CN102888854A - 用于特高压接地极线路的铁塔基础及其施工方法 - Google Patents

用于特高压接地极线路的铁塔基础及其施工方法 Download PDF

Info

Publication number
CN102888854A
CN102888854A CN2012104188449A CN201210418844A CN102888854A CN 102888854 A CN102888854 A CN 102888854A CN 2012104188449 A CN2012104188449 A CN 2012104188449A CN 201210418844 A CN201210418844 A CN 201210418844A CN 102888854 A CN102888854 A CN 102888854A
Authority
CN
China
Prior art keywords
main body
foundation
iron tower
basic main
asphalt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104188449A
Other languages
English (en)
Other versions
CN102888854B (zh
Inventor
王海乔
徐力
谢斌
何天胜
庄志伟
房向日
黄炳权
黎景辉
林方新
王学军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Tianan Project Management Co ltd
Original Assignee
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd filed Critical China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority to CN201210418844.9A priority Critical patent/CN102888854B/zh
Publication of CN102888854A publication Critical patent/CN102888854A/zh
Application granted granted Critical
Publication of CN102888854B publication Critical patent/CN102888854B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明公开了一种用于特高压接地极线路的铁塔基础,其包括基础垫层及放置于该基础垫层上的基础主体,在该基础主体的上部预埋有地脚螺栓,该地脚螺栓的上部从基础主体的顶面竖直向上伸出,在所述基础主体的表面上由内至外依次包覆有第一沥青胶层和第一玻璃纤维布层,在所述基础垫层与所述基础主体的配合面上由内至外依次包覆有第二沥青胶层和第二玻璃纤维布层。本发明提供的铁塔基础,其表面通过沥青胶层和玻璃纤维布层绝缘,满足了特高压接地极线路的安全运行要求,保证了特高压接地极线路的可靠性;而且,采用沥青胶和玻璃纤维布作为绝缘材料,造价低,施工简便,环境污染小,绝缘效果好。同时,本发明还公开了一种上述铁塔基础的施工方法。

