CN103009898B - Ornamental water body giant acrylic glass installation construction method - Google Patents

Ornamental water body giant acrylic glass installation construction method Download PDF

Info

Publication number
CN103009898B
CN103009898B CN201110281574.7A CN201110281574A CN103009898B CN 103009898 B CN103009898 B CN 103009898B CN 201110281574 A CN201110281574 A CN 201110281574A CN 103009898 B CN103009898 B CN 103009898B
Authority
CN
China
Prior art keywords
glass
acrylic glass
acrylic
splicing
bealock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110281574.7A
Other languages
Chinese (zh)
Other versions
CN103009898A (en
Inventor
黄延铮
张建新
张煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201110281574.7A priority Critical patent/CN103009898B/en
Publication of CN103009898A publication Critical patent/CN103009898A/en
Application granted granted Critical
Publication of CN103009898B publication Critical patent/CN103009898B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Glass To Other Materials (AREA)

Abstract

The present invention discloses a giant acrylic glass installation construction method for an ornamental water body, which comprises the following steps: transporting, fitting, splicing, and acrylic glass and structure connection. According to the present invention, a main body casting polymerization method splicing technology is adopted, large scale mechanical equipment is not required, and a treatment surface on a seaming position is smooth; a polymerization reaction gelatification effect tends mild so as to avoid occurrence of flash polymerization phenomenon; and the acrylic glass and structure connection position adopts alum expanding cement and a structure sealant to carry out a treatment, such that seepage resistance and compression resistance of the acrylic glass and structure connection position are ensured with the dual waterproof treatment. With the present invention, a series of effective processes are further adopted, such that a plurality of important and difficult problems during transporting, fitting, splicing and other steps of the giant acrylic glass are effectively solved so as to save cost, shorten a construction time, and create good social benefits and economic benefits for enterprises.

Description

For the huge acrylic glass construction method of installation of viewing and admiring water body
Technical field
The present invention relates to one and view and admire the huge acrylic glass of water body construction method of installation.
Background technology
Along with viewing and admiring the increase of the water body scale of construction, the increasing of acryl glass size, the transport of acryl glass, the complexity that becomes in place; The acryl glass of simultaneously viewing and admiring water body is arranged under water, the plasticity of acryl glass is strong, the pressure that is subject to water easily produces distortion, therefore one-tenth is attached most importance in being connected also between glass and glass and glass and concrete structure, the generation of these problems makes the installation difficulty of huge acryl glass increasing.
Summary of the invention
The object of the invention is to provide a kind of step simple, and constructability efficiently solves some heavy difficulties that run in the operations such as the transport of huge acrylic glass, in place, connection, provides cost savings, and has shortened the duration.
The present invention is achieved by the following technical solutions:
?for viewing and admiring a huge acrylic glass construction method of installation for water body, it comprises the following steps:
A, transport:
Transport supporting trolley is connected with bolt with carrier frame, supports huge glass handling on carrier frame by movable Scaffold, make carrier frame be placed in the tunnel bealock Liang Chu of mounting glass, mobile transport supporting trolley is crossed over rectangle bealock obstacle;
B, in place:
After transport supporting trolley walks to acrylic glass and aligns with tunnel bealock, utilizing movable Scaffold to support allocates and transports acrylic glass to bealock place, tunnel, a Chain block fixed point of water body one side roof part peace of acrylic glass is being installed, by the handling of Chain block, make acrylic glass carry out in place at bealock place, tunnel;
C, splicing:
1) first make framed that splicing seams uses, acrylic glass splicing seams section is processed into roughly to the grooves of 15~20 degree, and process totally, two blocks of acrylic glass after treatment are combined into " V " v notch vs of 30~40 degree, and it is wide that 1mm is left at tip; Paste glassine paper at the most advanced and sophisticated finedraw of " V " v notch v and two ends breach, stick with paste into the not Sheng slurry model of spillage at the opening surface of " V " v notch v with 3mm polyvinyl chloride panel or other hard materials, glassine paper, and make slurries in framed only and glassine paper and the wish acrylic glass contact of splicing;
2) acrylic monomer, organic peroxide evocating agent, accelerator are added in the prepolymerization reactor with mixer according to a certain ratio, making viscosity with conventional prepolymerization pulp-making method is the slurries of 10~20 seconds/50~60 DEG C;
3) in two small-sized acryl glass brick, wear two fraisings with reamer, will be to drawing adjusting rod to be installed in acryl fraising, fill and splice slurries in fraising and to drawing between adjusting rod, small-sized acryl glass brick and acryl glass, regulate drawing adjusting rod, make to splice slurries and under 20~35 DEG C of conditions, be polymerized to curing;
4) by framed the Sheng slurry that slowly injects splicing seams after the splicing slurries vacuum defoamation configuring, taking slurries not overflow outward as degree, then cover one deck width glassine paper consistent with framed width in slurry surface, get rid of the air bubble between slurry surface and glassine paper, place under 20~35 DEG C of conditions, be polymerized to curing;
5) after splicing seams solidifies, be as the criterion to insert not feed, peel off pattern-making material, wash the foul of specimen surface off by wipes of alcohol, construction environment is carried out to totally-enclosed processing, reduce in heat treatment process and dispel the heat, then heat-treat by baking oven, oven temperature is controlled at 100~110 DEG C, and holding time is 1~2 hour;
6) heat treatment is skimmed after completing and is spliced protruding surplus, finally carries out sanding and polishing processing;
D, acryl glass are connected with structure:
Before glass allocation and transportation, should first to acrylic glass, tunnel bealock be installed measures, put the acrylic cushion block of different-thickness according to the same absolute altitude underlay of measuring, and cushion block is combined with structure with 504 all-purpose adhesives, guarantee that acrylic glass can be placed on same absolute altitude, acrylic cushion block need carry out level and vertical both direction setting; After acrylic glass installation in position, need fill out filling with alum expansion agent cement in the place without acrylic cushion block, acrylic glass position is positioned and fixed; After dry, carry out base cleaning, after having cleared up, note and seal and carry out structure glue surfacing with application specific architecture glue at acrylic glass and structural anticorrosion mouth.
Advantage of the present invention is:
Acrylic glass of the present invention adopts body cast polymerization splicing, and without heavy mechanical equipment, seam crossing treatment surface is smooth simultaneously, and the gelation effect of polymerisation tends towards stability, and has avoided the generation of sudden and violent poly-phenomenon.Acrylic glass and structure junction adopt alum expansive cement and structure sealant to process, and by two pass waterproof, have guaranteed antiseepage, the compressive property of acrylic glass and structure junction.Because the present invention has adopted a series of effective technique, efficiently solve some heavy difficulties that run in the operations such as the transport of huge acrylic glass, in place, connection, provide cost savings, shortened the duration, for enterprise has created good social and economic effects.
Detailed description of the invention
Embodiment: for viewing and admiring the huge acrylic glass construction method of installation of water body, it comprises the following steps:
A, transport:
Transport supporting trolley is connected with bolt with carrier frame, supports huge glass handling on carrier frame by movable Scaffold, make carrier frame be placed in the tunnel bealock Liang Chu of mounting glass, mobile transport supporting trolley is crossed over rectangle bealock obstacle;
B, in place:
After transport supporting trolley walks to acrylic glass and aligns with tunnel bealock, utilizing movable Scaffold to support allocates and transports acrylic glass to bealock place, tunnel, a Chain block fixed point of water body one side roof part peace of acrylic glass is being installed, by the handling of Chain block, make acrylic glass carry out in place at bealock place, tunnel;
C, splicing:
1) first make framed that splicing seams uses, acrylic glass splicing seams section is processed into roughly to the grooves of 15~20 degree, and process totally, two blocks of acrylic glass after treatment are combined into " V " v notch vs of 30~40 degree, and it is wide that 1mm is left at tip; Paste glassine paper at the most advanced and sophisticated finedraw of " V " v notch v and two ends breach, stick with paste into the not Sheng slurry model of spillage at the opening surface of " V " v notch v with 3mm polyvinyl chloride panel or other hard materials, glassine paper, and make slurries in framed only and glassine paper and the wish acrylic glass contact of splicing;
2) acrylic monomer, organic peroxide evocating agent, accelerator are added in the prepolymerization reactor with mixer according to a certain ratio, making viscosity with conventional prepolymerization pulp-making method is the slurries of 10~20 seconds/50~60 DEG C;
3) in two small-sized acryl glass brick, wear two fraisings with reamer, will be to drawing adjusting rod to be installed in acryl fraising, fill and splice slurries in fraising and to drawing between adjusting rod, small-sized acryl glass brick and acryl glass, regulate drawing adjusting rod, make to splice slurries and under 20~35 DEG C of conditions, be polymerized to curing;
4) by framed the Sheng slurry that slowly injects splicing seams after the splicing slurries vacuum defoamation configuring, taking slurries not overflow outward as degree, then cover one deck width glassine paper consistent with framed width in slurry surface, get rid of the air bubble between slurry surface and glassine paper, place under 20~35 DEG C of conditions, be polymerized to curing;
5) after splicing seams solidifies, be as the criterion to insert not feed, peel off pattern-making material, wash the foul of specimen surface off by wipes of alcohol, construction environment is carried out to totally-enclosed processing, reduce in heat treatment process and dispel the heat, then heat-treat by baking oven, oven temperature is controlled at 100~110 DEG C, and holding time is 1~2 hour;
6) heat treatment is skimmed after completing and is spliced protruding surplus, finally carries out sanding and polishing processing;
D, acryl glass are connected with structure:
Before glass allocation and transportation, should first to acrylic glass, tunnel bealock be installed measures, put the acrylic cushion block of different-thickness according to the same absolute altitude underlay of measuring, and cushion block is combined with structure with 504 all-purpose adhesives, guarantee that acrylic glass can be placed on same absolute altitude, acrylic cushion block need carry out level and vertical both direction setting; After acrylic glass installation in position, need fill out filling with alum expansion agent cement in the place without acrylic cushion block, acrylic glass position is positioned and fixed; After dry, carry out base cleaning, after having cleared up, note and seal and carry out structure glue surfacing with application specific architecture glue at acrylic glass and structural anticorrosion mouth.

Claims (1)

1. for viewing and admiring a huge acrylic glass construction method of installation for water body, it is characterized in that: it comprises the following steps:
A, transport:
Transport supporting trolley is connected with bolt with carrier frame, supports huge glass handling on carrier frame by movable Scaffold, make carrier frame be placed in the tunnel bealock Liang Chu of mounting glass, mobile transport supporting trolley is crossed over rectangle bealock obstacle;
B, in place:
After transport supporting trolley walks to acrylic glass and aligns with tunnel bealock, utilizing movable Scaffold to support allocates and transports acrylic glass to bealock place, tunnel, a Chain block fixed point of water body one side roof part peace of acrylic glass is being installed, by the handling of Chain block, make acrylic glass carry out in place at bealock place, tunnel;
C, splicing:
1) first make framed that splicing seams uses, acrylic glass splicing seams section is processed into roughly to the grooves of 15~20 degree, and process totally, two blocks of acrylic glass after treatment are combined into " V " v notch vs of 30~40 degree, and it is wide that 1mm is left at tip; Paste glassine paper at the most advanced and sophisticated finedraw of " V " v notch v and two ends breach, stick with paste into the not Sheng slurry model of spillage at the opening surface of " V " v notch v with 3mm polyvinyl chloride panel or other hard materials, glassine paper, and make slurries in framed only and glassine paper and the wish acrylic glass contact of splicing;
2) acrylic monomer, organic peroxide evocating agent, accelerator are added in the prepolymerization reactor with mixer according to a certain ratio, making viscosity with conventional prepolymerization pulp-making method is the slurries of 10~20 seconds/50~60 DEG C;
3) in two small-sized acryl glass brick, wear two fraisings with reamer, will be to drawing adjusting rod to be installed in acryl fraising, fill and splice slurries in fraising and to drawing between adjusting rod, small-sized acryl glass brick and acryl glass, regulate drawing adjusting rod, make to splice slurries and under 20~35 DEG C of conditions, be polymerized to curing;
4) by framed the Sheng slurry that slowly injects splicing seams after the splicing slurries vacuum defoamation configuring, taking slurries not overflow outward as degree, then cover one deck width glassine paper consistent with framed width in slurry surface, get rid of the air bubble between slurry surface and glassine paper, place under 20~35 DEG C of conditions, be polymerized to curing;
5) after splicing seams solidifies, be as the criterion to insert not feed, peel off pattern-making material, wash the foul of specimen surface off by wipes of alcohol, construction environment is carried out to totally-enclosed processing, reduce in heat treatment process and dispel the heat, then heat-treat by baking oven, oven temperature is controlled at 100~110 DEG C, and holding time is 1~2 hour;
6) heat treatment is skimmed after completing and is spliced protruding surplus, finally carries out sanding and polishing processing;
D, acryl glass are connected with structure:
Before glass allocation and transportation, should first to acrylic glass, tunnel bealock be installed measures, put the acrylic cushion block of different-thickness according to the same absolute altitude underlay of measuring, and cushion block is combined with structure with 504 all-purpose adhesives, guarantee that acrylic glass can be placed on same absolute altitude, acrylic cushion block need carry out level and vertical both direction setting; After acrylic glass installation in position, need fill out filling with alum expansion agent cement in the place without acrylic cushion block, acrylic glass position is positioned and fixed; After dry, carry out base cleaning, after having cleared up, note and seal and carry out structure glue surfacing with application specific architecture glue at acrylic glass and structural anticorrosion mouth.
CN201110281574.7A 2011-09-21 2011-09-21 Ornamental water body giant acrylic glass installation construction method Active CN103009898B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110281574.7A CN103009898B (en) 2011-09-21 2011-09-21 Ornamental water body giant acrylic glass installation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110281574.7A CN103009898B (en) 2011-09-21 2011-09-21 Ornamental water body giant acrylic glass installation construction method

Publications (2)

Publication Number Publication Date
CN103009898A CN103009898A (en) 2013-04-03
CN103009898B true CN103009898B (en) 2014-08-20

Family

ID=47959226

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110281574.7A Active CN103009898B (en) 2011-09-21 2011-09-21 Ornamental water body giant acrylic glass installation construction method

Country Status (1)

Country Link
CN (1) CN103009898B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110181838A (en) * 2019-07-05 2019-08-30 浙江横海科技有限公司 Underwater uniform thickness acrylic hemisphere production method
CN113863687A (en) * 2021-10-12 2021-12-31 中建八局第三建设有限公司 Installation process of large-volume acrylic plate in limited space
CN117966913A (en) * 2024-03-05 2024-05-03 中建八局第一建设有限公司 High-altitude integral joint treatment method for ultra-large acrylic member

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101435229A (en) * 2008-11-14 2009-05-20 上海绿特丹保温工程有限公司 Heat-insulating layer construction process of formwork method
CN201330510Y (en) * 2008-12-19 2009-10-21 苏州二建建筑集团有限公司 Transparent acrylic board mounting structure for aquarium
CN101691784A (en) * 2009-08-19 2010-04-07 贵州大学 Steel structured wide-bay energy-saving residential building with gypsum walls and on-site layering and sectioning manufacturing method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001241118A (en) * 2000-02-25 2001-09-04 Kanebo Ltd Waterproof sheet and waterproofing method by using the sheet

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101435229A (en) * 2008-11-14 2009-05-20 上海绿特丹保温工程有限公司 Heat-insulating layer construction process of formwork method
CN201330510Y (en) * 2008-12-19 2009-10-21 苏州二建建筑集团有限公司 Transparent acrylic board mounting structure for aquarium
CN101691784A (en) * 2009-08-19 2010-04-07 贵州大学 Steel structured wide-bay energy-saving residential building with gypsum walls and on-site layering and sectioning manufacturing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开2001-241118A 2001.09.04

Also Published As

Publication number Publication date
CN103009898A (en) 2013-04-03

Similar Documents

Publication Publication Date Title
CN203583528U (en) Waterproof structure for joints of sidewall and top and bottom plates of peat soft soil stratum subway station
CN103643973A (en) CRD construction method tunnel waterproof construction method
CN103669417B (en) Prefabricated outer wall of basement seam crossing epoxy resin cement concrete and construction method thereof
CN103009898B (en) Ornamental water body giant acrylic glass installation construction method
CN112942600A (en) Construction device and construction method for improving construction quality of post-cast joint concrete of prefabricated laminated slab
CN102031848A (en) Waterproof insulation board and paving method thereof
CN106401083A (en) Roofing project system structure and construction method thereof
CN202431281U (en) Waterproof structure outside side wall of subway station main body
CN103088996B (en) A kind of tile paste method
CN105421679A (en) Dividing joint structure of fine aggregate concrete roof surface layers and construction method of dividing joint structure
CN204940365U (en) A kind of single-coated foam for waterproof roll
CN204343623U (en) A kind of combined floor of ground decoration
CN106284855A (en) A kind of compound curved surface photoelectric integral plate and preparation method thereof
CN109372030A (en) A kind of post-cast strip waterproof construction and its construction method
CN104343137B (en) Underground waterproof engineering construction method
CN204266404U (en) A kind of outer-wall crack-resisting anti-leakage structure
CN205314466U (en) Take dampproofing ground plate brick of self -adhesive layer
CN203795854U (en) Preformed hole formwork fixing device for bare concrete floor
CN105649224A (en) External wall thermal insulation system and construction process
CN205857241U (en) Different-thickness raft plate underground structure with post-cast strip
CN204940055U (en) A kind of presetting system pervious concrete pavement Expandable strip
CN104264947B (en) The construction method of ventilating shaft of not leaking out in a kind of building and ventilating shaft
CN203097136U (en) Waterproof roof
CN204238519U (en) Extension waterproofing materials
CN220132969U (en) Pre-spraying anti-sticking waterproof layer construction structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant