CN102889041A - Method for constructing seepage and heat prevention bridges of external doors and windows - Google Patents

Method for constructing seepage and heat prevention bridges of external doors and windows Download PDF

Info

Publication number
CN102889041A
CN102889041A CN2011103676258A CN201110367625A CN102889041A CN 102889041 A CN102889041 A CN 102889041A CN 2011103676258 A CN2011103676258 A CN 2011103676258A CN 201110367625 A CN201110367625 A CN 201110367625A CN 102889041 A CN102889041 A CN 102889041A
Authority
CN
China
Prior art keywords
window
frame
door
windows
doors
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011103676258A
Other languages
Chinese (zh)
Inventor
陈少波
王建民
曹铖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGXI DANGDAI ENERGY-SAVING REAL ESTATE Co Ltd
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
JIANGXI DANGDAI ENERGY-SAVING REAL ESTATE Co Ltd
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGXI DANGDAI ENERGY-SAVING REAL ESTATE Co Ltd, China Construction Fourth Engineering Division Corp Ltd filed Critical JIANGXI DANGDAI ENERGY-SAVING REAL ESTATE Co Ltd
Priority to CN2011103676258A priority Critical patent/CN102889041A/en
Publication of CN102889041A publication Critical patent/CN102889041A/en
Pending legal-status Critical Current

Links

Landscapes

  • Door And Window Frames Mounted To Openings (AREA)
  • Wing Frames And Configurations (AREA)

Abstract

The invention discloses a method for constructing seepage and heat prevention bridges of external doors and windows. The method comprises the following steps of: positioning the doors and windows according to control lines and elevation; constructing reinforced concrete door and window frames; rechecking an axis; mounting hot-dip galvanized steel pipe auxiliary frames of the doors and the windows; controlling side gaps; closing holes (internal and external holes) of the doors and the windows and trowelling the closed holes; primarily gluing the steel auxiliary frames; performing heat preservation and crack resistance construction by using mortar; mounting main frames of the doors and the windows; filling sealing glues; and protecting finished products. By the method, heat preservation and water prevention processes are integrated, and the bridges are scientifically constructed by new materials, so that a cold/thermal bridge phenomenon is avoided, and heat preservation, energy conservation, water resistance and seepage resistance of the side walls of doors and the windows are guaranteed.

Description

Outer door and window antiseepage solar heat protection bridge construction method
Technical field
The present invention relates to outer door and window technical field of construction, particularly relate to a kind of outer door and window antiseepage solar heat protection bridge construction method.
Background technology
Along with improving constantly that building energy conservation requires, traditional outer timber has limited use, and timber window also is eliminated, and Novel door window is able to large-scale popularization and uses.Door and window is that position, particularly sidewall and the body of wall contact position that the heat conduction is concentrated very easily produces the heat conduction especially, and the slit on the sidewall also easily produces seepage simultaneously.Although standard has proposed specific requirement to the processing of door and window peripheral, because this position way disunity, constructing operation is lack of standardization, easily causes commonplace common quality defect.
Summary of the invention
Technical problem to be solved by this invention is to overcome the defective that existing outer door and window job practices easily produces heat conduction and seepage, and a kind of outer door and window antiseepage solar heat protection bridge construction method is provided, and increases globality and the fastness of outer door and window structure.
In order to solve the problems of the technologies described above, the present invention adopts following technical scheme:
The outer door and window antiseepage solar heat protection bridge construction method of the present invention comprises the steps:
(1) locus of door and window in body of wall oriented in line;
(2) construction reinforced bar concrete doorframe and window frame: install frame template, carry out concrete after the assembling reinforcement and build, before the concreting, brick wall, wooden form water moistening in advance, and ponding must not be arranged; When vibrating concrete, vibrating spear inserts near interior wall, and when vibrating the collar tie beam concrete, vibrating spear vibrates with the concrete surface bevel is oblique, when vibro-rammer stitches concrete, selects small-sized vibrating spear, after building, the steel bar concrete doorframe and window frame is carried out maintenance;
(3) secondary frame is installed: the secondary frame of galvanizing by dipping square steel pipe is fixed on the steel bar concrete frame with expansion bolt;
(4) close up: door and window hole closes up and plasters, and adopts the insulating cement mortar to carry out disposable closing between steel bar concrete doorframe and window frame and the secondary frame;
(5) play glue: adopt silicone adhesive to play glue all around at secondary frame and the closing in inner corner trim of plastering;
(6) construction of exterior insulation system;
(7) beat and annotate fluid sealant: inside and outsidely between door and window master frame and the secondary frame adopt the blowing agent sealing, repair out inside and outside the blowing agent 〉=the 5mm deep trouth after, outer groove mouth adopts exterior wall weather-resistant glue crescent to seal, crescent width 8mm-12mm once survives when playing glue; The indent notch adopts common silicone adhesive crescent sealing, once survives when playing glue, and sealing glue-line width is not more than 8mm; Guarantee not shaken in the doorframe and window frame 24h after breaking the notes fluid sealant;
(8) surrounding, hole investment precoat outside the brushing door and window carries out beating glue the second time.
In the above-mentioned job practices, when step (3) fixed joint frame, expansion bolt fixed point spacing on the corner is not more than 180mm, the spacing at the edge place is not more than 500mm.In step (5), described silicone adhesive is the thick common silicone adhesive of 6mm.
Compared with prior art, the present invention will be incubated with waterproof technology and unite two into one, and adopt the new material scientific construction, eliminate the door and window cold-heat bridge and guarantee heat preservation energy-saving and the waterproof, seepage control of door jamb:
(1) the construction way of unified standard has solved the difficult problem that process in the door and window peripheral slit;
(2) adopt insulating cement mortar (water-proof heat-insulation material) to satisfy the requirement of standard as elastomeric material, have certain energy-conserving action;
(3) adopt blowing agent to seal, guaranteed the quality of sidewall filling and fluid sealant filleting, eliminated cold bridge and seepage common quality defect;
(4) adopt the galvanizing by dipping square steel pipe as secondary frame, effectively guarantee the fastness of door and window;
(5) increase the steel bar concrete window frame all around, effectively prevented the door jamb infiltration, increased the globality of door and window structure.
The specific embodiment
Construction technology process of the present invention: the construction → axis of control line and absolute altitude location → steel bar concrete doorframe and window frame checks → the secondary frame installations → side seam control → door and window hole of door and window galvanizing by dipping square steel pipe (inside and outside) close up floating → steel auxiliary frame beat for the first time glue → heat insulation anti-crack mortar construction → door and window master frame installation → → notes fluid sealant → finished product protection.
The Specific construction step is as follows:
(1) locus of door and window in body of wall oriented in line
The locus of door and window in body of wall will keep the accuracy of its three directions.In the horizontal direction, the horizontal level of door and window is as the criterion with floor indoor horizontal control line, measures door and window hypodermis absolute altitude snap the line according to the position relationship of horizon and door and window and looks for directly; In the vertical direction, find out the door and window sideline at top layer or variation place of building vertical door window position, to draw under the door and window sideline with the line pendant, and at each layer door and window mouth place marking, will in time be processed indivedual not straight mouth limits, the complicated available transit of building of highrise building or facade moulding is looked for vertical line; In the wall thickness direction, measure the door and window sideline according to alignment both sides in the door and window hole, determine that door and window is in the position of wall thickness direction.
(2) construction reinforced bar concrete doorframe and window frame:
(a) eject axis, wall sideline, door and window hole line, through checking, handle the preliminary examination formality;
(b) window frame formwork erection, template adopt set shaped steel formwork or nine clamping plate, and template firmly, stable, absolute altitude, size etc. meet designing requirement, when the template slit surpasses regulation, stop up tightly, and finish the preliminary examination formality;
(c) window frame reinforcing bar binding carries out reinforcing bar binding according to the requirement of design drawing, and reinforcing bar is finished hidden inspection formality and can be carried out concrete and build;
(d) the window frame concrete is built, and during normal temperature, before the concreting, brick wall, wooden model should shift to an earlier date and water in right amount moisteningly, but ponding must not be arranged, and when vibrating concrete, vibrating spear inserts near interior wall as far as possible.When vibrating the collar tie beam concrete, vibrating spear and concrete surface are answered bevel, oblique vibrating.During vibro-rammer seam concrete, should select the small-sized vibrating spear of φ 30mm.Should note simultaneously protecting reinforcement location and outer brick wall, shuttering supporting, not make its infringement, the special messenger checks whether template, reinforcing bar are out of shape, are shifted; Whether bolt, pull bar become flexible, come off; Find the phenomenons such as spillage, assign special messenger's maintenance;
(e) maintenance of steel bar concrete window frame and repairing.
(3) secondary frame is installed
(a) the door and window position line that pulls of door window auxiliary frame temporary fixed basis in place is installed aluminium alloy doorframe and window frame.When doorframe and window frame is put into the hole, do preliminary fixing on the both sides of four jiaos of doorframe and window frame with timber wedge piece plug, and by quality specifications installation site, levelness, verticality etc. are adjusted;
(b) the doorframe and window frame adjustment is fixing afterwards, at last doorframe and window frame is installed index by quality specifications and once checks, and the discovery deviation is in time adjusted.Meeting the demands is fixed to doorframe and window frame on the concrete window frame body of wall afterwards with expansion bolt, and expansion bolt selects expansion sleeve and fluting or cruciform slot screw to support the use.Bore first the hole of a corresponding size during use with Churn drill at wall, again expand tube is filled in the hole, then pass the through hole of doorframe and window frame with screw, screw in the expand tube again.Expansion bolt fixed point spacing, the corner is not more than 180mm, and the edge place is not more than 500mm;
(c) installing should be firmly not loosening, carries out simultaneously the connection of lightning protection.
(4) close up
Door and window hole (inside and outside) closes up and plasters: wherein adopt the insulating cement mortar to carry out disposable closing between secondary structure and the steel auxiliary frame.
(5) play glue
Steel auxiliary frame is played glue with the inner corner trim surrounding of plastering of closing up for the first time, adopts the thick common silicone adhesive of 6mm.
(6) construction of exterior insulation system
Door and window outer surrounding, hole insulation, anticracking grout construction according to the construction technology of exterior-wall heat insulation, effectively guarantee the heat preservation construction quality, can carry out the next procedure construction after relevant unit's acceptance(check).
(7) break the notes fluid sealant
(a) adopt the blowing agent sealing between plastic-steel frame and the steel auxiliary frame, behind inside and outside finishing the out 〉=5mm deep trouth, collar extension adopts the sealing of exterior wall weather-resistant glue crescent, once survives when playing glue; Internal orifice adopts common silicone adhesive crescent sealing, once survives when playing glue.Inner seal glue-line width is not more than 8mm; Outside crescent width 12mm, thickness 6mm.Before playing glue the corresponding position protective tapes is torn, base cleaning is clean, keep dry:
(b) with colloid-injecting gun fluid sealant is coated in the place, slit, repeatedly scrapes with a type or U-shaped card as the case may be and smear evenly, need from equidirectional coating during gluing, control rate is even, unsuitable too fast, guarantees fluid sealant and substrate surface close contact;
(c) straight, attractive in appearance for guaranteeing fluid sealant edge, can paste the boundary gummed paper at the place, sideline along beating the glue direction in advance, after accomplishing fluently, tears immediately by glue to be sealed;
(d) beat and guarantee behind the glue not shaken in the doorframe and window frame 24h, guarantee that sealing firmly.
(8) surrounding, hole investment precoat outside the brushing door and window carries out beating glue the second time.

Claims (3)

1. an outer door and window antiseepage solar heat protection bridge construction method is characterized in that comprising the steps:
(1) locus of door and window in body of wall oriented in line;
(2) construction reinforced bar concrete doorframe and window frame: install frame template, carry out concrete after the assembling reinforcement and build, before the concreting, brick wall, wooden form water moistening in advance, and ponding must not be arranged; When vibrating concrete, vibrating spear inserts near interior wall, and when vibrating the collar tie beam concrete, vibrating spear vibrates with the concrete surface bevel is oblique, when vibro-rammer stitches concrete, selects small-sized vibrating spear, after building, the steel bar concrete doorframe and window frame is carried out maintenance;
(3) secondary frame is installed: the secondary frame of galvanizing by dipping square steel pipe is fixed on the steel bar concrete frame with expansion bolt;
(4) close up: door and window hole closes up and plasters, and adopts the insulating cement mortar to carry out disposable closing between steel bar concrete doorframe and window frame and the secondary frame;
(5) play glue: adopt silicone adhesive to play glue all around at secondary frame and the closing in inner corner trim of plastering;
(6) construction of exterior insulation system;
(7) beat and annotate fluid sealant: inside and outsidely between door and window master frame and the secondary frame adopt the blowing agent sealing, repair out inside and outside the blowing agent 〉=the 5mm deep trouth after, outer groove mouth adopts exterior wall weather-resistant glue crescent to seal, crescent width 8mm-12mm once survives when playing glue; The indent notch adopts common silicone adhesive crescent sealing, once survives when playing glue, and sealing glue-line width is not more than 8mm; Guarantee not shaken in the doorframe and window frame 24h after breaking the notes fluid sealant;
(8) surrounding, hole investment precoat outside the brushing door and window carries out beating glue the second time.
2. according to described outer the normal antiseepage solar heat protection bridge construction method of claim 1, it is characterized in that: in the step (3), during the fixed joint frame, expansion bolt fixed point spacing on the corner is not more than 180mm, the spacing at the edge place is not more than 500mm.
3. according to described outer the normal antiseepage solar heat protection bridge construction method of claim 1, it is characterized in that: in the step (5), described silicone adhesive is the thick common silicone adhesive of 6mm.
CN2011103676258A 2011-11-18 2011-11-18 Method for constructing seepage and heat prevention bridges of external doors and windows Pending CN102889041A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103676258A CN102889041A (en) 2011-11-18 2011-11-18 Method for constructing seepage and heat prevention bridges of external doors and windows

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103676258A CN102889041A (en) 2011-11-18 2011-11-18 Method for constructing seepage and heat prevention bridges of external doors and windows

Publications (1)

Publication Number Publication Date
CN102889041A true CN102889041A (en) 2013-01-23

Family

ID=47532705

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103676258A Pending CN102889041A (en) 2011-11-18 2011-11-18 Method for constructing seepage and heat prevention bridges of external doors and windows

Country Status (1)

Country Link
CN (1) CN102889041A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103244034A (en) * 2013-05-14 2013-08-14 中国二十二冶集团有限公司 Water-proof method for peripheries of aluminum alloy door and aluminum alloy window
CN103967386A (en) * 2014-05-13 2014-08-06 二十二冶集团第一建设有限公司 Anti-leakage joint processing method of first filling gap of outer window of building
CN104632007A (en) * 2015-01-15 2015-05-20 山东天畅环保工程有限公司 Door and window installing method using auxiliary frame

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH619023A5 (en) * 1977-12-06 1980-08-29 Dossetto Pierre Framing for openings of buildings
EP1335094A2 (en) * 2002-02-11 2003-08-13 Ian Douglas Law Installing architectural finishing components in a building
CN2881026Y (en) * 2006-03-21 2007-03-21 于长水 Heat insulating and label structure of door window
CN200943397Y (en) * 2006-08-31 2007-09-05 上海金粤幕墙有限公司 Water-proof seepage-resistant structure between door, window and wall
CN101560859A (en) * 2009-04-21 2009-10-21 深圳市富诚科技发展有限公司 Construction process of pressure injection seam filling for opening of window and door in building and universal auxiliary frame or side frame
CN101586430A (en) * 2008-05-23 2009-11-25 沈培青 Anti-leakage door and window installation structure
CN201416348Y (en) * 2009-04-21 2010-03-03 深圳市富诚科技发展有限公司 One-time pressure injection caulking Mounting structure for general auxiliary frame or border of building door/window

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH619023A5 (en) * 1977-12-06 1980-08-29 Dossetto Pierre Framing for openings of buildings
EP1335094A2 (en) * 2002-02-11 2003-08-13 Ian Douglas Law Installing architectural finishing components in a building
CN2881026Y (en) * 2006-03-21 2007-03-21 于长水 Heat insulating and label structure of door window
CN200943397Y (en) * 2006-08-31 2007-09-05 上海金粤幕墙有限公司 Water-proof seepage-resistant structure between door, window and wall
CN101586430A (en) * 2008-05-23 2009-11-25 沈培青 Anti-leakage door and window installation structure
CN101560859A (en) * 2009-04-21 2009-10-21 深圳市富诚科技发展有限公司 Construction process of pressure injection seam filling for opening of window and door in building and universal auxiliary frame or side frame
CN201416348Y (en) * 2009-04-21 2010-03-03 深圳市富诚科技发展有限公司 One-time pressure injection caulking Mounting structure for general auxiliary frame or border of building door/window

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘健,王文,许卓敏: "台风多雨地区建筑外门窗防渗漏技术措施", 《浙江建筑》, vol. 24, no. 4, 30 April 2007 (2007-04-30), pages 49 - 50 *
罗佛鑫: "铝合金门窗渗漏原因及预防措施", 《福建建筑》, no. 8, 31 December 2009 (2009-12-31), pages 91 - 92 *
黄苏: "外墙与外窗防渗保温施工方法的优化", 《建筑》, no. 6, 31 December 2010 (2010-12-31) *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103244034A (en) * 2013-05-14 2013-08-14 中国二十二冶集团有限公司 Water-proof method for peripheries of aluminum alloy door and aluminum alloy window
CN103244034B (en) * 2013-05-14 2015-03-11 中国二十二冶集团有限公司 Water-proof method for peripheries of aluminum alloy door and aluminum alloy window
CN103967386A (en) * 2014-05-13 2014-08-06 二十二冶集团第一建设有限公司 Anti-leakage joint processing method of first filling gap of outer window of building
CN103967386B (en) * 2014-05-13 2016-03-30 二十二冶集团第一建设有限公司 External window of building first closing in antiseep Node Processing Method
CN104632007A (en) * 2015-01-15 2015-05-20 山东天畅环保工程有限公司 Door and window installing method using auxiliary frame

Similar Documents

Publication Publication Date Title
CN101158213B (en) Exterior outer-insulating system construction method for using direct-compress EPS inorganic clad plate
CN103967386B (en) External window of building first closing in antiseep Node Processing Method
CN111945928A (en) Energy-saving heat-insulating wall and roof
CN103343655B (en) Wall window construction method
CN101956432B (en) Fireproofing structure of polyphenyl plate outer-wall outer heat-insulating building system and construction method thereof
CN207017857U (en) A kind of broken-bridge aluminum alloy exterior window closing-in structure
CN104074434A (en) Structure and construction method of aluminum alloy window
CN103046714A (en) Construction method for double-sided inorganic composite phenolic aldehyde fire-proof heat-insulating decorating integration plates
CN101187259A (en) Dry-hanging keel decorative board heat insulation composite wall and its construction method
CN101761286A (en) Installation method of aluminum alloy door/window
CN104213800B (en) Antiseep Combined aluminium alloy window and its installation method
WO2010127628A1 (en) Method for heat insulation, energy-conservation, waterproof and drainage for exterior wall of construction
CN110805212A (en) Construction method for roof flashing
CN102889041A (en) Method for constructing seepage and heat prevention bridges of external doors and windows
CN107269001A (en) Concealed distribution box is with the whole construction method poured of concrete wall structure
CN203822057U (en) Aluminum alloy window structure
CN211774781U (en) External wall insulation decorates intergral template construction structures
CN104775541B (en) During Light trabs is installed, plate stitches and the crack resistence processing method of Ban Mian basic unit
CN110259144A (en) A kind of novel energy-saving environment-friendly ash concrete lightweight wall plate construction method
CN116044106A (en) Integrated construction method for assembled phase-change heat-preservation decorative plate
CN214884349U (en) A protrusion structure that is used for window frame antiseep installation that wafts outward
CN108589793A (en) A kind of poured band of outer wall of basement postposition assembled advance water stop construction method
CN109339355A (en) The construction method of the aluminium sheet roofing waterproofing node of structural slab is done using ALC plate
CN204199587U (en) A kind of ultra-thin exterior wall composite thermal insulation stone plate
CN113882562A (en) Construction method of special-shaped double-sided wood grain fair-faced concrete wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130123