CN108470313A - A kind of operation operation overall process management-control method and system based on mobile internet - Google Patents

A kind of operation operation overall process management-control method and system based on mobile internet Download PDF

Info

Publication number
CN108470313A
CN108470313A CN201810199926.6A CN201810199926A CN108470313A CN 108470313 A CN108470313 A CN 108470313A CN 201810199926 A CN201810199926 A CN 201810199926A CN 108470313 A CN108470313 A CN 108470313A
Authority
CN
China
Prior art keywords
item
locked
code
action
unlocking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810199926.6A
Other languages
Chinese (zh)
Inventor
陈翔
任海
张梁
李民希
于远鹏
王东泉
史宝平
甘成勇
凃陈
侯飞
姜开波
向欣欣
梁浩
华秋明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YALONGJIANG RIVER BASIN HYDROPOWER DEVELOPMENT Co Ltd
Original Assignee
YALONGJIANG RIVER BASIN HYDROPOWER DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YALONGJIANG RIVER BASIN HYDROPOWER DEVELOPMENT Co Ltd filed Critical YALONGJIANG RIVER BASIN HYDROPOWER DEVELOPMENT Co Ltd
Priority to CN201810199926.6A priority Critical patent/CN108470313A/en
Publication of CN108470313A publication Critical patent/CN108470313A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • G07C9/00174Electronically operated locks; Circuits therefor; Nonmechanical keys therefor, e.g. passive or active electrical keys or other data carriers without mechanical keys
    • G07C9/00309Electronically operated locks; Circuits therefor; Nonmechanical keys therefor, e.g. passive or active electrical keys or other data carriers without mechanical keys operated with bidirectional data transmission between data carrier and locks
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/12Protocols specially adapted for proprietary or special-purpose networking environments, e.g. medical networks, sensor networks, networks in vehicles or remote metering networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • General Physics & Mathematics (AREA)
  • General Health & Medical Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Primary Health Care (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Human Resources & Organizations (AREA)
  • General Business, Economics & Management (AREA)
  • Water Supply & Treatment (AREA)
  • Theoretical Computer Science (AREA)
  • Public Health (AREA)
  • Computing Systems (AREA)
  • Medical Informatics (AREA)
  • Signal Processing (AREA)
  • Lock And Its Accessories (AREA)

Abstract

The operation based on mobile internet that the invention discloses a kind of operating overall process managing and control system, including:Mobile client, server, prepositive communication computer and unlocking device;The mobile client is provided with unlocking unit;Each field device is correspondingly arranged on the smart lock of acquiescence locking, and the smart lock is provided with RFID chip, which is provided with the unique code-locked that can be identified by the unlocking device;The unlocking unit connects the unlocking device, the code-locked recognized for receiving the unlocking device, and verify the code-locked whether be the smart lock that the action-item being carrying out in the electronic operational ticket need to unlock code-locked, send unlock operational order to the unlocking device after verification is correct.The present invention replaces papery operation order using mobile client, pass through logic verify and code-locked verification operation item operation order, make operator that can only be operated according to the operation order of action-item in electronic operational ticket, effectively prevents operations staff and leak item, jump the risk that item operation is brought.

Description

A kind of operation operation overall process management-control method and system based on mobile internet
Technical field
The present invention relates to power plant safe practices more particularly to power plant to prevent maloperation technology, belongs to electric system letter Breathization and technical field of automation.
Background technology
Power industry is the basic industry of national economy, with the fast development of China's economy, social production and people's life Living to rely on electric power height, to the safety and reliability of power supply, more stringent requirements are proposed.According to statistics, China's electric power is looked forward in recent years In the accident that industry is occurred, 90% or more is caused by violating the regulations, and 70% or more representative accident is attributed to habitual violating the regulations, especially accidentally drawing Combination switch, on-load, which miss drawing isolation switch, electrification misses hanging earthing conductor or accidentally close grounding switch, line with ground or grounding switch misses Electric power enterprise bringing on a disaster property consequence is often given in the pernicious maloperation such as power transmission, mistakenly entering charged chamber, gently then damages equipment, weight is then led It causes personal injury or externally has a power failure.For this purpose, power industry is promulgated《Electric power safety working regulation》, it is specified that operating in operation Operation order is used according to regulations in journey, and according to sequentially being operated as defined in operation order, to prevent the error of personnel.
But effective overall process management and control in actual operation, cannot be carried out due to the use of traditional operation ticket, is often grasped Item, leakage item are jumped during making, or first operates buy one's ticket after normal time afterwards Deng unsafe acts, and great security risk is left for power generation.Example Such as:On May 1st, 2011, Huaneng Group Nanjing power plant operations staff is during carrying out 6kV station service grid switching operations, not stringent operation Ticket sequence operates, live connection of ground wire, and people death, a people are severely injured caused by electric shock.
Invention content
The purpose of the present invention is to propose to a kind of, and the operation based on mobile internet operates overall process management and control technology, can be right Operation operation overall process is managed and controls, to prevent operation operating personnel from jumping item, leakage item in operation or first operate After equal unsafe acts of buying one's ticket after normal time improve operation operating efficiency to reduce operation operational risk.
In order to achieve the above-mentioned object of the invention, the present invention provides following technical schemes:
A kind of operation operation overall process managing and control system based on mobile internet, including:Mobile client, server, communication Front end processor and unlocking device;The mobile client is provided with:Electronic operational ticket for action-item to be generated to electronic operational ticket is given birth to At unit, the five prevention logic verification unit for carrying out five prevention logic correctness verification to action-item in the electronic operational ticket, And unlocking unit;The prepositive communication computer is used to acquire the status information of five anti-devices and field device and is uploaded to the clothes Business device;The electronic operational ticket is uploaded to server in real time;
Each field device is correspondingly arranged on the smart lock of acquiescence locking, and when smart lock locking, the scene Equipment cannot be operated;The smart lock is provided with RFID chip, which is provided with and can be identified by the unlocking device Unique code-locked;
The unlocking unit connects the unlocking device, the code-locked recognized for receiving the unlocking device, and verifies the code-locked and be The code-locked of the no smart lock that need to be unlocked for the action-item being carrying out in the electronic operational ticket verifies the correct backward unlock Device sends unlock operational order;Authentication error then prompts to jump item or leakage item by the unlocking unit.
Preferably, the mobile client is handheld terminal or Web browser end;
The handheld terminal is tablet computer or mobile phone, is provided with single including electronic operational ticket generation unit, operation order management The APP of member and five prevention logic verification unit.
Preferably, the mobile client passes through wireless network connection with server;The wireless network is 2G, 3G or 4G Mobile network, or be the self-built wireless WIFI network of enterprise.
Preferably, the unlocking unit passes through unlocking device described in bluetooth connection.
Preferably, the mobile client is additionally provided with operation indicating unit, the points for attention for prompting action-item.
Preferably, the mobile client is additionally provided with employee's evaluation unit, for being periodically generated operation operation dependency number Analysis report according to statistics.
A kind of operation operation overall process management-control method based on mobile internet, including following implemented step:
S1, electronic operational ticket is filled in by mobile client;
S2, five prevention logic correctness verification is carried out to the electronic operational ticket;
S3, the correct electronic operational ticket of five prevention logic verification is examined and is examined;
S4, it holds handheld terminal and is operated to scene by the action-item in the electronic operational ticket by examining and examining;
After S5, end of operation, terminated by handheld terminal click, electronic operational ticket is affixed one's seal in corresponding position, recorded automatically Operating time is simultaneously uploaded to servers archive;
Further, field device is provided with smart lock, before operating equipment in step S4, needs first to unlock;Unlock intelligence Can lock detailed process be:
S10, unlocking device is inserted into smart lock, reads code-locked;
S20, handheld terminal receive the code-locked by bluetooth, and are verified to the code-locked;
After S30, code-locked verification are correct, the handheld terminal sends unlock operational order to unlocking device;
S40, smart lock unlock, and unlock result is fed back to the handheld terminal by unlocking device;
S50, after unlocking successfully, action-item is executed, after the completion of waiting for that the action-item executes, the smart lock automatic blocking.
Specifically, the detailed process of step S4 is:
After often completing an action-item and confirming, by the handheld terminal accurate recording operating time, while open the next item down operates Permission;
When occurring leakage item in operating process, jumping item, by unlocking unit early warning, and refuse to unlock.
Specifically, it during executing action-item, changes the electronic operational ticket according to on-site actual situations and operates accordingly Xiang Shi, the monitoring account and/or operator's account logged in by handheld terminal is remotely applied, the value of mobile client login is passed through Class's responsible person's account executes after remotely examining.
Compared with prior art, beneficial effects of the present invention:
1, the present invention replaces papery operation order using mobile client, is operated by logic verify and code-locked verification operation item suitable Sequence makes operator that can only be operated according to the operation order of action-item in electronic operational ticket, effectively prevent operations staff leak item, It jumps item and operates the risk brought.
2, mobile client, prepositive communication computer can be slapped with server exchange data, Central Control Room responsible person on duty at any time in real time Execute-in-place people's operational circumstances are held, can be disposed in time when pinpointing the problems, is conducive to improve site safety management level, be also beneficial to Overall arrangement works, and improves work on the spot efficiency.
3,2G, 3G or 4G mobile network, or be the self-built wireless WIFI network of enterprise, network coverage is wide, signal Stablize, system Construction is at low cost.
4, mobile client can be tablet computer or mobile phone, purchase and easy to maintain, use cost is low.
Description of the drawings:
Fig. 1 is the system schematic of the embodiment of the present invention;
Fig. 2 is the method flow diagram of the embodiment of the present invention;
Fig. 3 is that the smart lock of the embodiment of the present invention unlocks flow chart;
It is marked in figure:1- mobile clients, 10- handheld terminals, 20- browser ends, 2- servers, 3- prepositive communication computers, 4- solutions Lock device, 5- smart locks.
Specific implementation mode
With reference to test example and specific implementation mode, the present invention is described in further detail.But this should not be understood It is only limitted to embodiment below for the range of the above-mentioned theme of the present invention, it is all that this is belonged to based on the technology that the content of present invention is realized The range of invention.
Referring to Fig. 1, a kind of operation operation overall process managing and control system based on mobile internet, including:Mobile client 1, server 2, prepositive communication computer 3 and unlocking device 4;The mobile client 1 is provided with:For action-item to be generated electronic operation The electronic operational ticket generation unit of ticket(It is not shown), for carrying out five prevention logic correctness to action-item in the electronic operational ticket The five prevention logic verification unit of verification(It is not shown)And unlocking unit(It is not shown);The prepositive communication computer 3 is for acquiring five The status information of anti-device and field device is simultaneously uploaded to the server 2;The electronic operational ticket is uploaded to server in real time 2;Field device described in the present embodiment includes at least:For monitoring and controlling the Intelligent earth wire cabinet of ground wire, for monitoring intelligence Intelligent lock cabinet, the key management cabinet for monitoring unlocking mechanism related to controlling of the state of energy lockset;
Each field device is correspondingly arranged on the smart lock 5 of acquiescence locking, and when the locking of the smart lock 5, described existing Field device cannot be operated;The smart lock 5 is provided with RFID chip, which, which is provided with, to be known by the unlocking device 4 Other unique code-locked;
The unlocking unit connects the unlocking device 4, the code-locked recognized for receiving the unlocking device 4, and verifies the code-locked Whether be the smart lock 5 that the action-item being carrying out in the electronic operational ticket need to unlock code-locked, verify correct backward described Unlocking device 4 sends unlock operational order;Authentication error then prompts to jump item or leakage item by the unlocking unit.It is verified by code-locked Whether action-item operation order is correct, leads to personal injury to prevent human error or system mistake from causing leakage item, jump item operation And equipment damage.
The system architecture of the present embodiment is further established, the mobile client 1 is handheld terminal 10 or Web browser end 20;The handheld terminal 10 is tablet computer or mobile phone, is provided with single including electronic operational ticket generation unit, operation order management The APP of member and five prevention logic verification unit;The mobile client 1, by wireless network connection, is led in real time with server 2 Letter;The wireless network is 2G, 3G or 4G mobile network, or is the self-built wireless WIFI network of enterprise, realizes mobile client The automatic roaming at end 1;Preferably, the unlocking unit passes through unlocking device described in bluetooth connection.It should be appreciated that the value controlled in the middle Class responsible person carries out the operation of electronic operational ticket using laptop or desktop computer by Web browser end 20 in browser When management, it can also be connected to server 2 by cable network, be that present invention realization is more convenient using mobile Internet 1 Operation operation overall process management and control preferred embodiment.
Further, the mobile client 1 is provided with operation indicating unit(It is not shown), for prompting operator's action-item Points for attention;Especially occur installing ground wire, the higher operation of combined floodgate power transmission equivalent risk in operation, automatic prompt should The points for attention of item operation, realize the risk for reducing operator's maloperation.
It should be appreciated that when using the managing and control system of the present invention, the account of different functions need to be registered according to executor's function Family, such as operator registers operator's account, guardian registers monitoring account and responsible person on duty registers responsible person's account on duty, Different functional functions is completed after logging in different accounts each by mobile client;Meanwhile the mobile client 1, service The quantity of device 2 and prepositive communication computer 3 can increase and decrease according to actual demand.
Further, the mobile client is additionally provided with employee's evaluation unit(It is not shown), for being periodically generated operation behaviour Make related data Statistical Analysis Report, such as the operating time of operator, situation violating the regulations etc. in operating process, with to operator's Work quality is for statistical analysis, is promoted for evaluation employee skill, working members, employee, provides support.
Referring to Fig. 2, the embodiment of the present invention also provides a kind of operation operation overall process being preferably based on mobile internet Management-control method, including following implemented step:
S1, electronic operational ticket is filled in by mobile client;
Specifically, operator is acknowledged a debt family by 1 register of mobile client, and electronic operational ticket is filled according to operation task;Into One step is uploaded to server 2 after generating the electronic operational ticket, while the electronic operational ticket is provided with serial number, in order to it His relevant staff downloads or historical record inquiry;
S2, five prevention logic correctness verification is carried out to the electronic operational ticket;
Before the electronic operational ticket is committed to guardian's examination, it is correct that five prevention logic need to be carried out by five prevention logic verification unit Property verification;After verification is correct, which is committed to guardian's examination;When verifying incorrect, above carried in mobile client Show the electronic operational ticket mistake, and refuses to be committed to guardian's examination;Further, five prevention logic is the tool according to each equipment Body attribute, carries out operation logic setting, and five prevention logic described in the present embodiment preferably includes:Accidentally division switch, on-load miss Drawing disconnecting link, electrification close earthing knife-switch, band earthing knife-switch power transmission, mistakenly entering charged chamber;Further, when verifying incorrect, in mobile client The electronic operational ticket mistake is prompted on end, and it is the specific a certain item not met in five prevention logic to prompt the mistake;
S3, the correct electronic operational ticket of five prevention logic verification is examined and is examined;
Specifically, guardian verifies correct electronic operational ticket to five prevention logic and examines, if guardian has found have in examining When problem, necessary modification is carried out to the electronic operational ticket or retraction operation people rewrites;Then responsible person on duty is to by examining The electronic operational ticket looked into is examined, if find problematic in responsible person on duty examination & approval, is carried out to the electronic operational ticket necessary Modification or retraction operation people rewrite;
During above-mentioned S1-S3 either steps generate electronic operational ticket, operator, guardian and responsible person on duty pass through shifting The electronic operational ticket generation unit of dynamic client is stringent to electronic operational ticket progress to fill in, examine and examines, meanwhile, management and control system System, which automatically records, fills in, examines, examines and changes process and operating time, to carry out pipe to the process for generating electronic operational ticket Control, it is ensured that the correctness of electronic operational ticket;
S4, it holds handheld terminal 10 and is operated to scene by the action-item in the electronic operational ticket by examination & approval;
Further, field device is provided with smart lock 5, when operating the equipment for being provided with smart lock 5, needs first to solve Lock;The smart lock include padlock, cabinet door lock, band power grid door lock and important equipment room door lock, for breaker, keep apart It closes, earthing switch and ground wire are latched;
Referring to Fig. 3, the detailed process of unlock smart lock 5 is:
S10, unlocking device 4 is inserted into smart lock 5, reads code-locked;
S20, handheld terminal 10 receive the code-locked by bluetooth, and are verified to the code-locked;
After S30, code-locked verification are correct, the handheld terminal 10 sends unlock operational order to unlocking device 4;
S40, the smart lock 5 unlock, and feed back unlock result to the handheld terminal by unlocking device;
S50, after unlocking successfully, action-item is executed, after the completion of waiting for that the action-item executes, 5 automatic blocking of the smart lock;
Further, after often completing an action-item and confirming, by the 10 accurate recording operating time of the handheld terminal, while institute It states operation order administrative unit and opens the next item down operating right;When occurring leakage item in operating process, jumping item, unlocking unit prompt prison Protect people and/or operator's " operating mistake please be checked ", and refuse to unlock, with prevent human error or system mistake cause to leak item, Jumping item operation leads to personal injury and equipment damage;
Further, in operating process, operational circumstances are passed to by server by handheld terminal 10 in real time, responsible person on duty passes through Mobile client 1 monitors operational circumstances in real time, controls execute-in-place situation in time, reminds operation when pinpointing the problems in time People;The real time monitoring includes that the electronic operational ticket of voice and/or video monitoring and real-time Transmission to server operates letter Breath;
Further, operator executes in operating process, needs to change the electronic operational ticket according to on-site actual situations corresponding Action-item when(That is, being changed to not execute this operation or increasing operation item), can remotely be applied by handheld terminal 10, passed through Responsible person's account on duty that mobile client 1 logs in executes after remotely examining, and is added deduct with preventing site operation personnel from arbitrarily increasing Hidden danger caused by few operation item, it is ensured that operation quality;Simultaneously by remotely applying, examining, site operation personnel can be also reduced Come the time of fallback, improves working efficiency;
After S5, end of operation, terminated by handheld terminal click, electronic operational ticket affixes one's seal in corresponding position, records operation automatically Time is simultaneously uploaded to servers archive;Operation order management process is simplified through the invention, improves working efficiency;It avoids artificial It affixes one's seal, record caused omission, mistake, it is ensured that field operation procedures are correct.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all the present invention spirit and All any modification, equivalent and improvement made by within principle etc., should all be included in the protection scope of the present invention.

