CN102882153A - Multi-return tower middle-phase insulator string replacement method for electrified replacement circuit - Google Patents

Multi-return tower middle-phase insulator string replacement method for electrified replacement circuit Download PDF

Info

Publication number
CN102882153A
CN102882153A CN2012103166245A CN201210316624A CN102882153A CN 102882153 A CN102882153 A CN 102882153A CN 2012103166245 A CN2012103166245 A CN 2012103166245A CN 201210316624 A CN201210316624 A CN 201210316624A CN 102882153 A CN102882153 A CN 102882153A
Authority
CN
China
Prior art keywords
jig
insulator
pulley
arm
cross
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012103166245A
Other languages
Chinese (zh)
Other versions
CN102882153B (en
Inventor
吴志成
陈永红
姚青煌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Quanzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Quanzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Quanzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201210316624.5A priority Critical patent/CN102882153B/en
Publication of CN102882153A publication Critical patent/CN102882153A/en
Application granted granted Critical
Publication of CN102882153B publication Critical patent/CN102882153B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)
  • Insulators (AREA)

Abstract

The invention discloses a multi-return tower middle-phase insulator string replacement method for an electrified replacement circuit. According to the method, a pulley clamp is adopted to replace the insulator string so as to realize indirect operation installation, stringing operation is performed on the ground rather than on the tower, clearance operation workload is greatly reduced, the operational efficiency is improved, and the labor intensity is reduced.

Description

Phase replacing insulator string method in many times towers of charged for replacement circuit
Technical field
The present invention relates to a kind of two phase replacing insulator string method in the phase replacing insulator string, particularly many times towers of a kind of charged for replacement circuit of returning in the towers.
  
Background technology
Because the requisition of circuit corridor is more and more difficult, power transmission sequence adopts double loop or multi-circuits transmission lines on single tower shaft tower in a large number, adopt vertical arrangement such as 110KV circuit double loop tangent tower wire, middle phase cross-arm is generally 3.5 meters with upper phase cross-arm, behind deduction insulator string length and the middle mutually cross-arm height, middle phase cross-arm and upper conductor distance only have about 1.2 meters, phase insulator during if Live line maintenance method is changed routinely, personnel need enter the operation of middle phase cross arm end, 1.2 safety requirements can't be satisfied in the gap of rice, can only power failure operation, this has reduced power supply reliability simultaneously just so that amount of power supply is subjected to a large amount of losses.
  
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art part, and provide a kind of applicable to phase replacing insulator string method in the two many times towers of charged for replacement circuit that return phase insulator in towers or the many times towers of earth potential live replacing circuit.
Phase replacing insulator string method in many times towers of a kind of charged for replacement circuit, its concrete steps are as follows: (1) at first forms assembly pulley with pulley jig and insulating cord, described pulley jig specifically includes jig and two s' running block, described jig is wing-shaped structure, be provided with the open seam of the snapped in cross-arm of linking up the jig front-back in the middle part of wing-shaped structure, reach the square groove vertical with open seam that extends along two flank directions of wing-shaped structure, the notch of this square groove is positioned at the jig lower surface, lower surface at jig two flanks is respectively arranged with the fixed pulley group, each fixed pulley group has more than one fixed pulley, be provided with the hangers be used to the jig of slinging in the upper end of jig, the fixed pulley number of the fixed pulley group on the pulley number on each running block and jig one flank is complementary, and is provided with the hook be used to the wire of slinging in the bottom of each running block;
The operating personnel steps on the supreme cross arm end of tower on (2) one towers, and the place hangs up properly purchase fall at upper cross-arm, and Ground Operation personnel thus purchase fall begin to hang and rise assembly pulley;
(3) operating personnel steps on tower to middle cross-arm root and with action bars the pulley jig is installed on the terminal insulator string suspension point of middle cross-arm place on another tower, jig middle aperture slots and square groove closely are fixed on the cross-arm, and the hook of two running blocks is hung into wire;
(4) the Ground Operation personnel tighten up insulating cord by the tail end of assembly pulley insulating cord, make the insulator load transfer to assembly pulley;
(5) take off the side of wire was spring catch with action bars, throw off insulator;
(6) load onto good insulator by reverse procedure, lay down the operation Work tool, personnel withdraw.
Above method mainly is applicable to change synthetic insulator, in order to be listed as good replacing porcelain bottle insulators, the present invention also increases following steps between step 5 is with 6: by two operating personnels to middle phase cross-arm root place, cooperate with action bars the self-control suspension centre that is loaded on the purchase fall is fixed due to the synthetic insulator upper end, or the first of porcelain bottle insulators, adjust the insulator position with the insulator adjuster, take off the cross-arm side spring catch, utilize insulator suspension centre card balanced hoisting insulator string, throw off the bulb of connecting insulator, insulator is put to ground.
Be provided with for the hangers that hangs the starter pulley group at running block.
Also be provided with two fixed pulley on the jig between the two fixed pulley groups of jig, two fixed pulleys are divided on the flank of open seam both sides.
Set up a fixed pulley between two fixed pulley groups of jig, changing the porcelain insulator period of the day from 11 p.m. to 1 a.m, because porcelain bottle insulators weight is very heavy, therefore available rope is sling porcelain vase by this fixed pulley, plays the effect of weight reduction.
The hood type structure of described suspension centre card for being made of two arc-like sheets is provided with the convenient hanger that this suspension centre card is upwards sling at two arc-like sheets, also is provided with convenient operation ring with the insulating bar operation on the suspension centre card.
In use, the suspension centre card is stuck in the first of insulator upper end or porcelain bottle insulators with insulating bar, then suspension centre is fastened by the hanger on the suspension centre card with insulating cord.
In sum, the present invention's following advantage compared to existing technology:
(1) phase replacing insulator string method in many times towers of charged for replacement circuit of the present invention, realized the indirect operation installation, it transfers to ground to the stringing operation from tower, has greatly reduced the gap operating workload, improve operating efficiency, reduced labour intensity;
(2) according to the routine work method, bearing tool hanging point and insulator string hanging point all need stagger about 400mm, the removable insulator string is very difficult indirectly, labour intensity is very big, the method cooperates by suspension centre card and pulley jig, realize the location dress, taken off insulator, simple to operate quick, and the while is applicable to the indirect loading and unloading of synthetic insulator and porcelain vase (glass) insulator;
Adopt two cover bearing tool operations when (3) using, when arbitrary cover tool failures wherein, another set of instrument still can work, and has improved greatly the job safety coefficient;
(4) operational method of this project research, the Work tool light and flexible, simple to operate;
Description of drawings
Fig. 1 is the structural representation of the jig of embodiments of the invention 1.
Fig. 2 is the vertical view of Fig. 1.
Fig. 3 is the schematic diagram that pulley jig and insulating cord form assembly pulley.
Fig. 4 is that the pulley jig of the embodiment of the invention 1 is at the schematic diagram of the state of use.
Fig. 5 is the sustained center chucking tool structural representation of the embodiment of the invention 2.
Fig. 6 is the vertical view of Fig. 5.
The operation that label declaration 1 pulley jig 11 jigs 111 jigs snap on open seam 112 jigs of cross-arm on the hangers 2 insulating cords 3 suspension centre cards 31 hangers 32 suspension centre cards with the hangers 13 fixed pulley groups 14 jig upper ends of hook 122 running blocks of the perpendicular square groove 12 running blocks 121 running block bottoms of open seam encircles 4 cross-arms.
Embodiment
Below in conjunction with embodiment the present invention is described in more detail.
Embodiment 1
Phase replacing insulator string method in many times towers of a kind of charged for replacement circuit, its concrete steps are as follows: (1) at first forms pulley jig 1 and insulating cord 2 assembly pulleys such as Fig. 1~shown in Figure 4, described pulley jig specifically includes jig 11 and two s' running block 12, described jig is wing-shaped structure, be provided with the open seam 111 of the snapped in cross-arm 4 of linking up the jig front-back in the middle part of wing-shaped structure, reach the square groove 112 vertical with open seam that extends along two flank directions of wing-shaped structure, the notch of this square groove is positioned at the jig lower surface, lower surface at jig two flanks is respectively arranged with fixed pulley group 13, each fixed pulley group has more than one fixed pulley, be provided with the hangers 14 be used to the jig of slinging in the upper end of jig, the fixed pulley number of the fixed pulley group on the pulley number on each running block and jig one flank is complementary, be provided with the hook 121 be used to the wire of slinging in the bottom of each running block, be provided with for the hangers 122 that hangs the starter pulley group at running block;
The operating personnel steps on the supreme cross arm end of tower on (2) one towers, and the place hangs up properly purchase fall at upper cross-arm, and Ground Operation personnel thus purchase fall begin to hang and rise assembly pulley;
(3) operating personnel steps on tower to middle cross-arm root and with action bars the pulley jig is installed on the terminal insulator string suspension point of middle cross-arm place on another tower, jig middle aperture slots and square groove closely are fixed on the cross-arm, and the hook of two running blocks is hung into wire;
(4) the Ground Operation personnel tighten up insulating cord by the tail end of assembly pulley insulating cord, make the insulator load transfer to assembly pulley;
(5) take off the side of wire was spring catch with action bars, throw off insulator;
(6) load onto good insulator by reverse procedure, lay down the operation Work tool, personnel withdraw.
It is same as the prior art that the present embodiment is not stated part.
Embodiment 2
The present embodiment is substantially the same manner as Example 1, just after the step 5 of embodiment 1, increase following step, by two operating personnels to middle phase cross-arm root place, cooperate with action bars the self-control suspension centre that is loaded on the purchase fall is fixed due to the synthetic insulator upper end, or the first of porcelain bottle insulators, hanger on the suspension centre card hangs on two fixed pulleys between the two fixed pulley groups on the pulley jig, adjust the insulator position with the insulator adjuster, take off the cross-arm side spring catch, utilize insulator suspension centre card such as Fig. 5~Fig. 7 balanced hoisting insulator string, throw off the bulb of connecting insulator, insulator is put to ground; The hood type structure of described suspension centre card 3 for being made of two arc-like sheets is provided with the convenient hanger 31 that this suspension centre card is upwards sling at two arc-like sheets, also is provided with convenient operation ring 32 with the insulating bar operation on the suspension centre card.Also be provided with two fixed pulley between two fixed pulley groups of jig, two fixed pulleys are divided on the flank of open seam both sides.The suspension centre Cali hangs on the hanger on it on two the fixed pulley.
It is identical with embodiment 1 that the present embodiment is not stated part.

