CN102879696A - Automatic judgment method for over-load operational feasibility of transformer - Google Patents

Automatic judgment method for over-load operational feasibility of transformer Download PDF

Info

Publication number
CN102879696A
CN102879696A CN2012104108425A CN201210410842A CN102879696A CN 102879696 A CN102879696 A CN 102879696A CN 2012104108425 A CN2012104108425 A CN 2012104108425A CN 201210410842 A CN201210410842 A CN 201210410842A CN 102879696 A CN102879696 A CN 102879696A
Authority
CN
China
Prior art keywords
transformer
overload
analysis
operational feasibility
judging method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104108425A
Other languages
Chinese (zh)
Other versions
CN102879696B (en
Inventor
傅晨钊
魏本刚
李红雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
East China Power Test and Research Institute Co Ltd
Original Assignee
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
East China Power Test and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Shanghai Municipal Electric Power Co, East China Power Test and Research Institute Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201210410842.5A priority Critical patent/CN102879696B/en
Publication of CN102879696A publication Critical patent/CN102879696A/en
Application granted granted Critical
Publication of CN102879696B publication Critical patent/CN102879696B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to an automatic judgment method for over-load operational feasibility of a transformer. The method comprises the following steps of: (1) acquiring meteorological data of an environment where the transformer is positioned, equipment parameters of the transformer and operation state data of the transformer; (2) calculating hot spot temperature of the transformer through a thermal circuit calculation model according to data acquired in the step (1); (3) performing pre-cooling analysis, over-load analysis and radiating analysis on the transformer according to the hot spot temperature of the transformer; (4) acquiring operation current of a switching circuit, performing distribution calculation on the operation current and judging whether switching operation current exceeding an upper limit value exists; (5) analyzing the state of the transformer according to the operation state of the transformer; and (6) judging whether over-load operation of the transformer is feasible according to an analysis result. Compared with the prior art, the method has the advantages of high reliability, capability of effectively solving the problem that whether the transformer in production and scheduling of a power grid is allowed to operate in an over-load state, and the like.

