation, " two tickets " downloaded on the PDA, the executable operations of " two tickets " is carried out at the scene of just can arriving.Be finished, " two tickets " execution information is transferred back in the management system, form the strict closed loop management of " two tickets ".
1. in management system, create by " two tickets "
After the field personnel receives operational order, utilize identity login management system, in management system establishment " two tickets " and through examining step by step, ratifying.Stipulated corresponding personnel's authority and workflow management in the management system, the personnel that must have associated rights just can carry out establishment, audit and the approval of " two tickets "." two tickets " data of management system comprise: " two tickets " operation item and dangerous point and control measure ticket.Concrete data comprise operation steps and the order of operation order, operating personnel, and the content of dangerous point and control measure and order, and permit on-stream time etc.
System adopts the interface mode of general WebService to carry out data transmission, is intercepted and captured or destroys for preventing information, adopts the verification mode of username and password, guarantees security of system.
2. " two tickets " downloads on the PDA
After PDA is connected with management system, just can carry out the operation that " two tickets " downloads to PDA.Under " two tickets " module of management system, open " two tickets " that need download.Mode by point " download " button just can download to " two tickets " on the PDA.
" two tickets " downloads on the PDA, employing be the mode of serializing file.The content of downloading mainly comprises operation task, operation steps, and the content of dangerous point control measure, operating personnel, the operation license start time, and the state of current ticket etc.
After " two tickets " successfully downloaded on the PDA, the state of " two tickets " changed in management system, becomes the ticket that downloads on the PDA.
The execution of " 3.PDA two tickets "
Open " two tickets " that needs execution at PDA, need the content of operation generally to be divided into two parts: the operation steps of " two tickets " and dangerous point and control measure item.
The flow process locking that system has carried out is mainly reflected in following several respects:
(1) recording must be carried out synchronously with operation
Before carrying out the dangerous point operation, must open first the operation of recording.If recording operation is not opened, then PDA " two tickets " does not allow operation.Equally, if in operating process, recording pause does not then allow dangerous point or " two tickets " are ticked operation yet.
The synchronous locking of recording and operation can be reacted the situation of execute-in-place, is conducive to monitor operation personnel's work, and can help managerial personnel in inquiry ticket operational circumstances, by recording, grasps the actual conditions at scene.
(2) could carry out " two tickets " after the dangerous point operation is finished
Must first the dangerous point control measure be finished, just can carry out the execution of " two tickets ".
If dangerous point and control measure do not execute, then do not allow to carry out the ticking operation of the operation steps etc. of " two tickets ".
(3) locking of " two tickets " execution in step
In the process that the operation steps to " two tickets " operates, system can carry out locking to operation steps, does not namely allow the user to carry out spanned item, more the operation of item and leakage item.
If the active user has carried out the 3rd operation steps, when directly going to carry out the 5th operation steps, system can provide prompting " you have jumped item and have operated ", and prompting user will operate according to correct operation steps.The user can't remove this locking, has guaranteed the tightness of operation steps.
3.1 the execution of dangerous point.The user can tick operation to dangerous point and control measure under the operator scheme of dangerous point.System can record the implementation status of current dangerous point, and determines according to implementation status whether current dangerous point control measure are finished.
According to the site work requirement, to the execution in step of dangerous point and control measure, the locking of not being correlated with, some dangerous point and control measure can not carried out.
The execution of " 3.2 two tickets ".The user can tick operation to operation steps under the operator scheme of operation.The implementation status of the concrete steps that system can record current " two tickets ", and determine according to implementation status whether current " two tickets " is finished.
" two tickets " do not allow the leak operation of item, jumping item in the process of implementation, and system has carried out strict locking.In operating process, system can according to current operation steps, record automatically." two tickets " is finished, and then recording file generates.
If " two tickets " carried out and arrived last, then " two tickets " automatically performs complete.If current " two tickets " because fortuitous event can not be proceeded operation, then system provides the function of ticket termination, namely current " two tickets " can be terminated, in the time of the pawn ticket termination, recording file generates automatically.
" 4.PDA two tickets " passback
After PDA " two tickets " is finished, just PDA " two tickets " can be returned.
" palm PC backfill " button in the some management system, system just can pass to the execution information of " two tickets " and dangerous point in the system, and recording file is passed back under the corresponding catalogue.The passback process has the prompting of progress bar, can help the user to understand current how many data of having transmitted.
Can in KXG, check the information of passback, comprise operation steps, the implementation status of dangerous point, the time of execution etc.
After certain " two tickets " passback was complete, the state of operation order changed automatically, transferred the state of " ticket of passing back from PDA " to from the state of " downloading to the ticket of PDA ".
5. the query statistic of " two tickets "
" two tickets " information that passback comes from PDA has been carried out the backup of data in management system, it is abundant that system provides, easily the function of the query statistic of " two tickets ".
The inquiry of " two tickets " is divided into various ways: can carry out a kind of inquiry of fare ticket type type by selecting the ticket template, also can by the key word of input ticket title, carry out the fuzzy query of ticket, can also be according to page number, the personnel that make out an invoice, responsible official, the information such as guardian are carried out the inquiry of " two tickets ".The variation of inquiry mode can make the user when carrying out the ticket inquiry, and more convenient operation is quick.
The statistical function of " two tickets " can freely be changed according to user's demand: by selecting start time, the concluding time of statistics, and the scope of statistics, can count current personnel, operator's item number, guardian's item number, person approving's item number, operation+monitoring, add up to, and the information of total umber of " two tickets ".
6. the recording of " two tickets " inquiry
In the management system, select certain " two ticket " that has been finished, can listen to the recording situation of current ticket.
For the operation recording of ticket, stipulated relevant personnel's authority, the personnel that do not have managerial personnel's authority can not listen to recording substance, only have managerial personnel just can listen to recording substance, the quality that the evaluation work at present is carried out.
After the field personnel receives the operation order, utilize identity login management system, in management system establishment " two tickets " and through examining step by step, ratifying, the operating personnel is from this operation order of system downloads or the extremely hand-held PDA equipment of work ticket, there is not intermediate link in whole transmission course, " two tickets " after the download is any can't be changed per capita, has guaranteed technically the safe reliability of " two tickets ".Changed in the past and took on-the-spot traditional operation mode to from system print " two tickets ".Then the operating personnel carries PDA equipment to on-the-spot executable operations.Operation steps according to the PDA prompting operates and guards at the scene, carry out item by item, and automatic synchronization recording, utilize the logic blocking function between the PDA operation steps, a generation of stopping leak or jumping, at any time query execution " two tickets " content and recording of crossing in the operating process, the on-line monitoring operational quality.Behind the complete operation, recycling PDA uploads to equipment management system, and this ticket performance information is back to management system, the flow process that these ticket stubs of autoshutdown are capable.Managerial personnel just can check " two tickets " and the operation recording that operated by factory's LAN (Local Area Network), and operational quality is monitored.Whole operating process has realized the standardization closed loop management, has greatly improved the security of operating personnel and equipment.
Although the present invention discloses as above with preferred embodiment, so it is not to limit the present invention.The persond having ordinary knowledge in the technical field of the present invention, without departing from the spirit and scope of the present invention, when being used for a variety of modifications and variations.Therefore, protection scope of the present invention is as the criterion when looking claims person of defining.

Claims (8)

1. an electric power safety production management system method of operating is characterized in that, comprises the following steps:
In management system, create electronic operational ticket and work ticket;
Described operation order and work ticket are downloaded on the palm PC, and change the supervisor status of described operation order and work ticket;
Carry out operation order and work ticket on the described palm PC, record synchronously and operate, and operating process is carried out locking;
The operation order and the work ticket that are finished are passed back in the management system, and change the supervisor status of described operation order and work ticket.
2. electric power safety production management system method of operating according to claim 1 is characterized in that the data of described operation order and work ticket comprise operation item, operation steps and order, operating personnel, dangerous point, the content of control measure and order, and permit on-stream time.
3. electric power safety production management system method of operating according to claim 1 is characterized in that, if recording operation is not opened or suspended, then described operation order and work ticket do not allow operation.
4. electric power safety production management system method of operating according to claim 1 is characterized in that, must first dangerous point and control measure be finished, and just can carry out the execution of operation order and work ticket.
5. electric power safety production management system method of operating according to claim 1 is characterized in that, after operation order and work ticket are finished, then automatically generates recording file.
6. electric power safety production management system method of operating according to claim 1 is characterized in that, described management system provides operation order and work ticket inquiry, by the key word of ticket title, page number, personnel make out an invoice, the responsible official, perhaps guardian's information is carried out the inquiry of operation order and work ticket.
7. electric power safety production management system method of operating according to claim 1 is characterized in that described management system provides statistical computation, add up current personnel, operator's item number, guardian's item number, person approving's item number, and total umber information of operation order and work ticket.
8. electric power safety production management system method of operating according to claim 1 is characterized in that, described management system is that the recording file of operation order and work ticket arranges administration authority.
CN2011102982595A 2011-09-30 2011-09-30 Electric power safe production management system operating method Pending CN103034918A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102982595A CN103034918A (en) 2011-09-30 2011-09-30 Electric power safe production management system operating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102982595A CN103034918A (en) 2011-09-30 2011-09-30 Electric power safe production management system operating method

Publications (1)

Publication Number Publication Date
CN103034918A true CN103034918A (en) 2013-04-10

Family

ID=48021794

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102982595A Pending CN103034918A (en) 2011-09-30 2011-09-30 Electric power safe production management system operating method

Country Status (1)

Country Link
CN (1) CN103034918A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103714422A (en) * 2013-12-16 2014-04-09 北京能源投资(集团)有限公司 Intelligent management method and intelligent management equipment
CN104050546A (en) * 2014-07-08 2014-09-17 国家电网公司 Scheduling operation monitoring method and system for scheduling operation ticket
CN104808516A (en) * 2014-01-28 2015-07-29 宁夏京能宁东发电有限责任公司 Electrical equipment operation control method and device
CN108537471A (en) * 2018-06-14 2018-09-14 宁夏京能宁东发电有限责任公司 A kind of flow management and control system and its data processing method of work ticket
CN109543962A (en) * 2018-11-05 2019-03-29 广东电网有限责任公司 A kind of method of programming count electronic operational ticket workload work point
CN109816352A (en) * 2019-02-13 2019-05-28 长园共创电力安全技术股份有限公司 A kind of work ticket generation method, device and the equipment of overhaul of the equipments process
CN111738675A (en) * 2020-05-29 2020-10-02 南京华盾电力信息安全测评有限公司 Intelligent two-ticket implementation method and system
CN113051309A (en) * 2020-12-30 2021-06-29 广东电网有限责任公司电力科学研究院 Digital implementation method for expert intelligent ticket checking
CN114154773A (en) * 2021-07-26 2022-03-08 北京京能信息技术有限公司 Technical method for guaranteeing relevant safety measures of electric power operation site

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201993802U (en) * 2010-12-20 2011-09-28 广东惠州天然气发电有限公司 Auxiliary system based on work ticket isolation measure field operation

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201993802U (en) * 2010-12-20 2011-09-28 广东惠州天然气发电有限公司 Auxiliary system based on work ticket isolation measure field operation

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
俞宏群等: "ERP操作票与巡检系统的结合与应用", 《电力信息化》, no. 12, 30 December 2009 (2009-12-30), pages 31 - 33 *
怀全等: "网络电气工作票系统在黄骅港的应用", 《港口装卸》, no. 4, 31 August 2011 (2011-08-31), pages 39 - 41 *
李焕中: "电厂可视化操作票及PDA防误操作系统的设计", 《科技资讯》, no. 28, 30 December 2009 (2009-12-30), pages 25 - 26 *
留军宏等: "水电厂运行操作探析", 《小水电》, no. 4, 15 August 2011 (2011-08-15) *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103714422A (en) * 2013-12-16 2014-04-09 北京能源投资(集团)有限公司 Intelligent management method and intelligent management equipment
CN104808516A (en) * 2014-01-28 2015-07-29 宁夏京能宁东发电有限责任公司 Electrical equipment operation control method and device
CN104050546A (en) * 2014-07-08 2014-09-17 国家电网公司 Scheduling operation monitoring method and system for scheduling operation ticket
CN108537471A (en) * 2018-06-14 2018-09-14 宁夏京能宁东发电有限责任公司 A kind of flow management and control system and its data processing method of work ticket
CN109543962A (en) * 2018-11-05 2019-03-29 广东电网有限责任公司 A kind of method of programming count electronic operational ticket workload work point
CN109543962B (en) * 2018-11-05 2021-04-02 广东电网有限责任公司 Method for automatically counting work load scores of electronic operation tickets
CN109816352A (en) * 2019-02-13 2019-05-28 长园共创电力安全技术股份有限公司 A kind of work ticket generation method, device and the equipment of overhaul of the equipments process
CN111738675A (en) * 2020-05-29 2020-10-02 南京华盾电力信息安全测评有限公司 Intelligent two-ticket implementation method and system
CN113051309A (en) * 2020-12-30 2021-06-29 广东电网有限责任公司电力科学研究院 Digital implementation method for expert intelligent ticket checking
CN114154773A (en) * 2021-07-26 2022-03-08 北京京能信息技术有限公司 Technical method for guaranteeing relevant safety measures of electric power operation site

Similar Documents

Publication Publication Date Title
CN103034918A (en) Electric power safe production management system operating method
CN111027932A (en) Safety management method for intelligent work ticket
CN103093552B (en) Operation order safety execution system based on personal digital assistants (PDAs)
Whittle et al. Executable misuse cases for modeling security concerns
JP5964077B2 (en) Control program management system and control program change method
CN103473844A (en) Intelligent control method and intelligent control system for public rental housing
CN109034425A (en) Substation secondary device maintenance safety managing and control system and method based on Internet of Things
CN108470313A (en) A kind of operation operation overall process management-control method and system based on mobile internet
CN103530924A (en) Dynamic password lock system and method for self-help network management
CN108986278A (en) A kind of intelligent door lock off-line cipher authorization method and authoring system
WO2008095866A2 (en) Method for authorizing the access to at least one automation component of a technical system
WO2020213956A1 (en) Method for managing work experience of worker through construction site work management
CN112699987B (en) Method and system for monitoring work task by using lock
CN103425916A (en) Safety operation device and method taking safety criteria as working process auditing standards
CN103544451A (en) Programmable logic controller (PLC) encryption method and system based on step-by-step maintaining
CN106327077A (en) Electrical maloperation-preventing control device based on entrance guard and control method thereof
CN111583465A (en) Intelligent key working method for electric power switching operation
CN204680024U (en) Computer security based on dynamic human face recognition technology is taken precautions against and early warning system
CN107808086A (en) Unlocking method, device and equipment of intelligent terminal
CN212627319U (en) System for wind-powered electricity generation field safety control
CN104282059A (en) Bluetooth-based safety intelligent lock system with video monitoring function and unlocking and locking methods
CN104978302B (en) A kind of intelligent and safe USB interface control method based on TCM chips
CN107197085A (en) A kind of comprehensive safety management-control method of intelligent movable mobile phone online
CN104392321B (en) A kind of biological authentification system of power scheduling graphic operation ticket, power scheduling operation ticket system
CN101646169A (en) System for authenticating permission distinction and permission encryption of tower crane user

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: FUCHUNJIANG HYDROELECTRIC POWER STATION OF EAST CHINA GRID CO., LTD.

Effective date: 20130603

Owner name: STATE GRID XINYUAN HYDROELECTRIC COMPANY LIMITED F

Effective date: 20130603

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 311504 HANGZHOU, ZHEJIANG PROVINCE TO: 100031 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20130603

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: State Grid Xinyuan Hydropower Co., Ltd.

Applicant after: Fuchunjiang Hydroelectric Power Station of East China Grid Co., Ltd.

Address before: 311504 the Fuchun River power plant, the Fuchun River Town, Tonglu County, Hangzhou, Zhejiang

Applicant before: Fuchunjiang Hydroelectric Power Station of East China Grid Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130410