Claims (5)

1. phase replacing insulator string method in many times towers of a charged for replacement circuit, it is characterized in that: concrete steps are as follows: (1) at first forms assembly pulley with pulley jig and insulating cord, described pulley jig specifically includes jig and two s' running block, described jig is wing-shaped structure, be provided with the open seam of the snapped in cross-arm of linking up the jig front-back in the middle part of wing-shaped structure, reach the square groove vertical with open seam that extends along two flank directions of wing-shaped structure, the notch of this square groove is positioned at the jig lower surface, lower surface at jig two flanks is respectively arranged with the fixed pulley group, each fixed pulley group has more than one fixed pulley, be provided with the hangers be used to the jig of slinging in the upper end of jig, the fixed pulley number of the fixed pulley group on the pulley number on each running block and jig one flank is complementary, and is provided with the hook be used to the wire of slinging in the bottom of each running block;
The operating personnel steps on the supreme cross arm end of tower on (2) one towers, and the place hangs up properly purchase fall at upper cross-arm, and Ground Operation personnel thus purchase fall begin to hang and rise assembly pulley;
(3) operating personnel steps on tower to middle cross-arm root and with action bars the pulley jig is installed on the terminal insulator string suspension point of middle cross-arm place on another tower, jig middle aperture slots and square groove closely is fixed on the cross-arm, and the hook of two running blocks is hung into wire;
(4) the Ground Operation personnel tighten up insulating cord by the tail end of assembly pulley insulating cord, make the insulator load transfer to assembly pulley;
(5) take off the side of wire was spring catch with action bars, throw off insulator;
(6) load onto good insulator by reverse procedure, lay down the operation Work tool, personnel withdraw.
2. phase replacing insulator string method in many times towers of charged for replacement circuit according to claim 1, it is characterized in that: described replacing method also is included in increases following steps between the step 5 and 6: two operating personnels are to middle phase cross-arm root place, cooperate with action bars the self-control suspension centre that is loaded on the purchase fall is fixed due to the synthetic insulator upper end, or the first of porcelain bottle insulators, adjust the insulator position with the insulator adjuster, take off the cross-arm side spring catch, utilize insulator suspension centre card balanced hoisting insulator string, throw off the bulb of connecting insulator, insulator is put to ground.
3. phase replacing insulator string method in many times towers of charged for replacement circuit according to claim 2 is characterized in that: be provided with for the hangers that hangs the starter pulley group at running block.
4. phase replacing insulator string method in many times towers of charged for replacement circuit according to claim 3, it is characterized in that: also be provided with two fixed pulley on the jig between the two fixed pulley groups of jig, two fixed pulleys are divided on the flank of open seam both sides.
5. phase replacing insulator string method to many times towers of 4 any one described charged for replacement circuit according to claim 1, it is characterized in that: the hood type structure of described suspension centre card for being consisted of by two arc-like sheets, be provided with the convenient hanger that this suspension centre card is upwards sling at two arc-like sheets, on the suspension centre card, also be provided with convenient operation ring with the insulating bar operation.
CN201210316624.5A 2012-08-30 2012-08-30 Phase replacing insulator string method in charged for replacement circuit many times towers Active CN102882153B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210316624.5A CN102882153B (en) 2012-08-30 2012-08-30 Phase replacing insulator string method in charged for replacement circuit many times towers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210316624.5A CN102882153B (en) 2012-08-30 2012-08-30 Phase replacing insulator string method in charged for replacement circuit many times towers

Publications (2)

Publication Number Publication Date
CN102882153A true CN102882153A (en) 2013-01-16
CN102882153B CN102882153B (en) 2015-09-30

Family

ID=47483381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210316624.5A Active CN102882153B (en) 2012-08-30 2012-08-30 Phase replacing insulator string method in charged for replacement circuit many times towers

Country Status (1)

Country Link
CN (1) CN102882153B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103872621A (en) * 2014-03-10 2014-06-18 国家电网公司 Fixture for replacing strain insulator string under electrified state based on earth potential method and operation method
CN103928867A (en) * 2014-04-24 2014-07-16 国家电网公司 Double-hoisting-point pole head clamp for replacing straight-line insulator of 220 kV line steel pipe pole in electrified mode
CN104201629A (en) * 2014-09-24 2014-12-10 国家电网公司 Insulator string hanging point buffer method and insulator string hanging point connecting structure
CN105514862A (en) * 2015-12-04 2016-04-20 国家电网公司 Live-line replacement method and device for jumper suspension insulator string of common-tower and multi-circuit power transmission line
CN107069562A (en) * 2017-06-28 2017-08-18 云南电网有限责任公司曲靖供电局 Replacing insulator under electrified method and load transfer device
CN107086495A (en) * 2017-06-28 2017-08-22 云南电网有限责任公司曲靖供电局 Load transfer instrument and electric power maintenance equipment
CN107611846A (en) * 2017-09-29 2018-01-19 国家电网公司 A kind of insulator section replacing device and replacing options
CN109586205A (en) * 2018-11-21 2019-04-05 国网宁夏电力有限公司电力科学研究院 Power transmission line ground wire presss from both sides auxiliary installation device
CN110112678A (en) * 2019-06-20 2019-08-09 中国南方电网有限责任公司超高压输电公司柳州局 A kind of complete Work tool of charged for replacement duplex V-type pendency composite insulator

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201466574U (en) * 2009-06-11 2010-05-12 华北电力科学研究院有限责任公司 Device for isoelectrically replacing insulator and accessory of iron tower of transmission line
CN201518397U (en) * 2009-06-16 2010-06-30 福建省福州电业局 Tool for replacing line suspension insulation string in 220 KV circuit with charged line
CN102163824A (en) * 2011-02-14 2011-08-24 福建省电力有限公司厦门电业局 Operating tool and operation method for electrically replacing T-type mounting point suspending insulator in 110kV line steel pipe rod

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201466574U (en) * 2009-06-11 2010-05-12 华北电力科学研究院有限责任公司 Device for isoelectrically replacing insulator and accessory of iron tower of transmission line
CN201518397U (en) * 2009-06-16 2010-06-30 福建省福州电业局 Tool for replacing line suspension insulation string in 220 KV circuit with charged line
CN102163824A (en) * 2011-02-14 2011-08-24 福建省电力有限公司厦门电业局 Operating tool and operation method for electrically replacing T-type mounting point suspending insulator in 110kV line steel pipe rod