Description

A kind of transformer overload operational feasibility automatic judging method
Technical field
The present invention relates to a kind of converting equipment status data disposal route, especially relate to a kind of transformer overload operational feasibility automatic judging method.
Background technology
Along with the development of national economy, the contradiction between the development of some areas power supply capacity and the growth of actual demand day by day manifests.For responding actively this situation, in the network system widespread use raising running temperature, the multinomial technology such as dynamic compatibilization, heat resistance circuit in short-term, greatly improved the ability to transmit electricity of circuit, supporting power transformation station equipment is then generally taked technological transformation with it, namely come to be complementary with the circuit transport capacity by the mode of integral replacing, to satisfy to greatest extent power demands.When obtaining certain effect, a large amount of converting equipments do not reach the time limit and retired in advance designed life, have increased the investment of improvement project newly, have caused the utilization ratio of assets to descend, and move simultaneously the converting equipment transformation and have influence on inevitably power supply reliability.Therefore, be necessary to judge whether the converting equipment running overload is feasible.
Summary of the invention
Purpose of the present invention be exactly provide in order to overcome the defective that above-mentioned prior art exists a kind of reliability high, can effectively solve the transformer overload operational feasibility automatic judging method whether transformer in electrical network production and the scheduling allows the running overload problem.
Purpose of the present invention can be achieved through the following technical solutions:
A kind of transformer overload operational feasibility automatic judging method, described transformer is arranged in the transformer station, also is provided with miniature weather station and SCADA system in the described transformer station, and described transformer is connected with cooling fan, and described method comprises:
1) obtains the weather data of transformer environment of living in, the device parameter of transformer and the running state data of transformer;
2) according to step 1) in the overheated road of the data communication device computation model calculating transformer hot(test)-spot temperature obtained;
3) carry out respectively precooling analysis, overload analysis and the analysis of heat transmission of transformer according to hot-spot temperature of transformer;
4) obtain the running current of switching circuit, and this running current is distributed accounting, and judge whether to exist the switch running current above higher limit;
5) according to the running state data of transformer the state of transformer is analyzed;
6) judge according to above-mentioned analysis result whether the transformer overload operation is feasible.
Described weather data is provided by miniature weather station.
The precooling of described transformer is analyzed specifically: judge whether hot-spot temperature of transformer surpasses preset value in the certain hour, if then output need increase the group number of the cooling fan of transformer, if not, then keeps former running status.
Described certain hour is 900 minutes.
Described overload is analyzed specifically: according to the hot(test)-spot temperature value under certain load factor and the relation between preset value, analyze the capability of overload of transformer.
Described certain load factor comprises that transformer operation can bear maximum load rate or 1.5 times of nominal load rates.
Described analysis of heat transmission is specifically: with the actual thermal resistance of certain frequency calculating transformer, and calculate this actual thermal resistance with respect to the rate of change of specified thermal resistance, analyze the cooling effectiveness of cooling fan according to rate of change, the operation of current cooling fan is diagnosed.
Described certain frequency be 12 hours once.
The running current of described switching circuit obtains from the SCADA system.
Compared with prior art, the present invention passes through running state of transformer data and environment weather data acquisition, transformer is carried out the analyses such as precooling, overload and heat radiation, and the switch running current that is connected with transformer analyzed, whether thereby automatic decision goes out transformer allows running overload, has high reliability.
Description of drawings
Fig. 1 is the schematic flow sheet of the inventive method.
Embodiment
The present invention is described in detail below in conjunction with the drawings and specific embodiments.
Embodiment
As shown in Figure 1, a kind of transformer overload operational feasibility automatic judging method, described transformer is arranged in the transformer station, also is provided with miniature weather station and SCADA system in the described transformer station, described transformer is connected with cooling fan, and described method may further comprise the steps:
1) obtain the weather data of transformer environment of living in, the device parameter of transformer and the running state data of transformer, described weather data is provided by miniature weather station, and the running state data of described transformer comprises top-oil temperature and load current;
2) according to step 1) in the overheated road of the data communication device computation model calculating transformer hot(test)-spot temperature obtained;
3) carry out respectively precooling analysis, overload analysis and the analysis of heat transmission of transformer according to hot-spot temperature of transformer:
The precooling of described transformer is analyzed specifically: judge whether hot-spot temperature of transformer surpasses preset value in 900 minutes, if then output needs the group number of the cooling fan of increase transformer, if not, then keeps former running status;
Described overload is analyzed specifically: according to the hot(test)-spot temperature value under certain load factor and the relation between preset value, analyze the capability of overload of transformer, certain load factor comprises that the transformer operation can bear maximum load rate or 1.5 times of nominal load rates;
Described analysis of heat transmission is specifically: with the actual thermal resistance of 12 hours frequency computation part transformers once, and calculate this actual thermal resistance with respect to the rate of change of specified thermal resistance, according to the cooling effectiveness of rate of change analysis cooling fan, the operation of current cooling fan is diagnosed;
4) obtain the running current of switching circuit, and this running current is distributed accounting, and judge whether to exist the switch running current above higher limit, the running current of described switching circuit obtains from the SCADA system;
5) according to the running state data of transformer the state of transformer is analyzed;
6) judge according to above-mentioned analysis result whether the transformer overload operation is feasible, and judge the hazard level of transformer overload operation.
The automatic decision of transformer overload operational feasibility must the real-time judge overload before and after the switching current that is associated of transformer whether surpass the upper bound current value of the permission of switch.Because Divergent line is interrelated, therefore, article one, when the power of circuit changes, need to again mate calculating to all switching currents that is associated, calculate the current value of each switch according to the switching current apportion model after simplifying, if surpassing higher limit, the current value of certain switch thinks that then switching circuit can't satisfy the transformer overload operation, as not surpassing the limits value of switch running current, then allows the overload implementation of strategies.

Claims (9)

1. transformer overload operational feasibility automatic judging method, described transformer is arranged in the transformer station, also is provided with miniature weather station and SCADA system in the described transformer station, and described transformer is connected with cooling fan, it is characterized in that described method comprises:
1) obtains the weather data of transformer environment of living in, the device parameter of transformer and the running state data of transformer;
2) according to step 1) in the overheated road of the data communication device computation model calculating transformer hot(test)-spot temperature obtained;
3) carry out respectively precooling analysis, overload analysis and the analysis of heat transmission of transformer according to hot-spot temperature of transformer;
4) obtain the running current of switching circuit, and this running current is distributed accounting, and judge whether to exist the switch running current above higher limit;
5) according to the running state data of transformer the state of transformer is analyzed;
6) judge according to above-mentioned analysis result whether the transformer overload operation is feasible.
2. a kind of transformer overload operational feasibility automatic judging method according to claim 1 is characterized in that described weather data is provided by miniature weather station.
3. a kind of transformer overload operational feasibility automatic judging method according to claim 1, it is characterized in that, the precooling of described transformer is analyzed specifically: judge whether hot-spot temperature of transformer surpasses preset value in the certain hour, if, then output needs the group number of the cooling fan of increase transformer, if not, then keep former running status.
4. a kind of transformer overload operational feasibility automatic judging method according to claim 3 is characterized in that described certain hour is 900 minutes.
5. a kind of transformer overload operational feasibility automatic judging method according to claim 1, it is characterized in that, described overload is analyzed specifically: according to the hot(test)-spot temperature value under certain load factor and the relation between preset value, analyze the capability of overload of transformer.
6. a kind of transformer overload operational feasibility automatic judging method according to claim 5 is characterized in that, described certain load factor comprises that transformer operation can bear maximum load rate or 1.5 times of nominal load rates.
7. a kind of transformer overload operational feasibility automatic judging method according to claim 1, it is characterized in that, described analysis of heat transmission is specifically: with the actual thermal resistance of certain frequency calculating transformer, and calculate this actual thermal resistance with respect to the rate of change of specified thermal resistance, according to the cooling effectiveness of rate of change analysis cooling fan, the operation of current cooling fan is diagnosed.
8. a kind of transformer overload operational feasibility automatic judging method according to claim 7 is characterized in that, described certain frequency be 12 hours once.
9. a kind of transformer overload operational feasibility automatic judging method according to claim 1 is characterized in that the running current of described switching circuit obtains from the SCADA system.
CN201210410842.5A 2012-10-24 2012-10-24 Automatic judgment method for over-load operational feasibility of transformer Active CN102879696B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210410842.5A CN102879696B (en) 2012-10-24 2012-10-24 Automatic judgment method for over-load operational feasibility of transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210410842.5A CN102879696B (en) 2012-10-24 2012-10-24 Automatic judgment method for over-load operational feasibility of transformer

Publications (2)

Publication Number Publication Date
CN102879696A true CN102879696A (en) 2013-01-16
CN102879696B CN102879696B (en) 2015-04-15

Family

ID=47481092

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210410842.5A Active CN102879696B (en) 2012-10-24 2012-10-24 Automatic judgment method for over-load operational feasibility of transformer

Country Status (1)

Country Link
CN (1) CN102879696B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103245857A (en) * 2013-04-23 2013-08-14 浙江大学 Assessment method for loadable index of oil immersed power transformer
CN103324215A (en) * 2013-05-17 2013-09-25 郑州华力信息技术有限公司 Method for setting up thermal circuit model used for transformer load intelligent management system
CN103543352A (en) * 2013-09-25 2014-01-29 国家电网公司 Method for determining dynamic overload curves of transformers based on operating data
WO2014135015A1 (en) * 2013-03-07 2014-09-12 国网安徽省电力公司芜湖供电公司 Network for online monitoring of power transformer at intelligent substation
CN105353233A (en) * 2015-09-30 2016-02-24 南京南瑞继保电气有限公司 Method and device of on-line operation capability detection of transformer
CN107246925A (en) * 2017-05-27 2017-10-13 上海海能信息科技有限公司 A kind of current transformer thermal circuit model analysis method
CN108680801A (en) * 2018-03-23 2018-10-19 国网河北省电力有限公司电力科学研究院 A kind of transformer overload computational methods, system and terminal device
CN112615371A (en) * 2020-12-18 2021-04-06 浙江大学 Asset optimal configuration method for improving utilization efficiency of distribution transformer
CN113390461A (en) * 2021-06-04 2021-09-14 广西电网有限责任公司北海供电局 Transformer dynamic capacity increasing system based on transformer monitoring

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202167322U (en) * 2011-07-20 2012-03-14 上海海能信息科技有限公司 Control system of energy-saving and synergistic transformer
CN202362395U (en) * 2011-10-28 2012-08-01 华东电力试验研究院有限公司 Real-time analysis system for overload capacity of transformer
CN202362089U (en) * 2011-12-05 2012-08-01 华东电力试验研究院有限公司 Overload pre-warning system for transformer