Claims (9)

1. a kind of operation based on mobile internet operates overall process managing and control system, which is characterized in that including:Mobile client End, server, prepositive communication computer and unlocking device;The mobile client is provided with:For action-item to be generated electronic operational ticket Electronic operational ticket generation unit, for carrying out the five anti-of five prevention logic correctness verification to action-item in the electronic operational ticket Logic verify unit and unlocking unit;The prepositive communication computer is used to acquire the status information of five anti-devices and field device And it is uploaded to the server;The electronic operational ticket is uploaded to server in real time;
Each field device is correspondingly arranged on the smart lock of acquiescence locking, and when smart lock locking, the scene Equipment cannot be operated;The smart lock is provided with RFID chip, which is provided with and can be identified by the unlocking device Unique code-locked;
The unlocking unit connects the unlocking device, the code-locked recognized for receiving the unlocking device, and verifies the code-locked and be The code-locked of the no smart lock that need to be unlocked for the action-item being carrying out in the electronic operational ticket verifies the correct backward unlock Device sends unlock operational order;Authentication error then prompts to jump item or leakage item by the unlocking unit.
2. operation according to claim 1 operates overall process managing and control system, which is characterized in that
The mobile client is handheld terminal or Web browser end;
The handheld terminal is tablet computer or mobile phone, is provided with single including electronic operational ticket generation unit, operation order management The APP of member and five prevention logic verification unit.
3. operation according to claim 2 operates overall process managing and control system, which is characterized in that the mobile client and clothes Business device passes through wireless network connection;The wireless network is 2G, 3G or 4G mobile network, or is the self-built wireless WIFI of enterprise Network.
4. operation according to claim 1 operates overall process managing and control system, which is characterized in that the unlocking unit passes through indigo plant Tooth connects the unlocking device.
5. operation according to claim 1 operates overall process managing and control system, which is characterized in that the mobile client is also set It is equipped with operation indicating unit, the points for attention for prompting action-item.
6. operation according to claim 1 operates overall process managing and control system, which is characterized in that the mobile client is also set It is equipped with employee's evaluation unit, for being periodically generated operation operation related data Statistical Analysis Report.
7. a kind of operation based on mobile internet operates overall process management-control method, which is characterized in that walked including following implemented Suddenly:
S1, electronic operational ticket is filled in by mobile client;
S2, five prevention logic correctness verification is carried out to the electronic operational ticket;
S3, the correct electronic operational ticket of five prevention logic verification is examined and is examined;
S4, it holds handheld terminal and is operated to scene by the action-item in the electronic operational ticket by examining and examining;
After S5, end of operation, terminated by handheld terminal click, electronic operational ticket is affixed one's seal in corresponding position, recorded automatically Operating time is simultaneously uploaded to servers archive;
Further, field device is provided with smart lock, before operating equipment in step S4, needs first to unlock;Unlock intelligence Can lock detailed process be:
S10, unlocking device is inserted into smart lock, reads code-locked;
S20, handheld terminal receive the code-locked by bluetooth, and are verified to the code-locked;
After S30, code-locked verification are correct, the handheld terminal sends unlock operational order to unlocking device;
S40, smart lock unlock, and unlock result is fed back to the handheld terminal by unlocking device;
S50, after unlocking successfully, action-item is executed, after the completion of waiting for that the action-item executes, the smart lock automatic blocking.
8. operation according to claim 7 operates overall process management-control method, which is characterized in that the detailed process of step S4 For:
After often completing an action-item and confirming, by the handheld terminal accurate recording operating time, while next action-item is opened Operating right;
When occurring leakage item in operating process, jumping item, by unlocking unit early warning, and refuse to unlock.
9. operation according to claim 7 operates overall process management-control method, which is characterized in that during executing action-item, When action-item corresponding according to the on-site actual situations change electronic operational ticket, pass through the monitoring account that handheld terminal logs in And/or operator's account is remotely applied, the responsible person's account on duty logged in by mobile client executes after remotely examining.
CN201810199926.6A 2018-03-12 2018-03-12 A kind of operation operation overall process management-control method and system based on mobile internet Pending CN108470313A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810199926.6A CN108470313A (en) 2018-03-12 2018-03-12 A kind of operation operation overall process management-control method and system based on mobile internet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810199926.6A CN108470313A (en) 2018-03-12 2018-03-12 A kind of operation operation overall process management-control method and system based on mobile internet

Publications (1)

Publication Number Publication Date
CN108470313A true CN108470313A (en) 2018-08-31

Family

ID=63264237

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810199926.6A Pending CN108470313A (en) 2018-03-12 2018-03-12 A kind of operation operation overall process management-control method and system based on mobile internet

Country Status (1)

Country Link
CN (1) CN108470313A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109976285A (en) * 2019-04-24 2019-07-05 安易享(深圳)科技有限公司 A kind of safety management system and its control method based on the acquisition of 5G terminal
CN110378803A (en) * 2019-06-25 2019-10-25 鞍钢股份有限公司 A kind of industry stops power transmission C2C platform and method
CN111506375A (en) * 2020-04-13 2020-08-07 慧控九州(北京)科技有限公司 Intelligent management and control method for operation behaviors of enterprise operators
CN111885521A (en) * 2020-06-28 2020-11-03 国家电网有限公司 System and method for defect investigation and recording without power outage
CN112419696A (en) * 2020-11-18 2021-02-26 国网四川省电力公司映秀湾水力发电总厂 Intelligent anti-misoperation device system and method based on wireless transmission
CN112990872A (en) * 2021-03-16 2021-06-18 国家电网有限公司 Interactive ground wire control method
CN113036910A (en) * 2021-02-26 2021-06-25 云南电网有限责任公司曲靖供电局 Control method of intelligent online anti-misjudgment five-prevention system
CN113794754A (en) * 2021-08-25 2021-12-14 国网福建省电力有限公司 Electronic operation ticket control system and method based on mobile application
CN113920627A (en) * 2021-10-27 2022-01-11 江苏睿孜星智控科技有限公司 Electrical operation ticket anti-misoperation mobile application system and method based on electronic lock
WO2023098375A1 (en) * 2021-12-01 2023-06-08 珠海优特电力科技股份有限公司 Operation sheet processing method and device, storage medium, and electronic device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101013635A (en) * 2006-12-13 2007-08-08 淄博微联电子有限公司 Intelligent remote control locking method and apparatus for preventing electric misoperation
CN101834471A (en) * 2010-05-25 2010-09-15 广东电网公司珠海供电局 Transformer substation dynamic anti-maloperation locking system realized on basis of integrated online five-prevention
CN103338063A (en) * 2013-06-17 2013-10-02 南京邮电大学 Android electric intelligent key and Bluetooth unlock system, as well as implementation method thereof
CN105449867A (en) * 2015-12-25 2016-03-30 国网浙江省电力公司丽水供电公司 Visual operation process monitoring mistake precaution system and control method
CN106877508A (en) * 2017-03-28 2017-06-20 长园共创电力安全技术股份有限公司 A kind of grid switching operation monitor in real time anti-error system and its control method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101013635A (en) * 2006-12-13 2007-08-08 淄博微联电子有限公司 Intelligent remote control locking method and apparatus for preventing electric misoperation
CN101834471A (en) * 2010-05-25 2010-09-15 广东电网公司珠海供电局 Transformer substation dynamic anti-maloperation locking system realized on basis of integrated online five-prevention
CN103338063A (en) * 2013-06-17 2013-10-02 南京邮电大学 Android electric intelligent key and Bluetooth unlock system, as well as implementation method thereof
CN105449867A (en) * 2015-12-25 2016-03-30 国网浙江省电力公司丽水供电公司 Visual operation process monitoring mistake precaution system and control method
CN106877508A (en) * 2017-03-28 2017-06-20 长园共创电力安全技术股份有限公司 A kind of grid switching operation monitor in real time anti-error system and its control method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109976285A (en) * 2019-04-24 2019-07-05 安易享(深圳)科技有限公司 A kind of safety management system and its control method based on the acquisition of 5G terminal
CN110378803A (en) * 2019-06-25 2019-10-25 鞍钢股份有限公司 A kind of industry stops power transmission C2C platform and method
CN110378803B (en) * 2019-06-25 2023-03-03 鞍钢股份有限公司 Industrial power outage and transmission C2C platform and method
CN111506375A (en) * 2020-04-13 2020-08-07 慧控九州(北京)科技有限公司 Intelligent management and control method for operation behaviors of enterprise operators
CN111885521A (en) * 2020-06-28 2020-11-03 国家电网有限公司 System and method for defect investigation and recording without power outage
CN112419696A (en) * 2020-11-18 2021-02-26 国网四川省电力公司映秀湾水力发电总厂 Intelligent anti-misoperation device system and method based on wireless transmission
CN113036910A (en) * 2021-02-26 2021-06-25 云南电网有限责任公司曲靖供电局 Control method of intelligent online anti-misjudgment five-prevention system
CN112990872A (en) * 2021-03-16 2021-06-18 国家电网有限公司 Interactive ground wire control method
CN113794754A (en) * 2021-08-25 2021-12-14 国网福建省电力有限公司 Electronic operation ticket control system and method based on mobile application
CN113920627A (en) * 2021-10-27 2022-01-11 江苏睿孜星智控科技有限公司 Electrical operation ticket anti-misoperation mobile application system and method based on electronic lock
WO2023098375A1 (en) * 2021-12-01 2023-06-08 珠海优特电力科技股份有限公司 Operation sheet processing method and device, storage medium, and electronic device
GB2619167A (en) * 2021-12-01 2023-11-29 Zhuhai Unitech Power Tech Co Operation sheet processing method and device, storage medium, and electronic device

Similar Documents

Publication Publication Date Title
CN108470313A (en) A kind of operation operation overall process management-control method and system based on mobile internet
CN103473844B (en) Public affairs are rented a house intelligent control method and system
CN110428533B (en) Intelligent lockset management system for realizing integration of misoperation-preventive lock control based on Internet of things
CN101893867B (en) Operation ticket management system and method
CN109326034B (en) Intelligent lock work ticket management system for electric cabinet
CN110011848B (en) Mobile operation and maintenance auditing system
CN103049936B (en) Rail traffic ticket automatic selling and checking system station control center system
CN104504782A (en) Intelligent door lock system of hydropower station
CN108064398B (en) Electron key management method and device
CN102361354A (en) Remote intensive management and control system of unattended converting station automatic system
CN111106671B (en) Five-prevention management control method and system for substation coded lock
Amin Securing the electricity grid
CN101127133A (en) Door access remote management method
CN103941652A (en) Method and device suitable for security protection and security audit of various DCS production control systems
CN104318652A (en) Intelligent door lock management method of hydropower station
CN106877508A (en) A kind of grid switching operation monitor in real time anti-error system and its control method
CN205476951U (en) Electric control lock
CN102842162A (en) Comprehensive managing system and managing method of anti-error and intelligent locking group of electric microcomputer
CN103166316A (en) Intellectualization transformer substation configuration file management method and system based on error-closing-prevention lock
CN214154147U (en) Intelligent anti-misoperation system for switching operation
CN105978147A (en) File interaction based remote constant value amending system for automatic safety devices
CN106586748A (en) Elevator failure instruction code treatment method, device and system
CN109636971A (en) A kind of intelligent Community safety entrance guard management method and system
CN112054599A (en) System and method for safety management of wind power plant
CN110348545B (en) AR intelligent operation ticket method and device based on ERP system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180831