Description

用于特高压接地极线路的铁塔基础及其施工方法
技术领域
本发明涉及一种铁塔基础,尤其是一种用于特高压接地极线路的铁塔基础,以及该铁塔基础的施工方法。
背景技术
在特高压直流供电系统建设初期,为了尽快地发挥经济效益,往往要将先建立起来的一极投入运行。直流输电线路投入双极运行后,当一极故障退出运行时,为了稳定系统和提高系统供电可靠性和可用率,健全极将继续运行。此时,直流系统可处于单极大地回线方式(借助接地极线路)运行,在此运行间,接地极线路与高压直流线路发挥着同样重要的作用。因此,要求接地极线路应有较高的可靠性。然而,在特高压接地极线路的极址一端,由于附近地面场强比较大,当特高压接地极线路使用了铁塔,地电流很容易在塔腿间流动,从而导致对基础和塔腿的电腐蚀,由此会造成铁塔和基础的运行存在安全问题。
发明内容
为了克服现有技术存在的上述缺陷,本发明的目的在于提供一种用于特高压接地极线路的铁塔基础,以满足特高压接地极线路的安全运行,保证特高压接地极线路的可靠性。
本发明的另一目的在于提供上述铁塔基础的施工方法。
本发明提供的一种用于特高压接地极线路的铁塔基础,其包括基础垫层及放置于该基础垫层上的基础主体,在该基础主体的上部预埋有地脚螺栓,该地脚螺栓的上部从基础主体的顶面竖直向上伸出,在所述基础主体的表面上由内至外依次包覆有第一沥青胶层和第一玻璃纤维布层,在所述基础垫层与所述基础主体的配合面上由内至外依次包覆有第二沥青胶层和第二玻璃纤维布层。
优选地,所述第一沥青胶层和所述第二沥青胶层的厚度为1~1.5mm。
优选地,所述铁塔基础还包括玻璃钢护套,该玻璃钢护套套设于所述地脚螺栓伸出所述基础主体的部分上。
优选地,所述铁塔基础还包括玻璃钢板,该玻璃钢板设于所述基础主体顶面的所述第一玻璃纤维布层的外部,并在该玻璃钢板上设有供所述玻璃钢护套穿过的通孔。
优选地,所述基础主体为板式基础,其包括下部的长方体状底座及上部的梯形台状安装座。
本发明提供的上述铁塔基础的施工方法,包括如下步骤:
(1)制造所述基础垫层,再在制造好的基础垫层与所述基础主体的配合面上先均匀涂敷沥青胶,再铺贴玻璃纤维布;
(2)制造所述基础主体,所述地脚螺栓预埋入基础主体的上部内,再在制造好的基础主体的表面上先均匀涂敷沥青胶,再铺贴玻璃纤维布;
(3)将步骤(2)所得的所述基础主体放置于步骤(1)所得的所述基础垫层上。
优选地,步骤(1)、(2)中,所用沥青胶的配制方法如下:将10号沥青胶和60号沥青胶按重量比1∶2~1∶3的比例进行配制,熬制温度≤240℃。
优选地,步骤(1)、(2)中,涂敷沥青胶的厚度为1~1.5mm。
优选地,在所述地脚螺栓伸出所述基础主体的上部套装玻璃钢护套。
优选地,所述基础主体为板式基础,其包括下部的长方体状底座及上部的梯形台状安装座。
与现有技术相比,本发明的优点是:
(1)本发明提供的铁塔基础,其表面通过沥青胶层和玻璃纤维布层绝缘,其绝缘电阻大于500Ω,满足了特高压接地极线路的安全运行要求,保证了特高压接地极线路的可靠性;
(2)本发明提供的铁塔基础,其绝缘材料采用沥青胶和玻璃纤维布,造价低,施工简便,环境污染小,绝缘效果好。
(3)本发明提供的铁塔基础,其与塔腿之间通过玻璃钢护套和玻璃钢板绝缘,进一步增加了铁塔基础的绝缘效果。
附图说明
图1是本发明实施例的铁塔基础的结构示意图。
附图标记说明:1-基础主体、11-安装座、12-底座、2-第一沥青胶层、3-第一玻璃纤维布层、4-地脚螺栓、5-玻璃钢护套、6-玻璃钢板、7-玻璃垫片、8-铁塔的塔脚板、9-基础垫层、10-第二沥青胶层、11-第二玻璃纤维布层。
具体实施方式
下面结合附图对本发明的实施例进行详细说明。
如图1所示,本发明的用于特高压接地极线路的铁塔基础,主要由基础垫层9、放置于基础垫层9上的基础主体1及预埋于该基础主体1上部的地脚螺栓4组成,其中,基础主体1为板式钢筋混凝土基础,板式基础不仅基础材料量小,而且便于基础绝缘技术的实现,有足够的空间进行漆刷沥青胶和铺贴玻璃纤维布。基础主体1由下部的长方体状底座12及上部的梯形台状安装座11组成。在该基础主体1的表面上由内至外依次包覆有第一沥青胶层2和第一玻璃纤维布层3。第一沥青胶层2的厚度为1~1.5mm。地脚螺栓4的下部预埋入基础主体1内,上部从该基础主体1的顶面竖直向上伸出。在地脚螺栓4伸出基础主体1的部分上套装有玻璃钢护套5。玻璃钢板6设于基础主体1顶面的第一玻璃纤维布层3与塔脚板8之间,并在该玻璃钢板6上设有供所述玻璃钢护套5穿过的通孔。在基础垫层9的与基础主体1相配合的表面上由内至外依次包覆有第二沥青胶层10和第二玻璃纤维布层11。安装时,在螺母与塔脚板8之间放置玻璃垫片7。
上述铁塔基础的施工方法如下:
(1)制造基础垫层,再在制造好的基础垫层与基础主体的配合面上先均匀涂敷沥青胶,再铺贴玻璃纤维布;
(2)制造基础主体,地脚螺栓预埋入基础主体的上部内,再在制造好的基础主体的表面上先均匀涂敷沥青胶,再铺贴玻璃纤维布;
(3)将步骤(2)所得的所述基础主体放置于步骤(1)所得的所述基础垫层上。
步骤(1)、(2)中所用沥青胶的配制方法如下:将10号沥青胶和60号沥青胶按重量比1∶2~1∶3的比例进行配制,熬制温度≤240℃。沥青胶厚度的控制在1~1.5mm,且要均匀,因为础底面与垫层直接相接触,如果沥青胶不均匀,就会使基础与大地的绝缘效果变得很差。玻璃纤维布的铺贴。为防止玻璃纤维布铺贴时出现歪斜,涂刷沥青胶后难于纠正,造成玻璃纤维布扭曲、皱褶缺陷,按照刷沥青胶、沥青胶刮平、铺贴玻璃纤维布及滚压收边四道工序进行施工。
以上仅为本发明的具体实施例,并不以此限定本发明的保护范围;在不违反本发明构思的基础上所作的任何替换与改进,均属本发明的保护范围。

Claims (10)

1.一种用于特高压接地极线路的铁塔基础,其包括基础垫层及放置于该基础垫层上的基础主体,在该基础主体的上部预埋有地脚螺栓,该地脚螺栓的上部从基础主体的顶面竖直向上伸出,其特征在于:在所述基础主体的表面上由内至外依次包覆有第一沥青胶层和第一玻璃纤维布层,在所述基础垫层与所述基础主体的配合面上由内至外依次包覆有第二沥青胶层和第二玻璃纤维布层。
2.根据权利要求1所述的铁塔基础,其特征在于:所述第一沥青胶层和所述第二沥青胶层的厚度为1~1.5mm。
3.根据权利要求1所述的铁塔基础,其特征在于:还包括玻璃钢护套,该玻璃钢护套套设于所述地脚螺栓伸出所述基础主体的部分上。
4.根据权利要求3所述的铁塔基础,其特征在于:还包括玻璃钢板,该玻璃钢板设于所述基础主体顶面的所述第一玻璃纤维布层的外部,并在该玻璃钢板上设有供所述玻璃钢护套穿过的通孔。
5.根据权利要求1至4任一项所述的铁塔基础,其特征在于:所述基础主体为板式基础,其包括下部的长方体状底座及上部的梯形台状安装座。
6.一种如权利要求1所述的铁塔基础的施工方法,其特征在于,包括如下步骤:
(1)制造所述基础垫层,再在制造好的基础垫层与所述基础主体的配合面上先均匀涂敷沥青胶,再铺贴玻璃纤维布;
(2)制造所述基础主体,所述地脚螺栓预埋入基础主体的上部内,再在制造好的基础主体的表面上先均匀涂敷沥青胶,再铺贴玻璃纤维布;
(3)将步骤(2)所得的所述基础主体放置于步骤(1)所得的所述基础垫层上。
7.根据权利要求6所述的施工方法,其特征在于:步骤(1)、(2)中,所用沥青胶的配制方法如下:将10号沥青胶和60号沥青胶按重量比1∶2~1∶3的比例进行配制,熬制温度≤240℃。
8.根据权利要求6所述的施工方法,其特征在于:步骤(1)、(2)中,涂敷沥青胶的厚度为1~1.5mm。
9.根据权利要求6所述的施工方法,其特征在于:在所述地脚螺栓伸出所述基础主体的上部套装玻璃钢护套。
10.根据权利要求6至9任一项所述的施工方法,其特征在于:所述基础主体为板式基础,其包括下部的长方体状底座及上部的梯形台状安装座。
CN201210418844.9A 2012-10-26 2012-10-26 用于特高压接地极线路的铁塔基础及其施工方法 Active CN102888854B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210418844.9A CN102888854B (zh) 2012-10-26 2012-10-26 用于特高压接地极线路的铁塔基础及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210418844.9A CN102888854B (zh) 2012-10-26 2012-10-26 用于特高压接地极线路的铁塔基础及其施工方法

Publications (2)

Publication Number Publication Date
CN102888854A true CN102888854A (zh) 2013-01-23
CN102888854B CN102888854B (zh) 2015-04-08

Family

ID=47532521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210418844.9A Active CN102888854B (zh) 2012-10-26 2012-10-26 用于特高压接地极线路的铁塔基础及其施工方法

Country Status (1)

Country Link
CN (1) CN102888854B (zh)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5744028A (en) * 1980-08-29 1982-03-12 Toyo Doro Shisetsu Kk Construction method for shallow foundation
FR2687024A1 (fr) * 1992-01-31 1993-08-06 Danis Nathalie Dispositif destine a apporter ameliorations et securite dans la pose, la fixation et le raccordement de supports devant recevoir une ou plusieurs alimentations electriques.
CN201809780U (zh) * 2010-08-27 2011-04-27 国网直流工程建设有限公司四川工程建设部 新型铁塔基础绝缘防腐装置
CN102093815A (zh) * 2009-12-15 2011-06-15 徐昌彪 橡胶沥青防水涂料的制备方法
CN202117080U (zh) * 2011-06-23 2012-01-18 昆明有色冶金设计研究院股份公司 一种防腐绝缘建筑基础
CN202899155U (zh) * 2012-10-26 2013-04-24 中国能源建设集团广东省电力设计研究院 用于特高压接地极线路的铁塔基础

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5744028A (en) * 1980-08-29 1982-03-12 Toyo Doro Shisetsu Kk Construction method for shallow foundation
FR2687024A1 (fr) * 1992-01-31 1993-08-06 Danis Nathalie Dispositif destine a apporter ameliorations et securite dans la pose, la fixation et le raccordement de supports devant recevoir une ou plusieurs alimentations electriques.
CN102093815A (zh) * 2009-12-15 2011-06-15 徐昌彪 橡胶沥青防水涂料的制备方法
CN201809780U (zh) * 2010-08-27 2011-04-27 国网直流工程建设有限公司四川工程建设部 新型铁塔基础绝缘防腐装置
CN202117080U (zh) * 2011-06-23 2012-01-18 昆明有色冶金设计研究院股份公司 一种防腐绝缘建筑基础
CN202899155U (zh) * 2012-10-26 2013-04-24 中国能源建设集团广东省电力设计研究院 用于特高压接地极线路的铁塔基础

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑亚雄: "浅谈输电线路基础绝缘的施工方法", 《云南电力技术》, vol. 39, no. 6, 31 December 2011 (2011-12-31) *

Also Published As

Publication number Publication date
CN102888854B (zh) 2015-04-08

Similar Documents

Publication Publication Date Title
CN106549629A (zh) 装配式太阳能光伏发电路面模块及其应用
CN106592374A (zh) 太阳能光伏发电路面及其应用
JP5772323B2 (ja) 防水層のメンテナンス方法
CN104993440B (zh) 利用结构钢筋外接引下线的防雷人工接地体系及施工方法
CN202899155U (zh) 用于特高压接地极线路的铁塔基础
CN102529750B (zh) 电动平车地面供电滑触线绝缘结构的施工工艺
CN201883720U (zh) 可调垂直度的风光电互补集约化自立式通信基站
CN102888854A (zh) 用于特高压接地极线路的铁塔基础及其施工方法
CN105350816A (zh) 电网电线杆加固加高装置及其施工方法
CN205100643U (zh) 一种避雷电线杆
CN205452982U (zh) 用于更换电缆终端支柱绝缘子的支撑装置
CN204492310U (zh) 一种±500kV直流输电线路避雷器安装支柱式结构
CN202788126U (zh) 一种锚栓式柱脚人字形构架
CN207097560U (zh) 新型复合支柱绝缘子
CN211079822U (zh) 一种发光地砖系统
CN110820469B (zh) 一种装配式沥青混凝土-光伏发电路面结构及施工方法
CN206942282U (zh) 一种加固型电力杆塔
CN202017323U (zh) 一种绝缘地板砖
JP2014163053A (ja) 発熱体構造及びその成形方法
CN201447651U (zh) 绝缘地板砖
CN201671390U (zh) 一种自立式输电线路铁塔纠偏装置
CN204510984U (zh) 一种应急用电力线路支撑杆
CN204820508U (zh) 高强度防水卷材
CN202915447U (zh) 一种地暖地板
CN202899029U (zh) 一种绝缘盆式橡胶支座

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA ENERGY ENGINEERING GROUP GUANGDONG ELECTRIC

Free format text: FORMER NAME: CHINA ENERGY ENGINEERING GROUP GUANGDONG ELECTRIC POWER DESIGN INSTITUTE

CP01 Change in the name or title of a patent holder

Address after: 510663 Luogang District, Guangdong, Guangzhou Science City Fung Road, No. 1, No.

Patentee after: CHINA ENERGY ENGINEERING GROUP GUANGDONG ELECTRIC POWER DESIGN INSTITUTE Co.,Ltd.

Address before: 510663 Luogang District, Guangdong, Guangzhou Science City Fung Road, No. 1, No.

Patentee before: GUANGDONG ELECTRIC POWER DESIGN INSTITUTE OF CHINA ENERGY ENGINEERING GROUP Co.,Ltd.

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160506

Address after: 510663 Luogang District, Guangdong, Guangzhou Science City Fung Road, No. 1, No.

Patentee after: Guangdong Tian Tian Engineering Supervision Co.,Ltd.

Address before: 510663 Luogang District, Guangdong, Guangzhou Science City Fung Road, No. 1, No.

Patentee before: CHINA ENERGY ENGINEERING GROUP GUANGDONG ELECTRIC POWER DESIGN INSTITUTE Co.,Ltd.

CP01 Change in the name or title of a patent holder

Address after: 510663 No.1 Tianfeng Road, Guangzhou Science City, Luogang District, Guangzhou City, Guangdong Province

Patentee after: GUANGDONG TIANAN PROJECT MANAGEMENT CO.,LTD.

Address before: 510663 No.1 Tianfeng Road, Guangzhou Science City, Luogang District, Guangzhou City, Guangdong Province

Patentee before: Guangdong Tian Tian Engineering Supervision Co.,Ltd.

CP01 Change in the name or title of a patent holder