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202167322U (en) * 2011-07-20 2012-03-14 上海海能信息科技有限公司 Control system of energy-saving and synergistic transformer
CN202362395U (en) * 2011-10-28 2012-08-01 华东电力试验研究院有限公司 Real-time analysis system for overload capacity of transformer
CN202362089U (en) * 2011-12-05 2012-08-01 华东电力试验研究院有限公司 Overload pre-warning system for transformer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡惠然等: "湖北电网110~220kV主要电力变压器过负荷能力分析", 《湖北电力》, vol. 28, 31 December 2004 (2004-12-31), pages 35 - 37 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014135015A1 (en) * 2013-03-07 2014-09-12 国网安徽省电力公司芜湖供电公司 Network for online monitoring of power transformer at intelligent substation
CN103245857A (en) * 2013-04-23 2013-08-14 浙江大学 Assessment method for loadable index of oil immersed power transformer
CN103245857B (en) * 2013-04-23 2015-06-03 浙江大学 Assessment method for loadable index of oil immersed power transformer
CN103324215A (en) * 2013-05-17 2013-09-25 郑州华力信息技术有限公司 Method for setting up thermal circuit model used for transformer load intelligent management system
CN103324215B (en) * 2013-05-17 2016-08-03 国网河南省电力公司郑州供电公司 The method to set up of Intelligent load management system for transformer thermal circuit model
CN103543352B (en) * 2013-09-25 2016-05-18 国家电网公司 Determine the method for the dynamic overload curve of transformer based on service data
CN103543352A (en) * 2013-09-25 2014-01-29 国家电网公司 Method for determining dynamic overload curves of transformers based on operating data
CN105353233A (en) * 2015-09-30 2016-02-24 南京南瑞继保电气有限公司 Method and device of on-line operation capability detection of transformer
CN105353233B (en) * 2015-09-30 2018-03-13 南京南瑞继保电气有限公司 A kind of transformer on-line operation ability detection method and device
CN107246925A (en) * 2017-05-27 2017-10-13 上海海能信息科技有限公司 A kind of current transformer thermal circuit model analysis method
CN108680801A (en) * 2018-03-23 2018-10-19 国网河北省电力有限公司电力科学研究院 A kind of transformer overload computational methods, system and terminal device
CN112615371A (en) * 2020-12-18 2021-04-06 浙江大学 Asset optimal configuration method for improving utilization efficiency of distribution transformer
CN112615371B (en) * 2020-12-18 2021-10-08 浙江大学 Asset optimal configuration method for improving utilization efficiency of distribution transformer
CN113390461A (en) * 2021-06-04 2021-09-14 广西电网有限责任公司北海供电局 Transformer dynamic capacity increasing system based on transformer monitoring

Also Published As

Publication number Publication date
CN102879696B (en) 2015-04-15

Similar Documents

Publication Publication Date Title
CN102879696B (en) Automatic judgment method for over-load operational feasibility of transformer
CA2742854C (en) Real-time power line rating
Ipakchi et al. Grid of the future
KR101825225B1 (en) System for operating smart power grid
Kreikebaum et al. Smart Wires—A distributed, low-cost solution for controlling power flows and monitoring transmission lines
US9450413B2 (en) Power regulating system for solar power station
CN102663530A (en) Safety early warning and evaluating system for high-voltage direct current transmission system
CN103500999B (en) Low voltage distribution area power supply radius optimization method based on real-time loss
Carlini et al. Methodologies to uprate an overhead line. Italian TSO case study
CN105391168A (en) Transformer load real-time control method
CN210422883U (en) Multi-wind-field fan electric centralized control system based on c/s framework
CN108108871B (en) Type selection method for wind power plant group power transmission equipment
Carlini et al. Uprating an overhead line. Italian TSO applications to increase system N− 1 security
US11159046B1 (en) Dynamic computation and control of distributed assets at the edge of a power grid
CN102044913A (en) Method for managing load management terminal in power distribution terminal
CN103915901A (en) Transformer area load management system
CN103248042B (en) Peak shifting and avoiding method for electric management system
CN106208042B (en) Power distribution network outage information sharing method based on battalion's auxiliary tone fusion
Al_Issa et al. Monitoring of power transformers using thermal model and permission time of overload
CN111985794B (en) Line loss management method based on marketing and distribution information integration platform
CN202041600U (en) Intelligent online monitoring system for lightning arresters
He et al. Statistical Analysis of Heavy-load Transformers in Zhejiang Power Grid during Summer
Emmanuel et al. Impacts of control set-points on battery energy storage performance for peak shaving application
CN116843361B (en) Power grid audit informatization management method and system
CN101976379A (en) Method for assessment and statistics as well as alarm of power factors

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant