CN103015566B - Multiple-chamber type double steel plate concrete combined shear wall - Google Patents

Multiple-chamber type double steel plate concrete combined shear wall Download PDF

Info

Publication number
CN103015566B
CN103015566B CN201210553483.9A CN201210553483A CN103015566B CN 103015566 B CN103015566 B CN 103015566B CN 201210553483 A CN201210553483 A CN 201210553483A CN 103015566 B CN103015566 B CN 103015566B
Authority
CN
China
Prior art keywords
bin
wall
chamber
concrete
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210553483.9A
Other languages
Chinese (zh)
Other versions
CN103015566A (en
Inventor
周耀
郭全全
黄泽宇
赵唯以
谭力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beihang University
Original Assignee
Beihang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beihang University filed Critical Beihang University
Priority to CN201210553483.9A priority Critical patent/CN103015566B/en
Publication of CN103015566A publication Critical patent/CN103015566A/en
Application granted granted Critical
Publication of CN103015566B publication Critical patent/CN103015566B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention relates to a multiple-chamber type double steel plate concrete combined shear wall, which integrally consists of two wall body surface steel plates (6) and a wall inner plain concrete (7), wherein the wall body surface steel plates (6) and the wall inner neat concrete (7) are connected by bolt screws (2), split reinforced bars (1) and vertical separating plates (4) to ensure the cooperated work, the bolt screws (2), the split reinforced bars (1) and the vertical separating plates (4) are welded on the steel plates, the wall body space between the two steel plates is separated into bin chambers by the vertical separating plates (4), the inside of one part of bin chambers is cast with concrete to form concrete bin chambers (8), the other part of bin chambers is kept empty and is filled with a foam aluminum porous energy dissipating material to form an empty bin chamber (9) and an energy dissipating material filling bin chamber (10), and then the alternative distribution of the concrete bin chambers (8), the empty bin chamber (9) and the energy dissipating material filling bin chamber (10) is realized. The multiple-chamber type double steel plate concrete combined shear wall has the advantage that the rigidity is reduced, and the extensibility is increased, so the suitability is further improved.

Description

A kind of multiple-chamber type double steel plate combined concrete shear wall
Technical field:
The present invention relates to a kind of novel shear wall, relate in particular to a kind of multiple-chamber type double steel plate combined concrete shear wall, belong to civil engineering structure technical field.
Background technology
In recent years, along with the fast development of China's economy, urbanization was accelerated greatly.A large amount of population is poured into city, and expanding economy, and land resources day is becoming tight.For relaxing people ground contradiction, house and commercial building etc. all presents the development trend of high stratification, superelevation, and this also has higher requirement to corresponding form of structure, and the one, it has good mechanical property requirement, as lateral deformation stiffness, ultimate bearing capacity etc.; The 2nd, it has good ductility and energy dissipation capacity requirement, so that whole building is under stronger seismic loading, can there is moderate finite deformation, more energy dissipates, thereby guarantee that structure does not collapse and significantly destroy, with effective guarantee people's life security and property safety; The 3rd, it has good application property, simple structure requirement.
In highrise building, conventional lateral resistant member has two kinds of framework and shear walls, and wherein the mechanical property of shear wall is better than framework, builds higher, shear wall application is more, and the shear wall of traditional form is in mechanical property, anti-seismic performance with more or less there is certain deficiency above construction simplification.
1) reinforced concrete shear wall and Profiled bar concrete combination shearing wall
Although reinforced concrete shear wall and Profiled bar concrete combination shearing wall rigidity large bearing capacity are high, all there is serious deficiency in ductility and energy dissipation capacity.
2) steel plate shear force wall
Steel plate shear force wall mechanical property or Hysteresis Behavior are all more satisfactory in theory, but due to the outer flexing of its easy generating plane, make its complex structure and utilize insufficient.
3) single steel plate concrete combined shear wall
Single steel plate concrete combined shear wall is hanging concrete plate on steel plate shear force wall, to prevent the outer flexing of face of steel plate.Correlation test shows, the purer steel plate shear force wall of the Hysteresis Behavior of the shear wall of this kind of form and mechanical property improves, but due to the large reason of concrete slab rigidity, concrete slab is easy to ftracture, make it can not effectively prevent steel plate flexing, also largely affect its comfortableness and applicability simultaneously, in addition, its also more complicated of constructing.
A kind of novel compound shear wall, i.e. double steel plate combined concrete shear wall have been risen the nineties in 20th century.This kind of compound wall is comprised of steel plate and the inner cast-in-place plain concrete body of wall of both sides, between steel plate and concrete, by a large amount of shearing resistance pegs, stiffening rib, vertical next door etc., be connected, to guarantee the collaborative work between the two, two block plates in plain concrete outside are by drawing the connections such as batten plate of welding on reinforcing bar, vertical baffle, stiffening rib, with the shearing outside resistance wall dignity and constraint concrete deformation, as Fig. 1.The experimental study of double steel plate combined concrete shear wall shows, its initial stiffness is large, and bearing capacity is high, and ductility is better, and hysteresis loop is full, and energy dissipation capacity is strong, without the flexing sound.In construction, wall outer side double steel plate is equivalent to template, and additionally formwork, and double steel plate outside framework can be processed in factory's modularization again, then welding at the scene, greatly reduces the difficulty of its site operation, has greatly accelerated speed of application.Aspect fire resistance, the fire resistance test of double steel plate combined concrete shear wall shows, the purer steel plate shear force wall of fireproof performance of this body of wall is good, because when being heated, the steel plate of wall outer side mainly plays heat is conducted to inner concrete effect, and heat can not accumulated on the steel plate of outside, even so, outside steel plate is still in direct exposed thermal field, and steel billet temperature is still higher, and its fire line still needs specially treated.In addition, double steel plate combined concrete shear wall is the same with other steel work, need to do special preservative treatment, to improve the durability of structure.
Therefore, can say that double steel plate combined concrete shear wall is a kind of ideal lateral resistant member, but in actual applications, still there is the excessive and not very good shortcoming of ductility of rigidity in it.Excessive rigidity is not easy to the rigidity of structure distributes and adjusts, and causes the rigidity of total to concentrate too much on double steel plate combined concrete shear wall, is not easy to realize multiple anti-vibration defense lines and the integrated carrying in standard, advocated.The not very good antidetonation that is unfavorable for double steel plate combined concrete shear wall of ductility own.In addition, it is large especially that rigidity is crossed the thermal stresses that conference makes structure, thereby make it lose a part of bearing capacity.
The present invention (Fig. 2 and Fig. 3) multiple-chamber type double steel plate combined concrete shear wall is for above two shortcomings, to a kind of improvement of double steel plate combined concrete shear wall and breakthrough, thus a kind of novel double steel plate combined concrete shear wall forming.It is by common double steel plate concrete combined shear wall, along the high direction of wall, to divide bin by vertical baffle, concreting in part bin again, another part bin is the power consumption material such as concreting or placement foamed aluminium not, thereby the body of wall of script one is divided into concrete-filled steel square tubular column arranged side by side, making the anti-side mechanism of body of wall is that the main crooked flexural deformation that changes quadrate steel pipe column arranged side by side into is main by whole shear strain, reach the object that reduces body of wall lateral deformation stiffness and further increase ductility, this is with similar with the working mechanism of perps reinforced concrete shear wall.What need specified otherwise is, in multiple-chamber type double steel plate combined concrete shear wall have concrete bin with without concrete bin, not wide, generally there is concrete bin to comprise an above bin, than many without concrete bin, and wide, be to have concrete bin and be interspersed without concrete bin on the whole.For guaranteeing without the steel plate of concrete bin flexing not, without the steel plate width of concrete bin, to meet Stability Checking, if do not met, need take the strengthening measures such as stiffening rib.Say on the whole, multiple-chamber type double steel plate combined concrete shear wall can further improve mechanical property and the anti-seismic performance of double steel plate combined concrete shear wall.
Summary of the invention
1. goal of the invention:
The object of this invention is to provide a kind of multiple-chamber type double steel plate combined concrete shear wall.It is in order to reduce the rigidity of double steel plate combined concrete shear wall, increases the ductility of double steel plate combined concrete shear wall, thereby further improves the applicable performance of double steel plate combined concrete shear wall.
2. technical scheme
Technical scheme of the present invention is as Fig. 2, and its integral body is comprised of two blocks of surface of wall steel plates 6 and the inner plain concrete 7 of body of wall, between the two by being welded on peg 2 on steel plate, to drawing the realizations such as reinforcing bar 1 and vertical baffle 4 to be connected, to guarantee the collaborative work between the two.And utilize vertical baffle 4, by the body of wall space between two steel plates, divide bin, then concreting in a part of bin, form concrete bin 8, another part bin keeps the porous power consumption materials such as hole capital after selling all securities and filled and process aluminium, form hole capital after selling all securities chamber 9 and fill bin 10 with power consumption material, thereby form concrete bin 8, fill being alternately distributed of bin 10 with hole capital after selling all securities chamber 9 and power consumption material.In addition, when hole capital after selling all securities chamber 9 meets Stability Checking, on the 9 place's surface of wall steel plates 6 of hole capital after selling all securities chamber, stiffening rib 3 can be set, when hole capital after selling all securities chamber 9 does not meet Stability Checking, on the 9 place's surface of wall steel plates 6 of hole capital after selling all securities chamber, need by calculating and setting stiffening rib 3.
On unitary construction, the width that hole capital after selling all securities chamber 9 and power consumption material are filled bin 10 is not more than the twice of the thickness of wall body between two steel plates, and the width of concrete bin 8 is not more than 4 times of thickness of wall body between two steel plates; Hole capital after selling all securities chamber 9 and power consumption material filling bin 10 are not less than 1/8 of body of wall place floor floor height from the distance of body of wall end; When having door and window hole, hole capital after selling all securities chamber 9 and power consumption material are filled bin 10 distances from edges, hole such as door and windows and are not less than 1/8 of hole height.Steel plate, peg, to drawing the size of reinforcing bar, vertical baffle and stiffening rib etc. should meet the calculation requirement of structure.
3. advantage and effect:
Compare with traditional double steel plate combined concrete shear wall (Fig. 1), the present invention (Fig. 2 and Fig. 3) has the following advantages and effect:
1) appropriateness has reduced rigidity, is convenient to the rigidity adjustment of structure, and effectively reduces thermal stresses;
2) change structure distortion pattern, and then improve structure ductility;
3) without concrete bin, can place the power consumption materials such as foamed aluminium, further strengthen the anti-seismic performance of structure;
4) reduced concrete amount.
In a word, one aspect of the present invention has been improved mechanical property and the anti-seismic performance of double steel plate combined concrete shear wall, does not substantially increase again on the other hand difficulty of construction, and economic performance is also substantially constant, can say, comparatively feasible.
Accompanying drawing explanation
Fig. 1 double steel plate combined concrete shear wall axle measures intention
Fig. 2 axle of the present invention measures intention
Fig. 3 vertical cross section schematic diagram of the present invention
Mark in figure:
1---to drawing reinforcing bar; 2---peg; 3---stiffening rib; 4---vertical baffle; 5---the porous power consumption materials such as foamed aluminium; 6---surface of wall steel plate; 7---the inner plain concrete of body of wall; 8---concrete bin; 9---hole capital after selling all securities chamber; 10---power consumption material is filled bin.
The specific embodiment
Fig. 1 is traditional double steel plate combined concrete shear wall axonometric drawing.
See Fig. 2, Fig. 3, a kind of multiple-chamber type double steel plate of the present invention combined concrete shear wall, its integral body is comprised of two blocks of surface of wall steel plates 6 and the inner plain concrete 7 of body of wall, between the two by being welded on peg 2 on steel plate, to drawing reinforcing bar 1 to be connected with realizations such as vertical baffles 4, to guarantee the collaborative work between the two.And utilize vertical baffle 4, by the body of wall space between two steel plates, divide bin, then concreting in a part of bin, form concrete bin 8, another part bin keeps the porous power consumption materials 5 such as hole capital after selling all securities and filled and process aluminium, form hole capital after selling all securities chamber 9 and fill bin 10 with power consumption material, thereby form concrete bin 8, fill being alternately distributed of bin 10 with hole capital after selling all securities chamber 9 and power consumption material.In addition, when hole capital after selling all securities chamber 9 meets Stability Checking, on the 9 place's surface of wall steel plates 6 of hole capital after selling all securities chamber, stiffening rib 3 can be set, when hole capital after selling all securities chamber 9 does not meet Stability Checking, on the 9 place's surface of wall steel plates 6 of hole capital after selling all securities chamber, need by calculating and setting stiffening rib 3.
On unitary construction, the width that hole capital after selling all securities chamber 9 and power consumption material are filled bin 10 is not more than the twice of the thickness of wall body between two steel plates, and the width of concrete bin 8 is not more than 4 times of thickness of wall body between two steel plates; Hole capital after selling all securities chamber 9 and power consumption material filling bin 10 are not less than 1/8 of body of wall place floor floor height from the distance of body of wall end; When having door and window hole, hole capital after selling all securities chamber 9 and power consumption material are filled bin 10 distances from edges, hole such as door and windows and are not less than 1/8 of hole height.Steel plate, peg, to drawing the size of reinforcing bar, vertical baffle and stiffening rib etc. should meet the calculation requirement of structure.

Claims (1)

1. a multiple-chamber type double steel plate combined concrete shear wall, it is characterized in that: its integral body is comprised of two blocks of surface of wall steel plates (6) and the inner plain concrete of body of wall (7), between the two by the peg (2) being welded on steel plate, to drawing reinforcing bar (1), realize and being connected with vertical baffle (4), to guarantee the collaborative work between the two, and utilize vertical baffle (4), by the body of wall space between two steel plates, divide bin, then concreting in a part of bin, form concrete bin (8), another part bin keeps hole capital after selling all securities and filled and process aluminium porous power consumption material, form hole capital after selling all securities chamber (9) and power consumption material filling bin (10), thereby form concrete bin (8) and fill being alternately distributed of bin (10) with hole capital after selling all securities chamber (9) and power consumption material, in addition, when hole capital after selling all securities chamber (9) meet Stability Checking, hole capital after selling all securities chamber (9) is located, on surface of wall steel plate (6), stiffening rib (3) is not set, and when hole capital after selling all securities chamber (9) do not meet Stability Checking, hole capital after selling all securities chamber (9) are located to need by calculating and setting stiffening rib (3) on surface of wall steel plate (6), on unitary construction, the width that hole capital after selling all securities chamber (9) and power consumption material are filled bin (10) is not more than the twice of the thickness of wall body between two steel plates, and the width of concrete bin (8) is not more than 4 times of thickness of wall body between two steel plates, hole capital after selling all securities chamber (9) and power consumption material filling bin (10) are not less than 1/8 of body of wall place floor floor height from the distance of body of wall end, when having door and window hole, hole capital after selling all securities chamber (9) and power consumption material filling bin (10) are not less than 1/8 of hole height from the distance at door and window hole edge, steel plate, peg, to drawing the size of reinforcing bar, vertical baffle and stiffening rib should meet the calculation requirement of structure.
CN201210553483.9A 2012-12-19 2012-12-19 Multiple-chamber type double steel plate concrete combined shear wall Expired - Fee Related CN103015566B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210553483.9A CN103015566B (en) 2012-12-19 2012-12-19 Multiple-chamber type double steel plate concrete combined shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210553483.9A CN103015566B (en) 2012-12-19 2012-12-19 Multiple-chamber type double steel plate concrete combined shear wall

Publications (2)

Publication Number Publication Date
CN103015566A CN103015566A (en) 2013-04-03
CN103015566B true CN103015566B (en) 2014-11-05

Family

ID=47964623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210553483.9A Expired - Fee Related CN103015566B (en) 2012-12-19 2012-12-19 Multiple-chamber type double steel plate concrete combined shear wall

Country Status (1)

Country Link
CN (1) CN103015566B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485441A (en) * 2013-09-10 2014-01-01 华南理工大学 Combined shearing wall
CN105839777A (en) * 2016-03-31 2016-08-10 初明进 Line-shaped steel-concrete composite structure member
CN108149835A (en) * 2018-01-08 2018-06-12 青岛理工大学 A kind of pipe supporting steel plate storehouse and production method
CN108571169B (en) * 2018-06-15 2021-05-28 河南绿建建筑科技有限公司 Construction method for factory prefabricated steel concrete superposed shear wall assembly type building
CN110872874B (en) * 2019-11-28 2021-06-22 无锡市光彩机械制造有限公司 Shear wall with integrated profile steel as framework and field construction method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007063954A (en) * 2005-09-02 2007-03-15 Takenaka Komuten Co Ltd Method of forming steel plate concrete
KR101049963B1 (en) * 2008-12-01 2011-07-15 한국전력기술 주식회사 Steel plate structure and construction method of wall-slab joint structure using same
CN101824863B (en) * 2010-04-21 2012-05-23 中南大学 Concrete shear wall
CN202055373U (en) * 2011-04-22 2011-11-30 上海江欢成建筑设计有限公司 Combined structure of double-steel-plate sandwich concrete wall and square steel tube concrete
CN202148619U (en) * 2011-06-20 2012-02-22 南通建筑工程总承包有限公司 Double steel plate structure scissors wall
CN102296723A (en) * 2011-07-21 2011-12-28 广州容柏生建筑结构设计事务所 Outer multi-cavity steel plate concrete combined shear wall and construction method thereof
CN202401613U (en) * 2011-09-22 2012-08-29 姚攀峰 Non-template and energy-dissipating steel plate shear wall structure
CN202416627U (en) * 2012-01-06 2012-09-05 西安理工大学 Composite steel plate shear wall

Also Published As

Publication number Publication date
CN103015566A (en) 2013-04-03

Similar Documents

Publication Publication Date Title
CN103015566B (en) Multiple-chamber type double steel plate concrete combined shear wall
CN102912896B (en) Separate type steel plate shear force wall
CN102704593B (en) Steel tube reinforced concrete composite column-steel beam-lattice steel support shear wall and manufacturing method
CN206091045U (en) Antinode core precast concrete assembled composite wall
CN204510467U (en) A kind of cap node for basement flat slab structure
CN103485443B (en) A kind of window shape steel plate concrete shear wall and preparation method thereof
CN103088842A (en) Rubble retaining wall reinforced single-face pattern plate support system and construction method
CN108086535A (en) A kind of assembled square steel tube steel plate concrete combined shear wall
CN108589969B (en) Combined assembly type shear wall with vertical ECC energy consumption belt and manufacturing method thereof
CN103061408B (en) Powerful confined concrete core wall with obvious columns and hidden beams
CN203559502U (en) Window-shaped steel plate concrete shear wall
CN202882166U (en) Distributed steel plate shear wall
CN104612291A (en) Non-dismantling heat preservation wall module unit
CN106677379A (en) Steel plate shear wall structure and construction method
CN107740536A (en) A kind of damping type beam body for building
CN209227757U (en) Modularization stitching lamination wood keeps the temperature multifunction structure plate
CN204510538U (en) A kind of disassembly-free heat-insulation wall body module unit
CN207633573U (en) A kind of novel anti-buckling combined steel plate shearing force wall
CN208088555U (en) A kind of box compound shear wall of double L-shaped rectangle steel
CN205637335U (en) Prefabricated L type dysmorphism steel pipe -concrete composite post
CN204491903U (en) Built-in for the split type combined concrete shear wall of concrete steel plate
CN203200957U (en) Anti-seismic self-insulation wall
CN205663030U (en) Prefabricated T type dysmorphism steel pipe -concrete composite post
CN210857598U (en) Safety anti-theft assembled wall
CN211850134U (en) Fireproof shear wall building structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhou Yao

Inventor after: Guo Quanquan

Inventor after: Huang Zeyu

Inventor after: Zhao Weiyi

Inventor after: Tan Li

Inventor before: Guo Quanquan

Inventor before: Huang Zeyu

Inventor before: Zhao Weiyi

Inventor before: Tan Li

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: GUO QUANQUAN HUANG ZEYU ZHAO WEIYI TAN LI TO: ZHOU YAO GUO QUANQUAN HUANG ZEYU ZHAO WEIYI TAN LI

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141105

Termination date: 20211219