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴志成: "110kV双回线路直线塔中相绝缘子的带电更换", 《供用电》, vol. 26, no. 1, 28 February 2009 (2009-02-28) *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103872621A (en) * 2014-03-10 2014-06-18 国家电网公司 Fixture for replacing strain insulator string under electrified state based on earth potential method and operation method
CN103872621B (en) * 2014-03-10 2016-08-24 国家电网公司 A kind of earth potential method charged changing tension-resisting insulator fixture and operational method
CN103928867A (en) * 2014-04-24 2014-07-16 国家电网公司 Double-hoisting-point pole head clamp for replacing straight-line insulator of 220 kV line steel pipe pole in electrified mode
CN104201629A (en) * 2014-09-24 2014-12-10 国家电网公司 Insulator string hanging point buffer method and insulator string hanging point connecting structure
CN105514862A (en) * 2015-12-04 2016-04-20 国家电网公司 Live-line replacement method and device for jumper suspension insulator string of common-tower and multi-circuit power transmission line
CN105514862B (en) * 2015-12-04 2017-03-29 国家电网公司 Multiple-loop line transmission line of electricity jumper suspension insulator chain charged for replacement method and device
CN107069562A (en) * 2017-06-28 2017-08-18 云南电网有限责任公司曲靖供电局 Replacing insulator under electrified method and load transfer device
CN107086495A (en) * 2017-06-28 2017-08-22 云南电网有限责任公司曲靖供电局 Load transfer instrument and electric power maintenance equipment
CN107086495B (en) * 2017-06-28 2019-05-31 云南电网有限责任公司曲靖供电局 Load transfer tool and electric power maintenance equipment
CN107611846A (en) * 2017-09-29 2018-01-19 国家电网公司 A kind of insulator section replacing device and replacing options
CN107611846B (en) * 2017-09-29 2023-10-13 国家电网公司 Segmented insulator replacement device and replacement method
CN109586205A (en) * 2018-11-21 2019-04-05 国网宁夏电力有限公司电力科学研究院 Power transmission line ground wire presss from both sides auxiliary installation device
CN109586205B (en) * 2018-11-21 2023-10-31 国网宁夏电力有限公司电力科学研究院 Auxiliary installation device for ground wire clamp of power transmission line
CN110112678A (en) * 2019-06-20 2019-08-09 中国南方电网有限责任公司超高压输电公司柳州局 A kind of complete Work tool of charged for replacement duplex V-type pendency composite insulator

Also Published As

Publication number Publication date
CN102882153B (en) 2015-09-30

Similar Documents

Publication Publication Date Title
CN102882153B (en) Phase replacing insulator string method in charged for replacement circuit many times towers
CN201323409Y (en) Tool for live line replacing of high voltage transmission line V-shaped insulator chain
CN102420401A (en) Triangular insulating hanging fulcrum bar
CN103594968A (en) Lifting device of multiple divided conductors of transmission tower
CN101814707B (en) Tool for live replacement of 220kV line 'V' string insulator and method
CN205595695U (en) High altitude block system
CN202094562U (en) Suspension type synchronous hoisting system for pipe type bus
CN202197048U (en) Double angle steel hanging point lifting and connecting tool for tower use
CN102237654B (en) Method for replacing jumper string using tool at double angle hanging point
CN105514867A (en) Method for replacing V-shaped insulator string of power transmission line pole
CN102163824B (en) Operating tool and operation method for electrically replacing T-type mounting point suspending insulator in 110kV line steel pipe rod
CN203839885U (en) 10kV/35kV double-loop straight-line electrified pole replacing device
CN206349693U (en) Conductors on quad bundled Split type line lifter and its application structure
CN202856238U (en) Tool for live-line replacement of phase insulator chain in multi-circuit steel tower
CN105119203A (en) Lifting tool for comprehensive live overhaul of distribution network
CN202353100U (en) Triangular insulation lifting strut
CN202029999U (en) Helicopter hanger
CN204243605U (en) Power line tension string composite insulator changes hook special
CN207977667U (en) A kind of more changing device twisting formula overhanging golden tool for transmission line of electricity aerial condutor
CN210118696U (en) Lighting system of cable bearing bridge
CN205304094U (en) A fixture that is used for electrified two independent many yoke plates of some combination insulator chain that hang that change
CN207218124U (en) A kind of insulator replacement equipment
CN207490436U (en) The double models for hanging V-type composite insulator string replacing options of ± 500kV DC power transmission lines duplex
CN206658002U (en) 1000kV extra-high-voltage alternating currents wire clamp changes instrument
CN209516463U (en) Porcelain vase dynamic traction device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant